item 9 Award a contract to Southland Industries, Inc. to replace four (4) Heating, Ventilation, Air Conditioning Units at the Courtyard Center located at 12732 Main Street, Garden Grove. (Cost: $52,804) (Act

Garden Grove City Council
June 25, 2024

Document
item 9 Award a contract to Southland Industries, Inc. to replace four (4) Heating, Ventilation, Air Conditioning Units at the Courtyard Center located at 12732 Main Street, Garden Grove. (Cost: $52,804) (Act
Meeting
June 25, 2024
Body
Garden Grove City Council
Pages
2
Original file
96 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 266/2024
Final
City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 6/25/2024

Subject: Award a contract to Southland Industries, Inc. to replace four (4) Heating, Ventilation, Air Conditioning Units at the Courtyard Center located at 12732 Main Street, Garden Grove. (Cost: $52,804) (Action Item)

OBJECTIVE

For City Council to award a contract to Southland Industries, Inc., for the replacement of four (4) Heating, Ventilation and Air Conditioning (HVAC) package units at the Courtyard Center (CYC).

BACKGROUND

The Public Works Department Facilities Division is responsible for the maintenance of City buildings. In 2019, the City contracted with a consultant to perform a comprehensive Facilities Condition Assessment (FCA) of City owned buildings. The FCA includes forecasts on the useful lifecycle and costs of building maintenance needs, and replacement of major assets inside each building. Additionally, the assessment captured current building deficiencies and categorizes them by categories including Safety, Perfor mance/Integrity, Accessibility, Environmental, Retrofit/Adaptation and Lifecycle/Renewal. Priorities are determined within each of these categories.

DISCUSSION

Based on the FCA , building maintenance projects were established in our five-year Capital Improvement Plan (CIP). The Fiscal Year 2023-24 CIP includes the replacement of four (4) HVAC package units located at the CYC. These units have reached the end of their useful service lives and replacement is deemed necessary.

Specifications were generated and submitted for bid (IFB S-1322A). The results shown reflect the four (4) lowest bids.

Southland Industries, Inc. $52,804
A & H Refrigeration, Inc. $57,500
F.M. Thomas Air Conditioning $67,578
Harbor Pointe, Inc. $81,863
Item 266/2024

Page 2 of 2 ends

FINANCIAL IMPACT

The cost for replacing the four (4) HVAC units the CYC is included in the FY 2023-24 CIP, and funded from the Building Rehabilitation internal service fund. No additional appropriation is needed.

RECOMMENDATION

It is recommended that City Council:
• Award a contract to Southland Industries, Inc. in the amount of $52,804 for the replacement of four (4) Heating Ventilation and Air Conditioning units at the Courtyard Center; and
• Authorize the City Manager to sign the contract, and to make minor modifications as appropriate.

By: Phillip Carter, Facilities Manager