item 5 Acceptance of Project No. CP1287000 - Anabel-Woodbury Water Improvement Project, as complete. (Action Item)

Garden Grove City Council
August 27, 2024

Document
item 5 Acceptance of Project No. CP1287000 - Anabel-Woodbury Water Improvement Project, as complete. (Action Item)
Meeting
August 27, 2024
Body
Garden Grove City Council
Pages
2
Original file
224 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 344/2024
Final
City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: Samuel Kim
Dept:

City Manager Dept: Public Works
Date: 8/27/2024

Subject: Acceptace of Project No. CP1287000 – Anabel-Woodbury Water Improvement Project, as complete. (Action Item)

OBJECTIVE

For the Garden Grove City Council to accept Project No. CP1287000 – Anabel-Woodbury Water Improvement Project as complete , and authorize the City Manager to execute the Notice of Completion of Public Improvements and Work.

BACKGROUND

The 2020 Water Master Plan has identified the Anabel-Woodbury Water Improvement Project as a priority project due to fire flow deficiency. The construction of this project will increase fire flow capacity and meet OCFA fire flow requirements surrounding Woodbury Elementary; Anabel Avenue, from school entrance to Libby L ane; Libby L ane from Anabel Ave nue to Woodbury Road, and Woodbury Road from Euclid Street to Newhope Street.

The water improvements include the installation of approximately 970 feet of 12 -inch PVC pipe, 3,140 feet of 8-inch PVC pipe, and 110 feet of 6-inch PVC domestic water pipe. It also includes the construction of approxima tely eleven (11) fire hydrant assemblies, eighty -two (82) water service connections and nine (9) connection points at existing mains. This project will abandon approximately 4,245 feet of 4 and 6-inch AC pipe in place.

DISCUSSION

The contractor, CEM Construction Corporation, has completed this project in accordance with the plans, specifications and other contract documents.

FINANCIAL IMPACT

There is no financial impact to accept Project No. CP1287000 – Anabel-Woodbury Water Improvement Project as complete, and authorize the City Manager to execute the Notice of Completion of Public Improvements and Work . The project was funded with Water Funds.

The retention payment will be released after recordation of the Notice of Completion with the County of Orange.

Item 344/2024

Page 2 of 2 ends

RECOMMENDATION

It is recommended that the City Council:
 Accept Project No. CP1287000 – Anabel-Woodbury Water Improvement Project as complete, and authorize the City Manager to execute the Notice of Completion of Public Improvement and Work; and
 Authorize the Finance Director to release the retention payment when appropriate to do so.

ATTACHMENT

1. Notice of Completion