THE SYSTEM
CONSTRUCTION OF
THE BOLSA CHICA ST -
VALLEY VIEW ST. TSSP
Request for Proposals for
November 8, 2024
11477-230.25
Submitted to:
November 8, 2024
Mr. Dai Vu
Traffic Engineer
City of Garden Grove, Public Works Department Engineering Division 11222 Acacia Parkway
Garden Grove, CA 92842
Re: Proposal for City the System Construction of the Bolsa Chica St. – Valley View St. TSSP in the City of Garden Gove
11477-230.25
Dear Mr. Vu
Iteris is a trusted leader in the Intelligent Transportation Systems (ITS) space. Over the past five years, we have launched more than 1,000 ITS/engineering, construction, and planning projects for a wide range of public and private entities, spanning local and regional agencies, counties, and Caltrans. This extensive track record underscores our capability and dedication to delivering superior transportation solutions. Iter is is proposing a team of seasoned professionals for construction and implementation tasks, each possessing extensive experience across every phase of project deployment and construction. This breadth of expertise in multiple disciplines ensures seamless project continuity, encompassing technical solutions and stakeholder engagement needed to deliver a successful project. At the project’s conclusion, Iteris ensures the city will have a fully functioning system that they understand and can utilize for years to come.
Iteris proposes Mr. Brian Akerley, MELE, as Project Manager for this project. He will be the principal contact with the City and other entities per the City’s direction. Mr. Akerley will oversee work from project inception to completion and will also be responsible for coordinating staff activities and meetings. Iteris will provide the City with the following distinct advantages:
Iteris Does It All.
Iteris is a “one-stop-shop” turnkey integration solutions provider offering a full spectrum of services in planning, consulting, design, installation, integration, and operations and maintenance. Our extensive expertise across transportation disciplines equips our team with a comprehensive understanding of the steps necessary to successfully complete ITS projects.
We Know Garden Grove.
With a long, successful history of collaboration with the City of Garden Grove, the Iteris team possesses an in-depth understanding of the City’s transportation network and objectives. Our project team’s professional experience provides valuable insight into the technical background and needs of the area, while our personal experience gives firsthand knowledge and a local connection to the project.
This proposal is valid for ninety (90) days from date of submittal.
We have included sample certificates to show coverage included in the Appendix and we are asking the City of Garden Grove to consider accepting our policies and limits as -is. Our current coverage does not include the loss payee endorsement, however, upon award and negotiation with the City, Iteris is open to discussing options to obtaining additional coverage.
Iteris carries the following insurance coverage for our electrical contracting line of business:
• CGL: $1M per occurrence / $2M in the aggregate
• Excess: $3M per occurrence and in the aggregate
• Professional / Pollution Liability: $1M per claim and in the aggregate
Additionally, Iteris carries the following policies for the business overall:
• Auto: $1M combined single limit
• WC: $1M each accident/disease
Thank you for the opportunity to submit our proposal. Iteris looks forward to working with the City on this important project. Please contact me at (949) 270-9647 or [email protected], or the designated Project Manager (PM), Mr. Akerley, MELE, at (657) 652-8288 or [email protected], should you have any questions.
Sincerely,
Iteris, Inc.
Steven Bradley, PE - Regional Vice President | Mobility Consulting Solutions Steven has the authority to bind and negotiate on behalf of Iteris.
iii | Iteris, Inc.
MICROSIMULATION MODEL DEVELOPMENT FOR HARBOR BOULEVARD
A. QUALIFICATIONS, RELATED EXPERIENCE, AND REFERENCES OF OFFEROR
COVER LETTER………………….………………………………………………………………………………………………………………………………I TABLE OF CONTENTS………………………………………………………………………………………………………………………………………………. III COMPANY OVERVIEW ................................................................................................................................................... 1 PROJECT TEAM .............................................................................................................................................................. 3 RELEVANT EXPERIENCE ................................................................................................................................................. 6 PROJECT UNDERSTANDING AND APPROACH .............................................................................................................. 10 SCOPE OF WORK .......................................................................................................................................................... 10 PROPOSED PROJECT SCHEDULE……………………………………………………………………………………………………………………… ..……14 APPENDIX: CONTRACTOR LICENSE | INSURANCE COVERAGE | RESUMES ................................................................. 15
Tables
Table 1 – Project Qualifications Matrix ......................................................................................................................... 6
Figures
Figure 1 – Project Team Organization ........................................................................................................................... 4
Figure 2 – Proposed Project Schedule ......................................................................................................................... 14
1 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST . TSSP
COMPANY OVERVIEW
Iteris, Inc. is the market leader in smart mobility infrastructure management since 1987. Iteris’ 470 staff have decades of expertise in traffic management, along with superior services and patented products that help detect, measure, and manage traffic and vehicular performance, minimize traffic congestion, enhance safety, and empower Iteris clients with solutions to better manage their transportation networks.
Iteris team members are experts in the fields of ITS
construction, transportation planning, traffic engineering, and Implementation. Knowledge of these practice areas
enables Iteris to provide comprehensive services ranging from initial traffic impact studies, transportation
modeling, planning, systems engineering, and detailed
design, through implementation and performance
measurement/monitoring. Iteris combines the knowledge
of transportation engineers, construction professionals, system integrators, software engineers, and
transportation planners to offer an unmatched
combination of talent and experience. Iteris develops and deploys innovative solutions that help agencies reduce traffic congestion, enhance transit use, monitor, and manage transportation networks and provide greater access to reliable traveler information.
Iteris, Inc., a wholly owned subsidiary of Almaviva S.p.A., is a financially solvent corporation with the financial capability to fulfill all project requirements subject to this RFP. Financial filings for its annual fiscal year-end 2024 and first quarter filing for its current fiscal year 2025 are available at SEC website at the following URL under company name “Iteris, Inc.” or ticker symbol “ITI” - www.sec.gov/edgar.shtml.
Core Disciplines
Iteris was founded based on the principle of providing quality solutions on time and within budget. Committed to the transportation industry, Iteris applies in depth knowledge to solve the most challenging problems associated with the movement of people and goods to enhance a growing economy. Iteris delivers precise solutions that meet customer needs and expectations in the following areas:
Field Installation
&
Implementation
Safety
Evaluation
Model
Development
Traffic Signal
Timing
Development
Data
Insights
Operations
Performance
Evaluation
Before/After
Analysis
2 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST . TSSP
COMPANY OVERVIEW
Knowledge in ITS Construction and Implementation
Successful project delivery starts with people, and our unrivaled team of experts draws from a deep industry understanding to guide the way forward to success. The Iteris construction management team has completed design, procurement, construction, integration, and quality control tasks for similar projects throughout Orange County. Many of these projects have the same construction and technology aspects to them as the Garden Grove TSSP project does. Iteris has even completed a handful of full TMC buildouts with cutting edge video wall technology throughout California and Texas. Additionally, with Brian Akerley’s experience as a Master Electrician (MELE), we have an all-encompassing proficiency that covers every aspect of construction, integration, and project management. In fact, Iteris has been providing construction management level support on ITS projects dating back to the early 2000s.
Iteris is also known in the ITS industry as being uniquely qualified to perform every aspect of ITS related project deliverables, from upfront planning to design and construction, and onto operations. This is primarily because Iteris has a long, demonstrated history of planning, designing, constructing, and implementing successful projects both as a licensed Professional Services firm and as a licensed Electrical Contractor . When applicable, leveraging analytics from Iteris’ traffic sensors and software products further differentiates Iteris as a leader in the transformation to smart mobility management. As a result, Iteris is recognized as a “One-Stop-Shop" and has had the pleasure of working with state and local agencies for several decades, including agencies like OCTA, LA Metro, Santa Ana, and Garden Grove to name a few.
3 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT TEAM
35 BRIAN AKERLEY, MELE
Project Manager
Mr. Akerley serves as a Vice President for Iteris’ Consulting Solutions division and has been with the firm since 2022. He has over 24 years of comprehensive experience as a results-focused professional with extensive experience in electrical engineering, electrical contracting, telecommunications, and Intelligent Transportation Systems (ITS) installation and maintenance. His performance track record is characterized by successful planning, implementation, and execution skills, as well as an effective participatory management style that reflects strong coaching, delegation, and leadership skills, as well as an ability to establish clear and measurable goals. Brian has been responsible for the oversight and delivery of many high-level projects for Municipalities, County and State DOTs, and transit agencies. In addition to his leadership, and project delivery skills, Brian is the licensing Qualifier for Iteris and is responsible for acquiring the state licensing necessary to lay the groundwork for business development nationally.
Education &
Registrations
BS, Business and
Leadership Studies
Electrical Contractor
Licensing
CA #1096882
Project Team Organization
With local offices in Santa Ana, Los Angeles, and
Oakland, Iteris has the resources of over 100 team
members throughout California dedicated to Traffic
Engineering, Transportation Planning, and ITS. Iteris’
proposed team organization is provided in Figure 1.
We have partnered with Anderson Howard as our subcontractor for this project to perform the fiber optic tasks and to provide a Corning Landscape warranty where applicable. Anderson Howard is a leader in fiber optic installation, offering comprehensive services
tailored to meet the needs of both Industrial and
commercial clients. With a dedicated team of certified
technicians and state-of-the-art equipment, Anderson
Howard ensures efficient and reliable installation
processes that meet or exceed industry standards. These installation capabilities cover all aspects of fiber optic deployment, including:
• Underground and Aerial Installations: Expertise in
both underground and aerial installations,
ensuring adaptability to various environments.
• Splicing and Termination: High-precision splicing
Mr. Akerley has 24+
years in Electrical
Contracting experience.
4 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT TEAM
and termination of fiber cables, ensuring optimal performance and minimal signal loss. • Testing and Certification: Comprehensive testing procedures to validate network integrity, including OTDR testing, power loss measurements, and certification according to Corning and industry standards. • Troubleshooting, and repair services to ensure long-term reliability and performance of fiber optic networks.
Additionally, Anderson Howard has a long collaborative history of working with their partners and customers while adhering to their core tenants of authenticity and trust.
Figure 1 – Project Team Organization
Proposed Project Organization
KEY
Task Lead
Anderson Howard (Sub)
Joshua McNeill, PE, TE, PTOE
QA/QC & Senior Advisor
Brian Akerley, MELE
Project Manager
Peyvand Hajian
Deputy Project Manager
Project Team Profiles
EXPERT ADVISORY PANEL
Iteris aims to solve clients’ project problems by offering effective, innovative, and smart solutions. Our clients know Iteris as a firm that goes above and beyond expectations to make client projects successful. One method to achieve these goals is by offering clients an Expert Advisory Panel whose mission it is to assist the Project Team with innovation idea s, problem solving solutions and quality control (QA/QC). Iteris is pleased to offer Mr. Joshua McNeill, PE, TE, PTOE and Ms.
Payvand Hajian, as the Expert Advisory Panel for this project.
JOSHUA MCNEILL, PE, TE, PTOE
Role on Project
QA/QC Senior Advisor
Education &
Registrations
MS, Civil Engineering
BS, Civil Engineering
PE, CA #79151
PE, UT #9480116
Mr. McNeill serves as a Principal Engineer for Iteris’ Mobility Consulting Solutions and has been with the firm since 2017. He has 17 years of experience working in the fields of transportation engineering and planning.
Mr. McNeill has delivered PS&E packages for traffic signal system upgrades, fiber optic communication networks, freeway traffic management systems, as well as other traditional traffic handling, signing and pavement delineation plans. He has also managed signal timing development and implementation for several agencies. He provides solutions to traffic problems while effectively managing budgets and scope of
CONSTRUCTION INTEGRATION
Kent Spurr Alek Ingoglia
Alex Morales, IMSA
Joshua Lemestre, IMSA
Alex Gallardo, IMSA
Juan Ramos
Andrew Freeman, PE, PTOE
Raymond Liang
5 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT TEAM
TE, CA #2792
PTOE #4870
work. Mr. McNeill is committed to providing sustainable transportation design with an emphasis on systems engineering analysis and utilization of emerging technologies. As a resident of Garden Grove, Josh enjoys several of the amenities along Valley View such as the bowling alley and movie theatre. His local knowledge allows him to understand the community’s needs.
PAYVAND HAJIAN
Role on Project
Deputy Project
Manager
Education &
Registrations
MS, Civil Engineering
BS, Civil Engineering
Ms. Hajian serves as a Senior Engineer for Iteris’ Mobility Consulting Solutions and has been with the firm since 2024. Ms. Hajian has 10 years of experience working in the field of Transportation Infrastructure. Mrs. Hajian is a resourceful and analytical transportation engineer with experience in transit, intelligent transportation systems, and transportation infrastructure projects. Ms. Hajian has demonstrated the ability to design, permit, construct, and develop scope for complex large-scale, multimillion-dollar projects involving striping, traffic control, stage construction, and neighborhood traffic management.
KEY PERSONNEL
Iteris is pleased to present the following key personnel assigned to the project who will assist Mr. Akerley with the successful delivery of this project to the City.
KENT SPURR
Role on Project
Task Lead
Education &
Registrations
FOA Fiber Optic
Certification
#4090055 CFOT
CSLB C-10 Electrical
Contractors License
#1081585
Mr. Spurr serves as a Technical Field Support IV for Iteris’ Consulting Solutions division and has been with the firm since August 2022. He has over 21 years of experience working in the field of ITS electrical installation, operations, and maintenance. Mr. Spurr has spent his career as the “Go- To” technical lead for projects requiring a master level of expertise. This level of expertise is consistently leveraged to assist our clients with equipment issues , troubleshooting devices, and finding solutions to some of the industry’s most complicated challenges. As the Task lead for the construction portion of this project, Kent will oversee every aspect of the field work to ensure code compliance and specification adherence.
ALEX INGOGLIA
Role on Project
Task Lead
Education &
Registrations
BS, Civil Engineering
EIT, CA #160812
Mr. Ingoglia serves as a Senior Engineer in Iteris’ Mobility Consulting Solutions division and has been with the firm since April 2017. Mr. Ingoglia has over 7 years of experience in the fields of Traffic Signal Operations, Signal Timing & Coordination, Intelligent Transportation Systems (ITS) planning, design, and integration, Traffic Engineering & Design, and Municipal Traffic Engineering. His project experience includes preparing and implementing signal timing and synchronization, operational analysis, installing ITS and
communication equipment, preparing signing and striping plans as well as reviewing traffic studies and traffic control plans. Mr. Ingoglia has knowledge in signal timing, Intelligent Transportation Systems (ITS), electrical systems, and integration. Mr. Ingoglia is proficient in the use of design and traffic analysis software such as AutoCAD, MicroStation, and Synchro. Mr. Ingoglia grew up in nearby Huntington Beach and Westminster along the Bolsa Chica-Valley View corridor and is familiar with the corridor and frequently visits the area to visit family.
6 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
RELEVANT EXPERIENCE
Iteris is well known within the industry and has a long history of successful projects similar in scope for several California agencies. With a proven track record of on-time, within-budget performance, Iteris encourages the City/Agency to verify with the references provided for the project qualifications provided. Iteris has initiated over 1,000 ITS/Engineering and Planning projects within the last five years for a wide range of public and private entities including local agencies, counties, MPO, and Caltrans.
Approximately 70% of these projects represent repeat clients - a testament to Iteris’ ultimate goal of client satisfaction. Iteris’ extensive traffic engineering, transportation planning and ITS experience is demonstrated by the projects are summarized in Table 1.
Table 1 – Project Qualifications Matrix
PROJECT NAME AND LOCATION
ITS
Construction
ITS
Integration
Construction
Management /
Support
ITS Design
Installation and Integration for the Citywide Bus Signal Priority Project – City of Downey, CA
Countywide Signal Priority (CSP) Upgrade and Expansion Next Gen – Los Angeles, CA
First Street and Bolsa Avenue Regional Traffic Signal Synchronization Project (RTSSP), Orange County Transportation Authority (OCTA) – Orange County, CA
Alternative Signal Communication Demonstration Pilot, Orange County Transportation Authority (OCTA) – Orange County, CA Regional Traffic Signal Synchronization Program (RTSSP) Project For Tustin Avenue & Rose Drive – City Of Orange, CA
Over 70% of Iteris’ ITS/Engineering and Planning projects represent repeat clients - a testament to Iteris’ ultimate goal of client satisfaction.
7 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
RELEVANT EXPERIENCE
Project Qualifications
INSTALLATION AND INTEGRATION FOR THE CITYWIDE BUS SIGNAL PRIORITY PROJECT – CITY OF DOWNEY, CA
Reference Mr. Edwin J. Norris, PE, TE, Deputy Director of Public Works, City of Downey, 11111 Brookshire Avenue,Downey, CA 90241, (562) 904-7110, [email protected]
Staff Brian Akerley (PM), Kent Spurr (Field installation leader), Omid Modaghegh (Integration task leader) Duration 2/2023 – 12/2024 Budget $920,000
Iteris is responsible for constructing and
implementing the bus signal priority
system for 92 intersections along six
major corridors. Iteris had previously
done the development of plans,
specifications, and construction cost
estimate for 2.2-mile gap closures in the
city’s fiber-optic traffic signal
communications network, to enable the
connection of additional signalized
intersections to the City’s Traffic
Management Center (TMC), and
recommendations of bus signal priority systems to be integrated onto the DowneyLINK automatic vehicle location (AVL) system. The signal priority system is based on IEEE 802.11-compliant wireless bus-to-intersection communications; and upgraded intersection traffic controller technologies. In addition to the installation of radios, antennas and supporting cabling, Iteris is responsible for integration of the Wireless Local Area Network (WLAN) network including any interties that are required for network monitoring for each corridor. The WLAN network design will be consistent with Metro’s Countywide Signal Priority architecture and sys tem.
Project Relevance: Similar to the Valley View TSSP project, there is an abundance of controllers, ethernet switches and TMC network equipment in this project that Iteris installed, configured, and integrated into the city’s system.
COUNTYWIDE SIGNAL PRIORITY (CSP) UPGRADE AND EXPANSION NEXT GEN – LOS ANGELES, CA Reference Steven Gota, Engineer, Metro, 1 Gateway Plaza, Los Angeles, CA 90012, (213) 922-3043, [email protected] Staff Alek Hovsepian (Project Manager), Steven Bradley (Principal-In-Charge), Omid Modaghegh (WLAN Communication Design), Delbert Smith-Lavezzari (System Design Engineer) Duration 10/2021 – 8/2024 Budget $2,639,548
Iteris was responsible for evaluating and
implementing bus signal priority system for several
multi-jurisdictional Metro local corridors as part of
Metro’s Next Gen Bus Service and existing
Countywide Signal Priority corridors. Iteris provided
engineering design services, intersection system
hardware and installation services, jurisdictional
coordination support expansion and upgrade of the
CSP System for 12- local service corridors. The CSP
system is based on IEEE 802.11-compliant wireless
bus-to-intersection communications; and upgraded
intersection traffic controller technologies. In
addition, Iteris prepared the Preliminary Design
Report (PDR) that describes the overall design of the
8 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
RELEVANT EXPERIENCE
Wireless Local Area Network (WLAN) network including any interties that are required for network monitoring for each corridor. The WLAN network design is now consistent with Metro’s CSP architecture and system. Based on the design approach developed for the PDR and agreed upon by the local agencies, Iteris procure d all specified equipment in accordance with applicable Metro procurement standards and perform ed a pre-installation checkout (PIC) prior to receiving authorization to proceed with any equipment installations. Finally, Iteris successfully deployed, configured, and integrated all equipment as designed for a successful end result.
Project Relevance: Iteris successfully installed, configured, and integrated WLAN radios, antennas, ethernet switches, CAT6 cabling and related ITS equipment into the CSP infrastructure.
FIRST STREET AND BOLSA AVENUE REGIONAL TRAFFIC SIGNAL SYNCHRONIZATION PROJECT (RTSSP), CONTRACT TASK ORDER (CTO) (AGREEMENT C-9-1812), ORANGE COUNTY TRANSPORTATION AUTHORITY (OCTA) – ORANGE COUNTY, CA
Reference Alicia Yang, Project Manager III, OCTA, 600 S. Main Street, Orange, CA 92868, (714) 560-5362, [email protected] Staff Josh McNeill (PM), Bowen Yang, Michelle Haas, George Gener, Omid Modaghegh, , Evan Shipley, Delbert Lavezzari, Natali Mendez, Jason Xu, Bernard Li, Kassra Rafiee, Jin Eo, Stuart Hunter, Alex Nguyen, Steven Bradley, Alex Ingoglia, Sahila Sarjana, Lesley Ng, Eric Chiu
Duration 8/2021 – 12/2025 - Ongoing Budget $3,871,890
Iteris is assisting OCTA with multi-jurisdictional signal coordination for a 13.1-mile stretch of First Street/Bolsa Avenue. The project includes various traffic signal improvements and the retiming of 55 signalized intersections along First Street/Bolsa Avenue from Bolsa Chica Street in the City of Huntington Beach to Newport Avenue in the City of Tustin and five (5) signalized intersections offset from the corridor in the City of Santa Ana. Iteris designed and is managing the installation of traffic signal equipment, communication network equipment, and fiber optic cable for five (5) agencies along the corridor.
The team also coordinated the selection
and installation of a new video
management system for the City of
Westminster TMC. Iteris collected traffic
count data to create Synchro models that
will help optimize and synchronize the
signal timing along First Street/Bolsa
Avenue. Also included in the scope of the
project, Iteris has developed and will
implement new timing plans for the AM,
midday, PM, and Weekend peak periods.
Project Relevance: Iteris installed APS, CCTV cameras, Video Detection Systems (VDS) as part of this project, which included configuration and field testing similar to the Valley View TSSP project
ALTERNATIVE SIGNAL COMMUNICATION DEMONSTRATION PILOT (22411) – ORANGE COUNTY
TRANSPORTATION AUTHORITY (OCTA)
Reference Alicia Yang, Project Manager III, OCTA, 600 S. Main Street, Orange, CA 92868, (714) 560-5362, [email protected] Staff Bernard Li, Omid Modaghegh, Delbert Lavezzari, Natali Luevanos-Mendez, Raymond Liang Duration 6/2022 – 12/2023 Budget $250,000
This project provided traffic signal communication improvements throughout various city’s traffic signal networks within Orange County. Cities that required upgrades as part of the base tasks are the Cities of Huntington Beach, La Habra, Lake Forest, Newport Beach, Rancho Santa Margarita, Seal Beach, and Yorba Linda.
9 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
RELEVANT EXPERIENCE
The cities received upgrades to their existing communication infrastructure at intersections that were either offline, had outdated equipment, and/or seeking alternatives solutions to ensure reliability, enhanced security, and scalability for a robust network that will be viable for the next 10 to 15 years. The primary goal of this project was to analyze and test connectivity at locations where there is existing interconnect (copper, fiber, and wireless) systems, so that appropriate design measures can be applied to deploy new ethernet switches, ethernet cards, wireless radios, and/or cell modems to support the management of each city’s traffic network.
The result of these proposed improvements or alternative recommendations provided the cities with a robust, modern traffic signal communication system that will support future ITS deployments.
Project Relevance: Iteris installed ethernet switches, 170 communication modules, and dual panel ethernet radios to support the intended communications infrastructure
REGIONAL TRAFFIC SIGNAL SYNCHRONIZATION PROGRAM (RTSSP) PROJECT FOR TUSTIN AVENUE - ROSE DRIVE – CITY OF ORANGE, CA
Reference Gabrielle Hayes, PE, Principal Civil Engineer Public Works – Traffic, City of Orange, 300 E. Chapman Avenue, Orange, CA 92866, (714) 744-5561, [email protected] Staff Andrew Freeman (PM), Tom Petrosino, Omid Modaghegh, Evan Shipley, Delbert Lavezzari, Quan Nguyen, Brian Funk, Natali Luevanos, Raymond Liang, Jason Xu, Kassra Rafiee, Stuart Hunter, Nicole Richardson, SungWoo Jo, Alex Ingoglia, Richard Luo, Alex Nguyen
Duration 9/2021 - Ongoing Budget $1,100,000
Iteris provided ITS design, bid and
construction support, and traffic signal
synchronization services along the Tustin
Avenue/Rose Drive corridor from First Street
in the City of Tustin to Wabash Avenue in
the City of Yorba Linda. The project area
comprises of 54 signalized intersections in
Orange County, California, spanning six cities
(Tustin, Santa Ana, Anaheim, Orange,
Placentia, and Yorba Linda) as well as several
highway ramps under Caltrans jurisdiction.
ITS equipment upgrades installed as part of
this project include fiber-optic communications, closed-circuit television (CCTV), video detection systems (VDS), radar detection systems, traffic signal controllers and cabinets, and wireless radios. Iteris assisted the lead agency, the City of Orange, in assembling bid and contract documents. Additionally, Iteris provided construction support throughout the project, including scheduling and leading meetings, reviewing submittals, responding to requests for information (RFIs), reviewing change orders, investigating, and troubleshooting field issues, verifying, and documenting construction quantities, and assisting in preparing and processing reimbursements.
Iteris developed traffic signal coordination timing plans for the 54 signalized intersections and continues to provide management and signal timing support services throughout the Operations and Maintenance (O&M) phase of the project. Iteris also conducted a Before and After corridor analysis, which included a detailed report and video highlighting the improvements along the corridor. This project commenced in August 2020 and is currently in the (O&M) phase.
Project Relevance: Iteris provided design, integration, and construction management support services to install traffic signals controllers and cabinets, video detection systems (VDS), and CCTV cameras.
10 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT UNDERSTANDING AND APPROACH
Project Understanding
The City of Garden Grove has requested
proposals to provide professional services for
the System Construction of the Bolsa Chica
Street – Valley View Street Traffic Signal
Synchronization Project (TSSP). This project
entails the furnishing and installation of
communication equipment at the Garden
Grove Traffic Management Center (TMC) and
field equipment at the following five
signalized intersections along Valley View
Street:
1. Valley View Street & Chapman Avenue 2. Valley View Street & West Grove Center
3. Valley View Street & Belgrave Avenue 4. Valley View Street & Lampson Avenue
5. Valley View Street & Cerulean Avenue
The scope of work includes procurement and/or installation of traffic signal cabinets, service cabinets, controllers, video detection systems, CCTV camera systems, APS pedestrian push buttons, ethernet switches, pull boxes, conduits, and conductors. Iteris’ familiarity with the City of Garden Grove’s existing infrastructure, combined with our extensive experience in ITS design, construction and construction management support ensures that we are fully capable of completing this project on-time, within budget, and to the City’s satisfaction.
Prior to procurement, Iteris will submit cut sheets detailing product information and specifications for City review and approval. Immediately upon approval, Iteris will coordinate with vendors to begin the procurement process. Additionally, Iteris will verify that all necessary testing for equipment has been performed and that the equipment meets the project requirements. Lastly, Iteris will complete the construction, configuration, and integration of communication equipment into Garden Grove’s existing network as described in the RFP.
SCOPE OF WORK
The following paragraphs describe Iteris’ general approach to providing professional services for System Construction, and is divided into the following tasks:
1. PROJECT MANAGEMENT
Iteris is committed to the principle that exceptional project management is essential to the successful completion of any project, with success defined as achieving project completion within budget, on schedule, and to the client’s satisfaction. As Project Manager, Mr. Akerley will lead the Iteris project team and oversee this project from inception to completion, ensuring the delivery of a high-quality product while maintaining regular communication with the city. To keep the city informed of project progress, Iteris will hold bi-weekly meetings which will result in a Valley View Street / Lampson Avenue
11 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT UNDERSTANDING AND APPROACH
written progress report and meeting minutes. This report will detail the activities conducted during the previous period as well as outline upcoming project tasks and identify potential roadblocks.
Kickoff Meeting
As part of the Project Management task, Mr. Akerley will lead a kick-off meeting with City staff and other project stakeholders. During this kickoff meeting, Iteris will present a detailed project schedule encompassing the full scope of work and project milestones. The purpose of this meeting will be to ensure that all participants understand and support the project goals and the plan to achieve them.
Bi-weekly Construction Updates
Consistent and regular communication is a
cornerstone to successful project management. As
such, Iteris will hold bi-weekly update meetings with
designated city staff and project stakeholders to
keep all parties abreast of progress, schedule
adherence, field work changes, and any challenges
that may arise. Following each meeting Iteris will
distribute meeting minutes to all parties and will
keep a log of meeting attendance and activity
highlights.
Construction Documentation
It is imperative to document the condition of all
equipment that is accessed or modified through this
project prior to and after construction activities so that the condition of all equipment is documented, and the post construction condition does not negatively impact the existing traffic equipment. Equally important is to document the existing condition of all system and communication components prior t o replacing the existing systems, so the status and expectations of the new system is documented, and al l operational elements of the new system must be operational when the new system is activated.
Post Construction
Iteris will assist City inspectors in the final walk-through ensuring compliance with construction requirements and providing a thorough “punch-list” of items that must be corrected and/or completed to satisfy the project requirements. Iteris will maintain an accurate record of all changes in the plans which include any change orders, RFIs, addendums, and additional details. Iteris will compile and submit final as-built drawings to the city.
Deliverables
• Detailed Project Schedule
• As-builts
• Monthly Invoices and Progress Reports
2. EQUIPMENT PROCUREMENT
Product Submittals
Iteris recognizes that extended procurement times can disrupt project timelines. To mitigate these effects, Iteris will prioritize the procurement process to ensure the project remains on schedule and is completed promptly. The procurement process will begin with the submittal of detailed product specification sheets to the City for review and approval. This step ensures that the equipment to be procured is compatible with the City’s proposed design and fully meets the project’s needs and requirements.
Equipment Ordering and Tracking
Upon receiving City approval for the equipment, Iteris will immediately proceed with placing orders through vendors based on the approved submittals. Iteris will secure invoices for all ordered equipment, track estimated
12 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT UNDERSTANDING AND APPROACH
shipping times, and monitor shipment tracking. This information will be reviewed against the construction schedule and the City will be informed of potential schedule adjustments needed based on anticipated equipment arrival times.
Equipment Testing
Once the equipment has been procured and is in Iteris’ possession, Iteris will review the installation manuals provided and testing information to identify any potential additional testing that may be required. If necessary, Iteris will conduct additional product testing or engage a third-party testing service to verify the equipment is fully functional and meets the product specifications. This thorough testing procedure will reduce the likelihood of errors and defects occurring in the field, thereby minimizing the need for equipment replacement and preventing delays in the construction schedule.
Deliverables
• Product Submittals
• Product Testing Information
3. CONSTRUCTION
Iteris offers specialized installation services for traffic signal cabinets, service cabinets, video detection cameras, CCTV systems, APS systems, conduits, pull boxes, and conductors. We utilize the latest technology and equipment to ensure high-quality installations. Our skilled technicians are trained in best practices for installation and integration, allowing us to consistently deliver reliable systems that meet the specific needs of each project. While Iteris is known for being a “One-Stop-Shop,” for this project we will be focused on the following construction tasks:
• Traffic Signal Cabinet and foundation
Installation
• Service Cabinet Installation
• Video Detection Cameras and Supporting
Cabling
• CCTV Cameras and Supporting Cabling
• APS System/Push Button Installation
• Conduit Installation
• Pull Box Installation
• Conductor Installation
• Fiber Optic cabling, splicing, terminations,
testing
Our experienced team is dedicated to successful project delivery while keeping safety in focus as our top priority.
We adhere to all safety regulations and guidelines during installation to protect our team and the public. Our commitment to quality ensures that all installations are performed to the highest standards, providing long -lasting and dependable traffic management solutions.
Deliverables
• Expertly installed devices, equipment and supporting infrastructure
4. CONFIGURATION, INTEGRATION & DOCUMENTATION OF INSTALLED DEVICES
Upon receipt and verification of the ordered equipment and verified the equipment has been tested to meet its requirements, Iteris will begin configuration of the project equipment, including the following:
• Traffic signal controller hardware and firmware
• Communication systems, including field Ethernet switches
13 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROJECT UNDERSTANDING AND APPROACH
• CCTV cameras and Video Detection Systems (VDS)
• Traffic Management Center (TMC) upgrades, including hub switches, SFPs, and firewalls
Iteris’ configuration process will include setting up initial login information, updating IP addresses to align with the City’s network, and performing any other necessary tasks required to prepare the devices for operation. This configuration will be completed prior to field installation to minimize the likelihood of issues occurring during deployment.
Following configuration, Iteris will proceed with installation of the equipment in the field and TMC, including removing unnecessary equipment, furnishing, and installing all required cables and connectors, and securing equipment within the cabinets or TMC. The newly installed field and TMC equipment will be tested to ensure full communication with the City’s network and complete restoration of previous functionality. Connectivity between field equipment and the TMC will be tested and verified to meet the required bandwidth and latency needs. Iteris will collaborate with the equipment vendors and manufacturers to secure and activate the necessary licenses, ensuring the equipment is fully operational upon deployment. Iteris’ comprehensive configuration and integration process guarantees that the operations and connectivity of installed devices meets the City’s requirements.
If needed, Iteris’ in-house experts will expand upon or create new Virtual Local Area Network (VLANs) for the communications network. Iteris will coordinate with the City’s traffic and IT department to keep all stakeholders informed of the proposed solutions. Iteris’ networking experts will also be able to evaluate the communication topology and network schema to ensure optimal designs for the current project and future citywide operations.
To support the City in maintenance and recordkeeping efforts, Iteris will document configuration settings (including login information and IP addresses) for all project equipment and provide this information in a Configuration Settings Spreadsheet. Additionally, Iteris will provide the City with a Device Documentation Package, including relevant user manuals and warranties. These detailed records will assist the City maintaining and operating the equipment.
Deliverables
• Configuration Settings Spreadsheet
• Device Documentation Package
14 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. – VALLEY VIEW ST. TSSP
PROPOSED PROJECT SCHEDULE
Iteris has provided the following proposed project schedule as shown in Figure 2.
Figure 2 – Proposed Project Schedule
15 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA – VALLEY VIEW ST. TSSP APPENDIX : CONTRACTOR LICENSE | INSURANCE COVERAGE | RESUMES
Contractor License
• C10 California Contractor License
Insurance Coverage
• Certificate of Liability Insurance
• Evidence of Construction Insurance
Resumes
ITERIS, INC.
• Brian Akerley, MELE
• Joshua McNeill, PE, TE, PTOE
• Peyvand Hajian
• Kent Spurr
• Alex Ingoglia
• Alex Morales, IMSA
• Joshua Lemestre, IMSA
• Alex Gallardo, IMSA
• Andrew Freeman, PE, PTOE
• Raymond Liang
ANDERSON HOWARD
• Juan Ramos
16 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA – VALLEY VIEW ST. TSSP APPENDIX : CONTRACTOR LICENSE | INSURANCE COVERAGE | RESUMES
17 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA – VALLEY VIEW ST. TSSP APPENDIX : CONTRACTOR LICENSE | INSURANCE COVERAGE | RESUMES
18 | Iteris, Inc.
SYSTEM CONSTRUCTION OF THE BOLSA CHICA – VALLEY VIEW ST. TSSP APPENDIX : CONTRACTOR LICENSE | INSURANCE COVERAGE | RESUMES
Moving smarter, together.
Mr. Akerley serves as a Vice President for Iteris’ Consulting Solutions division and has been with the firm since 2022. He has over 23 years of comprehensive experience as a results-focused professional with extensive experience in electrical engineering, electrical contracting, telecommunications, and Intelligent Transportation Systems (ITS) installation and maintenance. His performance track record is characterized by successful planning, implementation, and execution skills, as well as an effective participatory management style that reflects strong coaching, delegation, and leadership skills, as well as an ability to establish clear and measurable goals. Brian has been responsible for the oversight and delivery of many high-level projects for
Municipalities, County and State DOTs, and transit agencies. In addition to his leadership, and project delivery skills, Brian is the licensing Qualifier for Iteris and is responsible for acquiring the state licensing necessary to lay the groundwork for business development nationally.
PROJECT EXPERIENCE
ITS CONSTRUCTION & INTEGRATION
Loop Detector Repair and Replacement - Caltrans District 7, Los Angeles, CA
Mr. Akerley served as Program Control Specialist as the contract champion and technical advisor for this $22M, three-year contract.
The project began with the initial intent of replacing four thousand loops, two million feet of DLC cable, four hundred 334 cabinets, and an abundance of network equipment throughout LA County. A change in agency direction shifted the scope of work to include the installation of over four hundred miles of fiber optic cable and associated splice enclosures, fiber distribution units (FDU), Ethernet and Aggregation Switches, and power conditioners. The project was a tremendous success and resulted in increased network uptime, added device visibility/functionality, added corridor communications, and provided an additional level of network redundancy. Despite the many challenges a project of this magnitude presents, the project began in January of 2019 and was delivered in December of 2021 on-time and within budget.
EDUCATION
BA, Business and Leadership Studies,
California State Polytechnic University,
Humboldt, CA
YEARS OF EXPERIENCE
With Iteris: 2 Total: 23
REGISTRATIONS
Electrical Contractor Licensing
AL #05322, 2022
AZ #299909, 2015-Present
CA #1096882, 2017-Present
FL #EC13006423, 2014-Present
GA #EN216554, 2014-Present
HI #CT-37570, 2020-Present
MD #12969, 2014-Present
NC #30582-U, 2014-Present
NM #410767, 2014-Present
OH #47630, 2015-Present
SC #CLM.116661, 2014-Present
TX #30536, 2014-Present
VA #2705184094, 2014-Present
WA #EC ITERII*782ML, 2015-Present
WV #M566864RENC0814, 2014-Present
CORE DISCIPLINES
Electrical Contracting & Engineering
Traffic Engineering & Operations
ITS Device maintenance
Quality Control Specialist
AFFILIATIONS
Associated Builders and Contractors (ABC)
Trustee
IMSA
BRIAN
AKERLEY, MELE
PROJECT MANAGER
BRIAN AKERLEY, MELE
PROJECT MANAGER
Moving smarter, together.
BACKHAUL COMMUNICATIONS NETWORK
Express Lanes Backhaul Communications
Network, BAIFA – San Francisco, CA
Mr. Akerley served as Program Control Specialist as
the contract champion and technical advisor for this
$5.5M project. The purpose of the project was to
provide an effective, robust, and secure backhaul
network that could support the needs of the new
express lane tolling system being implemented along
I-680 in Northern California. Highlights of the work
involved include proofing and installation of
underground conduit infrastructure, install forty-
four miles of 144-strand fiber optic cable, and
provide, install, and configure the network
equipment necessary for the completion of a fully
functional backhaul network. The project began in
November of 2015 and was completed in August of
2019. The O&M support continued for another two
years and ended in August of 2021.
TRAFFIC SIGNAL MAINTENANCE
Traffic-Related Electrical Devices Maintenance
Program - City of Glendale, CA
Mr. Akerley served as Program Control Specialist and
technical advisor to perform maintenance of all
traffic-related electrical devices including 235 traffic signals, 44 CCTV Camera locations, 13 hard-wired
flashing beacon systems, 41 solar-powered wireless
flashing beacon systems, one (1) in-roadway warning
light systems, and miscellaneous electrical
maintenance services for the City of Glendale. Mr.
Akerley was responsible for having his team
available with readily accessible required vehicles,
tools, equipment, apparatus, facilities, labor, and
material to perform all work necessary to maintain
the traffic related electrical devices in compliance
with latest State of California Department of
Transportation (Caltrans) standards and
specifications, as well as the latest City of Glendale
Specifications. The team provided and maintained
emergency service response twenty-four (24) hours
a day, seven (7) days per week basis, including all
holidays. This contract was $1 million annually. This
project begin 2018 and was completed in 2022.
Traffic Signal Maintenance - City of Santa Ana,
CA
Mr. Akerley served as program control specialist
technical advisor for dozens of traffic signal
maintenance projects during his time at Econolite
Systems, but one that stands out with high-level
visibility and achievement is the signal maintenance
contract with the City of Santa Ana. Mr. Akerley
assumed responsibility for Santa Ana’s multi-year
Traffic Signal Maintenance contract under Econolite
Systems, Inc. in 2015. With over three hundred
signalized intersections, the city of Santa Ana has an
abundance of ITS devices and assets to maintain so
that providing optimal levels of throughput and
safety for the City’s motoring public is realized daily.
The purpose of the project is to provide exceptional
levels of preventative and reactionary maintenance
to ensure the City’s traffic signal system is
operational at the highest level possible. Mr. Akerley
assumed oversight responsibility for the City’s Signal
Maintenance contract in 2015 and managed its
performance until 2022, when Mr. Akerley departed
Econolite Systems, Inc. to join Iteris. This project
begin 2015 and was completed in 2022.
TRANSPORTATION SYSTEMS OPERATIONS
& MAINTENANCE
Caltrans District 11 & 12 TOSNET - San Diego
& Orange County, CA
Mr. Akerley served in Program Control Specialist and
technical advisor for the Caltrans On-Call
Maintenance and Repair of the Transportation
Management Field Systems and Communications
(TOSNET) project. This contract was a critical
program for Caltrans as our technical field staff were
responsible for troubleshooting, repairing, and
supporting all of the communications infrastructure
within Caltrans districts 11 & 12. Typical tasks
included the troubleshooting, repair, and/or
replacement of ethernet switches, modems, twisted
pair cables, fiber optic cables, VDS devices, CCTV
devices, and the configuration and integration of
new ITS equipment and software. Mr. Akerley
assumed oversight responsibility for this contract in
2015 and oversaw its performance until 2022 when
Mr. Akerley departed Econolite Systems, Inc. to join
Iteris. This project begin 2018 and was completed in
2022.
Moving smarter, together.
Mr. McNeill serves as a Principal Engineer for Iteris’ Mobility Consulting Solutions and has been with the firm since 2017. He is a registered professional Civil Engineer and Traffic Engineer with 16 years of experience working in the fields of transportation engineering and planning. Mr. McNeill has delivered PS&E packages for traffic signal system upgrades, fiber optic communication networks, freeway traffic management systems, as well as other traditional traffic handling, signing and pavement delineation plans.
He has also managed signal timing development and
implementation for several agencies. He provides solutions to traffic problems while effectively managing budgets and scope of work.
Mr. McNeill is committed to providing sustainable transportation design with an emphasis on systems engineering analysis and utilization of emerging technologies.
PROJECT EXPERIENCE
OCTA First Street and Bolsa Avenue Regional Traffic Signal Synchronization Project (RTSSP), Contract Task Order (CTO) (Agreement C-9-1812), Orange County Transportation
Authority (OCTA) – Orange County, CA
Mr. McNeill is serving as Project Manager for the First Street/Bolsa Avenue Regional Traffic Signal Synchronization Project, which entails traffic signal improvements and synchronization. The project includes various traffic signal improvements and the retiming of 55 signalized intersections along First Street/Bolsa Avenue from Bolsa Chica Street in the City of Huntington Beach to Newport Avenue in the City of Tustin and five (5) signalized intersections offset from the corridor in the City of Santa Ana. Iteris designed and is managing the installation of traffic signal equipment, communication network equipment, and fiber optic cable for five (5) agencies along the corridor. The team also coordinated the selection and installation of a new video management system for the City of Westminster TMC.
Iteris collected traffic count data to create Synchro models that will help optimize and synchronize the signal timing along First Street/Bolsa Avenue. Also included in the scope of the project, Iteris will develop and implement new timing plans for the AM, midday, PM, and Weekend peak periods. This project began in August of 2022 and is expected to be completed in June of 2026.
EDUCATION
MS, Civil Engineering (Transportation
Systems), University of California, Irvine,
2012
BS, Civil Engineering, University of
California, Irvine, 2008
YEARS OF EXPERIENCE
With Iteris: 7 Total: 16
REGISTRATIONS
Civil Engineer (PE)
CA #79151, 2011
UT #9480116-2202, 2015
Traffic Engineer (TE)
CA #2792, 2015
Professional Traffic Operations Engineer
(PTOE)
#4870, 2020
League Cycling Instructor (LCI)
#6087, 2018
CORE DISCIPLINES
Traffic Engineering
Transportation Planning
ITS Planning and Design
AFFILIATIONS
Institute of Transportation Engineers
(ITE)
Orange County Traffic Engineering
Council (OCTEC)
JOSHUA
MCNEILL, PE, TE, PTOE
QA/QC & SENIOR ADVISOR
JOSHUA MCNEILL, PE, TE, PTOE
QA/QC & SENIOR ADVISOR
Moving smarter, together.
I-405 Design-Build Improvement Project,
Orange County Transportation Authority (OCTA)
– Orange County, CA
Mr. McNeill is serving as Electronic Toll and Traffic
Management (ETTM) System Infrastructure Design
Lead for Iteris, acting as a subconsultant of a
multidisciplinary design and construction team, on
this $1.2 billion dollar design build project in Orange County California. The project will improve 16 miles
of the I-405 between the SR-73 freeway in Costa
Mesa and the I-605 near the Los Angeles County line.
The project includes adding one regular lane in each
direction from Euclid Street to I-605, making
improvements to freeway entrances, exits and
bridges, and will also implement Express Lanes that
expands the existing HOV lane from one lane to two
lanes in each direction from SR-73 to I-605. Iteris is
responsible for the design of the Caltrans ITS field
infrastructure, temporary ITS field infrastructure
supporting maintenance of traffic during
construction, toll system infrastructure and
coordination, street lighting, agency traffic signal
improvements along the corridor and development
of the project Traffic Management Plan. The project
began in January 2017 and construction was
completed October 2023.
OCTA Main Street Regional Traffic Signal
Synchronization Projects (RTSSP), Orange
County Transportation Authority (OCTA) –
Orange County, CA
Mr. McNeill served as the Signal Timing Lead
under this project agreement, which provided
services that upgraded traffic signal electronics
and communications equipment, and optimize
signal timing along Main Street, a major north-
south corridor that comprises 67 major signalized
intersections. As part of the project, Iteris’
Intersection-as-a-Service™ end-to-end solution
offering delivered proactive monitoring of traffic
signal operations at all project intersections. The
primary goal of this project was to deploy new
Intelligent Transportation System (ITS) equipment
and communication infrastructure to support the
management of the cities’ transportation
network, implement optimized coordination
timing plans to achieve optimal traffic flow, and
improve safety for all road users, including
vehicles, buses, bicycles, and pedestrians. The
project began April 2019 and the O&M phase was
completed in June 2023.
Regional Traffic Signal Synchronization Program
(RTSSP) Project for Tustin Avenue - Rose Drive
– City of Orange, CA
Mr. McNeill serves as Signal Timing Lead on this
project. Under the project agreement, Iteris will
make infrastructure upgrades, signal coordination
and timing improvements, develop signal timing
plans for all signalized intersections along the
corridor, provide vehicle turning movement
counts and perform before-and-after corridor
analysis along the Tustin Avenue/Rose Drive
corridor from First Street in the City of Tustin to
Wabash Avenue in the City of Yorba Linda. The
project area comprises 54 signalized intersections
spanning six cities – Tustin, Santa Ana, Anaheim,
Orange, Placentia, and Yorba Linda – as well as
key highway on/off ramps under Caltrans, in
Orange County, California. The project started in
September 2021 and is ongoing. Construction
started in Summer 2023.
A&E On-Call Roadway Design and Project
Development and Construction Services
(Caltrans D12) – Orange County, CA
Iteris is part of the TranSystems team on this
Caltrans D12 On-Call contract to provide
consultation, research, professional and technical
services required for Roadway Design and related
Project Development and Construction Services,
including, but not limited to, field sampling,
construction materials testing, analysis, reports,
plant inspection and work related to testing
equipment calibration, on an “as-needed” basis to
support the Caltrans D12, from Project Report phase
to construction phase completion of three State
Route (SR) 91 Multi-Asset Projects, EA 12-0R312,
arrive. The Iteris team helped the City to turn on a
traffic signal before the school started. The traffic
signal installation was the result of a left turn
phasing analysis at the same intersection based on
existing guidelines as provided in the California
Manual on Uniform Traffic Control Devices
(CAMUTCD, Highway Capacity Manual (HCM) and
Federal Highway Signal Timing Manual. The project
started November 2016 and construction was
completed in December 2018.
Iteris, Inc. | 1
Ms. Hajian serves as a Senior Engineer for Iteris’ Mobility Consulting Solutions and has been with the firm since 2024. Ms. Hajian has 10 years of experience working in the field of Transportation Infrastructure. Mrs. Hajian is a resourceful and analytical transportation engineer with experience in transit, intelligent transportation systems, and transportation infrastructure projects.
Ms. Hajian has demonstrated the ability to design, permit, construct, and develop scope for complex large-scale, multimillion- dollar undertakings.
PRIOR PROJECT EXPERIENCE
Riverside County Transportation Authority (RCTC), Express Lane Connector (ELC), County of Riverside, CA
Ms. Hajian served as the Tolling Manager that oversaw all aspects of construction, which included electrical work, job site survey, coordination with internal quality inspectors and Caltrans representatives.
• Orchestrated the comprehensive management of Tolling
turnover packages, roadway barriers, and landscaping projects, seamlessly coordinating efforts among three subcontractors to ensure on-time delivery without compromising quality.
• Demonstrated adept management skills, overseeing
subcontractors with a commitment to no delay in project timelines, and resolving issues promptly to maintain project schedules. • Proactively communicated project updates, addressed
concerns, and ensured alignment with objectives through clear and concise letters to subcontractors and the agency.
• Applied strategic planning and problem-solving skills to overcome challenges, consistently optimizing project efficiency to achieve on-time delivery of all scope of work.
• Collaborated closely with internal teams to streamline processes, enhancing overall project coordination, and contributing to a track record of on-time, high-quality project outcomes. • Facilitated meetings with the owner and subcontractor on weekly basis.
• . Developed clear and persuasive position papers, supporting organizational claims on various issues.
• Collaborated with subject matter experts and stakeholders to gather insights and refine arguments
EDUCATION
MS, Civil Engineering, California State
University, Fresno, CA, 2016
BS, Civil Engineering, Razi University of
Kermanshah, Iran, 2010
YEARS OF EXPERIENCE
With Iteris: <1 Total: 10
CORE DISCIPLINES
Construction and Program Management
(PM/CM)
Toll Management
Transportation Planning
Traffic Signal Installations and Detection
Integrator
Traffic Signal Networking
Advanced Transportation Management
Systems (ATMS)
Adaptive Traffic Signals
AFFILIATIONS
Women in Transportation Seminar (WTS)
Transportation Research Board (TRB)
Advancing Women in Transportation
(WTS)
Associate Member of American Society of
Civil Engineers (ASCE)
Construction Management Association of
America (CMAA)
PEYVAND
HAJIAN
DEPUTY PROJECT MANAGER
PEYVAND HAJIAN
DEPUTY PROJECT MANAGER
Iteris, Inc. | 2
Multi-model Transportation Project in Palm
Desert, Coachella Valley Association of
Government (CVAG),
Ms. Hajian served as a Construction Manager and
oversaw all aspects of design constructability, which
included environmental issues, job site survey,
coordination with other local projects and agencies,
and cost estimates.
• Developed and provided daily site inspection
reports to verify compliance with approved
plans, specifications, and codes, including
asphalt concrete pavement, clear and grubbing,
concrete sidewalk, class II aggregate base, JPCP,
slurry seal, and solar LED lights for the CVLINK
project.
• Represented Coachella Valley Association of
Government (CVAG) for the CVLINK project,
which promotes healthy, alternative
transportation that aligns with the goals and
regulations set forth in California’s Global
Warming Solutions Act.
• Administered contracts daily and assisted
resident engineer with bid analysis, pre-
construction meetings, and award coordinating
activities.
• Monitored and documented contractor labor,
materials, and equipment usage for field
changes, and time and material work for project
billing.
• Estimated 70% of cost, measured and recorded
pay quantities based on California Department
of Transportation (Caltrans) specification for Pay
app, and utilized an invoice to ensure
contractors accurate monthly payment.
• Reviewed submittals and requests for
information (RFIs) based on Caltrans
specifications.
• Executed safety protocols and adhered to
regulations and policies based on Caltrans
requirements, facilitated safety meetings every
10 days, and performed safety audits.
PROJECT ENGINEERING
Ms. Hajian provided reviews of the existing
hydrology and hydraulic systems and evaluated
improvements needed for the street widening to
alleviate street ponding. All suggestions for
improvements complied with the city’s Bureau of
Engineering (BOE) and the Los Angeles County Flood
Control District (LACFCD). Reviewed work of 2
employees.
Selected Project Highlights
• Reseda Boulevard Complete Street Project, City
of Los Angeles, Los Angeles, CA
• Engineered the quality control (QC) for the
utility plans and utility matrices.
• Alameda Street Widening Hydrology and
Hydraulic Studies, City of Los Angeles, Los
Angeles, CA
• Planned QC/quality assurance (QA) for the
project submittals, involving hydrology and
hydraulic reports, drainage plans, and related
permitting.
• Dudley, Kinney St., and Grand Ave –
Revitalization and Street Improvement, City of
Los Angeles, Los Angeles, CA
• Executed design studies and analysis of ADA
compliant curb ramps and wrote report.
• Performed quality review with emphasis on ADA
compliance.
• Potrero Canyon – Cost Estimate, City of Los
Angeles, Los Angeles, CA
• Estimated construction cost and quantity take
offs for the irrigation system
CIVIL DESIGNER
Ms. Hajian supported the High-Speed Rail project,
reviewed work of 2 employees, oversaw IBM DOORS
and managed more than 5000 contract
requirements and developed cost estimate template
for Transportation Business Line (US West), which
realized easier and faster cost estimates for the LA
Metro proposals.
Quality Assurance Task Manager, High-Speed
Rail Project (CP2-3)/Design Build Contract
• Directed QA, verification, and validation (V&V)
activities as part of the project and contract
management consulting services contract.
• Oversaw the design and construction
specification.
• Managed 500+ submittals, RFIs, and change
orders. Maintained contract documents and a
complete set of procedure records for the
project. Efficiently processed all submittals,
documents, and work logs.
• Led QA audit ensuring compliance with ISO
standards.
Moving smarter, together.
Mr. Spurr serves as a Technical Field Support IV for Iteris’ Consulting Solutions division and has been with the firm since August 2022. He has over 21 years of experience working in the field of ITS electrical installation, operations, and maintenance.
PROJECT EXPERIENCE
OCTA First Street and Bolsa Avenue Regional Traffic Signal Synchronization Project (RTSSP), Orange County
Transportation Authority (OCTA) – Orange County, CA
Mr. Spurr serves as the Technical Field Manager on this project for OCTA. Iteris is assisting OCTA with multi-jurisdictional signal coordination for a 13.1-mile stretch of First Street/Bolsa Avenue.
The project includes various traffic signal improvements and the retiming of 55 signalized intersections along First Street/Bolsa Avenue from Bolsa Chica Street in the City of Huntington Beach to Newport Avenue in the City of Tustin and five (5) signalized intersections offset from the corridor in the City of Santa Ana. Iteris designed and is managing the installation of traffic signal equipment, communication network equipment, and fiber optic cable for five (5) agencies along the corridor. The project began in August 2021 and is ongoing.
Alternative Signal Communication Demonstration Pilot,
Orange County Transportation Authority (OCTA) – Orange
County, CA
Mr. Spurr serves as the Technical Field Manager on this project for OCTA. This project will provide traffic signal communication improvements throughout various city’s traffic signal networks within Orange County. The cities are getting upgrades to their existing communication infrastructure at intersections that are either offline, have outdated equipment, and/or seeking alternatives solutions to ensure reliability, enhanced security, and scalability for a robust network that will be viable for the next 10 to 15 years. The primary goal of this project is to analyze and test connectivity at locations where there are existing interconnect (copper, fiber, and wireless) systems, so that appropriate design measures can be applied to deploy new ethernet switches, ethernet cards, wireless radios, and/or cell modems to support the management of each city’s traffic network. This project began in June 2022 and is ongoing.
YEARS OF EXPERIENCE
With Iteris: 2 Total: 21
REGISTRATIONS
IMSA Traffic Signal Field Technician level
2 Certification #BE_91918
FOA Fiber Optic Certification #4090055
CFOT
CSLB C-10 Electrical Contractors License
#1081585
CORE DISCIPLINES
Traffic Signal Planning
Traffic Impact Analysis
Construction Support/Inspection
Traffic Signal System Upgrade
Traffic Signal Priority (TSP)
Fiber Optic Installation & Testing
KENT SPURR
TASK LEAD - CONSTRUCTION
KENT SPURR
TACK LEAD - CONSTRUCTION
Moving smarter, together.
Professional Engineering Services for the
Citywide Bus Signal Priority Project – City of
Downey, CA
Mr. Spurr serves as the Technical Field Manager for
this project. Iteris is responsible for evaluating and
implementing bus signal priority system for 92
intersections, along six major corridors,
development of plans, specifications, and
construction cost estimate for 2.2-mile gap closures
in the city’s fiber-optic traffic signal communications network, to enable the connection of additional
signalized intersections to the City’s Traffic
Management Center (TMC), and recommendations
of bus signal priority systems to be integrated onto
Downey LINK automatic vehicle location (AVL)
system. This project began in February 2022 and is
ongoing.
Countywide Signal Priority (CSP) Upgrade and
Expansion Next Gen – Los Angeles, CA
Mr. Spurr serves as the Technical Field Manager for
this project. Iteris is responsible for evaluating and
implementing bus signal priority system for several
multi-jurisdictional Metro local corridors as part of
Metro’s Next Gen Bus Service and existing
Countywide Signal Priority corridors. Iteris is
responsible for providing engineering design
services, intersection system hardware and
installation services, jurisdictional coordination
support expansion and upgrade of the CSP System
for 12- local service corridors. This project began in
October 2021 and is ongoing.
PREVIOUS EXPERIENCE
Prime Electrical Maintenance Service LLC,
Yucaipa, CA
Electrical Contractor/Owner, September 2021 –
August 2022
Duties:
Provide traffic signal field services for City Agencies, Contractors, and Vendors, such as:
• NEMA/332 Cabinet installations and
modifications
• Video Detection installations (ITERIS &
Gridsmart)
• Flash calls, cabinet, or video troubleshooting
• Turn-on support
• UPS installation and troubleshooting
Create or revise existing traffic signal cabinet and
video specifications for City Agencies.
Review new traffic signal plans or intersection
remodels for City Agencies.
Perform surveys at the intersection such as,
controller cabinet type (TS1, TS2-2, 33X or ATC),
video or in-ground detection, communication type
(fiber, twisted pair, Cat6), controller type (170, 2070 and NEMA).
Installation of residential/commercial load centers
and sub-panels.
Light commercial and residential building re-wire.
Underground utility installation.
Street light installation.
Commercial and residential electrical inspections for
fire damaged structures.
Underground electrical locating services.
City of Redlands, Redlands, CA
Traffic Signal Technician, June 2019 – September
2021
Duties:
• Oversee signal operations and maintenance for
72 intersections Citywide.
• Perform monthly PM’s for each signalized
intersection within the City.
• Repair or replace damaged 1A poles involved in
traffic collisions.
• Install, troubleshoot, and program video
detection (Iteris, Gridsmart).
• Create, modify, or maintain specifications used
by the City of Redlands for NEMA TS2-1
cabinets; controller unit, UPS system and video
detection system.
• Perform 80 hour burn-in testing for all newly
acquired traffic signal cabinets, components,
and plug-ins.
• Maintain accurate inventory records of all traffic
signal equipment such as; LED’s, Ped push
button assemblies, 1A assemblies, etc.
• Meet with Vendors to discuss upcoming
projects, product upgrades or replacement
orders.
• Perform USA locating services intended for
traffic signals and streetlights.
• Troubleshoot flash conditions for NEMA, 332
and ATC cabinets.
• Manage contractors during new traffic signal
installations or modifications.
Moving smarter, together.
Mr. Ingoglia serves as Engineer of Iteris’ Mobility Consulting Solutions division and has been with the firm since April 2017. Mr.
Ingoglia has over 6 years of experience in the fields of Traffic Signal Operations, Signal Timing & Coordination, Intelligent Transportation Systems (ITS) planning, design, and integration, Traffic Engineering & Design, and Municipal Traffic Engineering. His project experience includes preparing and implementing signal timing and
synchronization, operational analysis, installing ITS and communication equipment, preparing signing and striping plans as well as reviewing traffic studies and traffic control plans. Mr.
Ingoglia has knowledge in signal timing, Intelligent Transportation Systems (ITS), electrical systems, and integration. Mr. Ingoglia is proficient in the use of design and traffic analysis software such as AutoCAD, MicroStation, and Synchro.
PROJECT EXPERIENCE
TRAFFIC ENGINEERING & OPERATIONS
Regional Traffic Signal Synchronization Program (RTSSP) Project for Tustin Avenue - Rose Drive – City of Orange, CA Mr. Ingoglia serves as a Project Engineer on this project assisting with signal timing efforts. Under the project agreement, Iteris will make infrastructure upgrades, signal coordination and timing improvements, develop signal timing plans for all signalized intersections along the corridor, provide vehicle turning movement counts and perform before-and-after corridor analysis along the Tustin Avenue/Rose Drive corridor from First Street in the City of Tustin to Wabash Avenue in the City of Yorba Linda. The project area comprises 54 signalized intersections spanning six cities – Tustin, Santa Ana, Anaheim, Orange, Placentia, and Yorba Linda – as well as key highway on/off ramps under Caltrans, in Orange County, California. Mr. Ingoglia is developing the synchro model and proposed timing updates to the Tustin-Rose corridor. The project started in September 2021. Construction is slated to start in Summer 2023 and scheduled to be completed December 2024.
EDUCATION
BS, Civil Engineering, , California State
Polytechnic University, Pomona, 2017
YEARS OF EXPERIENCE
With Iteris: 3 Total: 6
REGISTRATIONS
Engineer-In-Training (EIT)
CA #160812, 2017
CORE DISCIPLINES
Traffic Signal Operations
Signal Timing & Coordination
ITS Planning, Design, & Integration
Traffic Engineering & Design
Municipal Traffic Engineering
AFFILIATIONS
Institute of Transportation Engineers
(ITE)
Orange County Traffic Engineering
Council (OCTEC)
ALEX
INGOGLIA
TASK LEAD – SWITCH INTEGRATION
ALEX INGOGLIA
TASK LEAD – SWITCH INTEGRATION
Moving smarter, together.
Euclid Street Corridor Project Regional Traffic
Signal Synchronization Program (RTSSP) – City
of La Habra, CA
Mr. Ingoglia serves as a Project Engineer on this
signal synchronization project for City of La Habra.
Project includes the synchronization of sixty-seven
(67) traffic signals and sixty-nine (69) offset traffic signals throughout the Cities of La Habra, Fullerton,
Anaheim, Garden Grove, Santa Ana, and Fountain
Valley along Euclid Street. Iteris is providing
communication system analysis for the City of
Fullerton and the City of Santa Ana through this
project. Iteris will conduct all engineering,
construction management, inspection, and
administrative tasks necessary to complete the
project. After the construction and implementation
phase of the project, Iteris will provide operations,
and maintenance services for three years. The
project began in March 2023 and is expected to be
completed March 2028.
Traffic and Intelligent Transportation Systems
Engineering Services, Katella Avenue, Orange
County Transportation Authority (OCTA) –
Orange County, CA
Mr. Ingoglia serves as Project Engineer on this
Project and participated in the timing
implementation and finetuning in the field or
through TMC central program for each city.
Additionally, Mr. Ingoglia installed edge switches at
project intersections to provide communication to
the traffic controllers. As part of the project, Iteris’ Intersection-as-a-Service™ end-to-end solution
offering will deliver proactive monitoring of traffic
signal operations at all project intersections. The
primary goal of this project is to deploy new
Intelligent Transportation System (ITS) equipment
and communication infrastructure to support the
management of the cities’ transportation network,
implement optimized coordination timing plans to
achieve optimal traffic flow, and improve safety for
all road users, including vehicles, buses, bicycles, and pedestrians. The project began in February 2020 and
is scheduled to be completed June 2023.
Culver Drive/Bonita Canyon Drive/Ford Road
Regional Traffic Signal Synchronization Program
(RTSSP) Project – City of Irvine, CA
Mr. Ingoglia serves as Project Engineer on this traffic signal synchronization project and assisted with the
development of the optimized synchronization
timing and lead the implementation of the new
timing. Mr. Ingoglia also assisted with preparing of
the before study. Project started in April 2019 and
was completed in April 2023.
Lake Forest Traffic Signal Management On-call
Services – City of Lake Forest, CA
Mr. Ingoglia is serving as Project Engineer and
monitors the operations and communication of all
traffic signals within the City of Lake Forest.
Additionally, Mr. Ingoglia investigates City Staff and
resident concerns about signal timing and makes
timing adjustments due to construction activities.
Project started in 2021 and is scheduled to be
completed in June 2025.
Irvine Center Drive – Edinger Ave Regional
Traffic Signal Synchronization Project O&M
(RTSSP), Orange County Transportation
Authority (OCTA) – Orange County, CA
Mr. Ingoglia is serving as Project Manager on the
O&M of the Irvine Center Dr –– Edinger corridor
through the Cities of Irvine and Tustin. The project
began in Dec 2020. Mr. Ingoglia’s involvement on
the project began in January 2022 and was
completed in December 2022.
Design and Construction Inspection Services for
Traffic Signal Infrastructure Upgrades: Phase II
& III – City of Diamond Bar, CA
Mr. Ingoglia is serving as Project Engineer for the
City’s replacement of 4.3 miles of twisted-pair
copper traffic signal interconnect with 96-strand
Single Mode Fiber-Optic (SMFO) cables along
Diamond Bar Blvd between Grand Ave and Highland
Valley Rd; and Golden Springs Dr. between Diamond
Bar Blvd and High Knob Rd. The PS&E package will
include intersection re-wire design plans, signal
inventory, controller upgrades, detail drawings for
fiber assignments and communications pull boxes,
splice boxes and conduits details. Iteris will also
provide ongoing support during the construction
phase of the project. Phase II project began in May
2016 and was completed in December 2017. Phase
III began in May 2017 and is expected to be
completed in December 2018.
Moving smarter, together.
Mr. Morales serves as a Journeymen Electrician for Iteris’ Consulting Solutions division and has been with the firm since January of 2024.
He has over 8 years of experience working in the fields of ITS electrical installation, operations, and maintenance.
PROJECT EXPERIENCE
ITS BUILDS
City of Huntington Beach Valley View/Bolsa Chica Regional Traffic Signal Synchronization Program (RTSSP)- City of Huntington Beach, CA
Mr. Morales serves as Journeyman Electrician on this RTSSP project for the city of Huntington Beach. Iteris was selected to provide ITS design, bid support, construction support, traffic signal synchronization services, and maintenance services to 22 signals along Valley View Street/Bolsa Chica Street, a major north-south arterial. The project covers approximately 5.35 miles of roadway from Chapman Avenue to Warner Avenue within the Cities of Huntington Beach, Westminster, and Garden Grove. ITS equipment improvements include fiber-optic communications, CCTV, VDS, and traffic signal controllers, cabinets, and foundations. As part of this project, improvement plans and specifications will be separately prepared for each City and each City will be issuing separate construction contracts; Iteris will also be responsible for developing signal synchronization plans that are compatible with the recently synchronized Warner Avenue and Edinger Avenue corridors along with major arterials including Westminster Boulevard, Garden Grove Boulevard, and Chapman Avenue. The project began in October 2023 and is ongoing, scheduled to end in October 2026.
Professional Engineering Services for the Citywide Bus Signal Priority Project – City of Downey, CA
Mr. Morales served as a Journeyman Electrician for evaluating and implementing bus signal priority systems for 92 intersections, along six major corridors, development of plans, specifications, and construction cost estimate for 2.2-mile gap closures in the city’s fiber-optic traffic signal communications network.
EDUCATION
IBEW electrician apprenticeship in State
certified Electrician, 2021
Certificate of Completion in
Industrial/Commercial/Residential
Electrician, 2014
YEARS OF EXPERIENCE
With Iteris: <1 Total: 8
REGISTRATIONS
Journeyman Electrician #E169878G
IMSA Work Zone Safety
IMSA Traffic Signal Technician 1
CORE DISCIPLINES
Construction Support/Inspection
Traffic Signal System Upgrade
Traffic Signal Priority (TSP)
Foundation and Pull Box Installation
Underground conduit
Concrete Restoration
ALEXANDER
MORALES
JOURNEYMEN ELECTRICIAN
ALEXANDER MORALES
JOURNEYMEN ELECTRICIAN
Moving smarter, together.
This enabled the connection of additional signalized
intersections to the City’s Traffic Management
Center (TMC), and recommendations of bus signal
priority systems to be integrated onto DowneyLINK
automatic vehicle location (AVL) system. The signal
priority system is based on IEEE 802.11-compliant
wireless bus-to-intersection communications; and
upgraded intersection traffic controller technologies.
In addition, Iteris is responsible preparing the
Preliminary Design Report (PDR) that describes the
overall design of the Wireless Local Area Network
(WLAN) network including any interties that are
required for network monitoring for each corridor.
The WLAN network design will be consistent with
Metro’s Countywide Signal Priority architecture and
system. The project began in October 2023 and was
completed October 2024.
First Street and Bolsa Avenue Regional Traffic
Signal Synchronization Project (RTSSP),
Contract Task Order (CTO) - Orange County
Transportation Authority (OCTA), Orange
County, CA
Mr. Morales serves as Journeyman Electrician on this
multi-jurisdictional signal coordination for a 13.1-
mile stretch of First Street/Bolsa Avenue. The project
includes various traffic signal improvements and the
retiming of 55 signalized intersections along First
Street/Bolsa Avenue from Bolsa Chica Street in the
City of Huntington Beach to Newport Avenue in the
City of Tustin and five (5) signalized intersections
offset from the corridor in the City of Santa Ana.
Iteris designed and is managing the installation of
traffic signal equipment, communication network
equipment, and fiber optic cable for five (5) agencies
along the corridor. The project began in August 2021
and is ongoing, due to end in October 2026.
Alternative Signal Communication
Demonstration Pilot - Orange County
Transportation Authority (OCTA)
Mr. Morales serves as Journeyman Electrician on this
traffic signal communication improvements
throughout various city’s traffic signal networks
within Orange County. There are seven cities that
are getting upgrades to their existing communication
infrastructure at intersections that are either offline, have outdated equipment, and/or seeking
alternatives solutions to ensure reliability, enhanced
security, and scalability for a robust network that will be viable for the next 10 to 15 years. The primary
goal of this project is to analyze and test connectivity at locations where there are existing interconnect
(copper, fiber, and wireless) systems, so that
appropriate design measures can be applied to
deploy new ethernet switches, ethernet cards,
wireless radios, and/or cell modems to support the
management of each city’s traffic network. The
project began in June 2022 and is ongoing due to
end in December 2024.
Regional Traffic Signal Synchronization Program
(RTSSP) Project for Tustin Avenue - Rose Drive
– City of Orange, CA
Mr. Morales serves as Journeyman Electrician on this
infrastructure upgrades, signal coordination and
timing improvements, develop signal timing plans
for key signalized intersections, provide vehicle turn
movement counts and perform before-and-after
corridor analysis along the Tustin Avenue/Rose Drive
corridor from First Street in the City of Tustin to
Wabash Avenue in the City of Yorba Linda. The
project area comprises 54 signalized intersections
spanning six cities – Tustin, Santa Ana, Anaheim,
Orange, Placentia, and Yorba Linda – as well as key
highway on/off ramps under Caltrans, in Orange
County, California. The project started in August
2020 and is ongoing. The project began in
September 2021 and is ongoing, ending May 2025.
Moving smarter, together.
M
r. Lemestre serves as a Traffic Operations Technician for Iteris’ Consulting Solutions division and has been with the firm since October 2023.
PROJECT EXPERIENCE
O
CTA First Street and Bolsa Avenue Regional Traffic Signal Synchronization Project (RTSSP), Orange County
Transportation Authority (OCTA) – Orange County, CA
Mr. Lemestre serves as a Technician on this project for OCTA. Iteris is assisting OCTA with multi-jurisdictional signal coordination for a
13.1-mile stretch of First Street/Bolsa Avenue. The project includes various traffic signal improvements and the retiming of 55 signalized intersections along First Street/Bolsa Avenue from Bolsa Chica Street in the City of Huntington Beach to Newport Avenue in the City of Tustin and five (5) signalized intersections offset from the corridor in the City of Santa Ana. Iteris designed and is managing the installation of traffic signal equipment, communication network equipment, and fiber optic cable for five (5) agencies along the corridor. The project began in August 2021 and is ongoing.
A
lternative Signal Communication Demonstration Pilot,
Orange County Transportation Authority (OCTA) – Orange
County, CA
Mr. Lemestre serves as a Technician on this project for OCTA. This project will provide traffic signal communication improvements throughout various city’s traffic signal networks within Orange County. The cities are getting upgrades to their existing communication infrastructure at intersections that are either offline, have outdated equipment, and/or seeking alternatives solutions to ensure reliability, enhanced security, and scalability for a robust network that will be viable for the next 10 to 15 years. The primary goal of this project is to analyze and test connectivity at locations where there are existing interconnect (copper, fiber, and wireless) systems, so that appropriate design measures can be applied to deploy new ethernet switches, ethernet cards, wireless radios, and/or cell modems to support the management of each city’s traffic network. This project began in June 2022 and is ongoing.
E
DUCATION
Electrical Lineworker Program, Northwest
Lineman College, Meridian, ID, 2023
I
ntroduction to Electricity 1, 2, 3, Los
Angeles Trade Technical College, Los
Angeles, CA, 2022
H
ayden Electrical Craft Helper Course
Los Angeles Trade Technical College, Los
Angeles, CA, 2021
YEARS OF EXPERIENCE
With Iteris: <1 Total: <1
CERTIFICATIONS
IMSA Work Zone Safety
IMSA Traffic Signal Technician 1
Class A CDL w/airbrakes
Climbing Certified
First Aid Certified
CPR Certified
Pole Top Rescue Certified
Aerial Lift Rescue Certified
Enclosed Space Rescue Certified
Chainsaw Safety Certified
Digger Derrick Certified
OSHA 10-Hour ET&D
Rigging
Forklift Certified
JOSHUA
LEMESTRE, IMSA
ELECTRICIAN APPRENTICE
JOSHUA LEMESTRE
TRAFFIC OPERATIONS TECHNICIAN
Moving smarter, together.
Professional Engineering Services for the
Citywide Bus Signal Priority Project – City of
Downey, CA
Mr. Lemestre serves as Technician for this project.
Iteris is responsible for evaluating and implementing
bus signal priority system for 92 intersections, along
six major corridors, development of plans,
specifications, and construction cost estimate for
2.2-mile gap closures in the city’s fiber-optic traffic signal communications network, to enable the
connection of additional signalized intersections to
the City’s Traffic Management Center (TMC), and
recommendations of bus signal priority systems to
be integrated onto DowneyLINK automatic vehicle
location (AVL) system. This project began in October
2023 and was completed in October 2024.
Countywide Signal Priority (CSP) Upgrade and
Expansion Next Gen – Los Angeles, CA
Mr. Lemestre serves as a Technician for this project.
Iteris is responsible for evaluating and implementing
bus signal priority system for several multi-
jurisdictional Metro local corridors as part of Metro’s Next Gen Bus Service and existing Countywide Signal
Priority corridors. Iteris is responsible for providing engineering design services, intersection system
hardware and installation services, jurisdictional
coordination support expansion and upgrade of the
CSP System for 12- local service corridors. This
project began in October 2021 and is ongoing.
Regional Traffic Signal Synchronization Program
(RTSSP) Project for Tustin Avenue - Rose Drive
– City of Orange, CA
Mr. Lemestre serves as a Technician on this
infrastructure upgrades, signal coordination and
timing improvements, develop signal timing plans
for key signalized intersections, provide vehicle turn
movement counts and perform before-and-after
corridor analysis along the Tustin Avenue/Rose Drive
corridor from First Street in the City of Tustin to
Wabash Avenue in the City of Yorba Linda. The
project area comprises 54 signalized intersections
spanning six cities – Tustin, Santa Ana, Anaheim,
Orange, Placentia, and Yorba Linda – as well as key
highway on/off ramps under Caltrans, in Orange
County, California. The project started in August
2020 and is ongoing. The project began in
September 2021 and is ongoing, ending May 2025.
PREVIOUS EXPERIENCE
Greens Metal Cutoff - Santa Fe Springs, CA
Mr. Lemestre served as a Machine Operator. His
duties included:
• Managed orders and machines to complete
orders in a timely fashion.
• Deburred and clean cut parts to specifications of
orders.
• Ran forklift to receive material for future orders.
Josh worked from February 2022 until February
2023.
S&L Contracting - Westminster, CA
Mr. Lemestre served as a General Helper. His duties
included:
• Dug footings for posts and support beams.
• Assist in framing walls and ceilings per job.
• Walked through finished jobs to fix any missed
hardware or fixtures per the specs of order.
Josh worked every summer from 2017 to 2021.
Moving smarter, together.
Mr
. Gallardo serves as an Electrician Apprentice for Iteris’ Consulting Solutions division and has been with the firm since January 2024.
Alex has spent his tenure at Iteris focusing on ITS related Electrical device installation, operations and maintenance. In addition to working as an Electrician Apprentice, Alex also provides technical support for our Sensors division and provides turn-on support for our video detection solutions.
PROJECT EXPERIENCE
IT
S ELECTRICAL
Ci
ty of Huntington Beach Valley View/Bolsa Chica Regional Traffic Signal Synchronization Program (RTSSP)- City of Huntington Beach, CA
Mr. Gallardo serves as an Electrician Apprentice on this RTSSP project for the city of Huntington Beach. Iteris was selected to provide ITS design, bid support, ITS device installation, construction support, traffic signal synchronization services, and maintenance services to 22 signals along Valley View Street/Bolsa Chica Street, a major north-south arterial. The project covers approximately 5.35 miles of roadway from Chapman Avenue to Warner Avenue within the Cities of Huntington Beach, Westminster, and Garden Grove. ITS equipment improvements include fiber-optic communications, CCTV, VDS, and traffic signal controllers, cabinets, and foundations.
The project began in October 2023 and is ongoing, scheduled to end in October 2026.
Ci
tywide Bus Signal Priority Project – City of Downey, CA Mr. Gallardo is serving as an Electrician Apprentice for the installation, integration and testing of bus signal priority devices and systems for 92 intersections along six major corridors. This project enables the connection of additional signalized intersections to the City’s Traffic Management Center (TMC), and integration into the DowneyLINK automatic vehicle location (AVL) system.
EDUCAT
ION
Los Angeles Trade Tech, 2015
El Camino Community College, 2012
YEARS OF EXPERIENCE
With Iteris: <1 Total: <1
CERTIFICATIONS
IMSA Work Zone Safety
IMSA Traffic Signal Technician 1
CORE DISCIPLINES
Construction Support/Inspection
Traffic Singal System Upgrade
Traffic Signal Priority (TSP)
Transportation Planning for Safety
Analysis and Managed Services
ALEXANDER
GALLARDO, IMSA
ELECTRICIAN APPRENTICE
ALEXANDER GALLARDO
ELECTRICIAN APPRENTICE
Moving smarter, together.
The signal priority system is based on IEEE 802.11-
compliant wireless bus-to-intersection
communications; and upgraded intersection traffic
controller technologies. Iteris is responsible for
installing the radios, antennas, network switches,
2070 controllers and supporting CAT6 cabling at
each intersection.
First Street and Bolsa Avenue Regional Traffic
Signal Synchronization Project (RTSSP),
Contract Task Order (CTO) - Orange County
Transportation Authority (OCTA), Orange
County, CA
Mr. Gallardo serves as an Electrician Apprentice on
this multi-jurisdictional signal coordination for a
13.1-mile stretch of First Street/Bolsa Avenue. The
project includes various traffic signal improvements
and the retiming of 55 signalized intersections along
First Street/Bolsa Avenue from Bolsa Chica Street in
the City of Huntington Beach to Newport Avenue in
the City of Tustin and five (5) signalized intersections offset from the corridor in the City of Santa Ana.
Iteris designed and is managing the installation of
traffic signal equipment, communication network
equipment, and fiber optic cable for five (5) agencies
along the corridor. The project began in August 2021
and is ongoing, due to end in October 2026.
Alternative Signal Communication
Demonstration Pilot - Orange County
Transportation Authority (OCTA)
Mr. Gallardo serves as an Electrician Apprentice on
this traffic signal communication improvement
project that extends throughout various city’s traffic
signal networks within Orange County. There are
seven cities that are getting upgrades to their
existing communication infrastructure at
intersections that are either offline, have outdated
equipment, and/or seeking alternatives solutions to
ensure reliability, enhanced security, and scalability
for a robust network that will be viable for the next
10 to 15 years. The primary goal of this project is to
analyze and test connectivity at locations where
there are existing interconnect (copper, fiber, and
wireless) systems, so that appropriate design
measures can be applied to deploy new ethernet
switches, ethernet cards, wireless radios, and/or cell
modems to support the management of each city’s
traffic network. The project began in June 2022 and
is ongoing due to end in December 2024.
Regional Traffic Signal Synchronization Program
(RTSSP) Project for Tustin Avenue - Rose Drive
– City of Orange, CA
Mr. Gallardo serves as an Electrician Apprentice on
this project which involves infrastructure upgrades,
signal coordination and timing improvements,
development of signal timing plans for key signalized
intersections, vehicle turn movement counts and
performing before-and-after corridor analysis along
the Tustin Avenue/Rose Drive corridor from First
Street in the City of Tustin to Wabash Avenue in the
City of Yorba Linda. The project area comprises 54
signalized intersections spanning six cities – Tustin,
Santa Ana, Anaheim, Orange, Placentia, and Yorba
Linda – as well as key highway on/off ramps under
Caltrans, in Orange County, California. The project
started in August 2020 and is ongoing. The project
began in September 2021 and is ongoing, ending
May 2025.
Moving smarter, together.
Mr. Freeman serves as a Senior Engineer for Iteris’ Mobility Consulting Solutions division and has been with the firm since July 2023. He has 10 years of experience working in the fields of traffic engineering and traffic signal design.
PROJECT EXPERIENCE
TRAFFIC ENGINEERING & OPERATIONS
Regional Traffic Signal Synchronization Program (RTSSP) Project for Tustin Avenue - Rose Drive – City of Orange, CA Mr. Freeman serves as Project Engineer on this project. Under the project agreement, Iteris will make infrastructure upgrades, signal coordination and timing improvements, develop signal timing plans for all signalized intersections along the corridor, provide vehicle turning movement counts and perform before-and-after corridor analysis along the Tustin Avenue/Rose Drive corridor from First Street in the City of Tustin to Wabash Avenue in the City of Yorba Linda. The project area comprises 54 signalized intersections spanning six cities – Tustin, Santa Ana, Anaheim, Orange, Placentia, and Yorba Linda – as well as key highway on/off ramps under Caltrans, in Orange County, California. The project started in August 2020 and is ongoing. Construction is slated to start in Summer 2023.
Yorba Linda Boulevard/Weir Canyon Road Corridor Regional Traffic Signal Synchronization Project- City of Yorba Linda, CA Mr. Freeman serves as Project Engineer on this project. Under the project agreement, Iteris will make infrastructure upgrades along Yorba Linda Boulevard from Van Buren Street to new River Road in the City of Yorba Linda. Additional, Iteris will analyze signal coordination and timing improvements, develop signal timing plans for all signalized intersections along the corridor, provide vehicle turning movement counts and perform before-and-after corridor analysis on Yorba Linda Boulevard from State College Boulevard in Fullerton to Canyon Drive in Anaheim. The project began in July 2023 and is ongoing.
.
EDUCATION
BS, Civil Engineering, University of Illinois
Urbana-Champaign, IL, 2014
YEARS OF EXPERIENCE
With Iteris: 1 Total: 10
REGISTRATIONS
Civil Engineer (PE)
IL #062.070815, 2018
Professional Traffic Operations Engineer
(PTOE)
#4607, 2019
CORE DISCIPLINES
Traffic Engineering
Traffic Signal Design
Traffic Signal System Upgrades
AFFILIATIONS
Institute of Transportation Engineers
(ITE)
ANDREW FREEMAN,
PE, PTOE
SENIOR ENGINEER
ANDREW FREEMAN, PE (IL) PTOE
SENIOR ENGINEER
Moving smarter, together.
Alternative Signal Communication
Demonstration Project – Orange County, CA
Mr. Freeman serves as Project Engineer on this
project. Iteris was selected by OCTA to provide low
cost solution to bring intersection online and/or
provide additional redundancy to the traffic
network. This project will provide traffic signal
communication improvements throughout various
cities’ traffic signal networks within Orange County.
Cities that require upgrades as part of the project
are:
• City of Huntington Beach
• City of La Habra
• City of Lake Forest
• City of Newport Beach
• City of Rancho Santa Margarita
• City of Seal Beach
• City of Yorba Linda
The cities will be getting upgrades to their existing
communication infrastructure at intersections that
are either offline, have outdated equipment, and/or
seeking alternatives solutions to ensure reliability,
enhanced security, and scalability for a robust
network that will be viable for the next 10 to 15
years. The primary goal of this project is to analyze
and test connectivity at locations where there is
existing interconnect (copper, fiber, and wireless)
systems, so that appropriate design measures can be
applied to deploy new ethernet switches, ethernet
cards, wireless radios, and/or cell modems to
support the management of each city’s traffic
network. Iteris will procure, configure, and install all the equipment as part of this project. The project
started in August 2022 and is expected to be
completed by August 2023.
PREVIOUS PROJECT EXPERIENCE
TRAFFIC ENGINEERING & OPERATIONS
C*NECT Capital Improvements Projects, Design
and Project Management – Chicago Department
of Transportation, Chicago, IL
Mr. Freeman served as Project Manager on this
project. While with another firm, Mr. Freeman
provided engineering and project management
services to develop traffic signal improvements and
modernizations for the Chicago Department of
Transportation’s capital improvement programs. Mr.
Freeman was responsible for traffic signal design,
interconnect fiber design, quantity and cost estimate
calculations, and agency coordination.
Traffic Engineering Services - Illinois Tollway
Mr. Freeman served as Project Engineer on this
project. While with another firm, Mr. Freeman
provided an assessment and recommendations to
improve the existing secondary crash processing and
identification logic for the Illinois Tollway. Mr.
Freeman provided data analysis support and assisted
in develop dashboards in PowerBI to ease data
manipulation and assist in trend analysis.
Village of Crestwood Traffic Signal
Modernization Project – Village of Crestwood, IL
Mr. Freeman served as Project Manager on this
project. While with another firm, Mr. Freeman
develop engineering and project management
services to provide traffic signal modernization plans
to three intersections in the Village of Crestwood.
Mr. Freeman was responsible for traffic signal design
including equipment layout, interconnect fiber
design, quantity and cost estimate calculations,
street sign layouts, and agency coordination.
In-House Traffic Consultant – Chicago
Department of Transportation
Mr. Freeman served as an in-house Project Engineer
for the Chicago Department of Transportation on
this project. While with another firm, Mr. Freeman
developed detailed plans for pavement markings,
signage, and geometric improvements including
pedestrian refuge islands and curb extensions. Mr.
Freeman was also responsible for analyzing crash
data to identify trends and potential improvements
to pedestrian and vehicle safety for corridors and
intersections. Mr. Freeman provided review of
proposed site plans and developments throughout
Chicago to ensure compliance with traffic
engineering best practices and city standards.
Moving smarter, together.
Mr. Liang serves as Associate Engineer for Iteris’ Mobility Consulting Solutions and has been with the firm since 2019. He has over 4 years of experience working in the fields of Traffic Engineering, ITS Designs, and Operations. Mr. Liang has ITS design experience with multiple TSSP projects around Orange County. Mr. Liang has prepared many PS&E packages for various local agencies and Caltrans in the Southern California Region. Mr. Liang’s software knowledge includes AutoCAD, Microstation, Microsoft Word, Excel, MATLAB, Synchro and ArcGIS.
PROJECT EXPERIENCE
TRAFFIC ENGINEERING
Euclid Street Corridor Project Regional Traffic Signal
Synchronization Program (RTSSP – City of La Habra, CA
Mr. Liang serves as a Project Engineer on this signal synchronization project for City of La Habra. Project includes the synchronization of sixty-seven (67) traffic signals and sixty-nine (69) offset traffic signals throughout the Cities of La Habra, Fullerton, Anaheim, Garden Grove, Santa Ana, and Fountain Valley along Euclid Street. Iteris is providing communication system analysis for the City of Fullerton and the City of Santa Ana through this project. Iteris will conduct all engineering, construction management, inspection, and
administrative tasks necessary to complete the project. After the construction and implementation phase of the project, Iteris will provide operations, and maintenance services for three years. The project began in March 2023 and is expected to be completed March 2028.
Tustin-Rose Regional Traffic Signal Synchronization Project (RTSSP) – Orange County, CA
Mr. Liang serves as the associate engineer to deploy new ITS communication infrastructure and implement optimized
coordination timing plans to achieve optimal traffic flow for Cities of Orange, Placentia, Santa Ana, Tustin, and Yorba Linda along the main corridors of Tustin Ave/Rose Dr. VDS, CCTV and fiber optic interconnect upgrades will be implemented throughout the main corridors. His responsibilities includes drafting the fiber communication plans and signal modification plans. The project began in September 2021 is ongoing.
EDUCATION
BS, Civil Engineering, University of Irvine,
CA, 2019
YEARS OF EXPERIENCE
With Iteris: 4 Total: 4
REGISTRATIONS
Engineer-In-Training (EIT)
CA #169619, 2019
CORE DISCIPLINES
Traffic Engineering & Operations
ITS Planning/Design/Integration
Traffic Signal Design
Operations and Maintenance
AFFILIATIONS
American Society of Civil Engineers
(ASCE)
Orange County Traffic Engineering
Council (OCTEC)
RAYMOND
LIANG, EIT
ASSOCIATE ENGINEER
RAYMOND LIANG, EIT
ASSOCIATE ENGINEER
Moving smarter, together.
Professional Design and Construction Support
for the TSS for ATMS – Rancho Cucamonga,
CA
Mr. Liang serves as the assistant engineer to deploy
new ITS communication infrastructure and
implement optimized coordination timing plans to
achieve optimal traffic flow for City of Rancho
Cucamonga along the main corridors of Haven
Avenue and Foothill Boulevard. CCTV, VDS, and fiber
optic interconnect upgrades will be implemented
throughout the main corridors. His responsibilities
includes drafting the fiber communication plans and
signal modification plans. The project began in
August 2019. Mr. Liang’s involvement on the project
began in August 2019 and is ongoing. The project
will be completed in August 2020, followed by two
years of Operations and Maintenance (O&M),
ending August 2022.
Traffic and Intelligent Transportation Systems
Engineering Services, Katella Avenue (TSSP),
(OCTA) – Orange County, CA
Mr. Liang served as Assistant Designer on this
Project. As part of the project, Iteris’ Intersection-as- a-Service™ end-to-end solution offering will deliver
proactive monitoring of traffic signal operations at
all project intersections. The primary goal of this
project is to deploy new Intelligent Transportation
System (ITS) equipment and communication
infrastructure to support the management of the
cities’ transportation network, implement optimized
coordination timing plans to achieve optimal traffic
flow, and improve safety for all road users, including
vehicles, buses, bicycles, and pedestrians. The
project began in February 2020 and is ongoing.
Traffic and Intelligent Transportation Systems
Engineering Services, Main Street Regional
Traffic Signal Synchronization Projects
(RTSSP), (OCTA) – Orange County, CA
Mr. Liang serves as Associate Engineer on this
project, which will provide services that will upgrade
traffic signal electronics and communications
equipment, and optimize signal timing along Main
Street, a major north-south corridor that comprises
67 major signalized intersections. As part of the
project, Iteris’ Intersection-as-a-Service™ end-to-end
solution offering will deliver proactive monitoring of
traffic signal operations at all project intersections.
The primary goal of this project is to deploy new
Intelligent Transportation System (ITS) equipment
and communication infrastructure to support the
management of the cities’ transportation network,
implement optimized coordination timing plans to
achieve optimal traffic flow, and improve safety for
all road users, including vehicles, buses, bicycles, and pedestrians. The project began in December 2019
and is ongoing.
A&E On-Call Roadway Design and Project
Development and Construction Services
(Caltrans D12) – Orange County, CA
Mr. Liang is serving as an Associate Engineer with
Iteris as part of the TranSystems team on the
Caltrans District 12 On-Call contract to provide
consultation, research, professional and technical
services required for Roadway Design and related
Project Development and Construction Services,
including, but not limited to, field sampling,
construction materials testing, analysis, reports,
plant inspection and work related to testing
equipment calibration, on an “as-needed” basis to
support the Caltrans D12, from Project Report phase
to construction phase completion of three State
Route (SR) 91 Multi-Asset Projects, EA 12-0R312, EA
12-0R313 and EA 12-0R314 in Orange County
between Los Angeles County Line to Riverside
County Line. Iteris' task focuses on performing
design service for Traffic Management Systems
(TMS) and electrical elements through PA&ED, PS&E,
and construction phase. The TMS/electrical
elements improvement includes, but not limited to,
CCTV, CMS, loop detectors, census station, RMS, FOC
and conduit. The project began in January 2021 and
is ongoing.
OCTA Warner Avenue Regional Traffic Signal
Synchronization Project (RTSSP) – Orange
County, CA
Mr. Liang serves as the associate engineer to deploy
new ITS communication infrastructure and
implement optimized coordination timing plans to
achieve optimal traffic flow for Cities of Huntington
Beach, Fountain Valley, and Santa Ana along the
main corridors of Warner Avenue. VDS, CCTV and
fiber optic interconnect upgrades will be
implemented throughout the main corridors. His
responsibilities includes drafting the fiber
communication plans and signal modification plans.
The project began in November 2020. Mr. Liang’s
involvement on the project began in August 2021
and is ongoing.
Snap, Inc., Santa Monica
Juan Ramos | Service Foreman
Summary
Juan Ramos has over 25 years of experience in the construction industry with a focus on fiber optic technology installation, repairs and maintenance. The role of service foreman for our communications division is to lead and coordinate the activities of the project team and provide full time daily supervision across the construction site. • Strong understanding of fiber optic technology, testing equipment, industry standard protocols and equipment.
• Plan and supervise activities includes determining method of construction, manpower levels, material quantities equipment, temporary power sources, work schedule and documenting hours worked.
• Attend weekly coordination meetings, monitor safety program, review and coordinate drawings and submittals, insure quality installation, and monitor work progress according to schedule.
• Schedule, coordinate and supervise employee activities. Coordinate assigned work with work of different crafts, company departments, or other contractors. • Maintain liaison with engineering, estimating, and planning to ensure work complies with drawings, specifications, and schedule.
• Assist in resolving construction hurdles as required. • Monitor compliance with project safety program requirements; document and ensure implementation.
• Maintain liaison with other departments (i.e., material control, purchasing, quality control, engineering) to ensure all materials, equipment, inspections and schedule.
• Represents Anderson Howard in a manner that meets the highest standards of professional conduct and integrity.
Certifications / Training / Specialties
• Panduit Certification
• Corning Certification
• Sumitomo Certification
• Specializes in fiber installation:
• Traditional fiber
• Air blown fiber
• Terminating with fusion
• Terminating with mechanical connectors
• Fiber testing and transmission signal integrity testing Google, Multiple Locations
Apple, Multiple Locations
NBCUniversal, Los Angeles
iteris
949.270.9400 1700 Carnegie Avenue, Suite 100
iteris.com Santa Ana, CA 92705
FEE
PROPOSAL
November 8, 2024
Mr. Dai Vu, Traffic Engineer
City of Garden Grove
11222Acacia Parkway
Garden Grove, CA 92842
Re: FEE PROPOSAL FOR SYSTEM CONSTRUCTION OF THE BOLSA CHICA ST. - VALLEY VIEW ST. TSSP
11477-230.25
Dear Mr. Vu,
Iteris, Inc. (Iteris) submits our fee proposal to provide ser/ices for the system construction of the Bolsa Chica Street and Valley View Street TSSP project. Table 1 (page 2) summarizes the lump sum price of the total project fee.
Proposal is valid for 90 days following submission.
Thank you for the opportunity to submit our Fee Proposal. Iteris looks forward to assisting the City on important traffic and transportation engineering projects. Iteris accepts the terms and conditions of the sample contract as-is. Please contact me at (949) 270-9647 or [email protected], or the designated Project Manager, Mr. Brian Akerley, MELE at (657) 652-8288 or [email protected], with any questions.
Sincerely,
Iteris, Inc.
f^JI:
Steven Bradley, PE
Regional Vice President | Mobility Consulting Solutions •Stei/en Bradley, PE, is authorized to negotiate the contract on behalf of Iteris and our project manager.
iteris
949.Z70.9400 1700 Carnegie Avenue, Suite 100
iteris.com Santa Ana, CA 92705
Table 1 - Fee Proposal
BOLSA CHICA ST. - VALLEY VIEW ST.
CITf OF GARDEN GROVE
FEE PROPOSAL FORMAT
Item 1
System Construction at the intersection of Chapman Ave../ Valley View St. per Drawng No. T-943.3 (Attachment E)
and Specifications (Attachment D)'.
Item 2
System Construction at the intersection of West Grove Ctr./ Valtey View St. per Drawing No. T 943.4 (/Mtachment E)
and Specifications (Attachment D)'.
Item 3
System Construction at the intersection of Be (grave Ave. / Valley View St. per Drawing No. T-943.5 (Attachment E)
and Specifications (Attachment D)'.
Item 4
System Construction at the intersection of LampsonAveY
Valley View St. per Drawing No. T'943.6 (Attachment E) and Specifications (Attachment D)'.
Item 5
System Construction at the intersection of Cerutean AveY Valley View St. per Drawing No. T-943.7 (Attachment E) ard Specifications (Attach ment D)'.
ItemS
System Construction in the Garden Grove TMC per Drawing No. T'943.10 (Attachment E) and Specifications (Attachn-wnt D).
Procure, Install and Configure equipment.
Total Project Fee (in figures): Not to Exceed
TSSP
Lump Sum Price
$ 79,823.00
$66,368.00
$ 95,132.00
$ 101.622.00
$ 121,819.00
$ 80,357.00
$ 545,121.00
*Lump sum cost shall indude all the tasks listed in the Scope of Services IndLriing procurement of field equipment & install per plan and specifications, configure ard integration of equipment, test equipment and coordinate equipment testing as needed, provkie construction management sup port as needed.