Cities Index.
item 6 Acceptance of Project No. S-1328-A, Phase One Roof Replacement Project at the Garden Grove Amphitheater Campus, as complete. (Action Item)

Garden Grove City Council
December 10, 2024

Document
item 6 Acceptance of Project No. S-1328-A, Phase One Roof Replacement Project at the Garden Grove Amphitheater Campus, as complete. (Action Item)
Meeting
December 10, 2024
Body
Garden Grove City Council
Pages
2
Original file
222 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 508/2024
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 12/10/2024

Subject: Acceptance of Project No. S-1328-A, Phase One Roof Replacement Project at the Garden Grove Amphitheater Campus, as complete. (Action Item)

OBJECTIVE

For the City Council to accept Project No. S-1328-A Phase One, Roof Replacement Project at the Garden Grove Amphitheater Campus located at 12762 Main Street as complete and authorize the City Manager to execute the Notice of Completion of Public Improvement and Work.

BACKGROUND

On June 25, 2024, City Council awarded a contract to AME Builders Inc., in the amount of $59,900 to complete the scope of work that specified replacing two (2) roofs on buildings located within the Amphitheater grounds. During the project, a third smaller roof was added to the scope of work. The cost of the additional work did not exceed the ten percent contract contingency designed to cover unforeseen conditions and work.

DISCUSSION

The contractor, AME Builders Inc., has completed phase one of the Amphitheater Roof Replacement Project in accordance with related plans, specification s and other contract documents.

FINANCIAL IMPACT

There is no financial impact to accept Project No. S -1328-A, Phase One, Roof Replacement Project at the Garden Grove Amphitheater Campus located at 12762 Main Street, as complete.

Item 508/2024

Page 2 of 2 ends

RECOMMENDATION

It is recommended that City Council:
 Accept Project No. S -1328-A, Phase One Roof Replacement Project at the Garden Grove Amphitheater Campus located at 12762 Main Street as complete;  Authorize the City Manager to execute the Notice of Completion of Public Wor ks improvement and work; and
 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Phillip Carter, Facilities Manager