item 5 Acceptance of Project No. S-1328 Phase Two Amphitheater Roof Replacement Project, as complete. (Action Item)

Garden Grove City Council
February 25, 2025

Document
item 5 Acceptance of Project No. S-1328 Phase Two Amphitheater Roof Replacement Project, as complete. (Action Item)
Meeting
February 25, 2025
Body
Garden Grove City Council
Pages
2
Original file
194 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 53/2025
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 2/25/2025

Subject: Acceptance of Project No. S-1333 Phase Two Amphitheater Roof Replacement Project, as complete. (Action Item)

OBJECTIVE

For the City Council to accept Project No. S-1333 Phase Two Amphitheater Roof Replacement Project at the Garden Grove Amphitheatre campus located at 12762 Main Street, as complete.

BACKGROUND

On September 24, 2024, the City Council awarded a contract to Chapman Coast Roofing Inc., in the amount of $119,518, to complete the scope of work that specified replacing two (2) roofs on buildings located within the Amphitheater grounds.

DISCUSSION

The contractor, Chapman Coast Roofing Inc., has completed Phase Two of the Amphitheater Roof Replacement Project in accordance with related plans, specifications and other contract documents.

FINANCIAL IMPACT

The project was funded through Building Rehab ilitation internal service fund s and was completed within budget. Accepting the project as complete will have no additional financial impact.

RECOMMENDATION

It is recommended that the City Council:

 Accept Project No. S-1333 Phase Two Roof Replacements at the Amphitheatre campus located at 12762 Main Street Garden Grove, as complete;  Authorize the City Manager , or designee, to execute the Notice of Completion of Public Works Improvement and Work; and
Item 53/2025

Page 2 of 2 ends

 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Phillip Carter, Facilities Manager

ATTACHMENT(S)

1. Notice Of Completion S-1333 Amphitheater Roof Project Phase II