Cities Index.
item 6 Approval of an Amendment to the agreement with CT&T Concrete Paving, Inc. for concrete construction services. (Cost: $90,000)(Action Item)

Garden Grove City Council
March 25, 2025

Document
item 6 Approval of an Amendment to the agreement with CT&T Concrete Paving, Inc. for concrete construction services. (Cost: $90,000)(Action Item)
Meeting
March 25, 2025
Body
Garden Grove City Council
Pages
2
Original file
196 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 86/2025
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 3/25/2025

Subject: Approval of an Amendment to the agreement with CT&T Concrete Paving, Inc. for concrete construction services. (Cost: $90,000)(Action Item)

OBJECTIVE

For the City Council to approve an amendment increasing the current contract price by 10% ($90,000) to cover the remaining concrete repairs needed for completion of slurry projects.

BACKGROUND

The City of Garden Grove currently has an agreement with CT&T Concrete Paving, Inc. for concrete repair services. The original contract, previously approved by the City Council, is set at $900,000. The contract includes provisions for optional renewal years, which allow s the City to extend the agreement based on performance and available budget.

DISCUSSION

Due to an increase in concrete repair prices and the volume of repairs needed across the city, staff recommends amending the contract to accommodate additional work. Specifically, staff is requesting a 10% increase to the existing contract amount for the remainder of the contract term ending on June 30, 2025. This adjustment will allow for the completion of additional repair projects identified during the fiscal year.

FINANCIAL IMPACT

There is no impact to the General Fund. The proposed contract increase of 10% will bring the contract to a new total of $990,000 for the remaining of the existing term, which expires on June 30, 2025. No additional appropriation is needed for the proposed contract amendment as f unding for th e increase will be covered by the existing Public Works Department ’s operating budget.

Item 86/2025

Page 2 of 2 ends

RECOMMENDATION

It is recommended that the City Council:

 Approve the Amendment with CT&T Concrete Paving, Inc., to increase the current contract amount by 10%, totaling a $90,000 increase for the remainder of the contract term ending on June 30, 2025; and

 Authorize the City Manager, or designee, to execute the amendment , any related documents, and make minor modification as appropriate thereto.