item 11 Award of a contract to Quality Fence Co. for the Caltrans Fencing Improvement Project, Phase III. (Cost: $139,682.70) (Action Item)

Garden Grove City Council
April 22, 2025

Document
item 11 Award of a contract to Quality Fence Co. for the Caltrans Fencing Improvement Project, Phase III. (Cost: $139,682.70) (Action Item)
Meeting
April 22, 2025
Body
Garden Grove City Council
Original file
49 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Quality Fence Co Inc.
14929 Garfield Ave
Paramount, Ca 90723
323-585-8585 F. 562-869-7804

City of Garden Grove Cal Trans Securfur Fence Installation - Phase III 3.27.25 Location Description Of Work Quantity Pre O+P Total OH & Profit 5% Total Newland Demo Ext Chain Link 170 $4,250.00 $212.50 $4,462.50 4D Fence Panel Install 435 $97,875.00 $4,893.75 $102,768.75 4' Gate 1 $3,995.00 $199.75 $4,194.75
12' Gate 3 $20,223.00 $1,011.15 $21,234.15
$132,660.15

Phase 3 Sub Total: $132,660.15
Permits $1,500
Insurance/Bonds $5,522.55

Phase 3 Total: $139,682.70

Project Manager Submission:

Natalie Reyes
[email protected]
(909) 223-5852