Cities Index.
item 11 Award of a contract to Quality Fence Co. for the Caltrans Fencing Improvement Project, Phase III. (Cost: $139,682.70) (Action Item)

Garden Grove City Council
April 22, 2025

Document
item 11 Award of a contract to Quality Fence Co. for the Caltrans Fencing Improvement Project, Phase III. (Cost: $139,682.70) (Action Item)
Meeting
April 22, 2025
Body
Garden Grove City Council
Pages
2
Original file
227 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 127/2025
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: Ursula Luna-Reynosa
Dept:

City Manager Dept: Economic Development &
Housing

Date: 4/22/2025

Subject: Award a contract to Quality Fence Co. for the Caltrans Fencing Improvement Project, Phase III. (Cost: $139,682.70)(Action Item)

OBJECTIVE

For the City Council to award a construction agreement to Quality Fence Co. to implement Phase III of the Caltrans Fencing Improvement Project (CFIP) in the amount of $139,682.70.

BACKGROUND

In March 2023, the City Council approved a Cooperative Agreement with Caltrans, providing funding and approval for the City to install fencing, gates, rock slopes and gravel on unpaved slopes and narrow areas within the City and along certain underpasses of the 22 Freeway (SR-22) from Springdale Street to Garden Grove Boulevard (the “Project”). Quality Fence Co. was awarded a construction contract in the amount of $1,500,000 to execute Phase I and II of the described scope. To date, Phase I and II are complete.

DISCUSSION

While robust efforts to mitigate the increase of encampments within the City have been on- going, the concern persists as reflected in continuous complaints from residents. The Garden Grove Police Department’s Special Resource Team (SRT) supports the effectiveness of deterrent fencing in preventing the rise of encampments within the City. Upon the completion of Phase I and II, community interest in exploring the expansion of the Project is apparent. Given the remaining balance of $150,000.00 from the Cooperative Agreement, Caltrans has agreed to fund Phase III as part of the scope of work for the Project.

Phase III scope includes the demolition of existing chain link fence and the installation of Securifor 4D fencing and gates beneath the underpass on both the East and West side of Newland Street. Quality Fence Co. submitted a cost proposal in the amount of $139,682.70 to implement Phase III of the Project, retaining their overhead cost and mark up at 5 percent.

Item 127/2025

Page 2 of 2 ends

FINANCIAL IMPACT

There is no financial impact to the City. Per the Cooperative Agreement with Caltrans, a hundred percent (100%) of the cost will be reimbursed by Caltrans.

RECOMMENDATION

It is recommended that the City Council:
 Award the construction contract to Quality Fence Co. in the amount of $139,682.70 to execute Phase III of the Caltrans Fencing Improvement Project (CFIP);
 Authorize the City Manager, or designee, to execute the contract and amendments to Quality Fence Co.’s construction contract, make minor modifications, as appropriate, and execute any documents necessary to effectuate the contract on behalf of the City.

ATTACHMENT(S)

Attachment 1: Agreement
Attachment 2: Proposal (Newland Street)
Attachment 3: Map