OBJECTIVE
To receive City Council approval of an emergency purchase order with Tess Electric for electrical equipment replacement at Well No.31.
BACKGROUND
The Garden Grove Public Works Department’s Water Services Division owns and operates the water system that provides water services throughout the city. The Division operates 17 total water production facilities that encompasses 13 wells, 5 pump stations, a nd 8 reservoirs that store approximately 53 million gallons of water. On April 13, 2025, the variable frequency drive (VFD) at Well No. 31 failed. Tess Electric was called out to diagnose the VFD for Well No. 31. This VFD equipment was reported as unrepairable, obsolete, and requires an immediate replacement.
DISCUSSION
This well site is a critical resource for meeting daily demands should additional wells be potentially shut down for PFAS water contamination. Hence, affecting the safety, health and property of the community at large. Staff obtained three (3) quotes with the lowest quote in the amount of $54,225.64. Currently, the VFD is available for immediate delivery, but this situation could change due to high demand and the cost could also increase b ased on current import cost fluctuations. Staff proceeded with ordering the VFD to lock in current pricing. There is an existing $25,000 blanket purchase order with Tess Electric with a balance of approximately $15,000. This balance is insufficient to cove r the replacement of this equipment. Therefore, staff is seeking to designate these costs as emergency repairs and issue an emergency purchase order in the amount of $54,225.64 as soon as possible to begin scheduling the replacement. During the replacement process, the contractor will be able to thoroughly inspect all components of the motor control centers and address any unanticipated additional work required, which may result in additional costs.
Item 161/2025
FINANCIAL IMPACT
The total cost of the electrical equipm ent replacement at Well No. 31 is $54,225.64. This amount will be funded from the existing Water utility budget. No additional appropriation is needed, and there is no impact to the General Fund.
RECOMMENDATION
It is recommended that City Council:
Approve and authorize the Finance Director to issue an emergency purchase order in the amount of $54,225.64 to Tess Electric for electrical equipment replacement at Well No. 31.
By: Samuel Kim, P.E.
Deputy Public Works Director/Water Services Manager
ATTACHMENT(S)
1. Quotes