item 14 Award a contract to Act 1 Construction, Inc. for the Woodbury Park Revitalization and Expansion Project IFB No. S-1340. (Cost: $10,992,000)(Action Item)

Garden Grove City Council
May 27, 2025

Document
item 14 Award a contract to Act 1 Construction, Inc. for the Woodbury Park Revitalization and Expansion Project IFB No. S-1340. (Cost: $10,992,000)(Action Item)
Meeting
May 27, 2025
Body
Garden Grove City Council
Pages
2
Original file
230 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 181/2025
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: John Montanchez
Dept:

City Manager Dept: Community Services
Date: 5/27/2025

Subject: Award a contract to Act 1 Construction, Inc. for the Woodbury Park Revitalization and Expansion Project IFB No. S-1340. (Cost: $10,992,000)(Action Item)

OBJECTIVE

To request that the City Council award a contract for the Woodbury Park Revitalization and Expansion Project IFB No. S-1340 to Act 1 Construction, Inc.

BACKGROUND

On March 14, 2025, pursuant to Municipal Code Section 2.50.100, staff solicited bids for the Woodbury Park Revitalization and Expansion Project IFB No. S-1340.

The project includes a full park reconstruction across approximately 3.8 acres and features a new 25-meter, six-lane swimming pool, two playground area, skate plaza, outdoor fitness equipment, basketball courts, park restrooms, a pool house building, lighting, landscaping, and a new parking lot.

DISCUSSION

On May 6, 2025, six (6) bids were recei ved and opened by the City Clerk’s office at 11:00 a.m. On May 19, 2025, staff notified the lowest bidder, Horizons Construction Company that their bid proposal was found unresponsive as there were several bid irregularities identified by the City, and additional irregularities identified by the protest filed by Act 1 Construction, Inc. The City’s correspondence with Horizons Construction Company, along with its bid, is attached as Attachment 1. Act 1 Construction’s protest letter is attached as Attachment 2.

State law provides that bids that do not conform to the Invitation for Bids must be rejected as nonresponsive unless the City Council determines that the irregularities are inconsequential, do not affect the bid price, and do not give the bidder a c ompetitive advantage over the other bidders. Staff’s independent review of Horizons Construction Company’s bid has concluded that waiving the irregularities in their bid would give Horizons Construction Company a competitive advantage over the other bidders given the number and breadth of irregularities in their bid.

Item 181/2025

Page 2 of 2 ends

Staff proceeded to review the bid documents submitted by the second lowest contractor, Act 1 Construction, Inc., with a total bid of $10,393,088, and the bid alternate item 2A additional cost of $598,912 for the LSI play equipment, for a project total bid amount of $10,992,000.

The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.

If approved, the contract schedule would start in June 2025, with completion anticipated by March 2026.

FINANCIAL IMPACT

The Woodbury Park Revitalization and Expansion Project is included in the adopted Community Services Five -Year Capital Improvement Plan . The Project is funded by the Proposition 68 Statewide Park Development and Community Revitalization Grant funds and Park Fee funds. There is no financial impact to the City’s General Fund.

RECOMMENDATION

It is recommended that the City Council:
 Reject Horizons Construction Company’s bid as unresponsive; and  Award a contract for the Woodbury Park Revitalization and Expansion Project IFB No.

S-1340, in the amount of $10,992,000, to Act 1 Construction, Inc.; and  Authorize the City Manager, or designee, to execute the agreement on behalf of the City, and make minor modifications as appropriate.

By: Janet Pelayo, Deputy Director

ATTACHMENT(S)

Attachment 1. Bid and Correspondence with Horizons Construction Company Attachment 2. Act 1 Construction, Inc. Protest Letter
Attachment 3. Construction Contract - Act 1 Construction, Inc.