Cities Index.
item 11 Acceptance of Project No. S-1341 Roof Replacement at Eastgate Park Activity Center located at 12001 St. Mark Street, as complete. (Action Item)

Garden Grove City Council
June 24, 2025

Document
item 11 Acceptance of Project No. S-1341 Roof Replacement at Eastgate Park Activity Center located at 12001 St. Mark Street, as complete. (Action Item)
Meeting
June 24, 2025
Body
Garden Grove City Council
Pages
2
Original file
194 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 208/2025
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: William E. Murray
Dept:

City Manager Dept: Public Works
Date: 6/24/2025

Subject: Acceptance of Project No. S-1341 Roof Replacement at Eastgate Park Activity Center located at 12001 St. Mark Street, as complete. (Action Item)

OBJECTIVE

To seek City Council acceptance of Project No. S-1341 Roof Replacement at the Eastgate Park Activity Center located at 12001 St. Mark Street, as complete.

BACKGROUND

On January 14, 2025, City Council awarded a contract to Right-Way Roofing Corporation in the amount of $69,535 to complete the scope of work that specified replacing the roof at the Activity Center.

DISCUSSION

The contractor, Right -Way Roofing Corporation , has completed th e roof replacement in accordance with related plans, specifications, and other contract documents

FINANCIAL IMPACT

There is no financial impact to accept Project No. S-1341 Roof Replacement at the Eastgate Park Activity Center as complete. The total project cost was $69,535 and was funded by the Building Rehabilitation Fund.

RECOMMENDATION

It is recommended that City Council:

 Accept Project No. S -1341 Roof Replacement at Eastgate Park Activity Center located at 12001 St. Mark Street, Garden Grove , as complete;  Authorize the City Manager , or designee, to execute the Notice of Completion of Public Works Improvement and Work; and
Item 208/2025

Page 2 of 2 ends

 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Phil Carter, Facilities Manager