Cities Index.
item 5 Acceptance of Project No. CP-1180000 Bolsa Chica Street-Valley View Street Traffic Signal Synchronization Project, as complete. (Action Item)

Garden Grove City Council
January 27, 2026

Document
item 5 Acceptance of Project No. CP-1180000 Bolsa Chica Street-Valley View Street Traffic Signal Synchronization Project, as complete. (Action Item)
Meeting
January 27, 2026
Body
Garden Grove City Council
Pages
2
Original file
227 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 18/2026
Final

City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: Samuel Kim
Dept:

City Manager Dept: Public Works
Date: 1/27/2026

Subject: Acceptance of Project No. CP -1180000, Bolsa Chica Street -Valley View Street Traffic Signal Synchronization Project, as complete. (Action Item)

OBJECTIVE

For City Council to accept the above projects as complete and authorize the City Manager to execute the Notice of Completion of Public Improvement and Work.

BACKGROUND

Project No. CP-1180000 consisted of procurement and installation of various field equipment at five (5) signalized intersections along Valley View Street from Cerulean Avenue to Chapman Avenue. The field equipment included traffic signal cabinets, service cabinets, controllers, video detection systems, CCTV cameras, APS pedestrian push buttons, Ethernet switches, pull boxes, conduits and condu ctors. The project also included the installation and integration of communication equipment to the Garden Grove Traffic Management Center (TMC).

DISCUSSION

The contractor, Iteris, Inc., has completed the improvements in accordance with the plans, specifications, and other contract documents. The project was completed within the project budget and schedule. The retention payment will be released after recordation of the Notice of Completion.

FINANCIAL IMPACT

There is no financial impact to accept the above projects as complete and authorize the City Manager to execute the Notice of Completion of Public Improvement and Work. Funding for the project included CTFP grant funds in the amount of $ 436,096.80 from OCTA, and the City’s local match of $109,024.20, which included $83,160.00 from in-kind sources, and $25,864.20 from Traffic Mitigation Fees.

Item 18/2026

Page 2 of 2 ends

RECOMMENDATION

It is recommended that the City Council:

 Accept Project No. CP-1180000 Installation and Integration of Equipment for the Bolsa Chica Street-Valley View Street Traffic Signal Synchronization Project, as complete;

 Authorize the City Manager, or designee, to execute the Notice of Completion of Public Improvement and Work; and

 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Juan Navarro, P.E., City Traffic Engineer