Cities Index.
item 16 Acceptance of City Project No. CP-1414000 - Lampson Avenue and Knott Street Storm Drain Improvements Project, as complete. (Action Item)

Garden Grove City Council
June 9, 2026

Document
item 16 Acceptance of City Project No. CP-1414000 - Lampson Avenue and Knott Street Storm Drain Improvements Project, as complete. (Action Item)
Meeting
June 9, 2026
Body
Garden Grove City Council
Pages
2
Original file
221 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 219/2026

Final
City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: Samuel Kim
Dept:

City Manager Dept: Public Works
Date: 6/9/2026

Subject: Acceptance of Project No. CP-1414000 - Lampson Avenue and Knott Street Storm Drain Improvements Project, as complete. (Action Item)

OBJECTIVE

For the City Council to accept the above project as complete and authorize the City Manager to execute the Notice of Completion of Public Improvement and Work.

BACKGROUND

On March 10, 2026, the City entered into a contract with Duffy General Engineering Inc., a general contractor to complete the Lampson Avenue and Knott Street Storm Drain Improvements Project (Project). Specifically, the Project addressed removal of existing two 48-inch diameter corroded corrugated metal pipes (CMPs) and concrete junction structure; installation of 48-inch diameter of reinforced concrete pipe (RCP) and adjustment of utility covers to finish grade.

DISCUSSION

The contractor, Duffy General Engineering, Inc., has completed the improvements in accordance with the plans, specifications, and other contract documents. Therefore, the City moves to close out the project and file a Notice of Completion of Public Improvement Work.

FINANCIAL IMPACT

There is no impact to accept the above project as complete. These improvements were included in the Fiscal Year 2026-27 Capital Improvement Plan budget and are funded by Gas Tax SB1 funds.

RECOMMENDATION

It is recommended that the City Council:

 Accept Project No. CP 1414000 – Lampson Avenue and Knott Street Storm Drain Improvements Project, as complete;
Item 219/2026

Page 2 of 2 ends

 Authorize the City Manager, or designee, to execute the Notice of Completion of Public Improvement and Work; and

 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Navin Maru, Project Manager

ATTACHMENT(S)

1. Notice of Completion

← All documents from this meeting