Orange County Transportation Authority
FY 2025/26 - FY 2031/32 Capital Improvement Program
TIP ID CP-12617 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: CP1442000 Project Title
Additional Project IDs: 2025 Arterial Street Rehabilitation Projects Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway This project will make repairs to 28 street segments throughout the City Limits
28 street segments throughout the City. See ProjectNotes for details.
Project Notes
This project will make repairs to the following arterialand residential streets: 1) Orangewood Ave from Knottto Western, 2) Markon Dr from Blades to Patterson, 3)Blades Ave from Markon to Monarch, 4) Monarch Stfrom S’ly End to Patterson, 5) Edison Way fromLampson to Belgrave, 6) Industry St from S’ly End toChapman, 7) Patterson Dr from Knott to Monarch, 8)Doig Dr from Monarch to street end, 9) Hunt Ave fromMonarch to street end, 10) Belgrave Ave from Knott toIndustry, 11) Anaconda Ave from Monarch to Western,12) Western Ave from Lampson to Chapman, 13)Commerce Dr from Capital to Forbes, 14) Capital Avefrom Commerce to Corporate, 15) Forbes Ave fromCommerce to Euclid, 16) Emperor Quang Trung fromCorporate to Euclid, 17) Corporate Dr from Capital toForbes, 18) Euclid St from Westminster to Trask, 19)Cardinal Cir from West End to Harbor, 20) Salinaz Drfrom Newhope to street end, 21) Anabel Ave fromNewhope to A Better Way, 22) A Better Way fromWestminster to Anabel, 23) West St from Westminster tostreet end, 24) Seaboard Cir from Westminster to streetend, 25) Morningside Dr from Clinton to Buena, 26)Sunswept Ave from Clinton to Buena, 27) Keel Ave fromClinton to Buena, 28) Buena Way from Morningside toWestminster, and 29) Clinton St from Morningside toWestminster "Other" funding is allocated throughdrainage fees.
FISCALYEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTALESCALATED 2026 Gas Tax $200,000 $0 $7,000,000 $0 $7,200,000 $7,375,000 2026 Other $0 $0 $300,000 $0 $300,000 $307,500
2026 Measure M2 LocalFairshare $0 $0 $6,300,000 $0 $6,300,000 $6,457,500 Totals: $200,000 $0 $13,600,000 $0 $13,800,000 $14,140,000 Last Revised: 25-00 - In Progress Total Programmed: $13,800,000 TIP ID CP-12618 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: CP1446000 Project Title
Additional Project IDs: 2025 Residential Street Rehabilitation Project Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway The City will make improvements to residential streets bounded by Ninth, Garden Grove Blvd, West, andLampson.
Limits
Project is bounded by Ninth, Garden Grove Blvd, West,and Lampson Project Notes
FISCALYEAR FUND TYPE ENGROWCON/IMPO&MTOTAL TOTALESCALATED 2026 Community Development BlockGrant $0 $0 $700,000 $0 $700,000 $717,500 Totals: $0 $0 $700,000 $0 $700,000 $717,500
Last Revised: 25-00 - In Progress Total Programmed: $700,000 TIP ID CP-12619 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: CP1502000 Project Title
Additional Project IDs: 2026 Arterial Street Rehabilitation Projects Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway This project will rehabilitate 10 street segments.
Limits
This project will make repairs to 10 street segments.See Project Notes for details.
Project Notes
This project will make repairs to the following streets: 1)Trask from Magnolia to Brookhurst, 2) Chapman fromDale to Magnolia, 3) Chapman from Magnolia toBrookhurst, 4) Dale from Orangewood to Katella, 5)Dale from Chapman to 540' north, 6) Haster from 22Fwy to Lampson, 7) Euclid from Trask to Garden GroveBlvd, 8) Orangewood from 9th St to West, 9)Orangewood from West to Harbor Blvd, and 10)Western from Garden Grove Blvd to Lampson. "Other"funding is allocated under drainage fees.
FISCALYEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTALESCALATED 2027 Other $0 $0 $500,000 $0 $500,000 $525,312
2027 Measure M2 LocalFairshare $0 $0 $3,900,000 $0 $3,900,000 $4,097,437 2027 Gas Tax $200,000 $0 $5,300,000 $0 $5,500,000 $5,768,312 2027 Traffic Impact Fees $0 $0 $700,000 $0 $700,000 $735,437 Totals: $200,000 $0 $10,400,000 $0 $10,600,000 $11,126,498 Last Revised: 25-00 - In Progress Total Programmed: $10,600,000 TIP ID CP-11566 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: 1115451520 Project Title
Additional Project IDs: Concrete Replacement Capital
Type of Work: Pedestrian Project Description
Type of Work Description: Pedestrian -Reconstruction or rehabilitation of sidewalk The City will repair residential sidewalks, driveway approaches, wheel chair ramps, and cross gutters at locationscitywide.
Limits
Citywide
Project Notes
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2026 General Fund $0 $0 $300,000 $0 $300,000 $307,500
2027 General Fund $0 $0 $234,000 $0 $234,000 $245,846
2028 General Fund $0 $0 $234,000 $0 $234,000 $251,992
2029 General Fund $0 $0 $234,000 $0 $234,000 $258,292
2030 General Fund $0 $0 $234,000 $0 $234,000 $264,750
Totals: $0 $0 $1,236,000 $0 $1,236,000 $1,328,380
Last Revised: 25-00 - In Progress Total Programmed: $1,236,000 TIP ID CP-11632 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: CP1303000 Project Title
Additional Project IDs: 22-GGRV-ICE-4016 Harbor Blvd. / Garden Grove Blvd. Intersection Improvement Type of Work: Intersection Project Description
Type of Work Description: Intersection - Add left turnand right turn lanes to intersection The project will add a northbound left-turn lane and an eastbound right-turn lane, as well as general widening tosubstandard lane widths at the intersection of Harbor and Garden Grove Blvd. Improvements will also include anew traffic signal Limits
Harbor Boulevard and Garden Grove Boulevard
Project Notes
ICE funding for engineering phase approved during2022 CTFP Call for Projects. ICE funding forconstruction phase approved during 2024 CTFP Call forProjects.
FISCALYEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTALESCALATED 2026 Intersection CapacityEnhancements (ICE) $0 $0 $3,957,100 $0 $3,957,100 $4,056,027 2026 Measure M2 Local Fairshare $0 $0 $817,900 $0 $817,900 $838,347 2026 Gas Tax $7,875 $0 $2,025,000 $0 $2,032,875 $2,083,500 Totals: $7,875 $0 $6,800,000 $0 $6,807,875 $6,977,874
Last Revised: 25-00 - In Progress Total Programmed: $6,807,875 TIP ID CP-11564 IMPLEMENTING AGENCY Garden Grove, City of Local Project Number: 2095451525 Project Title
Additional Project IDs: 2075451280 Residential Overlay Program Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway Annual slurry seal of residential roadways as determined by PMP and Council direction.
Limits
Citywide
Project Notes
In Fiscal Year 23/24, the City will slurry sealapproximately 16.1 lanes miles of residential streetscitywide.
FISCALYEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTALESCALATED 2026 Gas Tax $200,000 $0 $800,000 $0 $1,000,000 $1,020,000 2027 Gas Tax $100,000 $0 $900,000 $0 $1,000,000 $1,045,562 2027 Community DevelopmentBlock Grant $100,000 $0 $900,000 $0 $1,000,000 $1,045,562 2028 Gas Tax $200,000 $0 $830,000 $0 $1,030,000 $1,093,819 2028 Community DevelopmentBlock Grant $100,000 $0 $900,000 $0 $1,000,000 $1,069,202 2029 Gas Tax $200,000 $0 $860,000 $0 $1,060,000 $1,149,279 2029 Measure M2 Local Fairshare $100,000 $0 $900,000 $0 $1,000,000 $1,093,432 2030 Gas Tax $200,000 $0 $895,000 $0 $1,095,000 $1,212,610 2030 Community DevelopmentBlock Grant $100,000 $0 $900,000 $0 $1,000,000 $1,118,267 Totals: $1,300,000 $0 $7,885,000 $0 $9,185,000 $9,847,733 Last Revised: 25-00 - In Progress Total Programmed: $9,185,000