Item 327/2026
Final
City of Garden Grove
INTER-DEPARTMENT MEMORANDUM
To:
Lisa L. Kim From: Samuel Kim
Dept:
City Manager Dept: Public Works
Date: 8/11/2026
Subject: Approval of a Cooperative Agreement with the City of Anaheim for the street rehabilitation of Harbor Boulevard from Chapman Avenue to Convention Way in Garden Grove. (Cost: $114,898)(Action Item)
OBJECTIVE
For City Council to approve the Cooperative Agreement between the City of Anaheim and the City of Garden Grove for the street rehabilitation of Harbor Boulevard from Chapman Avenue to Convention Way, and to authorize the City Manager to execute the agreement.
BACKGROUND
The City of Anaheim prepared a street rehabilitation project for Harbor Boulevard, from Chapman Avenue to Convention Way and has offered to improve the City of Garden Grove’s portion. Approximately one-twentieth of the work lies within the City of Garden Grove.
This proposed agreement is for construction engineering and construction costs of Garden Grove's portion of the project. The City of Anaheim is serving as the lead agency.
DISCUSSION
Staff has reviewed the plans, specification s, and construction estimate of the project and verified the work located within Garden Grove's portion. The project cost for City of Garden Grove’s portion of Harbor Boulevard is estimated at $114,898.
FINANCIAL IMPACT
There is no impact to the General Fund. This improvement is included in the Fiscal Year 2026- 27 Capital Improvement Budget and is funded by Gas Tax (SB1).
Item 327/2026
RECOMMENDATION
It is recommended that the City Council:
Approve the Cooperative Agreement with the City of Anaheim with an estimated cost of $114,898, for the street rehabilitation of Harbor Boulevard from Chapman Avenue to Convention Way; and
Authorize the City Manager, or designee, to execute the agreement and make minor modifications as appropriate thereto on behalf of the City.
By: Nick Hsieh, P.E.
Associate Engineer
ATTACHMENT(S)
1. Cooperative Agreement