item 18 Acceptance of the 2025 Various Streets Rehabilitation Project, Project No. CP-1442000, as complete. (Action Item)

Garden Grove City Council
August 11, 2026

Document
item 18 Acceptance of the 2025 Various Streets Rehabilitation Project, Project No. CP-1442000, as complete. (Action Item)
Meeting
August 11, 2026
Body
Garden Grove City Council
Pages
2
Original file
223 KB
Text extracted from the city's file for reading and search. Open the original on agendasuite.org. That file is the official record.

Item 334/2026

Final
City of Garden Grove

INTER-DEPARTMENT MEMORANDUM

To:

Lisa L. Kim From: Samuel Kim
Dept:

City Manager Dept: Public Works
Date: 8/11/2026

Subject: Acceptance of the 2025 Various Streets Rehabilitation Project, Project No. CP- 1442000, as complete. (Action Item)

OBJECTIVE

For City Council to accept the 2025 Various Streets Rehabilitation Project, City Project No. CP- 1442000 as complete and authorize the City Manager, or designee, to execute the Notice of Completion of Public Improvement and Work.

BACKGROUND

Street segments included in the 2025 Various Streets Rehabilitation Project were:

Orangewood Avenue from Knott Street to Western Avenue; Markon Drive from Blades Avenue to Patterson Drive; Blades Avenue from Markon Drive to Monarch Street; Monarch Street from southerly end to Patterson Drive; Edison Way from Lampson Avenue to Belgrave Avenue; Industry Street from southerly end to Chapman Avenue; Patterson Drive from Knott Street to Monarch Street; Honold Circle from Westly End to Markon Drive; Doig Drive from Monarch Street to end; Hunt Avenue from Monarch Street to end; Belgrave Avenue from Knott Street to Industry Street; Anaconda Avenue from Monarch Street to Western Avenue; Western Avenue from Lampson Avenue to Chapman Avenue; Commerce Drive from Capital Avenue to Forbes Avenue; Capital Avenue from Commerce Drive to Corporate Drive; Forbes Avenue from Commerce Drive to Euclid Street; Emperor Quang Trung from Corporate Drive to Euclid Street; Corporate Drive from Capital Avenue to Forbes Avenue; Euclid Street from Westminster Avenue to Trask Avenue; Cardinal Circle from west end to Harbor Boulevard; Salinaz Drive from Newhope Street to End; Anabel Avenue from Newhope Street to A Better Way; A Better Way from Westminster Avenue to Anabel Avenue; West Street from Westminster Avenue to end; and Seaboard Circle from Westminster Avenue to end.

On July 8, 2025, the City entered into a contract with RJ Noble Company, a general contractor.

Specifically, the project addressed each street segment with different rehabilitation measures to properly manage the unique circumstances and involved some or most of the following elements: removal and replacement of trees; removal and reconstruction of failed pavement areas; cold milling; installation of asphalt rubber aggregate membrane (ARAM); asphalt paving; replacement of concrete improvements; adjustment of utility covers to finished Item 334/2026

Page 2 of 2 ends

grade; installation of catch basin inlet screens; installation of CCTV cameras and traffic loops; restoration of traffic striping and signing; landscaping and irrigation improvements; and reestablishment of centerline ties and monuments.

DISCUSSION

The contractor, RJ Noble Company, has completed the improvements in accordance with the plans, specifications, and other contract documents.

FINANCIAL IMPACT

There is no additional financial impact associated with accepting these projects as complete.

The improvements were included in the Fiscal Year 2025-26 Capital Improvement Plan, and all project costs were budgeted and funded through Gas Tax, Drainage Fees, and Measure M2.

RECOMMENDATION

It is recommended that the City Council:

 Accept Project No. CP-1442000 – 2025 Arterial Streets Rehabilitation Project, as complete;

 Authorize the City Manager, or designee, to execute the Notice of Completion of Public Improvement and Work; and

 Authorize the Finance Director to release the retention payment when appropriate to do so.

By: Nick Hsieh, P.E.

Associate Engineer

ATTACHMENT(S)

1. Notice of Completion