La Crescenta Avenue Rehabilitation Project
City Council Meeting
August 27, 2024
Presented By:
Department of Public Works
1 Option 1: Original Scope of Work
1. Begin Construction November 2024
2. Complete Underground work April 2025
a) Sewer/Storm Water
b) Traffic Signal Infrastructure
3. Complete Aboveground work July 2025
a) Intersection Realignments
b) Traffic Signal Poles/Pullboxes/Mid-Block Crossings
4. Complete Paving work August 2025
a) New Street Pavement/Reflective Pavement
5. Complete Trees/Signing/Striping October 2025
6. Complete Creative Crosswalks and Project Closeout November 2025 2 Option 2: Original Scope of Work + Quick
Build Demonstration
1. Begin Construction November 2024
2. Complete Underground work April 2025
a) Sewer/Storm Water
b) Traffic Signal Infrastructure
3. Complete Aboveground work July 2025
a) Intersection Realignments
b) Traffic Signal Poles/Pullboxes/Mid-Block Crossings
4. Complete Quick Build Demonstration work August 2025 – January 2026
5. Complete Paving work February 2026
a) New Street Pavement/Reflective Pavement
6. Complete Trees/Signing/Striping March 2026
7. Complete Creative Crosswalks and Project Closeout April 2026 3 4
Quick-Build Option
• A quick build uses short-term, low-cost, and scalable improvements that allow for modifications and feedback before permanent project improvements through the use of:
• Traffic marking paint
• Flexible delineators
• Signage
• Will provide an opportunity to test the new roadway realignment • Still creates temporary improvements for people walking and biking • Allows engagement of the local community and collects and evaluates feedback and data in real-time
• Expected to last between 6 months
• Estimated cost of $800,000 for this project corridor
END