CAPITAL IMPROVEMENT PROJECTS
City Hall in Your Neighborhood
January 20, 2026
Presented By:

City of Glendale - Department of Public Works
Upcoming Projects
West Glendale ADA Curb Ramp
Installation and Sidewalk Repair
Program (ADA) Phase 2
West Glendale Pavement Management
Program Implementation Project (PMP)
Phase 1
San Fernando Road Beautification
Project (SFR) Phase 2
2 Project Scopes
West Glendale
ADA Phase 2
West Glendale
PMP Phase 1
SFR Phase 2
Pedestrian and
Roadway
Improvements
Traffic Safety
and Signal
Improvements
Landscape
Parkway
Improvements
Creative
Crosswalks
Sidewalk
Repair
ADA Curb
Ramp
Installation
Curb, Gutter,
and Cross
Gutter Repair
Driveway and
Alley Apron
Improvements
Asphalt
Pavement
Improvements
Sewer
Improvements
Skewed
Intersection
Re-alignment
Street Striping
and Marking
Improvements
3 Project Locations

West Glendale ADA Phase 2 West Glendale PMP Phase 1
4 Project Locations

San Fernando Road
Beautification Project Phase 2
5 Construction Schedules
West Glendale ADA
Phase 2

ANTICIPATED

CONSTRUCTION
START DATE:

May 2026

ANTICIPATED

CONSTRUCTION END
DATE:

October 2026
*barring any unforeseen
conditions
West Glendale PMP
Phase 1

ANTICIPATED

CONSTRUCTION START
DATE:

September 2026

ANTICIPATED

CONSTRUCTION END
DATE:

January 2027
*barring any unforeseen
conditions
SFR Phase 2

ANTICIPATED

CONSTRUCTION
START DATE:

February 2027

ANTICIPATED

CONSTRUCTION
END DATE:

August 2027
*barring any
unforeseen conditions
6 Project Outreach
• Community Open House and
Meetings
• Stakeholder meetings as needed
• Community Events
• Social media and website updates
• Director’s Letter 1-2 months before
start of construction
• Door Hanger Notifications before
start of construction
7 Contact
Huang Zheng, P .E., Project Manager
[email protected]
(818) 548-3945
Yvonne Guerra, Public Outreach
[email protected]
(818) 548-3945

www.GlendalePWprojects.com