Pavement Management Program - 2025 Update
Presented by: Public Works Department
April 28, 2026
Item 10.c
378
Miles of Roadway
(27 miles of alleys)
$840M
Replacement
Asset Value
PCI 65
Current Network
Condition (Fair)
$238M
Cost to Restore
to Target Condition
WHY THIS MATTERS:
To maintain and improve the condition of
the City’s roadway infrastructure
systems, for safety, mobility, and quality
of life for Glendale citizens.
2 What is a Pavement Management Plan (PMP)
• Data-driven system using Pavement Condition
Index (PCI) scoring
• Assigns PCI (0–100) to every road segment
citywide
• Recommends most cost-effective treatment for
each segment
• Focuses on preservation over "worst-first"
replacement strategy
• Maximizes life-cycle return on investment
• Supports SB1 accountability and State funding
reporting requirements
Pavement Condition Index (PCI) Scale
Good 86–100
Satisfactory 71–85
Fair 56–70WE ARE HERE
Poor 41–55
Very Poor 26–40
Serious 11–25
Failed 0–10
3 Examples of PCI
• 1700 Block of Thurber Place
• PCI: 95
• 300 Block of California Avenue
• PCI: 70
• 400 Block of Howard Street
• PCI: 31
4 Our Network Today
378
Total Miles
92%
Asphalt
8%
Concrete/Other
PCI 65
Overall Score
Roadway Classification & PCI Scores
Main Streets PCI: 71 33 mi
Arterials PCI: 65 24 mi
Collectors PCI: 67 74 mi
Local Roads PCI: 61 210 mi
Alleys PCI: 78 27 mi
Data collected using LCMS, LiDAR, and 360° imaging technology Classification breakdown reflects asphalt roads only. 10 miles of concrete roads included in the 378-mile network are analyzed separately. 5 PCI Trends: 2007-2025
2007 2010 2012 2015 2020 2025
50 55
60 65
70 75
80 85
90 73
75 76
74 72
65 PCI History
Why the Decline?
Aging infrastructure past preservation
window
Improved PMP methodogly
Inflation & construction cost escalation
Expanded ADA and
complete-street requirements
Competing capital priorities
for funding
6 Current funding levels for pavement
rehabilitation
Why Timing Matters: The Cost of Delay
Preventive
Maintenance
$1
relative cost
At 75–85% life
Crack seal, slurry seal
Preserves good roads
Best ROI
Rehabilitation
(Wait too long)
$3–4
relative cost
At 50–65% life
Asphalt overlay
More disruption
Higher cost
Full
Reconstruction
$5+
relative cost
At 0–30% life
Remove & replace
Maximum disruption
Avoidable if treated early
7 Funding Scenarios: 5-Year Outlook
Investment vs. Outcome
Annual Invest. 2029 PCI 5-Yr Result
$0/yr ~60 Baseline Case
$3M/yr ~62 PCI decline
$9.7M/yr ~65 Hold current
condition
$22M/yr ~72 Significant
improvement
Investment level directly determines system performance and long-term costs Planning Scenarios
8 CompleteSan Fernando Road Beautification
Phase 1 ($13.2M)
Complete street reconstruction, bike lanes, pedestrian
improvements, creative crosswalks, storm water improvements CompletePermeable Alley Project ($6.3M)
Alley pavement rehabilitation with permeable pavement
improvement
CompleteCommunity Beautification Project
(Acacia Avenue and adj Streets) $8.1 M
Pavement Rehabilitation, curb/gutter, ADA ramps, streetscape upgrades, sewer and storm drain improvements
CompleteBroadway Rehabilitation Project
($4.1M)
Pavement Rehabilitation, curb/gutter, ADA ramps, streetscape upgrades, sewer and storm drain improvements
OngoingLa Crescenta Avenue Rehabilitation
Project ($14.5M)
Complete street reconstruction, bike lanes, pedestrian
improvements, creative crosswalks, storm water improvements OngoingMaintenance District 6 Pavement
Rehabilitation Project Phase 2 ($9M)
Pavement Rehabilitation, curb/gutter, ADA ramps, streetscape upgrades
capital projects delivered: 20 | total program investment: $97M Past 5 Year Highlight
9 $97M
Invested
FY 2022–2026
~$3 M/yr
Allocated to direct
pavement rehabilitation
vs. $9.7M/yr needed
Roadway Infrastructure Investment Past 5- Years
Asphalt Pavement
14%
Concrete
Improvement
22%
Green
Improvements
16%
Sewer and
Stormwater
10%
Striping and Traffic
Signal
29%
Misc. Improvements
9%
10 Trench Moratorium
Enforcement
PCI Based moratorium on cutting newly paved
streets. Utilities must coordinate before repaving.
Violations tracked and enforced.
Utility
Coordination
Pre-pave coordination with public and private
utilities to ensure roads aren't cut after
resurfacing.
Restoration
Standards
Updated trench restoration specifications ensure
repairs match surrounding pavement quality and
extend service life.
Project Packaging
& Unit Costs
Larger project packages achieve better unit
pricing. Tracking cost per square foot ensures
competitive bids and maximum coverage.
Protecting the Investment
11 The following interactive GIS web maps are available online and provide detailed spatial data referenced in this report:
Exhibit 4: Pavement Management Plan (PMP)
GIS Web Map
glendaleca.gov/PWPCIMap
Exhibit 5:Capital Improvement Program (CIP)
GIS Web Map
glendaleca.gov/PWCIPMap
Exhibit 6: Moratorium Streets GIS Web Map
glendaleca.gov/PWStreetMoratorium