Agenda Item B.6
CPMS CONSENT CALENDAR
Meeting Date: May 17, 2022
____________________________________________________________ TO: Mayor and Councilmembers
FROM: Charles W. Ebeling, Public Works Director
CONTACT: Teresa Lopes, Senior Project Manager
SUBJECT: Notice of Completion of Fairview Avenue Sidewalk Infill Project (Project No. 9070)
RECOMMENDATION:
A. Adopt Resolution No. 22-___ entitled “A Resolution of the City Council of the City of Goleta, California, Authorizing the Filing of a Notice of Completion for Fairview Avenue Sidewalk Infill Project”; and
B. Direct the City Clerk to file a Notice of Completion with County Recorder’s Office.
BACKGROUND:
The Fairview Avenue Sidewalk Infill Project was included as part of the City’s 5 -year Capital Improvement Program (CIP) and identified as Project No. 90 70. The project consisted of the completion of sidewalk along the north side of the South Fairview Avenue, west of the intersection of North Fairview Avenue and northbound US 101 on and off-ramps. The scope of work included sidewalk infill improvements necessa ry to conform to the existing bicycle and pedestrian ramp connecting South Fairview Avenue and Calle Real.
The City received a Measure A South Coast Regional Bicycle & Pedestrian Program Cycle 3 grant to construct the project improvements and in July 2018, the City entered into a Professional Design Services Agreement 201 8-060 with Stantec Consultant Services, Inc. to complete the design for the project.
On July 20 , 20 20, the City Manager awarded the construction contract to , Lash Construction, Inc. in a not-to-exceed amount of $59,874, with a contingency of $124.44.
On August 5, 2020, the City Manager execute d a consultant services agreement with MNS Engineers, Inc. in an amount not-to-exceed $44,000 for construction management and inspection services.
1 Meeting Date: May 17, 2022
Throughout the design process, Public Works engaged the community and neighboring businesses numerous times (in both English and Spanish) regarding the overall design, and potential construction impacts.
DISCUSSION:
On July 21, 2020, Public Works i ssued Lash Construction, Inc. a Notice to Proce ed to commence work on September 8, 2020. Construction activities consisted of construction of new sidewalk to fill the sidewalk gap along the north side of South Fairview Avenue leading to the signalized intersection at the northbound US 101 off -ramp. The work also included removal and replacement of existing sidewalk to conform to the existing bicycle and pedestrian ramp connection at Fairview Avenue and Calle Real per the Project plans and specifications.
The work was performed per the approved project Plans and Specifications. Lash Construction, Inc. completed construction on October 7 , 202 0, on budget. A change order, CCO-01, was issued to provide a credit for a materials quantity reduction, CCO-01 was issued to remove a “No Ped” sign, and CCO-03 was issued to include additional PCC Sidewalk.
Public Works is recommending adoption of the proposed resolution to facilitate the final close-out of this project (Attachment 1). A Notice of Completion pursuant to Public Contract Code §20854 is recommended for approval and direction to be filed with the County of Santa Barbara, County Recorder Office (Attachment 2).
FISCAL IMPACTS:
The construction, contingency, equipment, and construction management and inspection costs were estimated to be $103,998.44. The actual cost for construction, including quantity changes and construction management, totaled approximately $75,000. There were no change orders issued that affected the cost of the project. The final budget worksheet for the construction and the overall project costs are shown in the following tables.
TOTAL PROJECT COST SUMMARY
Project Components Estimated
Costs
Funding Source Funding
Amounts
Staff/Project Management
(City Staff and Consultant) $11,230 Measure A Grant (206) $17,524 Design (Stantec) $12,700 Measure A (205) $66,000
Construction $59,874 Transportation DIF (220) $7,625
CM (Consultant) $7,345
Total: $91,149 Total: $91,149
2 Meeting Date: May 17, 2022
Project Funding
The table below summarizes the project budget, funding source accounts, costs, and revised project budget amounts.
Fairview Avenue Sidewalk Infill Project Budget – Project No. 9070 Fund Account
FY 20/21
Amended
Budget
Actual
Costs*
Remaining
Budget*
Measure A 205-90-9070-57070
$17,524 $17,524 $0
Measure A
Grant
206-90-9070-57071
$66,000 $66,000 $0
GTIP Fund 220-90-9070-57071
$7,625 $7,625 $0
Total $91,149 $91,149 $0
* Estimated numbers. Final numbers will reflect actual costs from final invoices (estimated to date).
ALTERNATIVES:
The City Council may elect to direct staff to not file a Notice of Completion for the project.
If a Notice of Completion is not filed, then the project will not be officially closed out.
Reviewed By: Legal Review By: Approved By:
___________________ ___________________ _________________ Kristine Schmidt Megan Garibaldi Michelle Greene
Assistant City Manager City Attorney City Manager
ATTACHMENTS:
1. A Resolution of the City Council of the City of Goleta, California, Authorizing the Filing of a Notice of Completion for the Fairview Avenue Sidewalk Infill Project.
2. Notice of Completion for the Fairview Avenue Sidewalk Infill Project.
3 ATTACHMENT 1
A Resolution of the City Council of the City Goleta, California Authorizing the Filing of a Notice of Completion for the Fairview Avenue Sidewalk Infill Project 4 RESOLUTION NO. 22 - ___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
GOLETA, CALIFORNIA, AUTHORIZING THE FILING OF A NOTICE
OF COMPLETION FOR THE FAIRVIEW AVENUE SIDEWALK
INFILL PROJECT
WHEREAS, on July 20 , 20 20, the City of Goleta authorized award of a construction contract to Lash Construction, Inc., for the Fairview Avenue Sidewalk Infill Project; and
WHEREAS, the City Engineer has evaluated the work and has determined that the work was satisfactorily completed within the City extended contract period and within budget; and
WHEREAS, the City Engineer recommends the filing of a Notice of Completion pursuant to Government Code section 20854.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF GOLETA AS FOLLOWS:
SECTION 1.
The work required to be performed by said Contractor has been completed.
SECTION 2.
The work is hereby accepted and approved based on the recommendation of the City Engineer.
SECTION 3.
The Finance Department is directed to release retention posted for the completion of the project as required by the California Civil Code.
SECTION 4.
The City Clerk is directed to forthwith forward a Notice of Completion to the Recorder of the County of Santa Barbara for recording.
5 SECTION 5.
The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.
PASSED, APPROVED, AND ADOPTED this 17th day of May, 2022.
__________________________
PAULA PEROTTE,
MAYOR
ATTEST: APPROVED AS TO FORM:
_________________________ __________________________
DEBORAH S. LOPEZ MEGAN GARIBALDI
CITY CLERK CITY ATTORNEY
6 STATE OF CALIFORNIA )
COUNTY OF SANTA BARBARA ) ss.
CITY OF GOLETA )
I, DEBORAH S. LOPEZ, City Clerk of the City of Goleta, California, DO HEREBY CERTIFY that the foregoing Resolution No. 22-___ was duly adopted by the City Council of the City of Goleta at a regular me eting held on the 17th day of May 2022, by the following vote of the Council.
AYES:
NOES:
ABSENT:
(SEAL)
___________________________
DEBORAH S. LOPEZ
CITY CLERK
7 ATTACHMENT 2
Notice of Completion for the Fairview Avenue Sidewalk Infill Project 8 RECORDING REQUESTED BY:
WHEN RECORDED RETURN TO:
City of Goleta
130 Cremona Drive, Suite B
Goleta, CA 93117
ATTN: CITY CLERK
__________________________________________________________________ SPACE ABOVE THIS LINE FOR RECORDER’S USE
Exempt from recording fee, per Government Code
Section 27383
CITY OF GOLETA, CALIFORNIA
By: __Deborah S. Lopez______
City Clerk
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN that a contract was heretofore awarded by the City Manager of the City of Goleta, California, to Lash Construction, Inc. , (Attn: Matt Doyle), P.O. Box 4640, Santa Barbara, CA 93140 for the performance of the following work located in the public right of way on Fairview Avenue:
FAIRVIEW AVENUE SIDEWALK INFILL PROJECT
Said work was completed on October 7, 2020, by said company; was completed in accordance with City standards and to the satisfaction of the City Engineer of the City of Goleta; and was accepted by the City Council of the City of Goleta, owner, at a regular meeting thereof held on the 3rd day of May 2022, by Resolution No. 22-__.
DATED this 17th day of May, 2022, at Goleta, California.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
______________________________
DEBORAH S. LOPEZ,
CITY CLERK
9 STATE OF CALIFORNIA )
COUNTY OF SANTA BARBARA ) ss
CITY OF GOLETA )
I, Deborah S. Lopez, City Clerk of the City of Goleta, California, do hereby certify that the foregoing Notice of Completion is true and correct, and that said Notice of Completion was duly and regularly ordered to be recorded in the Office of the Santa Barbara County Recorder by said City Council.
DATED this 17th day of May 2022, at Goleta, California.
________________________________
DEBORAH S. LOPEZ
CITY CLERK