Agenda Item A.6
CPMS CONSENT CALENDAR
Meeting Date: November 1, 2022
TO: Mayor and Councilmembers
FROM: Jaime A. Valdez, Neighborhood Services Director
CONTACT: JoAnne Plummer, Parks and Recreation Manager
Teresa Lopes, Senior Project Engineer
SUBJECT: Approval of Plans and Specifications, and Authorization to Advertise for Bids for the Armitos Park Improvements /Community Garden and Multipurpose Bike Path (CIP 9084 and CIP 9007)
RECOMMENDATION:
A. Approve Plans and Specifications for CIP Projects 9084 and CIP 9007 Armitos Park Improvements/Community Garden and Multipurpose Bike Path; and
B. Authorize staff to advertise a notice inviting bids for CIP Projects 9084 and CIP 9007 Armitos Park Improvements/Community Garden and Multipurpose Bike Path.
BACKGROUND:
In 2015, the City Council adopted the Recreation Needs Assessment that included a recommendation for the design and construction of a community garden in Golet a.
Through careful evaluation of existing City-owned properties, it was determined that the ideal location would be the undeveloped portion of the Armitos Park property in Old Town on Armitos Avenue. At that time the project was added to the City’s adopte d Capital Improvement Project listing as CIP Project 9084. The San Jose Creek Bike Path – Middle Extent project was also a current CIP Project (CIP No. 9007) which consisted of constructing a section of the San Jose Creek Bike Path extending from Jonny D. Wallis Park to Armitos Ave. As a portion of this segment of the bike path occupie s the same parcel as the proposed community garden and the existing Armitos Park it was determined by Public Works and Neighborhood Services staff to combine the two projects to be constructed as one combined project.
In 2019, the City of Goleta applied for a State of California Proposition 68 Grant to fund this project. As part of the application process, it was necessary to provide a conceptual design of the proposed project. As part of this process, five community meetings were held to define community desires. The conceptual design was reviewed by representatives from UCSB’s Master Gardener Progra m, Fairview Gardens and community members with a strong interest in the project, which provided recommendations for improvements that were incorporated. The revised conceptual design was presented to and supported by the Parks and Recreation Commission at their meeting of October 2, 2019.
1 Meeting Date: November 1, 2022
Moreover, in February of 2019, Public Works staff submitted an application to the Santa Barbara County Association of Governments (SBCAG) to participate in Cycle 4 of the Measure A South Coast Regional Bicycle & Pedestria n (Bike and Ped) program for funding for the construction phase of the San Jose Creek Bike Path Middle Extent Project.
On June 2019, the SBCAG Board approved and authorized the execution of a Cooperative Agreement with the City of Goleta to contribute $181 ,320 of grant funding for the Project. The City Council approved the Cooperative Agreement with SBCAG on August 20, 2019.
At the end of October 2019, the City released a Request for Proposals for the professional design, plans, specifications and estimate services for the Community Garden, San Jose Creek Bike Path and Improvements at Armitos Park. Three proposals were received and upon staff evaluation, it was determined that RRM, Inc. was considered the most qualified to deliver the project.
On February 4, 2020, the City Council authorized the City Manager to enter into a Professional Design Services Agreement with RRM, Inc for the design of the Community Garden, Miscellaneous Improvements at Armitos Park, and the incorporation of the existing plans for San Jose Creek Bike Path at Armitos Park in an amount not to exceed $108,200.
In July 2020, the City Council reviewed the design and approved it with recommendations.
Since that time, RRM has been developing construction documents and the project is now ready to proceed to the bidding process.
DISCUSSION:
Armitos Park was built in 2009 as a response to the need for more opportunities for outdoor recreation in this area. The existing parcel is over 64,000 square feet (SF) and currently only 17,000 SF have been developed with an access path, a park bench, a small turf area, and small playground for 5 –12-year-olds. The playground structure is approximately ten years old and in good condition and could be salvaged. The project has a bid alternate to install a new playground in its place, should funding allow. The pour- in-place surfacing is damaged and will be replaced and expanded.
Improvements/additions to be made at the existing park include adding swings for all ages and abilities, bike racks, new safety surfacing, sand play features, musical elements, ADA accessible path, benches, and fencing.
In 2015 the City Council adopted the Recreation Needs Assessment that called for construction of a community garden in Goleta. The remaining 47,000 square feet of the Armitos Park property was chosen for the location of th is new community garden. The location is ideal for this project because it is already owned by the City, is located in close proximity to higher density housing, and the Old Town area is considered a food desert in terms of accessibility to affordable fresh fruits and vegetables.
The Community Garden features 50 raised garden beds of two different sizes, tool sheds, interpretive signs, hose bibs, tables/sink for cleaning, education and/or gathering area and a small picnic area with a pizza oven instead of BBQ brazier. The garden will be accessible to users by a code they will receive once they have reserved a garden plot. 2 Meeting Date: November 1, 2022
The fencing not only surrounds the garden area, but also the playground area. The gates surrounding playground will be battery operated and automatically unlocked during park hours and locked at dusk.
The rental cost of the garden plots and how the rental program will be managed is still under review. Staff is currently evaluating the benefits and cost effectiveness of this program managed by a non-profit organization, a business and or the City of Goleta. The maintenance of the facility will be absorbed by the Parks and Open Space Division in Public Works.
Conceptual Design
In addition to the new improvements to Armitos Park and the new community garden, the project includes construction of a new Multipur pose bike/pedestrian path (a segment of the overall San Jose Creek Multipurpose Path) that will connect Armitos Park to Jonny D.
Wallis Neighborhood Park to the south. The ne w Multipurpose path will provide a safe off-street connection between the two parks for active recreational and transportation uses and will eventually connect to the overall San Jose Creek Multipurpose Path Project Northern and Southern Segments providing Old Town Goleta residents with active transportation opportunities to both the north and south of the project site. The Multipurpose path is designed as a linear park and will include features such as interpretive/educational signage about the San Jose Creek and surrounding riparian area and opportunities for passive recreation for enjoying the beauty of the creek.
The plans and specifications for both projects consist of the plan sheets, bid documents, the City’s general provisions, and project special provisions. As discussed in greater detail in the Fiscal Impacts section of this report, the latest construction cost estimate for the 3 Meeting Date: November 1, 2022
Armitos Park improvements and community garden are approximately $1,180,725. The current cost estimate for the constructi on of the Multipurpose path is approximately, $450,000. Staff is requesting that the City Council approve these plans and specifications and authorize staff to advertise for construction bids for the project. It is intended that this project will follow th e same timelines as the Splash Pad and improvements at Jonny D.
Wallis Neighborhood Park in order to reduce construction impacts to the neighbors.
FISCAL IMPACTS:
The following table shows the total estimated project costs combined for both projects.
Project Components (CIP 9084 and CIP 9007) Estimated Costs Estimated Balance
Needed
CIP 9084 CIP 9007
Right-of-way Acquisition $0 $150,000 $0
Design/Environmental $62,271 $112,500** $0
Estimated Construction Cost* $1,180,725 $450,000 $1,630,725 Estimated Construction Management/Contingency $330,604 $157,500 $488,104 Total Expenditure Estimate $1,573,600 $870,000 $2,118,829
*Based on current cost estimates
**Design costs estimated as actual costs include the stretch of San Jose Creek Bike Path through JDW Park in addition to the portion being built with this Project
It is important to note that the Right -of-way Acquisition (all property needed has already been acquired) and Design/Environmental costs have already been expended. The following ta ble captures the currently available allocations for construction and construction management.
Armitos Park Improvements/Community Garden (CIP 9084) and Multipurpose Bike Path (CIP 9007), FY 2022/2023
Fund Type Account Approved
Allocations
Currently
Available
Appropriation
Requested
(Total not to
exceed
amount)
Park DIF 221-90-9084-57071 $1,524,334 0 $1,524,334
Subtotal $1,524,334 0 $1,524,334
Transportation
DIF
202-90-9007-57071 $28,097 0 $28,097
Measure A Local 205-90-9007-57071 $160,000 0 $160,000
Measure A Other 206-90-9007-57071 $168,320 0 $168,320
Transportation
Facilities DIF
220-90-9007-57071 $289,369 0 $289,369
Subtotal $645,786 0 $645,786
TOTAL $2,170,120 $2,170,120
Staff utilized current cost estimates for both projects , and it appears that there are sufficient funds allocated to complete the combined projects. Actual construction costs and construction management, inspection and testing costs will be determined once bids are received. Any additional allocation of funds which may or may not be necessary will be determined when the Project is brought back to City Council for award. Staff is aware 4 Meeting Date: November 1, 2022
and notes that labor and material costs have been increasing significantly—particularly since the beginning of 2022.
It should be noted that the City applied for two separate rounds of the Proposition 68 Competitive Grant Program, and an Urban Greening Grant, but was unfortunately unsuccessful.
GOLETA STRATEGIC PLAN:
City-Wide Strategy: Support Community Vitality and Enhanced Recreational Opportunities
Strategic Goal: Support programs that enhance quality of life in the Goleta community such as recreation, public safety, human services, and cultural arts
City-Wide Strategy: Strengthen Infrastructure
Strategic Goal: Strengthen Citywide infrastructure including roads and traffic circulation, including bicycle lanes, paths, and sidewalks.
Strategic Goal: Encourage use of Alternative Transportation Methods that Reduce Vehicle Miles Traveled.
City-Wide Strategy: Return Old Town to a Vital Center of the City
Strategic Goal: Complete design and construction of the San Jose Creek Bike Path Project (Middle Extent) from Jonny D. Wallis Park to Armitos Avenue.
ALTERNATIVES:
The City Council may elect to not approve the plans and specifications and not authorize staff to advertise for construction bids for this project. Doing so would delay the construction of the project.
Reviewed By: Legal Review By: Approved By:
___________________ ___________________ _________________ Kristine Schmidt Megan Garibaldi Robert Nisbet
Assistant City Manager City Attorney City Manager
ATTACHMENT:
1. Armitos Park Improvements/Community Garden and Multipurpose Bike Path – Plans (Available Online Only)
2. Armitos Park Improvements/Community Garden and Multipurpose Bike Path – Specifications (Available Online Only)
5 ATTACHMENT 1
Armitos Park Improvements/Community Garden
and Multipurpose Path
(CIP 9084 and CIP 9007)
Final Plans
6 7
G002
GENERAL NOTES
CHRIS DUFOUR
SSCD
AND ABBREVIATIONS
ABAGGREGATE BASE OR ANCHOR BOLT
ABV ABOVE
AC ASPHALTIC CONCRETE
ACP ASPHALTIC CONCRETE PAVING
ADJ ADJACENT
AGG AGGREGATE
ALT ALTERNATE
APANGLE POINT
APPROX APPROXIMATE
ARCH ARCHITECT (URAL)
BEL BELOW
BLDG BUILDING
BLK BLOCK
BOT BOTTOM
BOW BACK OF WALK
BRBOTTOM OF RAMP
BRG BEARING
BSW BACK SIDEWALK
CBCATCH BASIN
CFCUBIC FOOT
CICAST IRON
CIP CAST IN PLACE
C/L CENTERLINE
CLCENTERLINE
CLR CLEAR
CMU CONCRETE MASONRY UNIT
CO CLEAN OUT
COL COLUMN
CONC CONCRETE
CONST CONSTRUCTION
CONT CONTINUOUS, CONTINUE
CPCONTROL POINT
CRCURB RETURN
CTC CENTER TO CENTER
CTR CENTER
DAS DIRECTION AS SHOWN
DET DETAIL
DFDRINKING FOUNTAIN
DIDRAIN INLET
DIA DIAMETER
DIAG DIAGONAL
DIM DIMENSION
DSDOWN SPOUT
DWG DRAWING
EAEACH
EJEXPANSION JOINT
ELECT ELECTRICAL
ELEV ELEVATION
ENCL ENCLOSURE
EQEQUAL
EQPT EQUIPMENT
ESMT EASEMENT
EWF ENGINEERED WOOD FIBER
EXEXISTING
EXIST EXISTING
(E)EXISTING
FAB FABRICATION
FBO FURNISHED BY OTHERS
FFFINISHED FLOOR
FFEFINISHED FLOOR ELEVATION
FGFINISHED GRADE
FINFINISH (ED)
FLFLOWLINE
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF STEP
FND FOUNDATION
FSFINISHED SURFACE
FSTFINISHED SURFACE TURF
FTG FOOTING
FUT FUTURE
GA GAGE, GAUGE
GBGRADE BREAK
GKT GASKET
GLV GALVANIZED
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GRGRATE
HBHOSE BIB
HCHANDICAPPED
HCAP HANDICAPPED
HDB HEADBOARD
HEX HEXAGONAL
HOR HORIZONTAL
HPHINGE POINT, HIGH POINT
HTHEIGHT
IDINSIDE DIAMETER
INTINTERSECTION
INV INVERT
JTJOINT
LLENGTH
LBLAG BOLT
LHLEFT HAND
LOC LOCATION
LPLOW POINT
LSLAG SCREW
LTLEFT
MAS MASONRY
MATL MATERIAL
MAX MAXIMUM
MED MEDIUM
MFG MANUFACTURING
MFR MANUFACTURE(R)
MIN MINIMUM
MISC MISCELLANEOUS
MLMAINLINE
(N)NEW
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NTS NOT TO SCALE
OC ON CENTER
OCEW ON CENTER EACH WAY
OD OUTSIDE DIAMETER
O.F.C.I. OWNER FURNISHED, CONTRACTOR INSTALLED
OH OVERHEAD
OPP OPPOSITE
OPT OPTIONAL
PAPLANTER AREA
PCPOINT OF CURVE
PERF PERFORATE (D)
PERP PERPENDICULAR
PFE PUBLIC FACILITIES EASEMENT
PLPROPERTY LINE
POB POINT OF BEGINNING
POC POINT OF CONNECTION
PRC POINT OF REVERSE CURVE
PROP PROPOSED
PSIPOUNDS PER SQUARE INCH
PTPOINT, POINT OF TANGENCY
PTDF PRESSURE TREATED DOUGLAS FIR
PTLPRESSURE TREATED LUMBER
PUE PUBLIC UTLITIES EASEMENT
PVC POLYVINYL CHLORIDE
R, RAD RADIUS
RDWD REDWOOD
REBAR REINFORCING BAR
REF REFERENCE
REM REMOVE
REQ'D REQUIRED
REV REVISION(S), REVISED
RHRIGHT HAND
ROW RIGHT OF WAY
RTRIGHT
SSLOPE
SCH SCHEDULE
SDSTORM DRAIN
SFSQUARE FEET
SHT SHEET
SIM SIMILAR
SLSLOPE
SPEC SPECIFICATION(S)
SQSQUARE
SSSANITARY SEWER
S/SSTAINLESS STEEL
STSTREET
STA STATION
STD STANDARD
STLSTEEL
STRUC STRUCTURE/ STRUCTURAL
SURF SURFACE
SWCL SIDEWALK CENTERLINE
SYS SYSTEM
SYN SYNTHETIC
TBC TOP BACK OF CURB
TCTOP OF CURB
TFTOP OF FOOTING
TPTANGENT POINT
TRTOP OF RAMP
TSTOP OF STEP
TWTOP OF WALL
TYP TYPICAL
UON UNLESS OTHERWISE NOTED
VAR VARIES
V.I.F. VERIFY IN FIELD
VERT VERTICAL
WWATER
W/WITH
W/O WITHOUT
@AT
℄CENTERLINE
ØDIAMETER
SFSQUARE FEET
GENERAL CONSTRUCTION NOTES ABBREVIATIONS
KEY TO SHEET NUMBERING
DRAWING SHEET NUMBERING AND ORGANIZATION IS ADAPTED FROM THE UNITED STATES NATIONAL CAD STANDARD.
LC103
Discipline Designator
Sequence Number
Sheet Type
DISCIPLINE DESIGNATORS - LEVEL 1 (Partial List)
G General
R Resource (Existing Conditions)
H Hazardous Materials
V Survey/Mapping
B Geotechnical
C Civil
L Landscape
S Structural
A Architectural
E Electrical
Z Contractor/Shop Drawings
Level 1
Level 2
DISCIPLINE DESIGNATORS - LEVEL 2 (Partial List)
D Demolition
S Site
G Grading
E Erosion Control
U Utilities
C Construction
I Irrigation
P Planting
L Lighting
W Stormwater
H Horizontal Control
SHEET TYPES
0 General: Symbol legend, abbreviations,
general notes.
1 Plans
2 Elevations
3 Sections
4 Large Scale Drawings: plans, elevations,
sections (not details)
5 Details
6 Schedules and Diagrams
7 User Defined
8 User Defined
9 3D Drawings: isometric, perspective, photos
Example
Sheet number at left (LC103) is LANDSCAPE CONSTRUCTION PLAN, THIRD SHEET.
1. PRIOR TO BEGINNING CONSTRUCTION, THE CONTRACTOR SHALL
VERIFY ALL JOIN CONDITIONS FOR GRADING, DRAINAGE, AND
UNDERGROUND FACILITIES, INCLUDING LOCATION AND ELEVATION
OF EXISTING FACILITIES AT CROSSINGS WITH PROPOSED
UNDERGROUND FACILITIES. IF CONDITIONS DIFFER FROM THOSE
SHOWN ON THE PLANS, THE CONTRACTOR SHALL NOTIFY THE CITY
AND SHALL NOT BEGIN CONSTRUCTION UNTIL THE CHANGED
CONDITIONS HAVE BEEN EVALUATED AND RESOLVED.
2. THE CONTRACTOR SHALL BECOME FAMILIAR WITH THE PLANS AND SITE CONDITIONS PRIOR TO BEGINNING WORK. SHOULD
CONFLICTING INFORMATION BE FOUND ON THE PLANS, THE
CONTRACTOR SHALL NOTIFY AND RECEIVE DIRECTION FROM THE
CITY BEFORE PROCEEDING WITH THE WORK IN QUESTION.
3. ONLY "APPROVED" STAMPED AND SIGNED DRAWINGS SHALL BE USED FOR THE CONSTRUCTION OF THIS PROJECT.
4. NO CHANGES OR MODIFICATIONS TO THE PLANS SHALL BE MADE WITHOUT THE PRIOR WRITTEN APPROVAL OF THE CITY.
5. CONSULT WITH WITH THE CITY'S ARBORIST PRIOR TO PRUNING OR WORKING WITHIN THE DRIPLINE OF ANY TREE. ALL PRUNING OF TREES
SHALL BE KEPT TO A MINIMUM AND MUST FOLLOW CITY OF GOLETA STANDARDS. TREE PRUNING OCCURRING IN THE RIPARIAN ZONE
SHALL BE PERFORMED UNDER REVIEW OF CITY'S AUTHORIZED
BIOLOGIST.
6. NO TREES, OTHER THAN THOSE INDICATED ON THE DRAWINGS, SHALL BE REMOVED WITHOUT PRIOR APPROVAL OF THE CITY.
7. NO MATERIALS OR EQUIPMENT SHALL BE STORED WITHIN THE DRIPLINE OF ANY TREE.
8. ALL NUMERIC AND WRITTEN DIMENSIONS SHALL HAVE PRECEDENCE OVER ALL SCALE DIMENSIONS.
9. DETAILS AND NOTES ON THE DRAWINGS TAKE PRECEDENCE OVER TYPICAL DETAILS AND GENERAL NOTES. WRITTEN SPECIFICATIONS TAKE PRECEDENCE OVER DRAWINGS.
10. ALL CONSTRUCTION SHALL CONFORM TO THE APPROVED PLANS AND SPECIFICATIONS. IN THE ABSENCE OF A SPECIFIED STANDARD
OR SPECIFICATION, WORK SHALL CONFORM TO THE CURRENT CITY OF GOLETA STANDARDS. IF NONE EXISTS, STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION (GREENBOOK 2018), SHALL APPLY.
11. CONTRACTOR SHALL USE PRECAUTION TO PREVENT DISRUPTION OF PROJECT SITE IN AREAS OUTSIDE CONSTRUCTION ZONE. DAMAGES SHALL BE REPLACED OR REPAIRED BY CONTRACTOR. CONTRACTOR
SHALL SUBMIT VIDEO LOG OF CONSTRUCTION SITE THROUGHOUT
DURATION OF PROJECT.
12. THE CONTRACTOR SHALL NOTIFY THE CITY AT LEAST 48 HOURS BEFORE COMMENCING WORK.
13. PROPOSED DEVIATIONS FROM THE PLANS MUST BE SUBMITTED TO THE
CITY FOR REVIEW AND APPROVAL, INCLUDING FIELD REVISIONS REQUESTED BY THE CITY INSPECTOR.
14. THE CONTRACTOR SHALL EMPLOY ALL LABOR, EQUIPMENT, AND
METHODS REQUIRED TO PREVENT HIS OPERATIONS FROM
PRODUCING DUST IN AMOUNTS DAMAGING TO PROPERTY,
CULTIVATED OR NATIVE VEGETATION, AND DOMESTIC AND
NON-DOMESTIC ANIMALS OR CAUSING A NUISANCE TO PERSONS
OCCUPYING BUILDINGS IN THE VICINITY OF THE JOB SITE. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE CAUSED
BY DUST RESULTING FROM HIS OPERATIONS.
15. CONSTRUCTION LINE AND GRADE STAKES SHALL BE SET BY A CIVIL ENGINEER OR SURVEYOR LICENSED IN THE STATE OF CALIFORNIA.
CONTRACTOR SHALL IDENTIFY AND STAKE ACCESS AND DRAINAGE EASEMENTS IN THE FIELD.
16. CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OR PROPER
RESETTING OF ALL EXISTING MONUMENTS AND OTHER SURVEY
MARKERS. ANY SURVEY MONUMENTS DESTROYED BY THE
CONTRACTOR SHALL BE REPLACED IN ACCORDANCE WITH THE
STATE LAND SURVEYORS ACT AT THE CONTRACTOR'S EXPENSE.
17. ALL PROTECTIVE DEVICES TO BE INSTALLED BY THE CONTRACTOR, SHALL BE IN PLACE AT THE END OF EACH WORK DAY. A SAFE
PEDESTRIAN PATH OF TRAVEL SHALL BE PROVIDED AT ALL TIMES TO
AND FROM BUILDING ENTRANCES TO PARKING FACILITIES, PIER AND PROMENADE WALKWAYS. COORDINATE PEDESTRIAN WALK
CLOSURES WITH OWNER PRIOR TO CONSTRUCTION.
18. CONTRACTOR SHALL REFER TO MATERIALS SPECIFICATIONS
THROUGHOUT THE APPROVED PLAN SET AND SPECIFICATIONS. ANY
SUBSTITUTIONS OF THE MATERIALS SPECIFIED IN THESE DOCUMENTS SHALL REQUIRE WRITTEN APPROVAL FROM THE CITY.
19. DURING THE COURSE OF WORK, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR CALLING THE CITY OF GOLETA FOR TESTING AND INSPECTION 48 HOURS IN ADVANCE. WORK NOT PROPERLY TESTED AND INSPECTED WILL BE SUBJECT TO REJECTION.
20. WORK IN AND ALONG PUBLIC STREETS AND PARKING LOTS, ONCE
BEGUN, SHALL PROCEED TO COMPLETION WITHOUT DELAY SO AS TO PROVIDE MINIMUM INCONVENIENCE TO THE PUBLIC.
21. SUBSURFACE UTILITY DATA IS DEPICTED TO LEVEL C OF CI/ASCE 38-02 AS DEFINED IN THE GUIDANCE OF THE EXISTING UTILITY DATA.
CONTRACTOR SHALL BE RESPONSIBLE FOR THE VERIFICATION OF
LOCATION OF ALL EXISTING UTILITIES IN THE FIELD PRIOR TO CONSTRUCTION. ALL UTILITIES SHALL BE PROTECTED AND REPAIRED BY THE CONTRACTOR IF DAMAGED. CONTRACTOR SHALL BE
RESPONSIBLE FOR NOTIFICATION OF ALL UTILITY COMPANIES 48 HOURS PRIOR TO THE BEGINNING OF WORK. BRING ANY CONFLICTS
WITH NEW IMPROVEMENTS IMMEDIATELY TO THE ATTENTION OF THE CITY.
22. ENTRANCE TO THE SITE AND LAY DOWN AREA DURING
CONSTRUCTION SHALL BE SPECIFIED BY THE CITY.
23. CONTRACTOR SHALL PROVIDE A LEGIBLE AND COMPLETE SET OF
PLANS IDENTIFYING ALL MODIFICATIONS MADE DURING
CONSTRUCTION TO THE CITY FOR THE PREPARATION OF RECORD
DRAWINGS.
24. ALL CONSTRUCTION SHALL CONFORM TO LATEST EDITION OF CALIFORNIA BUILDING CODE TITLE 24.
25. ALL CONSTRUCTION ACTIVITIES SHALL BE LIMITED TO MONDAY THROUGH FRIDAY OF THE CALENDAR WEEK. NO WEEKEND WORK
SHALL BE PERMITTED WITHOUT THE PRIOR APPROVAL OF THE CITY.
26. CONTRACTOR SHALL CONFORM TO THE WORKING HOURS FROM
8AM - 5PM. NO WORK SHALL BE DONE DURING CITY HOLIDAYS,
SPECIAL EVENTS OR OTHER PEAK SEASON TIMES PER THE CITY OF GOLETA.
27. CONTRACTOR SHALL NOTIFY BUSINESSES OF WORK PRIOR TO COMMENCEMENT OF CONSTRUCTION. COORDINATE NOTIFICATION
EFFORTS WITH CITY OF GOLETA.
28. THIS PROJECT SHALL COMPLY WITH THE 2019 EDITIONS OF THE
CALIFORNIA BUILDING CODE (CBC), CALIFORNIA MECHANICAL
CODE (CMC), CALIFORNIA PLUMBING CODE (CPC), CALIFORNIA
ELECTRICAL CODE (CEC), CALIFORNIA GREEN BUILDING STANDARDS
CODE (CGBS), AND THE CALIFORNIA ENERGY CODE (CENC), ALL
AMENDMENTS TO THE CA CODES ADOPTED BY THE CITY OF GOLETA
CITY, AND ALL OTHER CODES, REGULATIONS, AND APPROVALS
ESTABLISHED BY THE CITY OF GOLETA.
29. PRIOR TO START OF CONSTRUCTION, THE CONTRACTOR SHALL
SCHEDULE A PRECONSTRUCTION CONFERENCE WITH ALL PARTIES
INVOLVED AT THE PROJECT SITE TO REVIEW THE SPECIAL INSPECTION
REQUIREMENTS, PROCEDURES, AND INDIVIDUAL SPECIAL INSPECTORS
THAT WILL BE ASSIGNED TO THE PROJECT, AS WELL AS REQUIREMENTS FOR STRUCTURAL OBSERVATION. CONTRACTOR SHALL CONTACT
THE CITY OF GOLETA BUILDING DIVISION TO CONFIRM AN
ACCEPTABLE MEETING DATE AND TIME.
CIRCULATION AND ACCESS PLAN
1. CONTRACTOR WILL PROVIDE A TRAFFIC AND PEDESTRIAN
CIRCULATION AND ACCESS PLAN TO THE CITY FOR APPROVAL PRIOR TO THE START OF CONSTRUCTION.
2. THE CONTRACTOR-PROVIDED PLAN WILL ADDRESS HOW
CONTRACTOR WILL MEET THE FOLLOWING REQUIREMENTS
THROUGHOUT THE ENTIRE COURSE OF CONSTRUCTION:
A. ADA COMPLIANT PEDESTRIAN ACCESS ALONG ARMITOS
B. BIKEWAY CIRCULATION
3. STAGING - CONTRACTOR SHALL NOT OCCUPY PARKING SPACES ADJACENT TO NEIGHBORING BUSINESSES.
CONTRACTOR PARKING & STAGING AREAS ARE LIMITED TO WITHIN PARK BOUNDARIES AND PARKING STALLS ADJACENT TO THE PARK.
TRAFFIC AND PEDESTRIAN
NOTE: THESE ABBREVIATIONS ARE GENERAL FOR THE SET. OTHER ABBREVIATIONS SPECIFIC TO DISCIPLINE SETS AND/OR INDICATED ON SHEETS OR SPECIFICATION SHALL SUPERCEDE THIS LIST.
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Landscape-Architecture\Task-L2-ConDocs\Sheet-Files\TS-1725-02-RC19.dwg, G002, Oct 15, 2022 10:53am, CBDufour
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
8 9
WM
EXISTING BENCH, PROTECT IN PLACE
EXISTING CONCRETE PATHWAY,
PROTECT IN PLACE
EXISTING SIDEWALK, PROTECT IN PLACE
EXISTING IRRIGATION UTILITES. PROTECT IN PLACE.
ADJUST TO ACCOMMODATE NEW CONSTRUCTION.
EXISTING SIGNAGE, TO BE RELOCATED.
EXISTING ROCK FEATURE,
PROTECT IN PLACE
EXISTING IRRIGATION VALVES. CUT/CAP
IRRIGATION LATERAL ZONE FOR TURF AREA.
EXISTING BENCH,
PROTECT IN PLACE
EXISTING BENCH, PROTECT IN PLACE
X
X
X
XX
X
X
X
X
X
X
X X
X
X
X
X
X
X
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X
X
X
X
EXISTING IRRIGATION
UTILITES. PROTECT IN PLACE.
EXISTING EQUIPMENT TO REMAIN. REFURBISH
EQUIPMENT, REFER TO SPECIFICATIONS.
REFER TO MULTI-USE
PATH IMPROVEMENT
PLANS FOR
DEMOLITION IN THIS
AREA
EXISTING METAL PICKET FENCING.
EXISTING EASEMENT.
REMOVE EXISTING CONCRETE
CURB. PROTECT EXISTING
SIDEWALK IN PLACE.
TRIM EXISTING TREE TO ACCOMMODATE
NEW IMPROVEMENTS. REMOVAL NOT TO
EXCEED 25% TOTAL VOLUME.
CONTRACTOR TO PRUNE EXISTING SHRUBS TOACCOMMODATE IMPROVEMENTS
SYMBOLTYPEDESCRIPTION
DEMOLISH & REMOVE FULL DEPTH OF (EX) CONCRETE
PAVEMENT AND AGGREGATE BASECONCRETE
DEMOLITION LEGEND
EXISTING TREE TO REMAIN, PROTECT IN PLACE.
INSTALL PROTECTIVE FENCING AT DRIPLINE, TYP.
CLEAR AND
GRUB
EXISTING TURF, GROUNDCOVER, AND SHRUBS TO BE
CLEARED, GRUBBED, AND REMOVED. ADJUST AND
PROTECT ALL IRRIGATION PIPING, FITTINGS, HEADS,
AND ASSOCIATED ITEMS TO ALLOW FOR NEW
CONSTRUCTION.
TREE TO
REMAIN
TEMPORARY
FENCING
XXTREE PROTECTION FENCING
6 FT ORANGE TEMPORARY FENCING
REMOVE FULL DEPTH OF (EX) RUBBER PLAY
SURFACING TO NATIVE. CLEAR & GRUB
ROOTS BELOW.
RUBBER PLAY
SURFACE
EXISTING TREE TO BE REMOVEDTREE TO
REMOVE
LIMIT OF
WORKBIKE PATHWAY IMPROVEMENT LIMIT OF WORK
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Landscape-Architecture\Task-L2-ConDocs\Sheet-Files\DM-1725-02-RC19.dwg, DM101, Oct 15, 2022 11:29am, CBDufour
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
DM101
DEMOLITION PLAN
CHRIS DUFOUR
SSCD
REFER TO SHEET DM001 FOR DEMOLITION NOTES.
MATCHLINE - SEE SHEET DM102
0feet 40
1" = 10'
2060
N O R T H
10 Exist. 6' chain link fence
constr.
6' chain link fence6' wood fence
X
X
X X
X
X
X X
X
REFER TO MULTI-USE
PATH IMPROVEMENT
PLANS FOR
DEMOLITION IN THIS
AREA
EXISTING 4' METAL PICKET FENCE ON
WALL. PROTECT IN PLACE.
EXISTING DRAINAGE
EASEMENT
EXISTING CHAINLINK FENCING. PROTECT IN PLACE. NO
MODIFICATIONS OR ADDITIONS TO FENCING IS PERMITTED
EXISTING PROPERTY
LINE & LIMITS OF WORK
X
X
X
X
XX
X
X
X
XX
X
X
X
X X
X
X
X
X
EXISTING FENCING TO
BE REMOVED ALONG
EASTERN BOUNDARY
(APPROX 220 LF)
EXISTING STORM DRAIN
PIPE TO BE REMOVED
APPROXIMATELY 65 LF.
VERIFY IN FIELD
MODIFY EXISTING STORM DRAIN
OUTLET PIPE ELEVATIONS.
COORDINATE CONSTRUCTION
WITH CITY AND ADJACENT
OWNERSHIP. SEE CIVIL SHEETS
SYMBOLTYPEDESCRIPTION
DEMOLISH & REMOVE FULL DEPTH OF (EX) CONCRETE
PAVEMENT AND AGGREGATE BASECONCRETE
DEMOLITION LEGEND
EXISTING TREE TO REMAIN, PROTECT IN PLACE.
INSTALL PROTECTIVE FENCING AT DRIPLINE, TYP.
CLEAR AND
GRUB
EXISTING TURF, GROUNDCOVER, AND SHRUBS TO BE
CLEARED, GRUBBED, AND REMOVED. ADJUST AND
PROTECT ALL IRRIGATION PIPING, FITTINGS, HEADS,
AND ASSOCIATED ITEMS TO ALLOW FOR NEW
CONSTRUCTION.
TREE TO
REMAIN
TEMPORARY
FENCING
XX
TREE PROTECTION FENCING
6 FT ORANGE TEMPORARY FENCING
REMOVE FULL DEPTH OF (EX) RUBBER PLAY
SURFACING TO NATIVE. CLEAR & GRUB
ROOTS BELOW.
RUBBER PLAY
SURFACE
EXISTING TREE TO BE REMOVEDTREE TO
REMOVE
LIMIT OF
WORKBIKE PATHWAY IMPROVEMENT LIMIT OF WORK
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Landscape-Architecture\Task-L2-ConDocs\Sheet-Files\DM-1725-02-RC19.dwg, DM102, Oct 15, 2022 11:26am, CBDufour
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
DM102
DEMOLITION PLAN
CHRIS DUFOUR
SSCD
MATCHLINE - SEE SHEET DM101
0feet 40
1" = 10'
2060
N O R T H
REFER TO SHEET DM001 FOR DEMOLITION NOTES.
11 WM
45 41
42 43
44 40
45 3941424344
V
V
V
V
V
V
V
46 45
44 43
42 43
42 42
41 41
40 39
41 4245
45 44
43 42
4344
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Engineering\ConDocs\Sheet-Files\C3-ESC.dwg, CE101, Oct 18, 2022 9:17am, jmramos
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
CE101
EROSION CONTROL PLAN
MCH
JMR
0feet 20
1" = 10'
1030
N O R T H
ETA
STVI
CF
O
C
RN
LI
I
L
A
OF
AI
NO 62696
S
EEGR TI S
P
RED
ROEF
N
ERE GIN
AL
I
NO
S
E
MICHAEL
C
.HAMILTON
BMPNAME SYMBOL
SE-1 SILT FENCE
SE-7 STREET SWEEPING & VACUUMING
TC-1 STABILIZED CONSTRUCTION ENTRANCE
WM-1 MATERIAL DELIVERY & STORAGE AREA
CONSTRUCTION STAGING AREA
WM-8 CONCRETE WASTE MANAGEMENT
+
+ 1
2 3
4 5
STORMWATER POLLUTION PREVENTION BMPs
4 5
2 2
3 + + + + + +
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
++++++++++++
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
1 1
1 SCALE: N.T.S.
CONSTRUCTION HAUL/DELIVERY ROUTE
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
HOLLISTER AVE
S KELLOGG AVE
ARMITOS AVE
101 FREEWAY
CA 217
ARMITOS AVE
SAN JOSE CREEK
PROJECT
SITE
NOTES:
1. BMP REFERS TO DESIGNATION GIVEN IN THE CASQA STORMWATER BEST MANAGEMENT PRACTICE CONSTRUCTION HANDBOOK. SEE HANDBOOK FOR BMP DETAILS AND IMPLEMENTATION STRATEGIES.
2. CONTRACTOR TO PLACE AND MAINTAIN EROSION AND SEDIMENT CONTROL BMP'S
IN CONFORMANCE WITH CALIFORNIA STATE WATER RESOURCES CONTROL BOARD (CSWRCB)'S CONSTRUCTION ACTIVITIES STORMWATER GENERAL PERMIT ORDER NO. 2009-0009-DWQ (JULY 1, 2010).
3. EROSION CONTROL PLANS ARE CONCEPTUAL IN NATURE AND ARE PROVIDED FOR BIDDING PURPOSES ONLY. THEY DO NOT REFLECT THE ONLY EROSION CONTROL BMP'S NECESSARY FOR THE WORK. THE CONTRACTOR SHALL PREPARE THEIR OWN
EROSION CONTROL PLANS AS PART OF THE STORMWATER POLLUTION PREVENTION
PLAN TO BE SUBMITTED FOR APPROVAL AND SHALL INCLUDE ALL NECESSARY BMP'S
IN THE COST BREAKDOWN TO BE SUBMITTED WITH THE SORMWATER POLLUTION PREVENTION PLAN.
SCALE: N.T.S.
CONSTRUCTION SIGNAGE MAP
PROVIDE
'SIDEWALK CLOSED'
SIGN
PROVIDE
'SIDEWALK CLOSED AHEAD'
SIGN
S KELLOGG AVE
ARMITOS AVE
SEPTEMBER 12, 2022
12 WM
0.4%
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V V V V V V V V V V V V V V V V V V V
V V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
VVVVVVVVVVVV
45 41
42 43
44 40
45 39
41424344
45 41
41 42
43 44
46 40
40 45
41 42
43 44
4.1%
2.1%
1.9%
1.5%
1.8%
1.8%
3.2%
0.5%
3.0%
1.9%
0.4%
0.3%
0.6%
0.4%
22.5%
12.1%
7.0%
10.9%
1.8%1.8%
(42.18±) EG
(42.24±) EG
42.03 FS
41.99 FS
42.29 FS
42.19 FS
42.67 FS
42.41 FS
42.85 FS
42.79 FS
43.47 FS
43.49 FS
44.44 FS 46.15 FS
46.10 FS
41.34 FG
43.36 FS
42.59 FS
41.84 FS
41.96 FS
41.41 FS
41.63 FS
42.82 FS42.72 FS
42.18 FS
(41.72±) EG
(41.80±) EG
(41.71±) EG
(41.75±) EG
(41.89±) EG
(42.16±) EG
(42.11±) EG
(41.99±) EG
(42.17±) EG
(42.10±) EG
(40.75±) EG
(45.00±) EG
(41.19±) EG
(41.30±) EG
(43.90±) EG
(???±) EG
46.24 FS
46.30 FS
(46.62±) EG
(45.40±) EG
13.6%
17.8%
28.1%
44.50 FS
43.30 FS
1.6%
(40.27±) EG
(40.00±) EG
41.78 FS
41.25 FS
41.02 FS
41.40 FS
41.21 FS
42.43 FS
41.88 FS
41.47 FS
41.41 FS
41.08 FS
1.8%
1.8%
41.23 FS
40.79 FS
0.7%
43 43
42 41
45 44 42
42.09 FS
42.22 FS
42.19 FS
41.86 FS
41.90 FS
V
V
V
V
V
SD
40.19 FS
41.00 FL
>
>
>
>
>
>
>
>
40.40 FL40.40 FL
40.75 FL
40.75 FL
1.0%
3.6%
42 46
45 44
43 1.0%
40.71 FS
41.41 FS
42.20 FS
42.31 FS
41.76 FS
(41.94±) EG
43.41 TB
41.41 FS
43.29 TB
41.29 FS
43.11 TB
41.11 FS
43.05 TB
41.05 FS
42.87 TB
40.87 FS
41.71 TB
40.71 FS
43.54 TB
41.54 FS
43.42 TB
41.42 FS
43.38 TB
41.38 FS
43.26 TB
41.26 FS
43.23 TB
41.23 FS
42.99 TB
40.99 FS
43.36 TB
41.36 FS
43.08 TB
41.08 FS
43.17 TB
41.17 FS
41.47 TB
40.47 FS
41.53 TB
40.53 FS
41.29 TB
40.29 FS
41.91 TB
40.91 FS
41.95 TB
40.95 FS
42.15 TB
41.15 FS
41.91 TB
40.91 FS
41.73 TB
40.73 FS
41.97 TB
40.97 FS
41.49 TB
40.49 FS
41.53 TB
40.53 FS
41.73 TB
40.73 FS 41.71 TB
40.71 FS
43.20 TB
41.20 FS
41.77 TB
40.77 FS
41.89 TB
40.89 FS
42.07 TB
41.07 FS
42.01 TB
41.01 FS
42.18 TB
41.18 FS
43.40 TB
41.40 FS
43.52 TB
41.52 FS
43.70 TB
41.70 FS
43.75 TB
41.75 FS
43.93 TB
41.93 FS
43.99 TB
41.99 FS
44.17 TB
42.17 FS
45.07 TB
43.07 FS
45.25 TB
43.25 FS
44.95 TB
42.95 FS
44.85 TB
42.85 FS
44.67 TB
42.67 FS
44.55 TB
42.55 FS44.39 TB
42.39 FS
44.31 TB
42.31 FS
44.27 TB
42.27 FS
44.19 TB
42.19 FS
44.11 TB
42.11 FS
44.03 TB
42.03 FS
43.95 TB
41.95 FS
43.64 TB
41.64 FS
43.58 TB
41.58 FS
43.52 TB
41.52 FS
44.69 TB
42.69 FS
44.61 TB
42.61 FS
44.53 TB
42.53 FS
44.45 TB
42.45 FS
44.37 TB
42.37 FS
44.29 TB
42.29 FS
44.73 TB
42.73 FS
44.81 TB
42.81 FS
44.89 TB
42.89 FS
44.97 TB
42.97 FS
45.05 TB
43.05 FS
45.13 TB
43.13 FS
44.01 TB
42.01 FS
44.27 TB
42.27 FS
44.25 TB
42.25 FS
44.49 TB
42.49 FS
44.73 TB
42.73 FS
44.51 TB
42.51 FS
44.75 TB
42.75 FS
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Engineering\ConDocs\Sheet-Files\C-Grading.dwg, CG101, Oct 18, 2022 9:21am, jmramos
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
251
PROPERTY LINE/R.O.W.
PROPOSED GRADING/DISTURBANCE LIMIT
PROPOSED FENCE
EXISTING CONT. MAJOR
EXISTING CONT. MINOR
PROPOSED CONT. MAJOR
PROPOSED CONT. MINOR
PROPOSED FLOWLINE
250
XX
250
251V
V
PROPOSED RUBBER PLAY SURFACE
PROPOSED DECOMPOSED GRANITE
EXISTING CONCRETE PAVEMENT
CG101
GRADING AND DRAINAGE PLAN
MCH
DWF
0feet 20
1" = 10'
1030
N O R T H
PROPOSED CONCRETE PAVEMENT
EXISTING A.C. PAVEMENT
LEGEND
ETA
STVI
CF
O
C
RN
LI
I
L
A
OF
AI
NO 62696
S
EEGR TI S
P
RED
RO
EF
N
ERE GIN
AL
I
NO
S
E
MICHAEL
C
.HAMILTON
EARTH QUANTITIES:
AREA OF DISTURBANCE 1.0 AC±
RAW CUT450 CY
RAW FILL500 CY
QUANTITY ESTIMATES ON THESE PLANS ARE TO BE USED FOR PERMIT PURPOSES ONLY.
IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY ACTUAL QUANTITIES FOR THE PURPOSE OF CONSTRUCTION.
THE RAW EARTHWORK QUANTITIES SHOWN HEREON REPRESENT THE ESTIMATED
VOLUMETRIC DIFFERENCE BETWEEN THE PROPOSED ROUGH GRADE AND THE LIMITED TOPOGRAPHIC EXISTING GRADES. THESE ESTIMATES DO NOT MAKE CONSIDERATIONS FOR LOSSES OR BULKING DUE TO: SHRINKAGE, SOIL AMENDMENTS, STABILIZATION, CONSTRUCTION TECHNIQUE, FOOTING & TRENCHING SPOILS, ETC. THESE, IN
ADDITION TO ACTUAL FIELD CONDITIONS, CONSTRUCTION TECHNIQUE AND THE
FINAL RECOMMENDATIONS OF THE SOILS ENGINEER MAY SIGNIFICANTLY EFFECT THE FINAL IMPORT/EXPORT QUANTITIES.
PROPOSED PLANTER AREA
PER LANDSCAPE PLANS
PROPOSED BIORETENTION
CONSTRUCTION NOTES:
CONSTRUCT BIORETENTION FACILITY PER DETAIL 'A', SHEET CG101.
CONSTRUCT BIORETENTION FACILITY PER DETAIL 'B', SHEET CG501.
CONSTRUCT BIKEWAY DRAINAGE CROSSING PER DETAIL 1, SECTION A-A, SHEET BW4.04.
CONSTRUCT ROCK-LINED SWALE PER DETAIL 1, SECTION C-C, SHEET BWA.04.
INSTALL 12" PVC STORM DRAIN.
INSTALL 12"X12" CATCH BASIN PER DETAIL 'C', SHEET CG501. 1 2
3 4
5 6
BIORETENTION #2
AREA: 295 SF BIORETENTION #1
AREA: 430 SF
EXISTING TREES
EXISTING 12"
STORM DRAIN
INV = 39.30 ±
ARMITOS AVE
SAN JOSE CREEK
1 VARIABLE WIDTH
(PER PLAN
SAND/COMPOST MIX SHALL BE
60-70% SAND, 15-25% COMPOST
INSTALLED IN 6" LIFTS
24"12"
GRAVEL-CLASS 2
PERMEABLE MATERIAL
COBBLE OR SPLASH
BLOCK WHERE STORM
WATER ENTERS
3"
MULCH
FLAT BOTTOM
NO SLOPES
SCALE:AN.T.S
BIO-RETENTION SUMP DETAIL
6"
SUMP
TG = 42.60 ±
1 3
5 BIORETENTION #3
AREA: 865 SF
SEE SHEET CG501
FOR BASIN PLAN
AND PROFILE.
2 4
4:1
MAX
4:1MAX
SEPTEMBER 12, 2022
INV = 40.50
INV = 39.00
6 13
ELEVATION
ELEVATION
STATION
25.0 26.0
28.0 30.0
32.0 34.0
36.0 38.0
40.0 42.0
44.0 46.0
48.0 25.0
26.0 28.0
30.0 32.0
34.0 36.0
38.0 40.0
42.0 44.0
46.0 48.0
0+000+501+001+502+002+502+80
PROPOSED SURFACE
EXISTING SURFACE EXISTING 12" STORM DRAIN
INV: ±39.30
PROPOSED BIKEWAY
(SEPARATE PROJECT)
COUNTY OF SANTA BARBARA
HOUSING AUTHORITY
SAN JOSE CREEK
EXISTING 12" STORM DRAIN
TO BE REMOVEDEXISTING OUTLET: ±37.4
PROPOSED PIPE
PROPOSED OUTLET: 39.00
PROPOSED INV OUT: 40.50
VVVVVVV
V
V
V
V
V
V
V
V
V
VV
V
V
V
V
V
V
V V V V V V V
40 45
39 41
42 43
44 40
40 41
42 43
44 3.2%
41.41 FS
(45.00±) EG
28.1%
(40.27±) EG(40.00±) EG
41.21 FS
41.88 FS
41.47 FS
41.08 FS
1.8%
1.8%
41.23 FS
43 45
44 42
V
V
V
SD
SD
SD
40.19 FS
41.00 FL
>
>
>
>
>
>
>
>
40.40 FL
40.40 FL
40.75 FL
40.75 FL
1.0%
3.6%
41.41 FS
42.20 FS
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Engineering\ConDocs\Sheet-Files\C-Grading.dwg, CG501, Oct 18, 2022 9:20am, jmramos
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
CG501
OFF-SITE DRAINAGE TO
MCH
JMR
SAN JOSE CREEK
0feet 20
1" = 10'
1030
ETA
STVI
CF
O
C
RN
LI
I
L
A
OF
AI
NO 62696
S
EEGR TI S
P
RED
ROEF
N
ERE GIN
AL
I
NO
S
E
MICHAEL
C
.HAMILTON
PROPOSED BIORETENTION PROFILE VIEW
SCALE: H: 1"=10' V: 1"=5'
N O R T H
PROPOSED BIORETENTION PLAN VIEW
SCALE: 1"=10'
EXISTING 12"
STORM DRAIN
15' WIDTH
SAND/COMPOST MIX SHALL BE
60-70% SAND, 15-25% COMPOST
INSTALLED IN 6" LIFTS
24"12"
GRAVEL-CLASS 2
PERMEABLE MATERIAL
3"
MULCH
FLAT BOTTOM
NO SLOPES
ELEV 39.00
SCALE:BN.T.S
BIO-RETENTION SUMP DETAIL
24"SUMP
2:1MAX
2:1
MAX
ELEV 36.00
ELEV 41.00
SEPTEMBER 12, 2022
SCALE:CN.T.S
CONCRETE CATCH BASIN
12"X12" PRECAST CONCRETE CATCH BASIN
4"
OUTLET PIPE, SIZE AND
INVERT PER PLAN
4" SUMP BELOW OUTLET FOR
SEDIMENT CAPTURE
PROVIDE OPEN BOTTOM OR DRAIN
HOLES TO PREVENT STANDING WATER
ADJACENT PAVING PER PLAN,
SLOPE TO CATCH BASIN
6" MIN. NO 2. STONE
NON-WOVEN
GEOTEXTILE FABRIC
14 15
16 17
18 19
20 21
22 23
24 25
26 27
/
/
/
/
/ / / / / / / / / /
/////////
/ / / / / / / / / /
/
/
/
/
/ /
LIMIT OF WORK
LIMIT OF WORK
/
/
/
/
///////////////////
/ / / / / / / / / / / / / / / / / / / / / /
/ / / / / / / /
/
PLANTING NOTES
1. PLANT LIST IS FOR CONVENIENCE OF CONTRACTOR
ONLY. IN CASE OF DISCREPANCIES BETWEEN THE
PLANS AND THE LIST, PLANS SHALL PREVAIL.
2. PLANT LOCATIONS SHOWN ON THE PLANS ARE
DIAGRAMMATIC. CONTRACTOR SHALL LOCATE ALL
PLANT MATERIAL UNDER THE DIRECTION OF THE CITY
OF GOLETA PRIOR TO PLANTING HOLE EXCAVATION.
3. THE CITY OF GOLETA RESERVES THE RIGHT TO MAKE
SUBSTITUTIONS, ADDITIONS, AND DELETIONS TO THE
PLANTING LAYOUT AS WORK PROGRESSES.
4. ALL GROUNDCOVER SHALL BE TRIANGULARLY
SPACED UNLESS OTHERWISE NOTED.
5. CONTRACTOR SHALL INSTALL A 3" THICK LAYER OF
MULCH IN BIORETENTION AREAS.
PLANT SCHEDULE
TREESBOTANICAL NAMECOMMON NAMECONTWUCOLSQTY
ARBUTUS X `MARINA`ARBUTUS MULTI-TRUNK15 GAL LOW3
CASSIA LEPTOPHYLLAGOLD MEDALLION TREE24"BOX LOW1
CITRUS X LIMON 'IMPROVED MEYER'MEYER LEMON15 GAL MODERATE3 HANDROANTHUS HEPTAPHYLLUSPINK TRUMPET TREE24"BOX LOW3
LAGERSTROEMIA INDICACRAPE MYRTLE15 GAL LOW4
MELALEUCA NESOPHILAPINK MELALEUCA MULTI-TRUNK 15 GAL LOW5 PLATANUS RACEMOSACALIFORNIA SYCAMORE15 GAL MODERATE14
*MITIGATION SPECIES, SEE SPECIFICATIONS
QUERCUS AGRIFOLIACOAST LIVE OAK15 GAL VERY LOW7
*MITIGATION SPECIES, SEE SPECIFICATIONS
SALIX LASIOLEPISARROYO WILLOW15 GAL HIGH10
*MITIGATION SPECIES, SEE SPECIFICATIONS
UMBELLULARIA CALIFORNICABAY LAUREL15 GAL MODERATE5
*MITIGATION SPECIES, SEE SPECIFICATIONS
SHRUBSBOTANICAL NAMECOMMON NAMECONT WUCOLSQTY
EXISTING TREES TO REMAIN 10 UMBELLULARIA CALIFORNICABAY LAUREL15 GAL MODERATE5 *MITIGATION SPECIES, SEE SPECIFICATIONS
SHRUBSBOTANICAL NAMECOMMON NAMECONTWUCOLSQTY
ALOE STRIATACORAL ALOE3 GAL LOW43
ALOE X `ALWAYS RED`ALWAYS RED ALOE3 GAL LOW79
ANIGOZANTHOS FLAVIDUS `TEQUILA SUNRISE` KANGAROO PAW5 GAL LOW21 ARCTOSTAPHYLOS DENSIFLORA `HARMONY` HARMONY MANZANITA5 GAL LOW28 DUDLEYA PULVERULENTACHALK LETTUCE1 GAL VERY LOW39
ERIOGONUM GRANDE RUBESCENSRED BUCKWHEAT1 GAL VERY LOW22 PASSIFLORA EDULISPASSION FRUIT5 GAL MODERATE5
PENNISETUM SPATHIOLATUMRYE PUFFS1 GAL LOW15
SALVIA APIANAWHITE SAGE5 GAL VERY LOW22
SALVIA CLEVELANDIICLEVELAND SAGE1 GAL VERY LOW37
TAGETES LEMMONII `COMPACTA`COMPACT COPPER CANYON DAISY 1 GAL LOW31 VERBENA LILACINA `DE LA MINA`LILAC VERBENA1 GAL LOW27
VITIS CALIFORNICACALIFORNIA WILD GRAPE5 GAL LOW5
BIOSWALEBOTANICAL NAMECOMMON NAMECONTWUCOLSQTY
CAREX PRAEGRACILISCALIFORNIA FIELD SEDGE5 GAL MODERATE131 ENCELIA CALIFORNICACALIFORNIA ENCELIA1 GAL VERY LOW34
FESTUCA IDAHOENSISIDAHO FESCUE1 GAL LOW100
JUNCUS PATENSCALIFORNIA GRAY RUSH1 GAL LOW73
MIMULUS AURANTIACUSSTICKY MONKEYFLOWER1 GAL VERY LOW12
MUHLENBERGIA RIGENSDEER GRASS1 GAL LOW22
SALVIA MELLIFERABLACK SAGE1 GAL VERY LOW32
SALVIA SPATHACEAHUMMINGBIRD SAGE1 GAL LOW19
GROUND COVERSBOTANICAL NAMECOMMON NAMECONTWUCOLSSPACINGQTY VERBENA TAPIEN HYBRIDS `BLUE-VIOLET` TM TAPIEN BLUE-VIOLET VERBENA4" POT MODERATE 24" o.c. 120 3" LAYER BARK MULCH, SEE LC001 FOR DETAILS
N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Landscape-Architecture\Task-L2-ConDocs\Sheet-Files\LP-1725-02-RC19.dwg, LP102, Oct 15, 2022 11:24am, CBDufour
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
LP102
PLANTING PLAN
CHRIS DUFOUR
SSCD
MATCHLINE - SEE SHEET LP101
0feet 40
1" = 10'
2060
N O R T H
28 N:\1600\1725-02-RC19-Armitos-Ave-Comm-Garden-Trail-Park-Improvements\Landscape-Architecture\Task-L2-ConDocs\Sheet-Files\LP-1725-02-RC19.dwg, LP501, Oct 15, 2022 11:00am, CBDufour
PROJECT MANAGER
DRAWN BY
PROJECT NUMBER
CHECKED BY
SHEET
SEPTEMBER 07, 2022
1725-02-RC19
DATE
BID SET
rrmdesign.com | (805) 543-1794
3765 S. Higuera, San Luis Obispo, CA 93401
THE INCLUDED DRAWINGS, SPECIFICATIONS, IDEAS, DESIGNS AND ARRANGEMENTS
REPRESENTED THEREBY ARE AND SHALL REMAIN THE PROPERTY OF RRM DESIGN
GROUP AND NO PART THEREOF SHALL BE COPIED, DISCLOSED TO OTHERS OR
USED IN CONNECTION WITH ANY WORK OR PROJECT OTHER THAN THE SPECIFIED
PROJECT FOR WHICH THEY HAVE BEEN PREPARED AND DEVELOPED WITHOUT THE WRITTEN CONSENT OF RRM DESIGN GROUP. VISUAL CONTACT WITH THESE DRAWINGS
OR SPECIFICATIONS SHALL CONSTITUTE CONCLUSIVE EVIDENCE OF ACCEPTANCE OF THESE RESTRICTIONS. SUBMITTAL OF THESE DOCUMENTS FOR PUBLIC AGENCY REVIEW SHALL NOT BE CONSIDERED A WAIVER OF RRM DESIGN GROUP'S RIGHTS.
RRM DESIGN GROUP COPYRIGHT 2022.
RRM IS A CALIFORNIA CORPORATION
NO.REVISIONDATE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE
PATH, AND ARMITOS PARK IMPROVEMENTS
ARMITOS AVE, GOLETA CA 93117
LP501
PLANTING DETAILS
CHRIS DUFOUR
SSCD
TREE PLANTING WITH WOOD STAKING
2x ROOTBALL WIDTH
18" MIN.
6"
6"
6"
TREE TIES, ATTACHED TO
ALLOW TREE TO MOVE
BUT STILL BE HELD FIRMLY
IN PLACE
TREE STAKES, TWO
PER TREE
SHEET MULCH PER DETAIL
1/LP501
36" DEEP ROOT BARRIER
PER MANUFACTURER'S
INSTRUCTIONS
AMENDED NATIVE SOIL
TREE TRUNK
WATERING BERM
F.G.
DIRECTION OF
PREVAILING WIND
NOTES:
A. INSTALL ROOT BARRIER
WHEN TRUNK IS WITHIN 5'
OF PAVING, 10' FROM
BUILDING.
B. INSTALL TRUNK
PROTECTOR FOR ALL
TREES IN TURF UNLESS
OTHERWISE NOTED.
TOP VIEW
BACKFILL MIX
ROOTBALL
6"
1 11
2 x HEIGHT
OF ROOTBALL
AMENDED PLANTING BACKFILL - PUDDLE AND
SETTLE TO SET PLANT AT FINISHED GRADE
2x WIDTH
OF ROOTBALL
VINE PLANTING ON FENCE
REMOVE NURSERY STAKE.
ENTWINE VINE ON NEW STAKE.
LEAN STAKE AGAINST FENCE.
6" WATERING BASIN.
F.G.
3" MULCH OR D.G. PER PLAN
NATIVE SOIL
FENCE PER PLANS.
4 SHRUB PLANTING
2 TIMES ROOTBALL DIAMETER
1"
2" DECOMPOSED GRANITE
MULCH, NON-COMPACTED
BACKFILL MIX
FERTILIZER TABLET
UNCOMPACTED NATIVE SOIL
TOP OF ROOTBALL AT, OR
SLIGHTLY ABOVE, FINISH GRADE
SOIL SEPARATOR FABRIC
2" DECOMPOSED GRANITE
MULCH, COMPACTED
2 GROUNDCOVER SPACING
EQUALEQUAL
EQUAL
1/2 O.C. SPACING FROM
EDGE OF PAVING, BACK OF
CURB, OR BUILDING FACE
NOTE: GROUNDCOVER SHALL
BE TRIANGULARLY SPACED
PER THE ON-CENTER (O.C.)
SPACING INDICATED ON THE
PLANTING PLAN AND/OR
PLANTING LEGEND, UNLESS
OTHERWISE NOTED.
EDGE OF PLANTING AREA
PLANT PER PLANTING
PLAN, TYP.
5 29
TO BE SUPPLEMENTED BY THE 2015 STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION (GREENBOOK),
LOCATION OF CONSTRUCTION
SAN JOSE CREEK BIKEWAY
AND SANTA BARBARA COUNTY ENGINEERING DESIGN STANDARDS DATED SEPTEMBER 2011
PROJECT LOCATION
NOT TO SCALE
VICINITY MAP
NOT TO SCALE
ARMITOS PARK
MULTI-PURPOSE PATH
OWNERLANDSCAPE ARCHITECTCIVIL ENGINEER
SHEET INDEX
STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION STANDARD PLANS DATED 2018
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATH
PROJECT
LOCATION
BW0.01
TITLE SHEET AND NOTES
30 SAN JOSE CREEK BIKEWAY
SAN JOSE CREEK BIKEWAY
ARMITOS BIKEWAY
SAN JOSE CREEK BIKEWAY
TYPICAL CROSS SECTION NOTES:CONSTRUCTION NOTES
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW1.01
TYPICAL SECTIONS
ABBREVIATIONS
2 LEGEND
31 SAN JOSE CREEK
HOLLISTER AVE
KELLOGG PARK
ARMITOS AVE
ARMITOS PARK
HWY 217 DEARBORN PL
S KELLOGG AVE
ARMITOS AVE
KELLOGG RANCH
LEGEND
SURVEY CONTROL POINTS
SURVEY NOTES
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW2.01
3 SURVEY CONTROL
SURVEY CONTROL
32 BOARDWALK
SAN JOSE CREEK
ARMITOS
AVE
ARMITOSPARK
KELLOGG RANCH
ALIGNMENT CURVE DATA
Δ
36 38
40 42
44 46
48 50
36 38
40 42
44 46
48 50
LAYOUT
LEGEND
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW3.01
LAYOUT AND PROFILE
TREE REMOVAL SCHEDULE
4 NOTES
"BW" LINE PROFILE
LEGEND
33 36
38 40
42 44
46 48
50 52
36 38
40 42
44 46
48 50
52 ARMITOS BIKEWAY "A" LINE PROFILE
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW3.02
PROFILE5
34 ARMITOS AVE
NOTE:
REMOVABLE BOLLARD DETAIL
CONSTRUCTION NOTES:
ENLARGED PLAN
SCALE: 1"=5'
REMOVE AND PLACE PAVEMENT DETAIL
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW4.01
CONSTRUCTION DETAILS
35 SAN JOSE CREEK
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW4.02
7 CONSTRUCTION DETAILS
CONCRETE CURB TRANSITION
NOT TO SCALE
6 INCH CONCRETE CURB
NOT TO SCALE
42" WOOD RAIL FENCE
BOARDWALK APPROACH SLAB
SCALE: 1"=5'
BOARDWALK APPROACH SLAB
SCALE: 1"=5'
PATHWAY CONFORM 1
SCALE: 1"=5'
PATHWAY CONFORM 2
SCALE: 1"=5'
36 TYPICAL BOARDWALK SECTION
TYPICAL BOARDWALK ELEVATION
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW4.03
8 CONSTRUCTION DETAILS
NOTE:
37 B
A
A
B
C
C
C
C
B
B
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW4.04
9 CONSTRUCTION DETAILS
SECTION B-B
NOT TO SCALE
LOW WATER CROSSING DETAIL
SECTION A-A
NOT TO SCALE
SECTION C-C
NOT TO SCALE
38 BIKEWAY
SAN JOSE CREEK
ARMITOS
AVE
ARMITOSPARK
KELLOGG RANCH
BEST MANAGEMENT PRACTICES
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW5.01
THIS PLAN IS APPROVED FOR TEMPORARY WATER POLLUTION CONTROL WORK ONLY 10 NOTES:
TEMPORARY WATER POLLUTION CONTROL PLAN
TEMPORARY WATER POLLUTION CONTROL PLAN
39 BIKEWAY
SAN JOSE CREEK
ARMITOS
AVE
ARMITOSPARK
KELLOGG RANCH
BEST MANAGEMENT PRACTICES
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW5.02
THIS PLAN IS APPROVED FOR EROSION CONTROL WORK ONLY
11 NOTES:
EROSION CONTROL
EROSION CONTROL
40 V
V
V
V
VV
V
BIKEWAY
SAN JOSE CREEK
ARMITOS
AVE
ARMITOSPARK
KELLOGG RANCH
LEGEND
NOTE:
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW6.01
CONTOUR GRADING12
THIS PLAN IS APPROVED FOR CONTOUR GRADING ONLY
CONTOUR GRADING
41 LIMIT OF WORK
LIMIT OF WORK
LIMIT OF WORK
LIMIT OF WORK
PATH EASEMENT
STORM DRAIN EASEMENT
LEGEND
CLOSED
SIDEWALK BARRICADE MOUNTED PEDESTRIAN DETOUR SIGNS
NOTES:
THIS PLAN IS APPROVED FOR CONSTRUCTION AREA SIGNS WORK ONLY
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW7.01
13 CONSTRUCTION AREA SIGNS
CONSTRUCTION AREA SIGNS
42 BIKEWAY
SAN JOSE CREEK
ARMITOS
AVE
ARMITOSPARK
KELLOGG RANCH
NOTES:LEGENDKEYNOTE:
THIS PLAN IS APPROVED FOR PAVEMENT DELINEATION AND SIGN WORK ONLY
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW8.01
PAVEMENT DELINEATION AND SIGN PLAN14
ROADSIDE SIGNSPAVEMENT DELINEATION AND SIGN PLAN
ROADSIDE SIGNS (continuous)
43 BOLLARD / STRIPING
ARMITOS PARK
PROJECT NO.
SHT#OFSHTS.
SHT:
BY DATE REV
KEY
MAP:
DESIGNED:
DRAWN:
CHECKED:
APPROVED:
CONSULTANT:
CITY OF GOLETA
DEPARTMENT OF NEIGHBORHOOD SERVICES
& PUBLIC SAFETY
130 CREMONA DRIVE, SUITE B, GOLETA, CALIFORNIA 93117
TEL 98050 (805) 961-7500
SEPTEMBER 29, 2022
FINAL
SUBMITTAL
1725-02-RC19
MULTI-PURPOSE PATHBW8.02
PAVEMENT DELINEATION AND SIGN PLAN15
THIS PLAN IS APPROVED FOR PAVEMENT DELINEATION AND SIGN WORK ONLY TEXT
CENTER STRIPE DETAIL
SIGN INSTALLATION
44 ATTACHMENT 2
Community Garden, San Jose Creek Multi-
Purpose Path and Armitos Park Improvements
(CIP 9007 and 9084)
Specifications
45 CITY OF GOLETA
CONTRACT BIDDING DOCUMENTS
S
PECIFICATIONS AND STANDARD DRAWINGS
FOR THE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH,
AND ARMITOS PARK IMPROVEMENTS
Project Nos. 9007 and 9084
By _____________________
Charles W. Ebeling,
Public Works Director
Project Numbers: 9007 and
9084 Bid Number: *** Bid Opening: XXX, 2022 @ 3:00 P.M.
For use with Greenbook Standard Specifications and Standard Plans 2018 Edition (including applicable amendments)
46 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
ii
Th
is Page Intentionally Left Blank
47 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
iii
TABLE OF CONTENTS
T
his contract shall be in conformance with the Standard Specification for Public Works Construction, 2018 Edition (SSPWS or Greenbook 2018) (including amendments current as of the date of the Notice Inviting Sealed Bids, which are incorporated by reference) and supplements with CALTRANS STANDARD SPECIFICATIONS, 2015 EDITION
SECTION
A.
NOTICE INVITING SEALED BIDS ...................................................................................... A-1 B. BIDDING INSTRUCTIONS .................................................................................................. B-1
1. ATTACHMENT A TO BIDDING INSTRUCTIONS – EQUAL SUBSTITUTION REQUEST FORM……………………………………………………………………………B-11
C. PROPOSAL ........................................................................................................................ C-1 BIDDING SHEET ................................................................................................................. C-5 D. CONTRACT ......................................................................................................................... D-1
1. CONTRACT…………………………………………………………………………………….D-1
2. PERFORMANCE BOND FORM……………………………………………………………D-19
3. PAYMENT BOND FORM……………………………………………………………………D-23
E. CITY GENERAL PROVISIONS ........................................................................................... E-1 Section 1 – No Change ……………..…………….………………………………………...…E-1 Section 2 – Scope of Work ………………….………………………………………………….E-1 Section 3 – Control of Work……………….………………………………………….………...E-3 Section 4 – Control of Materials……………………………………………………….…….....E-4 Section 5 – Legal Relations and Responsibilities………………………………….…………E-4 Section 6 – Prosecution and Progress of the Work………………………………………….E-6 Section 7 – Measurement and Payment…………………………………………………..….E-8 Progress Payment Request Form ...................................................................... E-10 Progress Payment Request – Detail Form ......................................................... E-11 Quantity Change Verification Form .................................................................... E-12 Final Release Payment Form ............................................................................. E-13 48 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
iv
Post-Construction Waste Reduction & Recycling Summary Report Form ......... E-14 A
cknowledgement of Final Closeout and Release of Claims Form .................... E-15 Section 8 – No Changes…………….…………………………………………………..….….E-19 Section 9 – Claim Resolution Process.………………………………………………………E-19 Section 10-Potential Claims and Dispute Resolution……………………………………….E-19 F. TECHNICAL SPECIAL PROVISIONS ................................................................................. F-1
APPENDICES
A. Standards
1. City of Goleta Standards / County of Santa Barbara Standard Plans
2. Green Book Standard Plans
3. Caltrans Standard Plans
4. Sample Door Hanger
5. Temporary No Parking Sign
B. Water Pollution Control Plan (WPCP)
C. Prevailing Wage Rates
D. School Zone Work Hour Restriction Map
49 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK A-1
IMPROVEMENTS PROJECT NOS. 9007 AND 9084
SECTION A NOTICE INVITING SEALED BIDS
NOTICE INVITING SEALED BIDS
FOR THE
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
130 Cremona Drive, Suite B, City of Goleta, CA
PUBLIC NOTICE IS HEREBY GIVEN that the City of Goleta (“CITY”), invites sealed bids for the above stated project and will receive such bids via electronic transmission on the City of Goleta PlanetBids portal site until 3:00 P.M., XXX, 2022 , and will be publicly opened and posted promptly thereafter. Copies of the Contract Documents and Specifications are available from the CITY, 130 Cremona Drive, Suite B, Goleta, California 93117 upon payment of a $50.00 non- refundable fee if picked up, or payment of a $60.00 non-refundable fee, if mailed or no payment to CITY if obtained from the CITY website at http://www.cityofgoleta.org/i-want-to/view/city-bid- opportunities.
The work includes all labor, material, supervision, plant and equipment necessary to construct and deliver a finished COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084. Work includes construction of a new community garden with raised garden beds, outdoor classroom, outdoor picnic area with pizza oven, installation of new playground equipment and surfacing material, constructing ADA accessible walkways, ramps and curbs, construction of the multi-purpose path and all project associated clearing, grubbing, grading, asphalt, concrete, drainage, fencing, signage and landscape work. The contract period is One hundred (100) Working Days.
Deadline to submit Requests for Information (RFI) electronically to [email protected] is XXX, 2022. A Pre-Bid Meeting is not scheduled for this project.
Bidders must be registered on the City of Goleta’s PlanetBids portal in order to receive addendum notifications and to submit a bid. Go to PlanetBids for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.
The bid must be accompanied by a bid security in the form of a money order, a certified cashier’s check, or bidder’s bond executed by an admitted surety, made payable to CITY. The bid security shall be an amount equal to ten percent (10%) of the total annual bid amount included with their proposals as required by California law.
Note: All bids must be accompanied by a scanned copy of the bid security uploaded to PlanetBids. The original security of the three (3) lowest bidders must be mailed or submitted to the office of the City Clerk at 130 Cremona Drive, Suite B, Goleta, California 93117, in a sealed envelope and be received or postmarked within three (3) City business days after the bid due date and time for the bid to be considered. The sealed envelope should be plainly marked on the outside, “SEALED BID SECURITY FOR COMMUNITY
GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084.”
50 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
A-2
The Project is subject to compliance monitoring and enforcement by the Department of Industrial R
elations (DIR) per California Labor Code Section 1771.4, including prevailing wage rates and apprenticeship employment standards. Affirmative action to ensure against discrimination in employment practices on the basis of race, color, national origin, ancestry, sex, or religion will also be required. The CITY hereby affirmatively ensures that all business enterprises will be afforded full opportunity to submit bids in response to this notice and will not be discriminated against on the basis of race, color, national origin, ancestry, sex, or religion in any consideration leading to the award of contract.
A contract may only be awarded to the lowest responsive and responsible bidder that holds a valid Class “A” Contractor’s license, Class “C” Electrical specialty, or specialty licensing in accordance with the provisions of the California Business and Professions Code.
The successful Bidder will be required to furnish a Performance Bond and a Payment Bond each in an amount equal to 100% of the Contract Price. Each bond shall be in the forms set forth herein, shall be secured from a surety company that meets all State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer.
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the DIR. No Bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the DIR to perform public work. If awarded a contract, the Bidder and its subcontractors, of any tier, shall maintain active registration with the DIR for the duration of the Project. Failure to provide proof of the contractor’s current registration pursuant to Labor Code Section 1725.5 may result in rejection of the bid as non-responsive.
Pursuant to Public Contract Code section 22300, the successful bidder may substitute certain securities for funds withheld by CITY to ensure performance under the Contract or, in the alternative, request the CITY to make payment of retention to an escrow agent.
Any protest to an intended award of this contract shall be made in writing addressed to the City Clerk prior to the award. Any protest may be considered and acted on by the City Council at the time noticed for award of the contract. To request a copy of the notice of agenda for award, please contact the City Clerk (805) 961-7505 or register on the CITY’s website (www.cityofgoleta.org).
For information relating to the details of this Project and bidding requirements contact JoAnne Plummer in writing at [email protected].
CITY OF GOLETA
_____________________________
Deborah Lopez, City Clerk
Published: Santa Barbara Independent: November 10th and November 17th 2022 51 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-1
SECTION B BIDDING INSTRUCTIONS
1. DEFINITIONS. Unless provided otherwise, the definitions in the contract documents are applicable to all bidding documents.
1.1 “Addenda” means written or graphic instruments issued by the City before the bid deadline that modify or interpret the bidding documents by additions, deletions, clarifications, or corrections.
1.2 “Alternate” means an amount stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as Alternate Work, to be added or deducted from the Total Base Bid, which shall be the Contractor’s responsibility if the City accepts the Alternate Bid Item.
1.3 “Bid Deadline” means the date and time designated in the notice inviting sealed bids as the last date and time for receipt of bids, as may be revised by addenda.
1.4 “Bidder” means a person or firm that submits a bid.
1.5 “Bidding/Contract Documents” means the Contract, Addenda, Notice Inviting Sealed Bids, bidding instructions, Bid (including documentation accompanying the Bid and any post-bid documentation submitted prior to the Notice of Completion) when attached as an exhibit to the Contract, the Bonds, permits from jurisdictional regulatory agencies, Special Provisions, Plans, Standard Plans, Standard Specifications, Reference Specifications, Change Orders, and Supplemental Agreements.
1.6 “Contract Price” means the total aggregate amount of the Contractor’s bid price based on the estimated quantities listed in the Bidding Sheet as set forth in the award of the Contract approved by the City Council, subject to adjustment for variances in quantities and changes pursuant to Change Orders executed in accordance with the Contract Documents.
1.7 “Inspector” means the person designated by the engineer to ensure specification compliance.
1.8 “Total Base Bid” means the sum stated in the bid for which bidder offers to perform the Work described in the bidding documents, but not including alternates.
1.9 “Unit or Contract Unit Price” means an amount entered in the bid by bidder or a “Contract Item” price established by the City in the bid, as a price per unit of measurement for payment for materials, equipment or services including taxes, supervision, overhead and profit for a portion of the work described in the Contract Documents.
52 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-2
2. BIDDER’S REPRESENTATIONS. B y making its bid, bidder represents that:
2.1 Bidder has read, understood, and made the bid pursuant to the requirements in the Contract Documents.
2.2 The Bidder, at its sole cost and expense, has carefully examined the Contract Documents and visited the Project site to become fully acquainted with the local site conditions affecting the Work to be performed including transportation, disposal, handling, and storage of materials.
2.3 The bid and the Contract Unit Prices bid are based upon the labor, materials, equipment, and systems required by the Contract Documents.
2.4 Bidder and all subcontractors, regardless of tier, have the appropriate registrations and current licenses issued by the State of California Contractor’s State License Board and Department of Industrial Relations (DIR) for the Work to be performed.
If bidder is a joint venture, the bidder will have a joint venture license appropriate for the performance of the Work, and each member of the joint venture will likewise have the appropriate license. Business and professions code §§ 7000-7191 establish licensing requirements for contractors. If a bidder, that is a specialty contractor, submits a bid involving 3 or more specialized building trades, the Work of which is more than incidental and supplemental to the performance of the Work for which bidder holds a specialty contractor license, bidder must also hold either (1) a specialty contractor “C” license in each such trade or (2) a general engineering contractor “A” license. This requirement is applicable whether or not bidder lists a subcontractor for each such trade.
2.5 Bidder shall have the expertise, including the Responsible Managing Officer (RMO) for the Contractor Company, demonstrating a minimum of three (3) years' experience successfully performing projects of the same type, magnitude, and character of the work bid, and financial capacity to perform and complete all obligations under the Contract Documents.
2.6 The person executing the bid form is duly authorized and empowered to execute the bid form on bidder’s behalf.
2.7 Bidder is aware of and, if awarded the contract, will comply with legal requirements in its performance of the Work.
2.8 Bidder is aware of and, if identified as the apparent lowest responsible bidder, would be required to pay City business license fee(s).
2.9 Bidder shall not damage or endanger and shall preserve and protect adjacent properties.
2.10 Bidder has familiarized itself with the staging and material storage constraints of the Project site and surrounding buildings and will confine its staging and storage operations to approved areas.
53 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-3
2.11 Bidder will coordinate its construction activities with the other contractors and utility c
ompanies performing work on the Project site, if any, including, but not limited to, any separate contractor retained by the City.
2.12 Bidder has checked the figures set forth in the bid schedule and understands that neither the City nor any officer or employee therefore will be responsible for any misunderstandings, errors, or omissions on the part of the Bidder in submitting its Bid. The failure of a Bidder to receive or examine any of the Bidding Documents or to inspect the site shall not relieve such Bidder from any obligation with respect to the Bid, the Contract, or the Work required under the Contract Documents.
3. CONTRACT DOCUMENTS.
3.1. Bidders may obtain complete sets of the Contract Documents from PlanetBids, the City of Goleta website, or the City’s Public Works Department for the sum stated in the notice inviting sealed bids.
3.2. Bidders will use a complete set of Contract Documents in preparing bids.
3.3. The City makes copies of the Contract Documents available, on the above terms, for the sole purpose of obtaining bids for the Work and does not confer a license or grant permission for any other use of the Contract Documents.
3.4. The City does not assume any liability or responsibility based on any defective or incomplete copying, excerpting, scanning, faxing, downloading, or printing of the Bidding Documents.
4. INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS.
4.1. Before submitting its bid, bidder will carefully study and compare the various documents comprising the Contract Documents and compare them with any other work being bid concurrently or presently under construction which relates to the Work for which the bid is submitted; will examine the project site, the conditions under which the Work is to be performed, and the local conditions; and will at once report to the City’s representative errors, inconsistencies, or ambiguities discovered. The drawings and specifications contained in these Contract Documents do not constitute a representation or warranty that any conditions shown therein actually exist. All soil and test hole data, groundwater elevations, and soil analyses shown on the Plans or included in the Special Provisions apply only at the location of the test holes and to the depths indicated.
4.2. Bidder requests for clarification or interpretation of the Contract Documents will be addressed to the City’s representative at least five (5) calendar days before the bid deadline.
4.3. Clarifications, interpretations, corrections, and changes to the Contract Documents will only be made by addenda. Purported clarifications, interpretations, corrections, and changes to the Contract Documents made in any other manner will not be binding and bidders will not rely upon them.
54 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-4
5. PRODUCT SUBSTITUTIONS.
5 .1 No requests for product substitutions will be considered before award of contract unless requested through the Request for Information (RFI) process so that all bidders will be informed. Bidders wishing to obtain authorization for an or equal substitution of an equivalent material, product or equipment, shall submit all requests for or equal substitution using the form included as Attachment A to these Bidding Instructions, together with data substantiating Bidder’s representation that the non-specified item is of equal quality to the item. Requests for product substitutions not handled through the RFI process will only be considered after award of the contract and in the manner provided for in the contract documents. Authorization of an equal substitution of equivalent materials is solely within the discretion of the City and, if given, shall be made by Addendum or Change Order issued by the City. Bids shall not be based on any or equal substitution request that has not been authorized in writing by City Addendum. In the absence of a written Addendum authorizing a pre-Bid or equal substitution request, the request shall be deemed denied.
6. SUBCONTRACTORS.
6.1. Each bidder will list in the bid form all first-tier subcontractors that will perform work, labor or render such services in excess of ½ of one percent of the total bid of the total bid or $10,000, whichever is greater. The bid form contains spaces for the following information when listing subcontractors: (1) work activity; (2) name of subcontractor; (3) city of subcontractor’s business location; (4) California contractor’s license number, and (5) DIR public works contractor registration number. An inadvertent error in listing the California contractor’s license number or public works contractor registration number shall not be grounds for filing a bid protest or grounds for considering the bid nonresponsive if the corrected contractor's license number is submitted to the City by the Bidder within 24 hours after the bid opening and provided the corrected contractor's license number corresponds to the submitted name and location for that subcontractor. Failure to list any of these other items on the bid form will result in the City treating the bid as if no subcontractor was listed for the work and that bidder represents to the City that it is fully qualified to perform that portion of the Work and will so perform such Work.
6.2. Substitution of subcontractors after the bid deadline who are listed in the bid form will only be allowed with the City’s written consent and in accordance with California law.
7. ADDENDA.
7.1. Before the Bid Deadline, the City may modify the Work, the Bidding Documents or any portion(s) thereof by the issuance of written addenda. Addenda will be in writing and issued only by the City.
7.2. Bidders must be registered on the City’s PlanetBids portal to receive addendum notifications. Addenda will be posted on the PlanetBids portal. 55 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-5
7.3. Copies of addenda will be made available for inspection at the City’s Public Works D
epartment.
7.4. The City will issue addenda so that they are received by prospective bidders not less than three (3) business days before the bid deadline. Addenda that withdraw the request for bids or postpone the bid deadline may be issued any time before the bid deadline.
7.5. Each bidder is responsible for ensuring that it has received all issued addenda before submitting a bid. All bidders are required to acknowledge and confirm receipt of each and every addendum in their Bid Proposal Form. Failure to acknowledge all Addenda may result in a Bid being deemed nonresponsive and not eligible for award of the Contract.
8. NOT USED
9. FORM AND STYLE OF BIDS.
9.1. Bids will be submitted on the bid form included with the Contract Documents. Bids not submitted on the City’s bid form will be rejected. All blanks on the bid form will be filled in legibly.
9.2. Bidder’s failure to submit a price for any alternate or unit price will result in the bid being considered as non-responsive. If alternates are called for and no change in the lump sum base bid is required, enter “no change.”
9.3. Each bidder must fill out the “bidders statement of past contract disqualifications” form stating any and all instances of contract disqualifications due to a violation of a law or safety regulation. The bidder must explain the circumstances of each disqualification.
9.4. Bidder will make no stipulations on the bid form nor qualify the bid in any manner.
9.5. The bids will be based upon full completion of all the Work as shown on the plans and specifications. It is expressly understood that the plans are drawn with as much accuracy as is possible in advance, but should errors, omissions or discrepancies exist in the plans which show conditions that vary from those encountered in construction, the bidder (if awarded the contract) specifically agrees to construct a completed Work ready for the use and in the manner which is intended.
9.6. The bid form will be signed by a person or persons legally authorized to bind bidder to a contract. Bidder’s representative will sign and date the declaration of eligibility to contract included in the bid form. Failure to sign and date the declaration will cause the bid to be rejected.
10. BID SECURITY.
10.1. Each bid must be accompanied by bid security, in the amount of 10% of the Total Base Bid on the base Contract Work, excluding any Alternate Bid Items, as 56 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-6
security for bidder’s obligation to enter into a contract with the City on the terms s
tated in the bid form and to furnish all items required by the Contract Documents.
All bids must be accompanied by a scanned copy of the bid security uploaded to PlanetBids. The original security of the three (3) apparent lowest bidders must be mailed to the office of the City Clerk at 130 Cremona Drive, Suite B, Goleta, California 93117, in a sealed envelope and be received or postmarked within three (3) City business days of the bid due date and time for the bid to be considered.
The sealed envelope should be plainly marked on the outside identifying the names as shown in the notice inviting sealed bids.
10.2. If the apparent lowest responsible bidder fails to sign the contract and furnish all items required by the bidding documents within the time limits specified in these bidding instructions, the City may reject such bidder and select the next apparent lowest responsible bidder until all bids have been exhausted or the City may reject all bids. In the event the bid is rejected, such bidder will be liable for and forfeit to the City the amount of the difference, not to exceed the amount of the bid security, between the amount of the disqualified bid and the larger amount for which the City procures the Work. The City may also use the bid security to cover the cost of rebidding the project.
10.3. If a bid bond is submitted and an attorney-in-fact executes the bid bond on behalf of the surety, a notarized and current copy of the power of attorney will be affixed to the bid bond. The surety issuing the bid bond must be admitted to provide surety within the State of California.
10.4. The City will retain the bid security until the occurrence of one of the following:
10.4.1 All items required by the bidding documents have been furnished and the contract has been signed by the successful bidder and the City.
10.4.2 The specified time has elapsed during which bids may be withdrawn.
10.4.3 All bids have been rejected.
11. BID DELIVERY.
11.1 The bid form, bid security, and all other documents required to be submitted with the bid must be submitted via electronic transmission on the City of Goleta PlanetBids portal site.
11.2 Bidders must be registered on the City of Goleta’s PlanetBids portal in order to submit a bid. Go to PlanetBids for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.
11.3 Bid Security shall be submitted in accordance with Section 10. “Bid Security” above and per the notice inviting sealed bids.
57 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-7
12. MODIFICATION OR WITHDRAWAL OF BID.
1 2.1. Bids may not be modified, withdrawn, or canceled within one hundred twenty (120) days after the bid deadline unless otherwise provided in any supplementary instructions to bidders. The bidder shall be prohibited from further bidding on the project and the bid bond shall be forfeited. The City, at its discretion, may award the bid to the next responsive and responsible bidder. In the event the next bidder refuses to enter into the contract, that bidder’s bid bond shall then be forfeited.
13. OPENING OF BIDS.
13.1 Bids submitted in the manner required by these instructions and received on or before the bid deadline will be opened publicly.
14. EVALUATION AND REJECTION OF BIDS.
14.1. Bidders will be evaluated for responsiveness and responsibility based on bid proposal information provided in the bid documents under “designation of subcontractors” and bidder’s references.”
14.2. A responsive Bid is a Bid that conforms, in all material respects, to these Instructions to Bidders. Non-responsive Bids will be rejected.
14.3. A responsible bidder means a bidder who has demonstrated the attributes of trustworthiness, quality, fitness, capacity, and experience to satisfactorily perform fully the requirements of the Contract Bidding Documents and the moral and business integrity and reliability that will assure good faith performance in the sole discretion of the County. Any determination of a bidder’s non-responsibility by the City shall be based on the fitness and capacity of the bidder to satisfactorily perform the obligations of the Contract, whether or not the bidder is qualified to perform those obligations, whether or not the bidder is trustworthy, and such other bases as may be relevant.
14.4. In addition to other provisions of the Bidding Documents, upon the request of the City, a bidder whose Bid is under consideration for the award of the Contract shall promptly submit satisfactory evidence to City showing the bidder’s financial resources, experience in the field, and organization and other factors evidencing bidder’s ability to successfully execute and complete the Contract.
14.5. The City reserves the right to reject any or all bids and to waive discrepancies, irregularities, informalities, or any other error in the bid or bidding, when to do so seems to best serve the public interest. The right of the City to waive errors applies even if the Bidding Documents state that a discrepancy, irregularity, informality, or other error make a bid nonresponsive, so long as the error does not constitute a material error. The City reserves the right, in its sole discretion, to: judge the bidder’s representations as stated in the Bid forms and any post-Bid information to determine whether or not bidder is qualified to perform the Work; be the sole judge regarding the suitability of the products, services, or supplies offered; to not purchase all items or the full quantity of each item listed in the Bid Item List; reject any or all Bids; waive any deficiencies, irregularities, or informalities in any Bids or 58 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-8
in the bidding process; modify, cancel, or withdraw the Notice Inviting Sealed Bids; i
ssue a new Notice Inviting Sealed Bids; suspend or abandon the Project; seek the assistance of outside technical experts in Bid evaluation; require a bidder to provide a guarantee (or guarantees) of the Contract by a third party; and not issue a Notice to Proceed after execution of the Contract. In submitting a Bid in response to the Notice Inviting Sealed Bids, the bidder is specifically acknowledging the City holds these rights. The Notice Inviting Sealed Bids does not commit the City to enter into a Contract, to reject, in its sole discretion, all Bids, nor does it obligate the City pay for any costs incurred by bidders in preparation and submission of a Bid or in anticipation of a Contract. By submitting a Bid, the bidder disclaims any right to be paid for such costs.
14.6. The City may reject any bid not accompanied by the required bid security or any other item required by the bidding documents, or a bid which is in any other way materially incomplete, irregular or not responsive to the bid request in the sole determination of the City.
15. AWARD.
A. The City may retain all bids for a period of one hundred twenty (120) days for examination and comparison, and to delete any portion of the Work from the contract.
B. The City may waive nonmaterial irregularities in a bid and will accept the lowest responsive bid from a responsible bidder as determined by the City.
C. The City will determine the low bidder on the basis of the total bid price in words on the bidding sheet as described on the bidding sheet.
D. City Staff will identify the apparent lowest responsive and responsible bidder and notify such bidder within one hundred twenty (120) days (unless the number of days is modified in any Addendum issued to bidders) after the Bid Deadline. Within fifteen (15) days after receiving the City’s written notice that bidder was identified as the apparent lowest responsible bidder, bidder will submit to the City all of the following items as required by the City:
15.4.1 Two originals of the contract signed by bidder.
15.4.2 One original of the payment bond.
15.4.3 One original of the performance bond.
15.4.4 Certificates of insurance and additional insured endorsements.
15.4.5 Copy of current city of Goleta business license certificate.
15.4.6 Names of all subcontractors, with their DIR registration number, license numbers, addresses, telephone number, facsimile number and trade on bidders’ company stationery. Evidence, as required by the city, of the 59 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-9
reliability and responsibility of the proposed subcontractors such as s
tatements of experience, statements of financial condition, and references.
E. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded. This Project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations.
F. If bidder submits the two original signed contracts and all other items within fifteen (15) days after receiving the City’s notification, and all such items comply with the requirements of the bidding documents, the City will submit the bid to the City Council for award of Contract. Following City Council Award of Contract, the City will sign the contract and return a signed copy of the contract to bidder
16. NOTICE OF INTENT TO AWARD CONTRACT. Following the opening of bids and determination of the lowest responsible Bidder, the City will issue a notice of intent to award the Contract, identifying the Bidder to whom the City intends to award the Contract. The award of the Contracts shall be made by the City Council.
17. PUBLIC RECORDS. City seeks to conduct its business openly. Upon identification of the lowest responsive and responsible bidder and upon notifying such bidder, Bids shall be regarded as public, with the exception any elements of each Bid that are identified by the Bidder as business or trade secrets and plainly marked as “trade secret,” “confidential,” or “proprietary.” Each element of a Bid which a Bidder desires not to be considered public must be clearly marked as set forth above; any blanket statement (i.e. regarding entire pages, documents, or other, non-specific designations) shall not be sufficient and shall not bind the City in any way whatsoever. If City receives a request from a third party to make a Bid available for inspection or copying, the City will notify the Bidder of the request. If a Bidder instructs the City that the information is not to be released, City will withhold the information, provided, the Bidder expeditiously seeks a protective order from a court of competent jurisdiction to prevent such release. If disclosure is required by law (despite the Bidder’s request for confidentiality), the City shall not in any way be liable or responsible for the disclosure of such records or part thereof.
18. BID PROTEST. Any registered Bidder may file a protest provided that each and all of the following are complied with:
18.1. The bid protest is in writing;
18.2. Protests based upon alleged defects or improprieties in the Bidding Documents are filed with the City prior to the Bid Deadline;
60 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-10
18.3. All other protests are filed and received by the City not more than five (5) calendar d
ays following the date of City’s Notice of Intent to Award the Contract; and
18.4. The written bid protest sets forth, in detail, all grounds for the bid protest, including without limitation all facts, supporting documentation, legal authorities and argument in support of the grounds for the bid protest. All factual contentions must be supported by competent, admissible and credible evidence.
18.5. Any matters not set forth in the written bid protest shall be deemed waived. Any bid protest not conforming to the foregoing shall be rejected by the City as invalid. 61 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-11
Th
is Page Intentionally Left Blank
62 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-12
ATTACHMENT A – BIDDING INSTRUCTIONS
O
R EQUAL SUBSTITUTION FORM
Pr
oject:
Lo
cation:
TO
:
FR
OM:
1. Section, Paragraph and Page Number of Specification or Drawing to which this Request applies:
2. Item specified for which substitution is requested:
Name or Brand:
Manufacturer:
Catalog No.:
3. The proposed substitution is:
Name or Brand:
Manufacturer:
Catalog No.:
4. Contractor is required to provide product data for the proposed substitution consisting of the description of the product or item, reference standards and performance test data, together with substantiating data, supporting the claim that the non-specified product is equal to that specified. No substitution request will be considered by the City without a completed Substitution Request form and substantiating data. Contractor shall attach hereto complete technical data, including technical information, complete manufacturer’s catalogs, brochures and drawings, certified laboratory test reports and samples as applicable for the proposed substitution, installation and operating instructions, manufacturing warranties and other descriptive material.
5. Reasons for substitution request:
63 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-13
6. Detailed comparison of significant qualities and properties (size, weight, durability, performance and similar characteristics) including the visual effect where applicable, for the proposed substitution in comparison with original requirements includes (list detailed comparison with supporting data, use separate sheets if required):
7. Installation changes and changes to Drawings and Specifications required by the proposed substitution are (list all required changes, use separate sheets if required):
8. Does this substitution affect dimensions shown on Drawings? Yes No
If yes, clearly indicate changes on each Drawing by Sheet No.:
9. List the effects of the proposed substitution on other parts of the Work or on separate contracts, including required changes in Drawings, dimensions, engineering and detailing costs and effect on other trades. 10 . What effect does substitution have on applicable code requirements? 11 . Identify differences between the proposed substitution and the specified item. 64 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-14
12 . Attach a copy of manufacturer’s warranty, Manufacturer’s guarantees and warranties of proposed and specified items are:
Same
Different
(Explain on attachment.)
Ma
nufacturer shall provide a letter stating the fitness for intended use, and performance equivalence with the specified item.
13. List the name and address of three similar projects (not necessarily installed by Contractor) on which the proposed product was used and date of installation:
(1) Name of Project:
Ad
dress:
Date of Installation:
(2
) Name of Project:
Ad
dress:
Date of Installation:
(3
) Name of Project:
Ad
dress:
Date of Installation:
14 . Use of the substitution will cause the Contract Time to be:
Same
Different
(Explain on attachment.)
65 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-15
1 5. Use of the substitution will affect the critical path of the Construction Schedule as follows (identify any proposed adjustment to the Contract Time):
16 . Reduction in the Contract Sum of $ will result from use of the substituted item.
17. Estimated cost of any engineering, design or agency fees required for work of all trades directly or indirectly affected by the substitution is: $ .
18 . The date by which City must accept this Request in order for the time and cost estimates in Paragraphs 14 and 16 to remain valid is:
.
19 . Contractor Affidavit. The undersigned, having thoroughly investigated the proposed substitution represents, certifies and declares, under penalty of perjury under the laws of the State of California that:
(1) Contractor has personally investigated the proposed substitution and determined that it is equal or superior in all respects to the material, product, thing or service specified except as specifically noted: ;
(2) Contractor will provide the same warranty and correction responsibility for the proposed substitution that the Contractor would have provided for that specified; (3) The cost data presented is complete and includes all related costs under this Contract except any redesign costs and agency fees;
(4) Contractor will indemnify City from and pay all redesign, engineering, detailing, special inspection costs and agency fees caused by the use of this substitution; (5) Contractor will coordinate the installation of the accepted substitution, making such changes as may be required for the Work to be complete in all respects. (6) Contractor waives all claims for additional costs relating to the substitution which may subsequently become apparent; and
(7) Contractor assumes all responsibility for and will indemnify City from and pay all direct or indirect costs and/or time impacts as a result of the use of the substitution.
Executed this _________ day of ________ 20__, at ___________, California. (Type or print name)
66 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-16
S
ubmitted by:
(Firm)
(Address)
For use by City:
___ Accepted ___ Accepted as noted
___ Not Accepted ___ Rejected as late
(By)
(Date)
67 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
B-17
Th
is Page Intentionally Left Blank
68 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-1
SECTION C PROPOSAL
B
ID PROPOSAL
FO
R
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
TO THE CITY OF GOLETA (“City”):
In accordance with City’s Notice Inviting Sealed Bids, the undersigned Bidder herby proposes to furnish all materials, equipment, tools, labor, and incidentals required for the COMMUNITY
GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS as set forth in the Plans, Specifications, and Contract Documents, and to perform all work in the manner and time prescribed therein.
Bidder declares that this Bid is based upon careful examination of the Work site, Plans, Specifications, Bidding Instructions, and all other Contract Documents. If this Bid is accepted for award, Bidder agrees to enter into a contract with City at the unit and/or lump sum prices set forth in the following Bid Schedule. Bidder understands that failure to enter into a contract in the manner and time prescribed will result in forfeiture to City of the Bid Security accompanying this Bid.
Bidder understands that a Bid is required for the entire Work, that the estimated quantities set forth in the Bid Schedule are solely for the purpose of comparing Bids, and that final compensation under the Contract will be based upon the actual quantities of Work satisfactorily completed. THE CITY RESERVES THE RIGHT TO INCREASE OR DECREASE THE AMOUNT OF ANY QUANTITY SHOWN AND TO DELETE ANY ITEM FROM THE CONTRACT per Sections 9-1.06B and C. It is agreed that the unit and/or lump sum prices bid include all overhead, profit, appurtenant expenses, taxes, royalties, and fees. In the case of discrepancies in the amounts bid, unit prices shall govern over extended amount, and words shall govern over figures.
If awarded the Contract, the undersigned further agrees that in the event of the Bidder’s default in executing the Contract and filing the necessary bonds and insurance certificates WITHIN FIFTEEN (15) WORKING DAYS, not including Saturdays, Sundays and legal holidays, after the City has mailed notice of the award of contract to the Bidder, the proceeds of the Bid Security accompanying this Bid shall become the property of the City and this Bid and the acceptance hereof may, at the City’s option, be considered null and void. 69 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-2
Th
is Page Intentionally Left Blank
70 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK C-3
IMPROVEMENTS PROJECT NOS. 9007 AND 9084
BID PROPOSAL
FOR
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
Bids will be received before 3:00 P.M., Monday, XXX, 2022, at the City of Goleta, City Hall Building, 130 Cremona Drive, Suite B, Goleta, CA 93117.
Questions regarding the Contract Documents, Specifications, Proposal or other Bidding Documents, shall be submitted in writing and emailed to JoAnne Plummer [email protected]
The Project insurance requirements are per the Caltrans Standard Specifications, as modified by t
he City General Provisions contained herein.
Contract Time: 30 Working Days. Time is of the essence in the performance of this contract.
BIDDER SHALL COMPLETE:
Bidder’s Name
Street Address
City State Zip Code
Telephone Number Fax Number
E-mail
The following Addenda are acknowledged: Number Dated Initials (Bidder must fill in number and date of each
Addendum or may enter the word “none” if
appropriate)
BIDDERS Signature DATE
Tax I.D. Number
71 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-4
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS P
ARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
BIDDING SHEET (Page 1 of 3)
The cost of all labor, material and equipment necessary for the completion of the work itemized, even though not shown or specified, shall be included in the unit or lump sum prices for the various items shown herein.
The City further reserves the right to reject any or all bids, to waive any informality or irregularity in any bid or the bidding procedure, and to delete any items of work in the award of contract. The City's decision on the bid amount is final.
Bidders must bid on all items in the Bid Schedule including the Supplemental and/or Alternative Bid Items in order for their bids to be complete. The award of contract will be based on the lowest responsive Base Bid only.
In the case of unit basis items, the amount set forth under the "Item Total" column (total base bid in words) shall be the product of the unit price bid and the estimated quantity for the item.
Bids on lump sum items are item totals. If a unit price of a lump sum item is entered and it differs from the item total, the item total prevails.
Entries are to be expressed in dollars or decimal fractions of a dollar. Symbols such as commas and dollar signs are ignored and have no significance in establishing unit price or item total.
Unit prices and item totals are interpreted by the number of digits and decimal placement. Do not round item totals or the total bid.
In case of discrepancy between the unit price and the total set forth for a unit basis item, the unit price prevails, except as provided in (a) or (b), as follows:
(a) If the amount set forth as a unit price is unreadable or otherwise unclear, or is omitted, or is the same as the amount of the entry in the item total column, then the amount set forth in the item total column for the item shall prevail and shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price; (b) (Decimal Errors) If the product of the entered unit price and the estimated quantity is exactly off by a factor of ten, one hundred, etc., or one-tenth, or one-hundredth, etc. from the entered total, the discrepancy will be resolved by using the entered unit price or item total, whichever most closely approximates percentage-wise the unit price or item total in the City's Final Estimate of cost.
If both the unit price and the item total are unreadable or otherwise unclear, or are omitted, the bid may be deemed irregular. Likewise, if the item total for a lump sum item is unreadable or otherwise unclear, or is omitted, the bid may be deemed irregular unless the project being bid has only a single item and a clear, readable total bid is provided. .
72 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-5
BIDDING SHEET – PART 1
A
RMITOS COMMUNITY GARDEN & PARKING IMPROVEMENTS
PART 1 - BASE BID SCHEDULE:
Item # Item Pay Ref Quantity Unit Unit
Cost Total Cost
Playground & Community Garden Areas
1.1 Mobilization, Bonds & Insurance 1 LS
1.2 Construction Surveying & Staking 3-10 1 LS
1.3 SWPPP Preparation & Implementation
and SMARTS registration
3-12.6 1 LS
1.4 Clearing and Grubbing 300-6.6 41,500 SF
1.5 Demolish Existing Play Surfacing 401-7 1 LS
1.6 Demolish Existing Fencing 401-7 1 LS
1.7 Demolish Existing Walks 401-7 1 LS
1.8 Rough Grading 301-7 41,500 SF
1.9 Finish Grading 801-2 41,500 SF
1.10 Import and Placement of Aggregate
Base
301-2 305 CY
1.11 Decomposed Granite Paving 301-7.5 11,200 SF
1.12 Portland Cement Concrete Paving 302-6.8 3,780 SF
1.13 Concrete Curbing at Fencing 302-6.8 480 LF
1.14 Interlocking Concrete Pavers 318-2 185 SF
1.15 Permeable Asphalt Concrete 302-5.9 6 CY
1.16 Metal Header 801-3.1 220 LF
1.17 Playground Equipment - Swings 317-7 1 LS
1.18 Playground Equipment – Refurbish
Existing Structure
317-7 1 LS
1.19 Playground Equipment – Sand Table 317-7 1 LS
1.20 Playground Equipment – Cantilever
Shade Sail
317-7 1 LS
1.21 Playground Equipment – Music Play 317-7 1 LS
1.22 Playground Equipment – Butterfly 317-7 1 LS
1.23 Playground Equipment – Flowers 317-7 1 LS
1.24 Playground Equipment – Signage 317-7 1 LS
1.25 Playground Rubber Surfacing 316-7 4,420 SF
1.26 Prefabricated Garden Shade Trellis
Structures
221-4 1 LS
1.27 Raised Garden Beds - Large 801-2.5.1 10 EA
1.28 Raised Garden Beds – Small 801-2.5.1 40 EA
1.29 Fencing – Wire Mesh 304-6.7 760 LF
1.30 Fencing – Wire Mesh Gate 304-6.7 1 EA
1.31 Fencing – Wire Mesh Double Gate 304-6.7 3 EA
73 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-6
BI
D PART 1 - ADDITIVE ALTERNATE SCHEDULE:
Item # Item Pay Ref # Unit Unit Cost Total Cost
A1 Mobilization, Bonds & Insurance 1 LS
A2 Demolish Existing Playground
Equipment
401-7 1 LS
A3 New Playground Structure 317-7 1 LS
TOTAL BID ALTERNATE “A”
1.32 Signage - Entry Monument 601-3.5.2 1 EA
1.33 Signage - Relocate Existing Signs 601-3.5.2 1 LS
1.34 Signage – Interpretive Sign 601-3.5.2 1 EA
1.35 Signage – Butterfly Garden Info Panel 601-3.5.2 1 EA
1.36 Site Furniture - Work Bench 220-4.2 1 EA
1.37 Site Furniture – Bench 220-4.2 1 EA
1.38 Site Furniture – Curved Bench 220-4.2 18 EA
1.39 Site Furniture – Picnic Table 220-4.2 4 EA
1.40 Site Furniture – Trash Receptacle 220-4.2 6 EA
1.41 Site Furniture – Shed 220-4.2 2 EA
1.42 Site Furniture – Bike Racks 220-4.2 10 EA
1.43 Site Furniture – Pizza Oven & Outdoor
Kitchen
220-4.2 1 EA
1.44 Site Furniture – Tree Grates 220-4.2 3 EA
1.45 Site Furniture – Compost Bins 220-4.2 1 EA
1.46 Landscape - Planting 801-7 1 LS
1.47 Landscape – Irrigation 801-7 1 LS
1.48 Landscape – Maintenance Period (Total
Project)
801-7 1 LS
Subtotal
Storm Drain Repair & Linear Drainage Area
1.50 Earthwork for Linear Drainage Area 301-1,
801-2
3,750 SF
1.51 Reconstruct Storm Drain 402-1.2 1 LS
1.52 Construct overflow to Creek 402-1.2 1 LS
1.53 Fencing – Chainlink 304-3.4 165 LF
1.54 Fencing – Chainlink Gate 304-3.4 1 EA
1.55 Landscape - Planting 801-7 1 LS
1.56 Landscape – Irrigation 801-7 1 LS
Subtotal
TOTAL BASE BID – PART 1
74 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-7
BIDDING SHEET – PART 2
S
AN JOSE CREEK MULTI-PURPOSE PATH
Item # Item Pay Ref Quantity Unit Unit Cost Total Cost
2.1 Construction Staking 3-10 1 LS
2.2 Develop Water Supply 300-2 1 LS
2.3 Construction Area Signs 600 1 LS
2.4 Traffic Control System 600 1 LS
2.5 Type II Barricade 601 4 EA
2.6 Type III Barricade 601 3 EA
2.7 Job Site Management 3-12 1 LS
2.8 Prepare Storm Water Pollution
Prevention Plan
3-12.6 1 LS
2.9 Rain Event Action Plan 3-12.6 3 EA
2.10 Storm Water Sampling and Analysis
Day
3-12.6 1 EA
2.11 Storm Water Annual Report 3-12.6 1 EA
2.12 Temporary Check Dam (Type 2) 3-12.6 6 LF
2.13 Temporary Silt Fence 3-12.6 880 LF
2.14 Temporary Construction Entrance 3-12.6 1 EA
2.15 Temporary Concrete Washout 3-12.6 1 LS
2.16 Temporary High-Visibility Fence 3-12.6 600 LF
2.17 Remote Tree 300-1 3 EA
2.18 Clearing and Grubbing 300-1 1 LS
2.19 Roadway Excavation 300-2 140 CY
2.20 Imported Borrow 300-5 10 CY
2.21 Fiber Rolls 3-12.6 880 LF
2.22 Hydroseed 800-1 1670 SQFT
2.23 Class 2 Aggregate Base 200-2 31 CY
2.24 Hot Mix Asphalt (Type A) 203-6 24 Ton
2.25 ¾” Crushed Rock 200-1 71 CY
2.26 Porous Asphalt Concrete 203-15 34 CY
2.27 Low Water Crossing 201/206-1 1 LS
2.28 Rock Slope Protection (20 lb, Class I,
Method B)(CY)
200-1 12 CY
2.29 Rock Slope Protection Fabric (Class
8)
213-1 56 SQYD
2.30 Minor Concrete (Curb, Gutter,
Sidewalk and Driveway)
303-5 4 CY
2.31 Minor Concrete (Curb) 303-5 12 CY
2.32 Minor Concrete (Approach Slab) 303-5 4 CY
2.33 Remove Concrete (Curb, Gutter, and
Sidewalk)
401-3 3 CY
2.34 42” Wood Rail Fence 204-1 59 LF
2.35 Relocated 42” Wood Rail Fence 204-1 21 LF
2.36 Remove Chain Link Fence 300-1 220 LF
2.37 Barricade 204-1 1 EA
75 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-8
2 .38 Object Marker, Type N-2(CA) 601-3.5 2 EA
2.39 Furnish Single Sheet Aluminum
(0.063” – Unframed)
601-3.5 45 SQFT
2.40 Roadside Sign – One post 601-3.5 14 EA
2.41 Removable Bollard 300-1 1 EA
2.42 4” Two-Component Paint Traffic
Stripe
314-4 400 LF
2.43 Boardwalk 204/205/206 1 LS
2.44 Mobilization 901-02 1 LS
TOTAL BASE BID – PART 2
76 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-9
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS P
ARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
BIDDING SHEET
SUMMARY OF BID SCHEDULE
TO
TAL BASE BID PART 1 - Armitos Community Garden & Park Improvements …………..………………………..……………………….………$
TO
TAL BASE BID PART 2 – San Jose Creek Multi Use Path
…………………………………………………………….………$
TO
TAL BASE BID………………………………………………$
__
____________________________________________________________ (Total Base Bid in Words)
Com
pany Name of Bidder
SUMMARY OF BID SCHEDULE
TO
TAL BASE BID PART 1 WITH ALTERNATES - Armitos Community Garden & Park Improvements …………..………………………..……………………$
TO
TAL BASE BID PART 2 – San Jose Creek Multi Use Path
…………………………………………………………….………………$
TO
TAL BASE BID……………………………………………..….……$
__
____________________________________________________________ (Total Base Bid in Words)
_______________________________________________
Company Name of Bidder
77 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-10
NO
TE: The City of Goleta will determine the lowest bid based on the total Base Bid.
Bidder shall bid on the Base Bid and all Bid Alternates. Bids that do not include all Bid Alternates will not be accepted. The City of Goleta reserves the right to add none or any combination of the Bid Alternates.
78 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-11
PROPOSED EQUIPMENT AND MATERIAL MANUFACTURERS
T
he Bidder must indicate the name of the manufacturer of the equipment, and supplier of the material, proposed to be furnished under the contract. Awarding of a contract based on this bid does not imply approval by the City of the manufacturers or suppliers listed by the Bidder. No substitution will be permitted after award of contract except upon written approval of the City.
Equipment/Materials Supplier
1. Portland Cement Concrete
2. Hot Mix Asphalt (HMA Type A)
3. Class 2 Aggregate Base
4. Detectable Warning Surface
5. Traffic Stripe and Marking Paint
6. PHB Assembly, Foundation, and Appurtenances
7. Controller
8. Battery Backup System
9. Type III Service Cabinet
10. PHB Pole
11. Pedestrian Push Button
12. Pull Boxes
Additional items in the Special Provisions
79 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-12
DE
SIGNATION OF SUBCONTRACTORS
Bidder proposes to subcontract certain portions of the Work which are in excess of one-half of one percent (0.5%) of the total amount base bid or $10,000, whichever is greater, and to procure materials and equipment from suppliers and vendors.
These Subcontractors are identified as follows:
Work to be
Performed
Subcontractor
Li
cense
Number
Subcontractor
DI
R
Registration
Number
(Note1)
Percent of
To
tal Bid
Subcontractor’s
Na
me & Address
No
te 1: Bidders have 24 hours after the Bid Deadline to submit this information 80 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-13
BIDDER’S REFERENCES
Th
e following are the names, addresses, and phone numbers for three public agencies for which Bidder has performed projects of the same magnitude and character of the work bid within the past three years:
1. Name of Agency
Agency Address
Telephone
Contact Person
Contract Amount
2. Name of Agency
Agency Address
Telephone
Contact Person
Contract Amount
3. Name of Agency
Agency Address
Telephone
Contact Person
Contract Amount
The following are the names, addresses, and phone numbers for all brokers and sureties from whom Bidder intends to procure insurance bonds:
__________________________________________________________________________ __________________________________________________________________________ __________________________________________________________________________
EQUAL EMPLOYMENT OPPORTUNITY COMPLIANCE
Bidder certifies that in all previous contracts or subcontracts, all reports which may have been due under the requirements of any local, State, or Federal equal employment opportunity orders have been satisfactorily filed, and that no such reports are currently outstanding. 81 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-14
ELIGIBILITY TO CONTRACT
The successful Bidder is prohibited from performing work on this Project with a Subcontractor who is ineligible to perform work on the Project pursuant to Section 1777.1 or 1777.7 of the Labor Code.
BIDDER’S INFORMATION
Bidder certifies that the following information is true and correct:
Bidder’s Name ______________________________________________________________ Business Address ____________________________________________________________ __________________________________________________________________________ Telephone __________________________________________________________________ State Contractor’s License No. and Class _________________________________________ Original Date Issued Expiration Date _____________________________ DIR Registration No:
The following are the names, titles, addresses, and phone numbers of all individuals, firm members, partners, joint venturers, and/or corporate officers having a principal interest in this Bid:
__________________________________________________________________________ __________________________________________________________________________ __________________________________________________________________________ The date of any voluntary or involuntary bankruptcy judgments against any principal having an interest in this Bid are as follows:
__________________________________________________________________________ __________________________________________________________________________ __________________________________________________________________________ All current and prior DBA’s, alias, and/or fictitious business names for any principal having an interest in this Bid are as follows:
__________________________________________________________________________ __________________________________________________________________________ __________________________________________________________________________ 82 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-15
I declare under penalty of perjury under the laws of the State of California that the above r
epresentations are true and correct. Executed this _____ day of ____________, 20__, at ___________________ California.
Signature and Title of Bidder
or Authorized Representative
(SEAL)
83 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-16
BIDDER’S STATEMENT OF PAST CONTRACT DISQUALIFICATIONS AND DEFAULTS I
dentify all instances of being disqualified, removed, determined to be a non-responsible bidder, debarred, assessed liquidated damages, terminated for default or otherwise prevented from bidding on, or completing, a federal, state, or local government project.
1. Have you ever been disqualified from any government contract? Yes No
2 . If yes, explain the circumstances including date of public entity action, name of project, contract award amount and current contact person at public entity:
__
__________________________________________________________ Signature and Title of Bidder or Authorized Representative 84 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-17
BID BOND
FO
R
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
KNOW ALL PERSONS BY THESE PRESENTS that [Bidder] ________________________ __________________________ as PRINCIPAL, and _______________________________, a corporation organized under the laws of the State of _________________________ and licensed by the State of California to execute bonds and undertakings as sole surety, as SURETY, are held and firmly bound unto the City of Goleta, as City, in the penal sum of ten percent (10%) of the total Base Bid Price on the base Contract Work, excluding any Alternate Bid Items submitted by PRINCIPAL to CITY for the above stated project, for the payment of which sum, PRINCIPAL and SURETY agree to be bound, jointly and severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas PRINCIPAL has submitted a proposal to CITY for the above stated project.
NOW, THEREFORE, the penal sum guaranteed by this bond shall be forfeited to the City in the event of any of the following: (1) The aforesaid Principal withdraws said bid after the Bid Deadline contrary to applicable law; or (2) Principal fails, within ten (10) business days after receipt of wr
itten notice that the contract has been awarded to Principal and tender of the Contract, to, deliver to City the executed Agreement, in the prescribed form, in accordance with the bid as accepted, and file with the City all documents required in section 3-1.18 of the City’s General Provisions.
In case suit is brought upon this bond, SURETY further agrees to pay all reasonable attorneys’ fees and costs incurred by CITY in an amount fixed by the court. SURETY hereby waives the provisions of California Civil Code Sections 2845 and 2849.
IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this _______day of , 20__.
PR
INCIPAL:
(Address)
BY
:
(Signature and Title of Authorized Officer)
BY:
(Signature and Title of Authorized Officer)
85 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-18
SU
RETY:
(Address)
BY
:
(Signature and Title of Authorized Officer)
BY:
(Signature and Title of Authorized Officer)
Note: All signatures must be acknowledged before a notary public. Attach appropriate acknowledgment. Also, evidence of the authority of any person signing as attorney-in-fact must be attached.
86 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-19
STATEMENT ACKNOWLEDGING PENAL AND CIVIL PENALTIES
C
ONCERNING THE CONTRACTOR’S LICENSING LAWS
[Business & Professions Code § 7028.15; Public Contract Code § 20103.5] The undersigned, a duly authorized representative of the Bidder, certify that I am aware of the provisions of California law and that I, or the company/individual on whose behalf this Bid is being submitted, hold a currently valid California contractor’s license as set forth in the Business and Professions Code § 7028.15 and Public Contract Code § 20103.5 (and any updates).
A contractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.
Bidder:
Li
cense No.: Class Expiration date:
DI
R Registration No.: _____________________
Date Signature
87 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-20
DECLARATION OF ELIGIBILITY TO CONTRACT
[
Labor Code §§ 1777.1 and 1777.7; Public Contract Code § 6109] The undersigned, a duly authorized representative of the Bidder, certifies and declares that:
1. The Bidder is aware of Sections 1771.1 and 1777.7 of the California Labor Code, which prohibit a contractor or subcontractor who has been found by the Labor Commissioner or the Director of Industrial Relations to be in violation of certain provisions of the Labor Code, from bidding on, being awarded, or performing work as a subcontractor on a public works project for specified periods of time.
2. The Bidder is not ineligible to bid on, be awarded or perform work as a subcontractor on a public works project by virtue of the foregoing provisions of Sections 1771.1 or 1777.7 of the California Labor Code or any other provision of law.
3. The Bidder is aware of California Public Contract Code Section 6109 (and any updates.)
4. The Bidder has investigated the eligibility of each and every subcontractor the contractor intends to use on this public works project, and determined that none of them is ineligible to perform work as a subcontractor on a public works project by virtue of the foregoing provisions of the Public Contract Code, Sections 1771.1 and 1777.7 of the Labor Code, or any other provision of law.
5. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Executed this day of , 20__, at ________________________, California.
Signature:
Name:
Title:
Name of Company:
Note: Signature must be acknowledged before a notary public. Attach appropriate acknowledgment.
88 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-21
89 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-22
NON-COLLUSION DECLARATION
FO
R
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
I am the [title] of [name of
bidder], the party making the foregoing bid, declares that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly, colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on ___ [date], at __ [city], ___ [state]
(Signature and Title of Authorized Representative)
.
90 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
C-23
This Page Intentionally Left Blank
91 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-1
SECTION D
C
ONTRACT AWARD AND EXECUTION
CO
NTRACT
PERFORMANCE BOND FORM
PAYMENT BOND FORM
92 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-2
Th
is Page Intentionally Left Blank
93 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-3
SAMPLE CONTRACT
Th
is Public Works Contract (herein referred to as “CONTRACT”) is made and entered into by and between the CITY OF GOLETA, a municipal corporation (herein referred to as "CITY"), and CONTRACTOR (hereinafter referred to as “CONTRACTOR”).
SECTION A. RECITALS
1. Pursuant to the Notice Inviting Sealed Bids for the ______________________________, bids were received, publicly opened, and declared on the date specified in the notice.
2. On ________, 2022 Goleta’s City Council declared CONTRACTOR to be the lowest responsible bidder and accepted the bid of CONTRACTOR and the City Council approved this CONTRACT and authorized the City Manager to execute the CONTRACT with CONTRACTOR for furnishing labor, equipment and material for the ______________________________ in the City of Goleta.
NOW, THEREFORE, in consideration of the foregoing and the mutual covenants herein contained, it is agreed:
SECTION B. TERMS
1. GENERAL SCOPE OF WORK: CITY agrees to engage CONTRACTOR and CONTRACTOR agrees to furnish all necessary labor, tools, materials, appliances, and equipment for and do the work for the ______________________________ in the City of Goleta. The work shall be performed in accordance with the Plans and Specifications (and as generally described in the “Notice Inviting Sealed Bids,” attached as Exhibit A) and in accordance with bid prices set forth in CONTRACTOR’S Bid Proposal (attached as Exhibit B) and in accordance with the instructions of the City Engineer, or City’s Manager’s designee.
2. INCORPORATED DOCUMENTS TO BE CONSIDERED COMPLEMENT
ARY: The contract
documents for the aforesaid project, a complete set of which is on file with the Goleta City Clerk’s Office, shall consist of the Notice Inviting Bids, Instructions to Bidders, Bid Proposal, Standard Specifications, Special Provisions, and all referenced specifications, details, standard drawings, and appendices; together with this CONTRACT and all required bonds, insurance certificates, permits, notices and affidavits; and also, including any and all addenda or supplemental agreements clarifying, amending, or extending the work contemplated as may be required to insure its completion in an acceptable manner. All of the provisions of said contract documents are made a part hereof as though fully set forth herein. This contract is intended to require a complete and finished piece of work and anything necessary to complete the work properly and in accordance with the law and lawful governmental regulations shall be performed by CONTRACTOR whether set out specifically in the contract or not. Should it be ascertained that any inconsistency exists between the aforesaid documents and this written CONTRACT, the provisions of this CONTRACT, and the Standard Specifications, in that order, shall control.
Collectively, these contract documents constitute the complete CONTRACT between CITY and CONTRACTOR and supersede any previous agreements or understandings. 94 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-4
3. COMPENSATION: CONTRACTOR agrees to receive and accept the prices set forth in its Bid Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder. Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid contract documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.
4. TIME OF PERFORMANCE:
CONTRACTOR agrees to complete the work within the timeframe specified in the Contract Documents from the date of the notice to proceed. By signing this CONTRACT, CONTRACTOR represents to CITY that the contract time is reasonable for completion of the work and that CONTRACTOR will complete such work within the contract time. In accordance with Government Code Section 53069.85, CONTRACTOR agrees to forfeit and pay CITY as liquidated damages, not as a penalty, the sum of $1000 per day for each and every day of unauthorized delay beyond the completion date, which amount shall be deducted from any payments due or to become due the CONTRACTOR.
5. PREVAILING WAGES:
A.
Pursuant to Labor Code Sections §§1720 et seq., including but not limited to sections 1771, 1774 and 1775, and as specified in Title 8, California Code of Regulations, Section 16000 et seq., CONTRACTOR must pay its workers prevailing wages. It is CONTRACTOR’s responsibility to interpret and implement any prevailing wage requirements and CONTRACTOR agrees to pay any penalty or civil damages resulting from a violation of the prevailing wage laws.
B. In accordance with Labor Code Section 1773.2, copies of the prevailing rate of per diem wages are available upon request from CITY’s Engineering Division or the website for State of California Prevailing wage determination at http://www.dir.ca.gov/DLSR/PWD. CONTRACTOR must post a copy of the prevailing rate of per diem wages at the job site.
C. CITY directs CONTRACTOR’s attention to Labor Code Sections 1777.5, 1777.6 and 3098 concerning the employment of apprentices by CONTRACTOR or any subcontractor.
D. Labor Code Section 1777.5 requires CONTRACTOR or subcontractor employing tradesmen in any apprenticeship occupation to apply to the joint apprenticeship committee nearest the site of the public works project and which administers the apprenticeship program in that trade for a certificate of approval. The certificate must also fix the ratio of apprentices to journeymen that will be used in the performance of the contract. The ratio of apprentices to journeymen in such cases will not be less than one to five except:
95 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-5
(1) When employment in the area of coverage by the joint apprenticeship c
ommittee has exceeded an average of 15 percent in the 90 days before the request for certificate, or
(2) When the number of apprentices in training in the area exceeds a ratio of one to five, or
(3) When the trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally, or (4) When assignment of an apprentice to any work performed under a public works contract would create a condition that would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large, or the specific task to which the apprentice is to be assigned is of a nature that training cannot be provided by a journeyman.
Pursuant to Labor Code § 1776, CONTRACTOR shall comply with all Department of Industrial Relations registration requirements.
E. CONTRACTOR is required to make contributions to funds established for the administration of apprenticeship programs if CONTRACTOR employs registered apprentices or journeymen in any apprenticeable trade on such contracts and if other contractors on the public works site are making such contributions.
F. CONTRACTOR and any subcontractor must comply with Labor Code Sections 1777.5 and 1777.6 in the employment of apprentices.
G. Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations (DIR), ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
H. CONTRACTOR and its subcontractors must keep an accurate certified payroll records showing the name, occupation, and the actual per diem wages paid to each worker employed in connection with this CONTRACT. The record will be kept open at all reasonable hours to the inspection of the body awarding the contract and to the Division of Labor Law Enforcement. If requested by CITY, CONTRACTOR must provide copies of the records at its cost.
6. LEGAL HOURS OF WORK:
CONTRACTOR agrees to comply with the provisions of California Labor Code Section 1813 concerning penalties for workers who work excess hours. Except as provided by Labor Code Section 1815, the CONTRACTOR shall, as a penalty to the CITY, forfeit twenty five dollars ($25) for each worker employed in the execution of the Contract by the CONTRACTOR or by any Subcontractor for each calendar day during which such worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2, Part 7, Chapter 1, Article 3 (commencing at Section 1810) of the California Labor Code. 96 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-6
7. TRAVEL AND SUBSISTENCE PAY : CONTRACTOR agrees to pay travel and subsistence pay to each worker needed to execute the work required by this CONTRACT as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed in accordance with Labor Code Section 1773.8.
8. CONTRACTOR'S LIABILITY: T
he CITY and its officers, agents and employees (“Indemnitees”) shall not be answerable or accountable in any manner for any loss or damage that may happen to the work or any part thereof, or for any of the materials or other things used or employed in performing the work; or for injury or damage to any person or persons, either workers or employees of CONTRACTOR, of its subcontractors or the public, or for damage to adjoining or other property from any cause whatsoever arising out of or in connection with the performance of the work. CONTRACTOR shall be responsible for any damage or injury to any person or property resulting from defects or obstructions or from any cause whatsoever.
CO
NTRACTOR will indemnify Indemnities against and will hold and save Indemnitees harmless from any and all actions, claims, damages to persons or property, penalties, obligations or liabilities that may be asserted or claimed by any person, firm, entity, corporation, political subdivision, or other organization arising out of or in connection with the work, operation, or activities of CONTRACTOR, its agents, employees, subcontractors or invitees provided for herein, whether or not there is concurrent passive negligence on the part of CITY. In connection therewith:
a. CONTRACTOR will defend any action or actions filed in connection with any such c
laims, damages, penalties, obligations or liabilities and will pay all costs and expenses, including attorneys' fees, expert fees and costs incurred in connection therewith.
b. CONTRACTOR will promptly pay any judgment rendere d against CONTRACTOR or Indemnitees covering such claims, damages, penalties, obligations and liabilities arising out of or in connection with such work, operations or activities of CONTRACTOR hereunder, and CONTRACTOR agrees to save and hold the Indemnitees harmless therefrom.
c. In the event Indemnitees are made a party to any a ction or proceeding filed or prosecuted against CONTRACTOR for damages or other claims arising out of or in connection with the work, operation or activities hereunder, CONTRACTOR agrees to pay to Indemnitees and any all costs and expenses incurred by Indemnitees in such action or proceeding together with reasonable attorneys' fees.
CO
NTRACTOR'S obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this CONTRACT, Contractor shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where 97 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-7
CITY active negligence accounts for only a percentage of the liability involved, the o
bligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City.
So much of the money due to CONTRACTOR under and by virtue of the contract as shall be considered necessary by CITY may be retained by CITY until disposition has been made of such actions or claims for damages as aforesaid.
It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California. This indemnity provision shall survive the termination of the CONTRACT and is in addition to any other rights or remedies which Indemnitees may have under the law.
This indemnity is effective without reference to the existence or applicability of any insurance coverage which may have been required under this CONTRACT or any additional insured endorsements which may extend to Indemnitees.
CONTRACTOR, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the Indemnitees, while acting within the scope of their duties, from all claims, losses and liabilities arising out of or incident to activities or operations performed by or on behalf of the CONTRACTOR regardless of any prior, concurrent, or subsequent passive negligence by the Indemnitees.
9. THIRD PARTY CLAIMS:
In accordance with Public Contracts Code Section 9201, CITY will promptly inform CONTRACTOR regarding third-party claims against CONTRACTOR, but in no event later than ten (10) business days after CITY receives such claims. Such notification will be in writing and forwarded in accordance with the “Notice” section of this CONTRACT. As more specifically detailed in the contract documents, CONTRACTOR agrees to indemnify and defend the City against any third-party claim.
10. WORKERS COMPENSATION:
In accordance with California Labor Code Sections 1860 and 3700, CONTRACTOR and each of its subcontractors will be required to secure the payment of compensation to its employees. In accordance with the provisions of California Labor Code Section 1861, CONTRACTOR, by signing this contract, certifies as follows: “I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.”
11. INSURANCE:
With respect to performance of work under this CONTRACT, CONTRACTOR shall maintain and shall require all of its subcontractors to maintain insurance as required in the Standard Specifications.
12. ASSIGNMENT:
This CONTRACT is not assignable nor the performance of either party's duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations of either party without the prior written consent of the other shall be void and of no force and effect. 98 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-8
13. INDEPENDENT CONTRACTOR: CONTRACTOR is and shall at all times remain as to the CITY, a wholly independent contractor. Neither the CITY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR'S employees, except as herein set forth. CONTRACTOR shall not at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of CITY.
14. TAXES:
CONTRACTOR is responsible for paying all retail sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes and operations incidental to or involved in this contract. CONTRACTOR is responsible for ascertaining and arranging to pay them. The prices established in the contract shall include compensation for any taxes CONTRACTOR is required to pay by laws and regulations in effect at the bid opening date.
15. LICENSES:
CONTRACTOR represents and warrants to CITY that it has all licenses, permits, qualifications, insurance, and approvals of whatsoever nature which are legally required of CONTRACTOR to practice its profession. CONTRACTOR represents and warrants to CITY that CONTRACTOR shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this CONTRACT any licenses, permits, insurance, and approvals which are legally required of CONTRACTOR to practice its profession. CONTRACTOR shall maintain a City of Goleta business license, if required under CITY ordinance.
16. RECORDS:
CONTRACTOR shall maintain accounts and records, including personnel, property, and financial records, adequate to identify and account for all costs pertaining to this CONTRACT and such other records as may be deemed necessary by CITY or any authorized representative, and will be retained for three years after the expiration of this CONTRACT. All such records shall be made available for inspection or audit by CITY at any time during regular business hours.
17. SEVERABILITY:
If any portion of these contract documents are declared by a court of competent jurisdiction to be invalid or unenforceable, then such portion will be deemed modified to the extent necessary in the opinion of the court to render such portion enforceable and, as so modified, such portion and the balance of this CONTRACT will continue in full force and effect provided that it does not frustrate the mutual intent of the parties herein.
18. WHOLE AGREEMENT:
This CONTRACT supersedes any and all other agreements either oral or written, between the parties and contains all of the covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this contract acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statements or promise not contained in this contract shall not be valid or binding. Any modifications of this contract will be effective only if signed by the party to be charged.
19. AUTHORITY:
CONTRACTOR affirms that the signatures, titles, and seals set forth hereinafter in execution of this CONTRACT represent all individuals, firm members, partners, joint ventures, and/or corporate officers having a principal interest herein. Each party warrants that the 99 COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-9
individuals who have signed this CONTRACT have the legal power, right, and authority to make t
his CONTRACT and to bind each respective party. This CONTRACT may be modified by written amendment. CITY’s City Manager may execute any such amendment on CITY’s behalf.
20. NOTICES: All notices permitted or required under this CONTRACT shall be in writing and shall be deemed made when delivered to the applicable party’s representative as provided in this CONTRACT. Additionally, such notices may be given to the respective parties at the following addresses, or at such other addresses as the parties may provide in writing for this purpose.
S
uch notices shall be deemed made when personally delivered or when mailed forty- eight (48) hours after deposit in the U.S. mail, first-class postage prepaid, and addressed to the party at its applicable address. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.
CITY OF GOLETA
130 Cremona Drive, Suite B
Goleta, CA 93117
Attn: City Manager
CONTRACTOR
CONTRACTOR
Address
Address
Attn: Contact
21. DISPUTES:
Disputes arising from this contract will be determined in accordance with the contract documents.
22. NON-DISCRIMINATION: N o discrimination shall be made in the employment of persons in the work contemplated by this CONTRACT because of race, religion, color, medical condition, sex, sexual orientation, national origin, political affiliation or opinion, or pregnancy or pregnancy- related condition. A violation of this section exposes CONTRACTOR to the penalties provided for in Labor Code Section 1735.
23. NO THIRD PARTY BENEFICIARY:
This CONTRACT and every provision herein is for the
exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of the CONTRACTOR’s or the CITY’s obligations under this Contract.
24. TIME IS OF ESSENCE: T
ime is of the essence for each and every provision of the Contract Documents.
25. ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES: The Parties agree that this CONTRACT, agreements ancillary to this CONTRACT, and related documents to be entered into in connection with this CONTRACT will be considered signed when the signature of a party is delivered by facsimile transmission or scanned and delivered via electronic mail. Such 100
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-10
facsimile or electronic mail copies will be treated in all respects as having the same effect as an o
riginal signature.
26. GOVERNING LAW: This CONTRACT shall be governed by the laws of the State of California, and exclusive venue for any action involving this CONTRACT will be in Santa Barbara County.
IN WITNESS WHEREOF, the parties hereto have executed this CONTRACT with all the formalities required by law on the respective dates set forth opposite their signatures.
This CONTRACT is executed on this seventeenth day of September, at Goleta, California, and effective as of XXX, 2022.
CITY OF GOLETA:
___________________________________
Robert Nisbet, City Manager
ATTEST:
___________________________________
Deborah Lopez, City Clerk
APPROVED AS TO FORM:
MEGAN GARIBALDI, CITY ATTORNEY
_
__________________________________
Winnie Cai, Assistant City Attorney
CONTRACTOR:
_____________________________________
Name Title
State of California License No.
_____________________________________
Department of Industrial Relations Registration No.
_____________________________________
Business Phone No.
101
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-11
_____________________________________
CONTRACTOR’S Emergency Phone No. at which
contractor can be reached at any time
_____________________________________
_____________________________________
102
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-12
FAITHFUL PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, the City of Goleta, (hereinafter referred to as “City”) has awarded to ____________________________, (hereinafter referred to as the “Contractor”) an agreement for the COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084, (hereinafter referred to as the “Project”).
WHEREAS, the work to be performed by the Contractor is more particularly set forth in the Contract Documents for the Project dated ________________, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents.
NOW, THEREFORE, we, ______________________, the undersigned Contractor and ________________________________________________ as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the City in the sum of ___________________________ DOLLARS, ($____________), said sum being not less than one hundred percent (100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including the one (1) year guarantee of all materials and workmanship; and shall indemnify and save harmless the City, its officials, officers, employees, and authorized volunteers, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees including reasonable attorney’s fees, incurred by City in enforcing such obligation.
As a condition precedent to the satisfactory completion of the Contract Documents, unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of one (1) year after the acceptance of the work by City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship.
The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations under the Contract, law or equity, including, but not limited to, California Code of Civil Procedure Section 337.15.
103
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-13
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the City’s option:
1. Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or
2. Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a Contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
3. Permit the City to complete the Project in any manner consistent with California law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City’s objection to Contractor’s further participation in the completion of the Project.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
104
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-14
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20___.
(Corporate Seal)
Contractor/ Principal
By
Title
(Corporate Seal)
Surety
By
Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
The rate of premium on this bond is ____________ per thousand. The total amount of premium charges is $_______________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety) ___________________________________________ ___________________________________________
___________________________________________
(Name and Address of Agent or ___________________________________________ Representative for service of ___________________________________________ process in California, if different ___________________________________________ from above)
(Telephone number of Surety ___________________________________________ and Agent or Representative for
service of process in California)
105
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-15
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal. 106
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-16
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of Attorney to local representatives of the bonding company must also be attached.
END OF PERFORMANCE BOND
107
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-17
This Page Intentionally Left Blank
108
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-18
LABOR AND MATERIAL PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Goleta (hereinafter designated as the “City”), by action taken or a resolution passed ___________________ , 20____, has awarded to ________________________ hereinafter designated as the “Principal,” a contract for the work described as follows: the COMMUNITY GARDEN,
SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084 (the “Project”); and
WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and __________________________ as Surety, are held and firmly bound unto the City in the penal sum of ______________ Dollars ($___________) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code Section 9100, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Revenue and Taxation Code Section 18663, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond.
It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for 109
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-19
whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Civil Code Section 9100, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned, including but not limited to the provisions of sections 2819 and 2845 of the California Civil Code.
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20__.
(Corporate Seal)
Contractor/ Principal
By
Title
(Corporate Seal)
Surety
By
Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
110
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-20
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal. 111
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
D-21
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of-Attorney to local representatives of the bonding company must also be attached.
END OF PAYMENT BOND
112
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-1
This Page Intentionally Left Blank
113
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-2
SECTION E
CITY GENERAL PROVISIONS
S
tandard Specifications
The work provided herein shall be performed in accordance with the Standard Specifications for Public Works Construction, 2018 Edition, of the Southern California Chapter American Public Works Association. Part 1, General Provisions of the Standard Specifications is incorporated herein by reference. In case of conflict between the Standard Specifications and these General Provisions, the General Provisions shall take precedence.
Modifications to Standard Specifications
Section 1 – No changes.
Section 2 – Scope of the Work
Add the following:
Section 2-1.1 Conflict in Plans
As the figured dimensions shown on the drawings and in the specifications of the contract may not in every case agree with scale dimensions, the figured dimensions shall be followed in preference to the scaled dimensions, and drawings to a large scale shall be followed in preference to the drawings to a small scale. Should it appear that the work to be done, or any of the matter relative thereto is not sufficiently detailed or explained in the contract documents, the Contractor shall apply to the Engineer for such further explanations as may be necessary and shall conform thereto as part of the contract so far as may be consistent with the terms thereof.
Section 2-1.2 Suggestions to Contractor
Any plan or method of work suggested by the Agency or the Engineer to the Contractor but not specified or required, if adopted or followed by the Contractor in whole or in part, shall be used at the risk and responsibility of the Contractor; and the Agency and the Engineer shall assume no responsibility therefore and in no way be held liable for any defects in the work which may result from or be caused by use of such plan or method of work.
Section 2-5.5 Water for Construction
Attention is directed to the various sections of the Standard Specifications and these Special Provisions which require the use of water for the construction of this project.
Water for construction purposes as required by these Specifications will be provided by the Goleta Water District at the Contractor's expense. The City encourages the Contractor to use reclaimed water when a fill station is located nearby.
Water required for controlling dust, caused by the Contractor's operations and the passage of traffic through the construction site shall be applied as necessary, at the Contractor's expense.
The Contractor shall, whenever possible and not in conflict with these specifications, minimize 114
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-3
the use of water during construction of the project. Watering equipment shall be kept in good working order and water leaks shall be repaired promptly.
Full compensation for providing water for the project shall be considered as included in the contract prices paid for the various items of work and no separate payment shall be Section 2-7.1 General
The City will issue a Contract Change Order (CCO) if a change to the Total Contract Price or Contract Time is necessary. The Contractor will not be entitled to any adjustments in either Contract Time or Total Contract Price for changes performed without written direction from the City. Adjustments in Contract Time or Total Contract Price for changes performed will not be made until a Contract Change Order is approved.
Section 2-10 Disputed Work
If the Contractor and the Agency are unable to reach agreement on disputed work, the Agency may direct the Contractor to proceed with the work. Disputes which remain unresolved shall be subject to Section 9 and 10, Claim Resolution Process. Payment shall be later determined by mediation, if the Agency and Contractor agree thereto, or as fixed in a court of law. Although not to be construed as proceeding under extra work provisions, the Contractor shall keep and furnish records of disputed work in accordance with the Contract Documents.
Section 3 – Control of the Work
Add the following:
Section 3-7.2 Precedence of the Contract Documents.
In the event of conflicts or discrepancies between the Contract Documents, the provision placing a more stringent requirement on the Contractor shall prevail. The Contractor shall provide the better quality or greater quantity of Work and/or materials, unless otherwise directed by Agency in writing. In the event none of the Contract Documents place a more stringent requirement or greater burden on the Contractor, the controlling provision shall be that which is found in the document with higher precedence.
The governing ranking of Contract parts in descending order is:
1. Permits and other governmental approvals;
2. Change Orders and Construction Change Directives, issued after execution of the Agreement
3. Agreement/Contract; including all attachments and Addenda with later Addenda having priority over earlier Addenda
4. City Special Provisions
5. City General Provisions
6. Project Plans
7. Standard Specifications for Public Works Construction, 2018 Edition (Greenbook)
8. City of Goleta standard Plans
9. County of Santa Barbara standard Plans
10. Caltrans Standard Special Provisions for 2015 Standard Specifications
11. Caltrans Revised Standard Specifications
12. Caltrans Standard Specifications
13. Caltrans Revised Standard Plans
115
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-4
14. Supplemental project information
15. Written numbers and notes on a drawing govern over graphics
16. A detail drawing governs over a general drawing
17. A detail specification governs over a general specification
18. A specification in a section governs over a specification referenced by that section
If a discrepancy is found or confusion arises, submit a Request for Information (RFI.) Section 3-13.3.1 Guaranty
The Contractor shall warrant and guarantee the entire work and all parts thereof, including that performed and constructed by Subcontractors, Sub-subcontractors, and others employed directly or indirectly on the work, against faulty or defective materials, equipment or workmanship for the maximum period provided by law. In addition, thereto, for a period of one year commencing on the date of acceptance of the work, the Contractor shall, upon the receipt of notice in writing from the Agency, promptly make all repairs arising out of defective materials, workmanship or equipment and bear the cost thereof. The Agency is hereby authorized to make such repairs and the Contractor and Surety shall bear the cost thereof if, ten (10) days after the giving of such notice to the Contractor, the Contractor has failed to make or undertake with due diligence the repairs, provided, however, that, in the case of an emergency where, in the opinion of the Agency, delay could cause serious loss or damage, repairs may be made without notice being sent to the Contractor or Surety, and all expense in connection therewith shall be charged to the Contractor and Surety.
For the purpose of this article, "acceptance of the work" shall mean the acceptance of the work by the Agency in accordance with the Contract Documents but not for the purpose of extinguishing any covenant or agreement on the part of the Contractor to be performed or fulfilled under this contract which has not in fact been performed or fulfilled at the time of such acceptance all of which covenants and agreements shall continue to be binding on the Contractor until they have been fulfilled.
The effective date of acceptance of the work for purposes of determining commencement of the warranty period shall be the date of recordation of the Notice of Completion by the County Recorder.
Section 4 – Control of Materials
Add the following:
Section 4-1.1. Retention of Defective Work
If, in the opinion of the Engineer, the defective work is not of sufficient magnitude or importance to make the work dangerous or undesirable, or if, in the opinion of the Engineer, the removal of such work is impractical or will create conditions which are dangerous or undesirable, the Agency shall have the right and authority to retain such work instead of requiring it to be 116
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-5
removed and reconstructed, but will make such deductions therefore in the payments due or to become due to the Contractor as the Agency may deem just and reasonable.
Section 5 – Legal Relations and Responsibilities
Add the following:
Section 5-1.1 Mandatory Notification Prior to Excavation The Contractor's attention is directed to Section 4215.5 through 4217 of the Government Code of the State of California. This requires that two (2) working days prior to commencing any excavation "Underground Service Alert of Southern California" be notified by telephone, toll free 1-800-422-4133 or 811, for the assignment of an Inquiry Identification Number.
No excavation shall commence unless the Contractor has obtained the Inquiry Identification Number and so notified the Engineer.
As part of the performance required, the Contractor shall assist the Agency to and provide the Agency with, any and all compliance required of Agency as an operator under the provisions of California Government Code Sections 4216-4216.5.
Section 5-1.2 Accuracy of Utilities Information`
The locations of existing major utilities, whether above ground or underground, are indicated on the drawings. The Agency does not guarantee the accuracy or completeness of this information and it is to be understood that other above-ground and underground facilities not shown on the 117
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-6
drawings may be encountered during the course of the work. In any case, existing minor lines are not indicated.
Section 5-4.2 General Liability Insurance
The general liability must be at least combined single limits of no less than $2,000,000 per occurrence for all covered losses and no less than $4,000,000 general aggregate, and must contain:
1. Extension of coverage to the City, its officials, officers, agents and employees, as additional insureds, with respect to Contractor's liabilities hereunder in insurance coverages identified above;
2. A provision that coverage will not be canceled or subject to reduction until at least thirty (30) days' prior written notice has been given to the City Clerk, addressed to 130 Cremona Drive, Suite B, Goleta, CA 93117;
3. A provision that Contractor's insurance shall apply as primary, and not excess of, or contributing with, the City;
4. Contractual liability coverage sufficiently broad so as to include the liability assumed by the Contractor in the indemnity and hold harmless provisions of the Standard Condition;
5. A cross liability clause, or equivalent wording, stating that coverage will apply separately to each named or additional insured as if separate policies had been issued to each;
6. A broad form property damage endorsement;
7. A provision that the policies be provided on an "occurrence" basis;
8. Coverage for XCU (explosion, collapse, underground) hazards if applicable to the work; and
9. Products and completed operations coverage.
Umbrella or Excess Liability policies (Over Primary) if used to meet limit requirements shall provide coverage at least as broad as specified for underlying coverages and covering those insured in the underlying policies. Any such policy shall include a drop-down provision providing primary coverage above a maximum $25,000 self-insured retention for liability not covered by primary but covered by the umbrella. Coverage shall be “pay on behalf,” with defense costs payable in addition to policy limits. There shall be no cross-liability exclusion of claims or suits by one insured against another. Coverage shall be applicable to City for injury to employees of Contractor, subcontractors or others involved in the Work. Limits are subject to review but in no event less than $1,000,000 per occurrence.
Approval of insurance by the City or acceptance of the certificate of insurance by City shall not relieve or decrease the extent to which the Contractor may be held responsible for payment of damages resulting from Contractor's services or operation pursuant to the Agreement, nor shall it be deemed a waiver of City's rights to insurance coverage hereunder.
Replace entire section 5-4.2-1 with:
5-4.2-1 Policy Forms, Endorsements and Certificates
Provide and maintain current certificates of Insurance on forms supplied by the City and evidencing the above coverage to City prior to execution of this Agreement by City. Exercise due diligence to require any and all subcontractors and/or sub-subcontractors and all tiers of such subcontractors to provide General and Automobile Liability, and Workers' Compensation and 118
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-7
Employer's Liability Insurance with minimum limits of coverage and upon terms and provisions required above.
Section 6- Prosecution and Progress of the Work
Add the following:
Section 6-1.3 Notice to Proceed
After the execution of the contract, written notice to proceed will be given by the Agency to the Contractor. Notwithstanding any other provision of the contract, the Agency shall not be obligated to accept or to pay for any work furnished by the Contractor prior to delivery of notice to proceed whether or not the Agency has knowledge of the furnishing of such work.
Section 6-4.1.1 Notice of Delays
Whenever the Contractor foresees any delay in the prosecution of the work, and in any event immediately upon the occurrence of any delay which the Contractor regards as unavoidable, the Contractor shall notify the Engineer in writing of the probability of the occurrence of such delay and its cause in order that the Engineer may take immediate steps to prevent, if possible, the occurrence or continuance of the delay, or, if this cannot be done, may determine whether the delay is to be considered avoidable or unavoidable, how long it continues, and to what extent the prosecution and completion of the work are to be delayed thereby. It will be assumed that any and all delays which have occurred in the prosecution and completion of the work have been avoidable delays, except such delays as shall have been called to the attention of the Engineer at the time of their occurrence and found by the Engineer to have been unavoidable.
The Contractor shall make no claims that any delay not called to the attention of the Engineer at the time of its occurrence has been an unavoidable delay.
Section 6-4.1.2 Avoidable Delays
Avoidable delays in the prosecution or completion of the work shall include all delays which in the opinion of the Engineer would have been avoided by the exercise of care, prudence, foresight and diligence on the part of the contractor or the subcontractors. The following shall be considered avoidable delays within the meaning of the contract: 1) Delay in the prosecution of parts of the work which may in themselves be unavoidable but do not necessarily prevent or delay the prosecution of other parts of the work nor the completion of the whole work within the time herein specified; 2) Reasonable loss of time resulting from the necessity of submitted samples of materials and drawings to the Engineer for approval and from making of tests of materials, measurements and inspections; 3) Reasonable interference of other contractors employed by the Agency which do not necessarily prevent the completion of the whole work within the time agreed upon.
Section 6-4.1.3 Extension of Time
In case the work is not completed in the time specified, including such extensions of time as may have been granted for unavoidable delays, the Contractor will be assessed damages for delay in accordance with the Contract Documents. The Agency, however, shall have the right to grant an extension of time for avoidable delay if it is deemed in the Agency's best interest to do so. 119
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-8
During such extension of time, the Contractor will be charged for engineering and inspection services and other costs as provided in the Contract Documents.
Section 6-2.1 Working Hours
Regular working hours shall be within the hours of 8:00 a.m. and 5:00 p.m., unless otherwise authorized by the Engineer or as otherwise identified in these Contract Documents. Overtime and shift work may be established as a regular procedure by the Contractor only with the written permission of the Engineer. Such permission may be revoked at any time. No work shall be permitted on Saturdays, Sundays or legal holidays, except such work as is necessary for the proper care and protection of the work already performed or in case of an emergency.
It is unlawful to construct, demolish, excavate, alter or repair any building or structure between the hours of 8:00 p.m. and 6:00 a.m. without the written approval of the Engineer. The following required information shall be provided to the Engineer in writing a minimum of fourteen (14) calendar days in advance of the commencement of the proposed work:
1. Specific date, hours and location of work
2. Complete description of work to be done
3. Number and type of equipment to be used
4. Noise mitigation measures to be employed
5. Distance of the nearest resident to the work
6. Inspection required
All work in the following commercial zones is prohibited between November 15 and January 2: Hollister Avenue between Pacific Oaks Road and Cortona Drive; Storke Road between the 101 Freeway and Marketplace Drive; Hollister Avenue between Fairview Avenue and Patterson Avenue; Fairview Avenue between Shirrell Way and Carson Street; and Calle Real between Vega Street and Kellogg Avenue.
All work on streets within a School Zone as defined by the California Vehicle Code 40802 shall be limited to days when school is not in session or while students are not traveling to and from school, unless otherwise authorized by the Engineer in writing.
To the extent practicable, all work shall be scheduled to minimize inconvenience to the public, such as coordinating the timing of work in a specific area, or to avoid potential conflicts with adjacent private development to the degree possible.
120
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-9
Section 6-8.1 Completion and Acceptance
A job walk will be performed at such time as the Contractor indicates that all items have been completed. A list of the remaining minor tasks (a punch list) will be prepared by the Engineer and given to the Contractor.
All punch list items shall be completed during the contract period, and the Agency will assess liquidated damages for each day that the punch list items are not completed beyond the contract period. When all items have been completed to the satisfaction of the City Engineer, the project will be submitted to the City Council recommending accept once the completed work.
The Engineer will, in reporting completion to the City Council, give the date when the work was completed. This will be the date when the Contractor is relieved from responsibility to protect and maintain the work, except for portions of the work for which the Contractor may have previously been relieved of such responsibility in accordance with the Contract Documents.
Section 6-9.1 Liquidated Damages for Avoidable Delay
For each and every day that any portion of the work remains unfinished after the time fixed for completion in the contract documents as modified by any extension of time granted pursuant to Section 6-4.6.3, damage will be sustained by the Agency. Because of the difficulty in computing the actual material loss and disadvantage to the Agency, it is determined in advance and agreed to by the parties hereto that the Contractor will pay the Agency the amount of damages set forth herein as representing a reasonable forecast of the actual damages which the Agency will suffer by the failure of the Contractor to complete the work within the stipulated time. The execution of the agreement shall constitute acknowledgment by the Contractor that he or she has ascertained and agrees that the Agency will actually suffer damages in the amount herein fixed for each and every day during which the completion of the work is avoidably delayed beyond the stipulated completion date.
Unless otherwise provided in the contract documents, the Contractor shall have no claim or right of action against the Agency for damages, costs, expenses, loss of profits, or otherwise because or by reason of any delay in the fulfillment of the contract within the time limited therefore occasioned by any cause or event within or without the Contractor's control, and whether or not such delay may have resulted from anything done or not done by the Agency of the contract.
Damages for avoidable delays shall be in the amount of $1,000.00 for each consecutive calendar day in excess of the time specified for completion of the work.
Section 7 – Measurement and Payment
Add the following:
Section 7-3.2.1 Request for Payment
Progress payments will be made monthly after, receipt of a properly completed request from the Contractor with qualities confirmed and approval by the City. The Contractor shall submit all such requests for monthly progress payments, and shall include the following forms as applicable:
121
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-10
Form CC1: Progress Payment Request
This form is to be completed and signed by the Contractor and attached as a cover sheet to the request for payment. This form will be mandatory on all contract payment requests.
Form CC2: Progress Payment Request - Detail
This form shall be used by the Contractor to provide the detail required to verify the payment quantities.
Form CC3: Quantity Change Verification Form
This form is required before any payment can be made based on actual quantities exceeding bid quantities. At the conclusion of the contract, the City will issue a "Balancing Change Order" incorporating all quantity increases and decreases in the contract items of work.
Form CC4: Final Release Form
This form shall be signed by the Contractor and submitted with the final payment request. The contractor shall also sign and submit the Acknowledgement of Final Closeout and Release of Claims with the final Payment Request, or other documents to the satisfaction of the engineer.
The City will withhold five (5) percent of all monthly progress payments as retention to assure completion and payment of labor and materials.
Retention will be released to the Contractor Thirty Five (35) days after acceptance of the work by the City Council and the filling of a Notice of Completion.
122
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-11
123
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-12
CITY OF GOLETA, CA
Public Works Department
Construction Contract
Form CC1 - Progress Payment Request
From: Date: _______________________
Contractor Contract No.: _________________
Payment Request No.: __________
Address
To: CITY OF GOLETA
Public Works Department
130 Cremona Drive, Suite B
Goleta, California 93117
Project Name:
Original Contract Amount: $
Approved Change Orders through #:_______ $
Quantity Changes:
(Requires Project Engineer verification)
$
Total Contract Amount to Date: $
Value of Work Completed to Date: $
Less Retention: $
Less Liquidated Damages: $
Subtotal: $
Less Previous Payments Approved: $
Progress Payment Requested: $
The undersigned Contractor or Contractor's Authorized Representative certifies that to the best of his or her knowledge, information and belief, the work covered in this application for payment has been completed in accordance with the contract documents and the costs shown are true and correct.
Signature Print Name
Title Date
124
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-13
CITY OF GOLETA, CA
Public Works Department
Construction Contract
Form CC2- Progress Payment Request - Detail
Date: Payment Request No: Contract No.:
Contractor:
Project Name:
ITEM
NO.
DESCRIPTION UNIT BID
QUANTITY
UNIT/
FIRM
PRICE
INPLACE
THIS PERIOD
INPLACE
TOTAL
QTY. OR % EXTN. QTY. OR % EXTN.
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 Contractor Signature Date Inspector Signature Date 125
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-12
CITY OF GOLETA, CA
Public Works Department
Form CC3- Quantity Change Verification Form
Date: Contract No.:
Contractor: Project Name:
INSTRUCTIONS
This form is to accompany progress payments where there is quantity changes (variations in quantities authorized as part of the progress or final payment.
The quantity changes in amount of $________________________ accompanying Progress Payment #__________________ have been reviewed and actual quantities verified.
Project Engineer Signature Date
Bid
Item #
Item Description
Variance
Total
ATTACH ADDITIONAL SHEETS IF NECESSARY
Contractor Signature Inspector Signature
Date Date
126
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-13
CITY OF GOLETA, CA
Public Works Department
Construction Contract
Form CC4- Final Release Payment
From: _____________________________ Date: __________________________ Contractor
Contract No. _____________________
_____________________________ Payment Request No. _______________ Address
_____________________________
Project Name:
To: CITY OF GOLETA, CA
Public Works Department
130 Cremona Drive, Suite B
Goleta, California 93117
Upon settlement of final quantities and approval of a Notice of Completion for the project by the Goleta City Council, including any approved changes, this document shall be effective to release any and all further rights of the Contractor to security for payment, including any worker's, mechanic's or material supplier's lien, stop notice claim or right to bond that the undersigned may have for the work furnished for the project. This document is offered as evidence for settlement of final payment and to induce the City Council to approve such final payment for Contractor in connection with the CROSSWALK AT CALLE REAL / FAIRVIEW CENTER - PEDESTRIAN HYBRID BEACON (PHB).
This release covers the final payment to the undersigned for all labor, services, equipment and material furnished on the job, including the work of all subcontractors and all materials furnished for all suppliers, and other agents acting on behalf of the undersigned on this work. There are no disputed claims for additional work.
______________________________ _________________________ Contractor Signature: Print Name:
______________________________ _________________________ Title: Date:
NOTICE: A signed final release is required with submittal of request for payment. 127
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-14
Post-Construction Waste Reduction & Recycling Summary Report Diversion Requirement: Reduce quantity of materials disposed at landfills by 65% or more.
Column A: List estimated quantities of waste for each material type (in tons). To convert material quantities to tons, use the Materials Conversion Worksheet provided in your packet.
Columns B, C, D: List estimated quantities reused, recycled, or disposed.
Column E: State the name of all vendors or facilities to be used to reuse, recycle or dispose of material listed. See example below for cases where more than one facility will be used for a particular material type.
Column Totals: Add up all quantities listed in Column A. Do the same for Columns B, C and D.
Waste Reduction & Recycling Summary REPORT (WRRS Report) Material Handling Methods - Indicate quantities (in tons only) for each material listed.
Material Type
A
Total Tons
Generated
(A=B+C+D)
B
Quantity
Salvaged or
Reused
C
Recycling
D
Estimated
Disposal
E
Anticipated Material
Destination(s)
(R): Recycled; (D): Disposal
Example:
Cardboard 2 tons 1.5 .5 (R) MarBorg
(D) Tajiguas Landfill
Asphalt & Concrete
Brick/Masonry/Tile
Building Materials (doors, windows,
fixtures, etc.)
Carpet
Carpet padding/Foam
Cardboard
Ceiling tile (acoustic)
Dirt
Drywall (used)
Drywall (new, unpainted sheets or scrap)
Landscape Debris (brush, trees, stumps,
etc.)
Scrap metal
Unpainted Wood and Pallets
Garbage/Trash
Other
Recycled mixed debris
Column Totals
7. To determine if the required 65% project waste reduction will be met, complete the following with the column totals: B + C ) / A = x 100 = %
8. Is the percentage listed in #7 greater than or equal to 65%? YES NO - If “NO” please explain why:
9. Print Name: Signature: Date: __ _ _/__ __/___ _
128
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-15
ACKNOWLEDGEMENT OF FINAL CLOSEOUT AND RELEASE OF CLAIMS
THIS ACKNOWLEDEMENT OF FINAL CLOSEOUT AND RELEASE OF CLAIMS (Acknowledgement) is made in Goleta, California, this _______ day of __________, _______, by and between the City of Goleta, (Owner), and ___________________________________ (Contractor).
KNOW ALL PERSONS BY THESE PRESENTS:
1. That the undersigned, as the authorized representative of Contractor, and for each of its successors, assigns and partners, for and in consideration of __________________________________________ ($___________), for the original Contract amount, and the sum of ________________________________________ ($___________) for Contract Change Orders Nos.(1) through ______ (__), receipt of which is acknowledged, does release and forever discharge Owner, and each of its successors, assigns, council members, officers, agents, servants, volunteers and employees, from any and all rights, claims, causes of action, demands, debts, obligations, liabilities, actions, damages, costs and expenses (including but not limited to attorneys’, paralegal and experts’ fees, costs and expenses) and other claims, which may be asserted against Owner by reason of any matter or thing which was the subject matter of or basis for:
A. The performance of all terms and conditions of the Public Works Contract agreement dated ____________, for Owner project described as COMMUNITY GARDEN, SAN
JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084.
B. Change Orders Nos. one (1) through __________ (___), as approved by the parties, pertaining to Purchase Order No. _____
2. Nothing contained in this Acknowledgement shall waive or alter the rights, privileges, and powers of Owner or the duties, liabilities and obligations of Contractor and its surety(ies) in respect to any portion of the Contract.
3. Owner has received the following claims from Contractor _________________ ______________________________________________________________. Except as expressly provided in this section, Owner has received no other claims from Contractor.
4. Upon execution of this Acknowledgement, Owner agrees to promptly initiate the process for City Council to approve the Notice of Completion (NOC) and record the NOC with the Santa Barbara County Recorder.
5. Contractor and Owner agree that the total adjusted Contract Price and time of performance after the execution of change orders, is as follows:
Original Contract Price $______________________ Original Calendar Days ___________________ days Adjusted Contract Price with Change Orders $______________________ Adjusted Calendar Days ___________________ days 129
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-16
Final Contract Price Per Actual Work Completed $______________________ Final Retention Amount $______________________
6. The retention will be released to Contractor within thirty-five (35) days after acceptance of the work by the City Council and the filing of a Notice of Completion.
7. It is understood and agreed by Contractor that the facts with respect to which the release provided pursuant to this Acknowledgement is given may turn out to be other than or different from the facts as now known or believed to be, and Contractor expressly assumes the risk of the facts turning out to be different than they now appear, and agrees that the release provided pursuant to this Acknowledgement shall be, in all respects, effective and not subject to termination or rescission by any such difference in facts and Contractor expressly waives any and all rights it has or may have under California Civil Code Section 1542, which provides as follows:
"A general release does not extend to claims which the creditor does not know or suspect to exist in his favor at the time of executing the Release which if known by him must have materially affected his settlement with the debtor."
8. The release made by Contractor is not to be construed as an admission or admissions of liability and Contractor denies any such liability. Contractor agrees that it will forever refrain and forebear from commencing, instituting or prosecuting any lawsuit, action or other proceeding against Owner based on, arising out of, or in any way connected with the subject matter of this release.
9. Except as specifically provided in this Acknowledgement, the Contractor releases Owner from all claims, including but not limited to those of its Subcontractors for all delay and impact costs, if any.
10. The Contractor represents and warrants to Owner that Contractor has not assigned or transferred or purported to assign or transfer to any person, firm, corporation, association or entity any of the rights, claims, warranties, demands, debts, obligations, liabilities, actions, causes of action, damages, costs, expenses and other claims and Contractor agrees to indemnify and hold harmless Owner, its successors, assigns, council members, officers, agents, servants, volunteers and employees, from and against, without limitation, any and all rights, claims, warranties, demands, debts, obligations, liabilities, actions, causes of action, damages, costs, expenses and other claims, including but not limited to attorneys’, paralegal and experts’ fees, costs and expenses arising out of or connected with any such assignment or transfer or purported assignment or transfer.
11. The parties acknowledge that they have been represented by counsel of their own choice in connection with the preparation and execution of this Acknowledgement. The parties acknowledge and represent that they understand and voluntarily consent and agree to each and every provision contained in this Acknowledgement.
12. The persons executing this Acknowledgement represent and warrant to the other party that the execution and performance of the terms of this Acknowledgement have been duly 130
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-17
authorized by all individual, corporate, partnership, or other entity requirements and that such persons have the right, power, legal capacity and authority to execute and enter into this Acknowledgement.
13. The parties further acknowledge and represent that no promise, inducement or agreement, not expressed in this Acknowledgement, have been made and that, with respect to the matters considered, this Acknowledgement contains the entire agreement among the parties and that the terms of the Acknowledgement are contractual and not a mere recital.
CITY OF GOLETA CONTRACTOR
__________________________ _________________________
By/Title Date By/Title Date
131
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-18
Replace Section 7-3.5.2 Increases of More Than 25 Percent
Should the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 25 percent, payment for the quantity in excess of 125 percent of the Bid quantity will be made on the basis of a decrease in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or in the event mutual agreement cannot be reached, on the basis of Extra Work per 7- 4 or at the Contract Unit Price at the Agency’s option. The Extra Work per 7-4, basis of payment, shall not include fixed costs. Fixed costs will be deemed to have been recovered by the Contractor through payment for 125% of the Bid quantity at the Contract Unit Price.
Section 7-3.5.3 Decrease of More Than 25 Percent.
The Agency, at its sole discretion, may decrease the quantities of the items of work to be completed under this contract. In such an event, payment will be made based upon the decrease in quantity at the Contract Unit Price, except for Major Bid Items as described below. A Major Bid Item is defined as a single Contract item constituting 10% or more of the original Total Contract Price. In the case of a decrease in a Major Bid Item, the following will apply:
Should the actual quantity of an item of work covered by a Contract Unit Price, and constructed with the Plans and Specifications, be less than 75 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per 3-3; however in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 75 percent of the Bid quantity at the Contract Unit Price.
Section 7-3.8 Eliminated Items
Should any Contract item be deleted in its entirety, payment will be made only for actual cost incurred for that item prior to notification of such deletion.
Section 7-4.3 Makeup
Add the following:
Section 7-4.3.1 Work by Contractor. The following percentages shall be the maximum allowed to be added to the Contractor’s costs and shall constitute the maximum markup for all overhead and profits:
1) Labor 15%
2) Materials 10%
3) Equipment Rental 10%
4) Other Items and Expenditures 10%
To the sum of the costs and markups provided for in this subsection, 1 percent shall be added as compensation for bonding.
132
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-19
Section 7-4.3.2 Work by Subcontractor.
When all or any part of the extra work is performed by a Subcontractor, the markup established in Section 7-4.3.1 shall be applied to the Subcontractor’s actual cost of such work. A markup of 10 percent on the first $5,000 of the subcontracted portion of the extra work and a markup of 5 percent on work in excess of $5,000 of the subcontracted portion of the extra work may be added for the Contractor's costs and supervision.
Section 8 – No changes
Section 9– Claim Resolution Process
Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Section shall be construed to be consistent with said statutes.
For purposes of these procedures, “Claim” means a separate demand by the Contractor, after the Agency has denied Contractor’s timely and duly made request of payment in accordance with the Standard Specifications for (A) a time extension, (B) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Contract for a public work and payment of which is not otherwise entitled to, or (C) an amount the payment of which is disputed by the Agency.
The following requirements apply to all claims to which this section applies:
Section 10 – Potential Claims and Dispute Resolution
Add the following:
Section 10-1 Potential Claim
Any demand or assertion by the Contractor seeking an adjustment of Contract Price and/or Contract Time, or other relief, for any reason whatsoever, must be in strict compliance with the requirements of the Contract Documents. For purposes of this Section 10-1, any and all work relating to any such demand or assertion shall be referred to as “Disputed Work,” regardless of whether the basis of the demand or assertion arises from an interpretation of the Contract Documents, an action or inaction of the Contractor, the Engineer, or the City, or any other event, issue, or circumstance. The Contractor shall bear all costs incurred in complying with the provisions of this Section 10-1.
Promptly upon becoming aware of any event, issue, or circumstance including, but not limited to, disputes arising under the Contract, the acts or omissions of the Engineer or City or by operation of law, which the Contractor believes, in whole or in part, provides a basis for an adjustment of Contract Price and/or Contract Time. Or that Contractor’s performance is excused, or other relief, Contractor shall provide a signed written Initial Notice of Potential Claim to the 133
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-20
Engineer in a format acceptable to the City. Contractor shall provide a signed written initial notice of potential claim to the Engineer within 5 days from the date the dispute first arose and before commencing any disputed work. The initial notice of potential claim shall provide the nature and circumstances involved in the dispute which shall remain consistent through the dispute. The initial notice of potential claim shall be submitted on Form CEM 6201A available on Caltrans’ website and shall be certified with reference to the California False Claims Act, Government Code Sections 12650 12655. Assign an exclusive identification number for each dispute, determined by chronological sequencing, based on the date of the dispute.
The exclusive identification number for each dispute shall be used on the following corresponding documents:
1. Initial notice of potential claim.
2. Supplemental notice of potential claim.
3. Full and final documentation of potential claim.
4. Corresponding claim included in the Contractor's written statement of claims.
Provide the Engineer the opportunity to examine the site of work within 5 days from the date of the initial notice of potential claim. Proceed with the performance of contract work unless otherwise specified or directed by the Engineer.
Throughout the disputed work, maintain records that provide a clear distinction between the incurred direct costs of disputed work and that of undisputed work. Allow the Engineer access to your project records deemed necessary by the Engineer to evaluate the potential claim within 20 days of the date of the Engineer's written request.
Within 15 days of submitting the initial notice of potential claim, submit a signed supplemental notice of potential claim to the Engineer that provides the following information:
1. The complete nature and circumstances of the dispute which caused the potential claim.
2. The contract provisions that provide the basis of claim.
3. The estimated cost of the potential claim, including an itemized breakdown of individual costs and how the estimate was determined.
4. A time impact analysis of the project schedule that illustrates the effect on the scheduled completion date due to schedule changes or disruptions where a request for adjustment of contract time is made.
Include your complete reasoning for additional compensation or adjustments.
Submit the supplemental notice of potential claim on Form CEM 6201B furnished by the Department and certify with reference to the California False Claims Act, Government Code Sections 12650 12655. The Engineer will evaluate the information presented in the supplemental notice of potential claim and provide a written response within 20 days of receipt. If the estimated cost or effect on the scheduled completion date changes, update information in items 3 and 4 above as soon as the change is recognized and submit this information to the Engineer.
Within 30 days of the completion of work related to the potential claim, submit the full and final documentation of potential claim to the Engineer that provides the following information:
134
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-21
(1.) A detailed factual narration of events fully describing the nature and circumstances that caused the dispute, including, but not limited to, necessary dates, locations, and items of work affected by the dispute.
(2.) The specific provisions of the contract that support the potential claim and a statement of the reasons these provisions support and provide a basis for entitlement of the potential claim.
(3.) When additional monetary compensation is requested, the exact amount requested calculated in conformance with the Contract Documents including an itemized breakdown of individual costs. These costs shall be segregated into the following cost categories:
3.1. Labor – A listing of individuals, classifications, regular hours and overtime hours worked, dates worked, and other pertinent information related to the requested reimbursement of labor costs.
3.2. Materials – Invoices, purchase orders, location of materials either stored or incorporated into the work, dates materials were transported to the project or incorporated into the work, and other pertinent information related to the requested reimbursement of material costs.
3.3. Equipment – Listing of detailed description (make, model, and serial number), hours of use, dates of use, and equipment rates. Equipment rates shall be at the applicable State rental rate as listed in the Department of Transportation publication entitled "Labor Surcharge and Equipment Rental Rates," in effect when the affected work related to the dispute was performed.
3.4. Other categories as specified by the Contractor or the Engineer.
(4.) When an adjustment of contract time is requested, include the following:
4.1. The specific dates for which contract time is being requested.
4.2. The specific reasons for entitlement to a contract time adjustment.
4.3. The specific provisions of the contract that provide the basis for the requested contract time adjustment.
4.4. A detailed time impact analysis of the project schedule. The time impact analysis shall show the effect of changes or disruptions on the scheduled completion date to demonstrate entitlement to a contract time adjustment.
(5.) The identification and copies of documents and the substance of oral communications that support the potential claim.
The full and final documentation of the potential claim shall be submitted on Form CEM 6201C furnished by the Department and shall be certified with reference to the California False Claims Act, Government Code Sections 12650 12655.
Pertinent information, references, arguments, and data to support the potential claim shall be included in the full and final documentation of potential claim. Information submitted subsequent to the full and final documentation submittal will not be considered. Information required in the full and final documentation of potential claim, as listed in items 1 to 5 above, that is not applicable to the dispute may be exempted as determined by the Engineer. No full and final documentation of potential claim will be considered that does not have the same nature and 135
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-22
circumstances, and basis of claim as those specified on the initial and supplemental notices of potential claim.
If you, in conjunction with or subsequent to the assertion of a potential claim, request inspection and copying of documents or records in the possession of the City that pertain to the potential claim, you must make your records of the project, as deemed by the City to be pertinent to the potential claim, available to the City for inspection and copying."
Unless otherwise specified, the Engineer will evaluate the information presented in the full and final documentation of potential claim and provide a written response within 30 days of receipt.
The Engineer's receipt of the full and final documentation of potential claim shall be evidenced by postal receipt or the Engineer's written receipt if delivered by hand. If you submit full and final documentation of potential claim after acceptance of the work by the City, the Engineer need not provide a written response.
10-2 Dispute Resolution
All disputes and claims arising under or by virtue of this contract shall be directed to and be determined by the Public Works Director. The Director’s determination can be appealed to City Manager or their designee. The determination by the City Manager or their designee of disputes and claims shall constitute the decision of the City of Goleta; provided, however, that Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code shall apply to the public works claim of $375,000 or less.
10-3 Dispute Resolution - Claims exceeding $375,000
Any claim, dispute, or other matter in question arising out of or related to the Contract or Project exceeding three-hundred seventy-five thousand dollars ($375,000.00) that cannot be resolved between the City and the Contractor shall be resolved by the Santa Barbara County Superior Court.
10-4 Claims Procedures as a Prerequisite to Filing Suit Contractor acknowledges and agrees that its failure to submit any notice of potential claim or claim arising under this Contract in accordance with Section10, shall constitute a waiver of Contractor’s right to additional compensation and/or extension of time. Failure to follow the provisions set forth in this Contract shall constitute a waiver of Contractor’s right to receive any additional time or money as a result of any event giving rise to a claim or request for change order. Notwithstanding any other provisions in the Contract relating to any additional time or money which Contractor may be entitled to upon the occurrence of any directive or other event, or any other circumstance, Contractor must comply with the provisions of Section 10 to avoid a waiver of any such entitlement to any additional time or money. Contractor’s failure, neglect, or refusal to comply with the requirements of Section 10, or any portion thereof, shall bar Contractor’s request for additional compensation or adjustments to contract time. Such failure, neglect, or refusal prejudices the City’s and the Engineer’s ability to recognize and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for adjustment of contract time, and whether such adjustments may be warranted. Contractor hereby waives all rights to additional compensation or adjustments of contract time due to delays or accelerations 136
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-23
that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of Section 10.
Section 10-5 Government Code Claims.
Notwithstanding Contractor’s participation in dispute resolution proceedings or other claims procedures under the Contract, such proceedings are in addition to Contractor’s obligation to present a written Government Code claim in accordance with Section 900 et al of the California Government Code, which is a prerequisite to filing a lawsuit for money or damages against the City. Contractor further acknowledges that notwithstanding Contractor’s compliance with the claims procedures set forth in Section 10or in the Contract Documents, such procedures are in addition to Contractor’s obligation to comply with the claims procedures set forth in Government Code sections 900 et al prior to filing a lawsuit against the City for any such claim. Failure to submit a Government Code claim, or comply with the claims provision contained in Section 10 or in the City Special Provisions, shall bar Contractor from bringing and maintaining a valid lawsuit against the City.
Section 10-6 Participation in Dispute Resolution Proceedings.
Contractor and the City agree that all parties necessary to resolve a claim or dispute should be parties to the same dispute resolution proceeding. Contractor agrees upon request of the City to be joined in any mediation or arbitration when Contractor’s presence is required if complete relief is to be accorded and to prevent the possibility of conflicting rulings on a common issue of law or fact and otherwise to prevent the risk of the parties being subjected to inconsistent obligations or decisions.
Section 10-7 Contractor’s Continuing Obligations.
At all times during the processing of the Contractor’s potential Claim, including, but not limited to, in response to a work directive issued by the Engineer, the Contractor shall diligently proceed with the performance of the Disputed Work and other Work, unless otherwise specified or directed by the Engineer.
The Contractor shall provide the Engineer the opportunity to examine the site of the Disputed Work as soon as reasonably possible, and in no event later than five (5) days from the date of the Initial Notice of Potential Claim. Throughout the processing of the Contractor’s potential Claim, the Contractor shall provide the Engineer a reasonable opportunity to examine the site of the Disputed Work within five (5) days of the date of Engineer’s written request therefor.
The Contractor shall promptly respond to any requests for further information or documentation regarding the Contractor’s potential Claim.
Although not to be construed as proceeding with force account work, throughout the performance of the Disputed Work, the Contractor shall maintain daily records in accordance with the Contact Documents that provide a clear distinction between the incurred direct costs of Disputed Work and other Work. The Contractor shall allow the Engineer access to its project records deemed necessary by the Engineer to evaluate the potential Claim within fifteen (15) days of the date of the Engineer's written request.
All Subcontractor’s and material supplier’s claims of any type shall be brought only through Contractor pursuant to the provisions of this Section 10 and Contractor’s prior good faith review 137
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
E-24
pursuant to the Contract Documents. Under no circumstances shall any Subcontractor or material supplier make any direct claim against City.
Except where provided by law, or elsewhere in these Contract Documents, THE CITY SHALL
NOT BE LIABLE FOR SPECIAL OR CONSEQUENTIAL DAMAGES AND THE CONTRACTOR SHALL NOT INCLUDE THEM IN ITS CLAIMS. Contractor shall be limited in its recovery on any Claim(s) to the adjustments allowed in the Contract Documents.
During each step in the processing of the Contractor’s Claim, each notice shall be accompanied by the Contractor’s written statement that the adjustment or relief claimed is the entire adjustment or relief to which the claimant believes it is entitled as a result of the event, issue, or circumstance giving rise to the Claim.
Under no circumstances may the Contractor submit an Initial Notice of Potential Claim, Supplemental Notice of Potential Claim, or Notice of Final Claim after the date of final payment.
Section 10-8 Notice of Third-Party Claims.
The City shall provide Contractor with prompt written notice of the receipt of any third-party claim relating to the Contract in accordance with Public Contract Code section 9201 by sending a copy of the third-party claim to Contractor at the address indicated in the Agreement via first class.
138
COMMUNITY GARDEN, SAN JOSE CREEK MULTI-PURPOSE PATH, AND ARMITOS PARK IMPROVEMENTS PROJECT NOS. 9007 AND 9084
F-80
This Page Intentionally Left Blank
139
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-1
Technical Specifications
Armitos Park Improvements, Community Garden
& San Jose Creek Multi-Purpose Path
For use with Greenbook Standard Specifications and Standard Plans 2018 Edition (including applicable amendments)
Prepared by:
RRM Design Group
3765 South Higuera, Suite 102
San Luis Obispo, CA 93401
140
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-2
This page intentionally left blank.
141
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-3
SPECIFICATIONS
ARMITOS PARK IMPROVEMENTS & COMMUNITY GARDEN - TABLE OF CONTENTS ARMITOS COMMUNITY GARDEN TECHNICAL SPECIFICATIONS ..................................................... 4 PART 2 – CONSTRUCTION MATERIALS ............................................................................................................... 4 SECTION 200 – ROCK MATERIALS ................................................................................................................... 4 SECTION 201 – CONCRETE, MORTAR, AND RELATED MATERIALS ................................................................. 6 SECTION 203 – paving asphalt AND RELATED MATERIALS .......................................................................... 10 SECTION 204 – wood fence and Wood Rail .................................................................................................. 10 SECTION 206 – MISCELLANEOUS METAL ITEMS ........................................................................................... 11 SECTION 207 – STORM DRAIN PIPE .............................................................................................................. 13 SECTION 210 – PAINT AND PROTECTIVE COATINGS..................................................................................... 14 SECTION 211 – MATERIAL TESTS .................................................................................................................. 15 SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT MARKERS .......... 15 SECTION 218 – PLAYGROUND SURFACING ................................................................................................... 18 SECTION 219 – PLAYGROUND EQUIPMENT ................................................................................................ 21 SECTION 220 - SITE FURNISHINGS ................................................................................................................ 23 SECTION 221 - PRE-FABRICATED STRUCTURES ............................................................................................ 24 PART 3 – CONSTRUCTION METHODS
............................................................................................................... 36 SECTION 300 - EARTHWORK ......................................................................................................................... 36 SECTION 301 – TREATED SOIL, SUBGRADE PREPARATION AND PLACEMENT OF BASE MATERIALS ............ 42 SECTION 303 – CONCRETE AND MASONRY CONSTRUCTION ....................................................................... 43 SECTION 304 – METAL FABRICATION AND CONSTRUCTION ........................................................................ 48 SECTION 315 – STORM DRAIN ...................................................................................................................... 51 SECTION 316 – PLAYGROUND SURFACING INSTALLATION .......................................................................... 52 SECTION 317 – PLAYGROUND EQUIPMENT INSTALLATION ......................................................................... 54 PART 4 – EXISTING IMPROVEMENTS
................................................................................................................ 56 SECTION 400 – PROTECTION AND RESTORATION ........................................................................................ 56 SECTION 401 – REMOVAL ............................................................................................................................. 57 PART 8 – LANDSCAPE AND IRRIGATION ........................................................................................................... 57 SECTION 800 – LANDSCAPE AND IRRIGATION MATERIALS .......................................................................... 57 SECTION 801 – LANDSCAPE AND IRRIGATION INSTALLATION ..................................................................... 64 SECTION 901 – LOW WATER CROSSING ....................................................................................................... 80 SECTION 902 – REMOVABLE BOLLARD ......................................................................................................... 80 SECTION 903 – SLOPE PROTECTION ............................................................................................................. 81 SECTION 904 – BARRICADES ......................................................................................................................... 84 SECTION 905 – ROADSIDE SIGNS .................................................................................................................. 84
142
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-4
ARMITOS COMMUNITY GARDEN TECHNICAL SPECIFICATIONS
PART 2 – CONSTRUCTION MATERIALS
SECTION 200 – ROCK MATERIALS
200-1 ROCK MATERIALS.
200-1.1 General. ADD the following:
Aggregate base material for all asphaltic concrete and concrete paving shall be as per the project soils report prepared for the park formally known as Hollister Kellogg Community Park (Jonny D.
Wallis Neighborhood Park), prepared by Earth Systems and all updates and addenda to that report.
The soils report is available for review by potential bidders on Planet Bid.
200-2 UNTREATED BASE MATERIALS.
200-2.2 Class II Crushed Aggregate. The base material shall be Class II Crushed Aggregate Base that conforms to Section 200-2.2 of the Standard Specifications. 143
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-5
ADD: 200-2.3 Class 2 Permeable. (Bio-infiltration areas) Gravel layer. “Class 2 permeable” shall conform to Caltrans 2018 specification 68-2.02(F)(3). Drain rock or other granular material may be used; however a layer of pea gravel or other intermediate- sized material should cover the top of the drain rock to reduce movement of fines from the soil layer into the interstices of the drain rock. Do not use filter fabric for this purpose.
Soil mix. Provide a mixture of 60%-70% washed sand (ASTM C33) and 30%-40% compost.
ADD: 200-3 CRUSHED DRAIN ROCK
200-3.1 General.
Crushed rock shall consist of 3/4 inch to 2” crushed washed rock, uniformly graded. Free of clay, shale, and organic matter.
ADD: 200-6 STABILIZED DECOMPOSED GRANITE SURFACING
200-6.1 General. Contractor shall comply with the requirements below:
200-6.1.1 References.
a. “Greenbook” Standard Specifications for Public Works Construction (2018 edition). b. CalTrans 301 – Resistance "R" Value of Treated and Untreated Bases, Subbases and Basement Soils (Stabilometer).
c. ASTM C136 – Sieve Analysis of Fine and Coarse Aggregates. d. ASTM D2419 – Sand Equivalent Value of Soils and Fine Aggregates. e. ASTM D2488 – Description and Identification of Soils (Visual-Manual Procedure).
200-6.1.3 Submittals. In accordance with the submittal requirements in the Contract Documents, Contractor shall submit to the Engineer the following:
144
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-6
a. Manufacturer’s product data sheet and installation instructions indicating that product complies with specifications for wax-coated decomposed granite surfacing.
200-6.2 Products.
200-6.2.2 Materials.
a. Decomposed Granite:
1. Produce from naturally friable granite. Blends of coarse sand and rock dust are not acceptable.
2. Gradation, in accordance with ASTM C136:
Sieve Size Percent Passing
3/8” 100
No. 4 90-100
No. 8 75-80
No. 16 55-65
No. 30 40-50
No. 50 25-35
No. 100 15-20
No. 200 10-15
b. Sand Equivalent shall be 30 minimum in accordance with ASTM D2419. c. Color: Refer to LC001 of the plans
e. Base Course Materials shall comply with Greenbook Section 200-2 – “Untreated Base Materials” for crushed aggregate base.
200-6.2.3 Stabilizer. Gorilla Snot by Soilworks, or approved equal.
SECTION 201 – CONCRETE, MORTAR, AND RELATED MATERIALS
201-1 PORTLAND CONCRETE
201-1.1 Requirements.
201-1.1.1 General. ADD the following:
The cement utilized shall conform to the Geotech report referenced in 200-1.1. The Contractor shall submit to the Engineer a copy of the mix design to be used in accordance with the procedures for submittals in these Specifications. Portland Cement Concrete delivered to the project site having a water content and/or slump greater than that specified in the mix design shall be rejected and removed from the project site.
Contractor shall use forms for all concrete work. Forms shall be designed according to ACE 347 and shall be made from plywood in good condition, metal, or smooth-paned boards free from large knots and shall be treated with a form release agent. The form release agent shall effectively prevent absorption of moisture and prevent bonding with the concrete. Agent shall be non-staining and non- toxic after 30 days.
145
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-7
201-1.1.2 Concrete Specified by Class and Alternate Class. REPLACE the second and third paragraphs with the following:
Concrete shall be specified by class as per Section 201-1.1.2 of the Standard Specifications with a 4- inch slump.
The class of concrete shall be 520-C-2500 for all concrete not otherwise specified on the Plans, with a maximum slump of four inches (4") for all concrete flatwork, curb, gutter, walks, aprons, footings (except building or wall footings), foundations (except building foundations), sidewalks, access ramps, curbs and gutters, and cross gutters, mow curbs, columns, thrust blocks, terraced concrete seating, monument signs, and other improvements.
201-1.1.5 Test for Portland Cement Concrete. ADD the following:
a. All material shall comply with the latest editions of the American Concrete Institute (ACI) and Uniform Building Code. Testing of Portland cement concrete shall apply to all site concrete including but not limited to: concrete paving, walls, footing, etc.
b. Product Data:
1. Submit complete materials list of items proposed for the work for City review and approval in accordance with Section 2-5.3, Submittals. Identify material source.
2. Submit admixture, curing compound, retarder, and accessory item product data.
3. Submit material certificates for aggregates, reinforcing, and join fillers.
c. Submit concrete test reports.
d. City will provide field quality control testing and inspection during concrete operations.
e. Strength Verification: Contractor shall submit mix design to the Engineer in conformance with the procedures for Submittals in these Specifications.
f. Concrete quality testing may be performed on the concrete by the City’s representative as follows:
1. Frequency of Sampling: Cast four concrete test cylinders from each 50 cubic yards, or a fraction thereof, of each class of concrete placed in any one day.
Sampling and curing of cylinders shall conform to ASTM C 31.
2. Strength Testing: Test cylinders in accordance with ASTM C 39. Test one cylinder at 7 days for information, two cylinders at 28 days for acceptance and hold one cylinder for verification. When samples are taken from same concrete delivery, strength acceptance will be based on the average strengths of the two cylinders for verification. Strength acceptance will be based on the average of the strengths of the two cylinders tested at 28 days.
If one cylinder of 28-day test manifests evidence of improper sampling, molding or testing other than low strength, discard it and use the fourth cylinder for the test result.
146
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-8
3. Determine concrete slump by ASTM C 143 with each strength test sampling and as required to establish consistency.
4. Determine air content of the concrete using ASTM C 231 to verify the percentage of air in the concrete immediately prior to depositing in forms.
5. If the 28-day strength tests fail to meet the specified minimum compressive strength, the concrete will be assumed to be defective and one set of three cores from each area may be taken as selected by the City’s representative and in accordance with ASTM C 42. All tests for compressive strength must pass. The City may require additional coring, nondestructive load testing or repair of defective concrete. Costs of coring, testing of cores, load testing and required repairing pertaining thereto, shall be paid by the Contractor at no extra cost to the City.
g. To facilitate concrete sampling and testing, the Contractor shall:
1. Furnish labor to assist the City’s representative in obtaining and handling samples at the project site.
2. Advise the City’s representative 48 hours in advance of concrete placing operations to allow for scheduling and completion of quality testing.
3. Provide and maintain facilities for safe storage and proper curing of concrete test specimens on the project site, as required by ASTM C 31.
201-1.2 Materials.
201-1.2.4 Chemical Admixtures. ADD the following to item (a):
Concrete shall contain a water-reducing admixture, which shall conform to ASTM C494 , Types A or D, except that it shall contain no chlorides, shall be nontoxic after 30 days, and shall be compatible with the air-entraining admixture. The amount of admixture added to the concrete shall be in accordance with the manufacturer’s written recommendations. Admixtures shall be Master Builders Pozzolith polymer-type normal setting, Plastocrete (Sikamix 160) Normal Set, Sike Chemical Corporation, or equal. Admixtures shall not contain chlorides or other corrosive elements in any concrete.
REPLACE item (d) with the following:
Air-Entraining Admixtures. Concrete shall contain an air-entraining admixture which shall conform to ASTM C260, except it shall be nontoxic after 30 days and shall contain no chlorides. Admixtures shall be Master Builders MB-AE-10, Sike AER (Sikamix 104) or equal. Concrete air-entraining mixtures shall be sampled and tested in accordance with 201-1.1.5. The air content at the point of discharge shall be within a tolerance of 1.5 percent of the value specified in ASTM C94. Air content shall be 5% to 7%.
201-1.4 Mixing.
201-1.4.3 Transit Mixers. REPLACE the seventh (7
th) paragraph with the following:
Submit concrete delivery tickets to the City Inspector. Show the following:
147
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-9
a. Name of Vendor
b. Name of Contractor
c. Work Location
d. Batch number, date, and time (must be machine stamped) e. Number of cubic yards in the load
f. Mix by class with maximum size aggregate
g. Amount of water added at the plant
h. Maximum allowable water
i. Brand and type of cement
j. Actual weights of cementitious materials and of each size of aggregate k. Brand, type, and amount of admixture
l. Air content
m. Slump
n. Time of loading
201-2 REINFORCEMENT FOR CONCRETE
201-2.2.1 Reinforcing Steel. ADD the following:
Reinforcing steel shall be Grade 40 (300) conforming to ASTM A615-A615M
201-3 EXPANSION JOINT FILLER AND JOINT SEALANTS.
201-3.2 Premolded Joint Filler. ADD the following:
Expansion joint filler material shall be Deck-O-Foam by W.R. Meadows Corporation OAE, ¼” in dimension or approved equal. Joint filler shall be installed as per manufacturer’s recommendations.
Joint sealant shall be SikaFlex or approved equal. Color as approved from standard list.
ADD: 201-6.8 Graffiti-Resistant Coating.
Graffiti coating: Provide anti-graffiti coating on all exposed proposed vertical surfaces including the following:
• Exposed fence concrete curbing
• Outdoor kitchen counter
• c
a. Graffiti-Resistant Coating:
1. All vertical concrete shall be sealed with Vandlgard 10, by Rainguard International, phone (619) 590-2001, OAE or approved equal.
2. Composition: water-based; VOC-compliant graffiti-resistant coating
3. Finish/Color: Low sheen finish, clear in color
201-6.8.1 – Payment
Cost for graffiti-resistant coating shall be included in the bid item for Concrete Curbing at Fencing, and no additional compensation shall be made therefor.
148
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-10
SECTION 203 – PAVING ASPHALT AND RELATED MATERIALS
SECTION 203-15 – POROUS ASPHALT CONCRETE
203-15.1 GENERAL
A. Section includes:
1. Construction of porous asphalt concrete as shown on the plans.
2. Material, aggregate, gradation and mixing specifications per Greenbook.
3. All other requirements per Greenbook.
4. As approved by the Engineer
B. Greenbook Related Sections:
1. Section 203 – Bituminous Materials
2. Section 203-15 Porous Asphalt Concrete
3. Section 211 – Material Testing
4. Section 300 – Earthwork
5. Section 301–Treated Soil, Subgrade Preparation and Placement of Base
SECTION 203-16 – CRUSHED ROCK
203-16 GENERAL
A. Section includes:
1. Construction of Crushed Rock as shown on the plans.
2. Material, screenings and gradation specifications per Greenbook.
3. All other requirements per Greenbook.
4. As approved by the Engineer.
B. Greenbook Related Sections:
1. Section 200 – Rock Materials
2. Section 200 -1.2Crushed Rock and Rock Dust Section 211 – Material Testing
3. Section 300 – Earthwork
4. Section 301–Treated Soil, Subgrade Preparation and Placement of Base Material
SECTION 204 – WOOD FENCE AND WOOD RAIL
204-1 GENERAL
A. Section includes:
1. Construction of 42”H Wood Rail fence.
2. Provide all labor, all materials (i.e., pickets, rails, posts, and hardware) required for installation of the wood fencing specified herein and as indicated on the Drawings. 149
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-11
3. Concrete footing.
B. REFERENCES
1. Greenbook Related Sections:
Section 201 – Concrete Mortar and Related Materials Section 206 – Miscellaneous Metal Items
Section 204 – Lumber and Treatment with Preservatives
2. SFPA/SPC Form #400 – Permanent Wood Foundation Guide to Design and Construction; Southern Forest Products Association/Southern Pine Council; 1998
3. AWPA C2–96 – Lumber, Timbers, Bridge Ties, Mine Ties---Preservative Treatment by Pressure Processes; American Wood Preservers’ Association; 1996
4. ACQ-94 – Preserve Quality Control Standard for all products treated with ACQ; 1994
C. QUALITY ASSURANCE
1. Qualifications: Provide laborers and supervisors who are thoroughly familiar with the type of construction involved and the materials and techniques specified.
D. SUBMITALS
1. Shop Drawings showing general fabrication of Wood Rail fencing.
E. DELIVERY, STORAGE AND HANDLING
1. Upon receipt at the job site, all materials shall be checked to ensure that no damages occurred during shipping or handling.
2. Materials shall be stored in such a manner to ensure proper ventilation and drainage, and to protect against damage, weather, vandalism and theft.
F. PAYMENT
Payment for wood fence or wood rail will be made at the contract price per linear foot and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing fence, complete in place, and no additional compensation will be made.
SECTION 206 – MISCELLANEOUS METAL ITEMS
206-6 CHAIN LINK FENCE
206-6.1 General. REPLACE the third sentence with the following: Class 1 or Class 1A materials shall additionally be clad coated with PVC, color Black as approved, in accordance with 210-5. All fencing attachments, posts, rails, and incidental materials shall be vinyl coated.
206-6.2 Materials for Posts, Rails and Braces. REPLACE the first sentence with the following:
Materials for posts, rails, and braces shall conform to Table 206-6.2 unless otherwise noted on plans.
206-6.3 Chain Link Fabric. REVISE the first sentence with the following: Chainlink Fabric shall conform to 206-6.3.2 (PVC Coated Fabric).
150
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-12
206-6.3.2 Polyvinyl Chloride (PVC) Coated Fabric. REVISE the first sentence of the second paragraph to read as follows: All chain link fabric shall be woven into approximately 1-inch (25 mm) mesh.
ADD: 206-7 PERIMETER WIRE MESH METAL SECURITY FENCING
206-7.1 Work Included
A. Wire mesh fencing and gates.
B. All hardware, attachments, and accessories as required to provide a complete installation.
C. Coordination of gate and fencing systems with adjacent site elements, landscaping, and curbs.
206-7.2 Quality Assurance
A. Manufacturer – As approved by the City. Manufacturer shall have a minimum of ten years in the practice of manufacturing this type of fence product.
B. Installer – Work to be performed only by workers thoroughly skilled and specially trained in the techniques of the manufacturer, and who are completely familiar with the published recommendations of the manufacturer and have at least three (3) years of experience installing the selected system. Installer to be approved by the manufacturer. 206-7.3 Submittals
A. Product Data – Submit material specifications and manufacturer’s installation instructions B. Shop Drawings to include:
1. Layout of fences and gates showing all dimensions, sizes, thickness, gauges, finishes, joining, attachments, gate operator and attachments, gate loops, and relationships to adjacent work.
2. Manufacturer's recommended post foundations details.
3. Gate hardware (including hinges, latches, drop bar for inactive leaf, card reader system, details, etc.).
C. Maintenance Data: Indicate lubrication requirements and frequency and periodic adjustments required.
206-7.4 Product Handling
A. Protection
1. Materials to be stored at the job site in a safe, dry place with all labels intact and legible at time of installation.
2. Use all means to protect materials before, during, and after installation. Do not allow products to become wet or damp.
B. Replacements: In the event of damage, including water intrusion, immediately make all repairs and replacements necessary to the approval of the Architect and at no additional cost to the Owner.
206-7.5 Warranty
A. Provide manufacturer’s standard limited warranty of 15 years from date of installation.
206-7.6 Materials
A. Decorative Welded Wire Mesh Fencing and Gates
151
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-13
1. Manufacturer: ClearVu Fencing or approved equal
a. Contact: Ryan Kalin – West Coast USA Regional Manager – 1-213-705-6022 [email protected]
2. Height: 6'-0”, or as shown on Drawings.
3. Gate Hardware - Single
a. Hardware listed below available through Allegion - David Harder or approved equal. 626-390-1354
b. Hinge & Gate Closer: Locinox Mammoth-180 (Color – Black) c. Panic Hardware: Von Dupron – LD-AX-98-EO-WH
d. Electronic Exit Device Trim – Schlage - AD-200-993R-70-KP-TLR-J 4AA BATTERY
e. FSIC Core: Schlage – 23-030
f. FSIC Core: Schlage – 23-030 ICX
g. Weld-in Lock Box: Keedex - K-BXED-V990NL-2
h. Floor Stop: Ives – FS18L/FS18S
i. Software: Schlage - SXPR-SFT-1
j. Software training: SCE – SCH-EXP-INST
k. Accessories: SCE – SUS-A-Cable-47282796
l. Kick Plates: Ives – 8400 series 12”Hx1”LDW-B-CS
4. Gate Hardware - Double
a. Hardware listed below available through Allegion - David Harder or approved equal. 626-390-1354
b. Hinge & Gate Closer: Locinox Mammoth-180 (Color – Black) c. Mullion: removable per plans
d. Panic Hardware: Von Dupron – LD-AX-98-EO-WH
one per each gate leaf
e. Electronic Exit Device Trim – Schlage - AD-200-993R-70-KP-SPA-J 4AA BATTERY
f. FSIC Core: Schlage – 23-030
g. FSIC Core: Schlage – 23-030 ICX
h. Weld-in Lock Box: Keedex – K-BXED-V990NL-2
i. Floor Stop: Ives – FS18L/FS18S
j. Software: Schlage - SXPR-SFT-1
k. Software training: SCE – SCH-EXP-INST
l. Accessories: SCE – SUS-A-Cable-47282796
m. Kick Plates: Ives – 8400 series 12”Hx1”LDW-B-CS
SECTION 207 – STORM DRAIN PIPE
207-17.6 Installation.
152
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-14
ADD: 207-17.6.1 Pipe Bedding. Pipe bedding shall conform to SDRSD D-60, SP-2, and/ or WAS WP-02 as required for the type of installation.
ADD: 207-17.6.2 Imported Trench Backfill. Imported trench backfill shall be required when native trench material has a moisture content greater than 4% above the optimum moisture content as measured in accordance with ASTM 1557, or does not meet the gradation requirements for imported trench backfill given below.
Imported trench backfill shall include material one foot above the pipe up to the existing pavement structural section.
All imported trench backfill material shall be a quarry waste or similar material with 100% passing a 3” screen, no more than 15% passing a #200 sieve and a sand equivalent of 20 minimum using California Test Method No. 217.
Measurement and payment for imported trench backfill shall be considered to be included in the bid item of work for which backfilling of trenches was required, and shall include full compensation for furnishing all labor, materials, tools, equipment, transportation, and incidentals for imported trench backfill in accordance with the Contract Document. No adjustment price will be made for any increase or decrease in the quantity of imported backfill used, regardless of the reason for such increase or decrease.
207-19 POLYETHYLENE (PE) SOLID WALL PIPE.
207-19.1 General. ADD the following:
Payment for HDPE pipe shall be in accordance with Section 306-1.6 of the Standard Specifications and additionally shall include fittings, temporary resurfacing, and shall include furnishing all materials, labor, tools, equipment, transportation, and other incidentals necessary to satisfactorily complete the Work.
ADD: 207-19.6 Installation. Pipe bedding shall conform to the more stringent of SDRSD D- 60, 306-1.2.1 of the Standard Specifications, and the pipe manufacturer’s recommendations.
SECTION 210 – PAINT AND PROTECTIVE COATINGS
210-1.1 General. ADD the following:
Contractor shall furnish equipment, processes, and a materials list indicating the painting and priming materials to be used in accordance with 2-5.3, Submittals.
210-6 Paint Schedule Add the following:
The following is a schedule for painting
Durable Greenbeds – Touch up Stain and paint materials to match manufacturer’s coatings. 153
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-15
Fencing Panels – Provide Manufacturer’s approved touch up paint for repair of blemishes, scratches and other damage to finish
Site Furnishings & Play Equipment – Provide manufacturer’s color touch up paint coatings for minor finish repair.
Prefabricated Trellis Structures – Structures shall be powder coated per manufacturer’s standard coatings. Contractor shall provide manufacturer’s approved field touch up materials.
SECTION 211 – MATERIAL TESTS
ADD 211-0 Reuse of Onsite Materials. Suitable excavated materials removed to accommodate new construction may be used as fill material subject to Soils Engineer’s inspection and approval.
211-1 Compaction Tests.
211-1.2 Field Density. ADD the following:
Field density tests will be made by the City’s Soils Engineer during the course of construction at the expense of the City. If field density tests indicate that any portion of the compacted subgrade has density lower than that specified, the Contractor shall rework that portion until the specified density is obtained, at Contractor’s sole expense.
Retest of areas which have failed compaction will be performed by the City’s Soils Engineer at the Contractor’s expense. All fill material and subgrade compaction shall be as noted in Project Soils Report by Earth Systems and all associated updates and addenda.
Pathway bioswales and vegetated areas receiving runoff from hardscape areas shall not be compacted in excess of 50% to allow proper infiltration and cleansing of the storm water. Soils with compaction rates in excess of 50% shall be scarified on top 12”.
SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT MARKERS
214-1 GENERAL
A. Related Documents:
1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
B. Section Includes:
1. Traffic paint on pavement surfaces, in traffic lanes, parking bays, areas restricted to handicapped persons, crosswalks, and other detail pavement markings.
C. Greenbook Related Sections:
1. Section 214 – Traffic Striping, Curb and Pavement Markings, and Pavement Markers
2. Section 314 – Traffic Striping, Curb and Pavement Markings, and Pavement Markers
D. Quality Assurance:
1. Use only materials, which are manufactured, exclusively for the purpose of pavement marking and painting.
154
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-16
2. Details not shown shall be in conformance with the State Standards for Traffic Control Devices for Streets and Highways, and similar requirements established by the U.S.
Department of Transportation, Federal Highway Administration.
E. Regulatory Requirements:
1. All products shall comply with the applicable requirements of the California Green Building Standards Code (CALGreen), South Coast Air Quality Management District (SCAQMD) Air Pollution Control Agency and other Authorities Having Jurisdiction.
F. Conformance Submittals:
1. Conformance Submittals will be allowed for products described in this section, and will not require Architect’s approval before incorporating the material into the work. a. Substitute Products: Where products are proposed for use, but are not as specified, approval of a substitute product is required.
i. Product Data: Manufacturer's literature, data sheets, and installation instructions.
ii. Material Certificates: From manufacturer, certifying that the following materials conform to the requirements specified.
G. Closeout Submittals:
1. Maintenance Data
H. References:
1. American Association of State Highway and Transportation Officials (AASHTO) a. AASHTO M 248-91: Specification for Ready-Mixed White, Blue, and Yellow Traffic Paints
2. Federal Specifications:
a. TT-P-110C: Paint, Traffic, Black (Non-reflectorized) b. TT-P-115F: Paint, Traffic, Highway, White, Blue, and Yellow
214-2 PAYMENT
A. Payment for striping will be made at the contract price per linear foot for the various striping details, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing striping, complete in place, and no additional compensation will be made.
214-3 MATERIALS
A. Refer to the latest edition of the Greenbook for material specifications in section 214.
B. Equipment:
1. Apply all markings using approved mechanical equipment (with provisions for constant agitation of paint), capable of applying the marking widths as shown.
2. Use pneumatic spray guns for hand application of paint.
3. All painting equipment and operations shall be under the control of experienced technicians thoroughly familiar with equipment and materials and marking layouts.
214-4 EXECUTION
155
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-17
A. Surface Preparation:
1. Clean all surfaces thoroughly before painting.
a. Remove dust, dirt, and other granular surface deposits by sweeping, blowing with compressed air, rinsing with water or using a combination of these methods as required.
b. Remove existing paint, rubber deposits, curing and/or sealer membrane, and other materials adhered to the pavement by using high temperature pressure washer, scrapers, wire brushings, sandblasting, approved chemicals, or mechanical abrasion.
c. Allow pavement surface to thorough dry and be free of moisture to ensure proper bonding of paint to pavement surface.
d. If previously applied paint markings remain after cleaning described above, cover with black paint suitable for vehicle traffic surfaces. Apply as many coats as needed to completely cover the existing markings.
2. Where oil or grease are present on old pavements to be marked, scrub affected areas with several applications of trisodium phosphate solution or other approved detergent or degreaser, and rinse thoroughly after each application. After cleaning, seal oil-soaked areas with cut shellac to prevent bleeding through the new paint.
3. Contractor shall establish control points for marking and provide templates to control paint application by type and color, at necessary intervals. It shall be the Contractor's responsibility to preserve, and apply marking in conformance with, the control points so established.
B. Application:
1. Apply markings to the color, length and widths indicated on Drawings or as needed to match and recover the existing applications.
a. Produce true, sharp edges and ends. The length and width of lines shall conform within a tolerance of plus or minus three inches and plus or minus 1/8-inch, respectively, in the case of skip markings, the length of intervals shall not exceed the line length tolerance.
b. Temperature of the surface to be painted and the atmosphere shall be above 50 degrees F (10 deg C) and less than 95 degrees F (35 deg C). c. Apply two coats of paint at a wet film thickness of 15 mils each coat, with proper curing time between each coat.
2. The maximum drying time requirements of the paint specifications will be strictly enforced, to prevent undue softening of asphalt, and pick-up, displacement or discoloration by tires of traffic.
a. If marking paint is applied to a newly paved surface less than 30 days after completion of paving installation, then the following shall apply:
i. The first coat of paint shall be applied at 50 percent of the specified 15 mils wet film thickness, or approximately 7.5 mils.
ii. The second coat of paint shall be applied no sooner than 30 days following completion of paving.
1) The thickness of the second coat of paint shall be increased from the specified 15 mils to 22.5 mils wet film thickness, to account for the reduced first coat.
iii. The minimum total wet film thickness of the two coats of marking paint shall be 30 mils.
156
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-18
b. If there is a deficiency in drying of the marking, paint operations shall be discontinued until cause of the slow drying is determined and corrected.
3. Marking applied at less than minimum material rates; deviating from true alignment; exceeding stipulated length and width tolerances; and showing light spots, smears, or other deficiencies or irregularities shall be removed and replaced. a. Removal methods shall be by carefully controlled sand blasting, approved grinding equipment or other approved method in such a manner that the surface to which the marking was applied will not be damaged.
C. Protection:
1. Conduct operations in such a manner that newly painted markings are protected.
2. Place warning signs at entrances to alert approaching traffic. a. For the benefit of the Contractor small flags or other similarly effective small objects may be placed near freshly applied markings at frequent intervals to reduce crossing by traffic.
3. Damaged portions of markings shall be effaced and replaced by the Contractor at no additional cost to the Owner.
D. Detail Pavement Marking:
1. Detail Pavement Markings shall be that marking, exclusive of actual traffic lane marking, at exit and entrance islands and turnouts, on curbs, at crosswalks, at parking bays and at such other locations as shown.
a. Handicapped parking spaces shall be marked by the International Handicapped Symbol at indicated parking spaces.
b. Use a suitable template that will provide a pavement marking with true, sharp edges and ends.
E. Final Clean-Up:
1. Remove all debris, rubbish and excess material from the site.
SECTION 218 – PLAYGROUND SURFACING
218-1.1 SECTION INCLUDES
A. Protective surfacing for playground area:
1. Poured-in-Place Rubber at existing Play Equipment
2. Poured-in-Place Rubber at new play equipment if bid alternate is selected B. Subbase under resilient surfacing.
218-1.2 RELATED REQUIREMENTS
A. Section 300 – Earthwork
B. Section 301 – Treated Soil, Subgrade Preparation and Placement of Base Material C. Section 219 – Playground Equipment
218-1.3 REFERENCE STANDARDS
A. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN m/m3)); 2012. 157
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-19
B. ASTM D2047 - Standard Test Method for Static Coefficient of Friction of Polish-Coated Floor Surfaces as Measured by the James Machine; 2011.
C. ASTM F1292 - Standard Specification for Impact Attenuation of Surface Systems Under and Around Playground Equipment; 2009.
D. ASTM F1487 - Standard Consumer Safety Performance Specification for Playground Equipment for Public Use; 2011.
E. CPSC Pub. No. 325 - Public Playground Safety Handbook; 2010. 218-1.4 DEFINITIONS
A. Use Zone: The area beneath and immediately adjacent to a play structure or equipment (play event) that is designated for unrestricted circulation around equipment, and on whose surface it is predicted that a user would land when falling from or exiting the equipment.
B. Critical Fall Height: The maximum fall height at which the protective surfacing meets the requirements of ASTM F1292.
C. Fall Height: The vertical distance between the finished elevation of the designated play surface and the finished elevation of the protective surfacing beneath it as defined by ASTM F1487.
D. Protective Surfacing: Resilient ground surfacing. The characteristics of the protective surfacing are based on the fall height of the playground equipment. Changes in either the surfacing or the fall height, particularly reducing the resilience of the protective surfacing or increasing the fall height, will reduce safety-related performance.
E. Subbase: A layer under the resilient layer of the protective surfacing but over the subgrade; may be rigid, as in concrete or bituminous, or aggregate.
F. Subgrade: The surface of the ground on which the protective surfacing is installed. 218-1.5 SUBMITTALS
A. Product Data: For all manufactured surfacing products, provide manufacturer's product data showing materials of construction, compliance with specified standards, installation procedures, and safety limitations.
1. Include IPEMA certifications where required.
B. Product Data: For natural surfacing materials, provide supplier's certification or mill certificate showing compliance with specified requirements.
C. Samples: For each product for which color must be selected provide color chart showing full range of colors.
1. Rubber, colored wearing course: actual material samples of manufacturer's full color range.
218-1.6 QUALITY ASSURANCE
A. Maintain one copy of the latest edition of ASTM F1487 and CPSC Pub. No. 325 at project site.
B. Installer Qualifications: Company certified by manufacturer for training and experience installing the protective surfacing; provide installer's company name and address, and training and experience certificate.
C. IPEMA Certification – Provide City with copy of current certificates of International Play Equipment Manufacturers Association (IPEMA) installers
158
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-20
218-1.7 PRE-INSTALLATION MEETING
A. Convene a meeting one week before starting earthwork for playground to discuss coordination between various installers.
1. Require attendance by personnel responsible for grading and installers of playground equipment, protective surfacing, footings, and adjacent work.
2. Include representatives of Contractor.
3. Notify Landscape Architect at least 2 weeks prior to meeting. 218-1.8 DELIVERY, STORAGE, AND HANDLING
A. Deliver, handle, and store protective surfacing to project site in accordance with manufacturer's recommendations.
B. Store materials in a dry, covered area, elevated above grade. 218-1.9 WARRANTY
A. Provide minimum 5 year manufacturer’s warranty for playground surfacing.
218-2.1 DESIGN CRITERIA
A. Because the safety of the playground depends on strict conformance to the design criteria, this information is provided for Contractor's information.
1. The protective surfacing constitutes a resilient layer installed over a non-resilient layer, which is installed over the subgrade, with the top of playground equipment footings and anchorage devices covered by full depth of the resilient portion of the protective surfacing.
2. The top elevation of the protective surfacing is intended to be flush with adjacent grades.
3. Use Zone: The protective surfacing has been designed to provide acceptable impact attenuation as defined in ASTM F1292. As critical fall heights can change by the manufacturer, the contractor shall provide confirmation of applicable fall heights as part of the product submittal for approval.
218-2.2 MATERIALS
A. Manufacturer
1. Submit from the following pre-approved list
a. Spectraturf
b. Play and Park
c. Approved Equal
B. Poured-In-Place Membrane Surfacing: Weather-resistant wear layer over impact attenuating substrate over aggregate subbase.
1. Wear Layer: Thermal Plastic Vulcanized (TPV) granules with an aliphatic binder formulated to produce an even, uniform, seamless surface.
2. Wear Layer Thickness: 1/2 inch, minimum.
3. Coefficient of Friction, when wet: 0.8, minimum, when tested in accordance with ASTM D2047.
4. Wear Layer Color(s): As selected from manufacturer's full range of bright colors. a. Color #1: blend of two (2) TPV colors. 100% color. No black b. Color #2 (Play Equipment Dismount zones ): Supreme color TPV or approved equal. 100% color, no black
159
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-21
5. Impact Attenuating Substrate: 100 percent recycled shredded styrene butadiene rubber (SBR) shreds or granules with 100 percent solids polyurethane binder to form a resilient material; do not use foam rubber.
6. Resilient Depth: As required to achieve specified Critical Fall Height as defined in ASTM F1292 but not more than depth indicated; maintain top elevation flush with adjacent grades.
7. Certification: Provide IPEMA certification of ASTM F1292 Critical Fall Height at thickness specified.
8. Product – Refer to plan sheet LC001
C. Geotextile Fabric: Nonwoven polypropylene sheet.
SECTION 219 – PLAYGROUND EQUIPMENT
219-1.1 SECTION INCLUDES
A. Playground layout (staking).
B. Playground equipment.
219-1.2 RELATED REQUIREMENTS
A. Section 300 – Earthwork
B. Section 303 – Concrete and Masonry Construction
C. Section 218 – Playground Surfacing
219-1.3 DEFINITIONS
A. Play Event: A piece of playground equipment that supports one or more play activities.
B. Use Zone: Area under and around a play event within which the ground surfacing must meet fall impact attenuation requirements of ASTM F1292 when tested at the fall height specified for the play event.
C. Fall Height: Vertical distance between the finished elevation of the designated play surface and the finished elevation of the protective surfacing beneath it, as defined in ASTM F1487.
D. Protective Surfacing: Resilient ground surfacing, specified in Section 32 1816.13. The characteristics of the protective surfacing are based on the fall height of the playground equipment. Changes in either the surfacing or the fall height, particularly reducing the resilience of the protective surfacing or increasing the fall height, will reduce safety-related performance.
E. Subgrade: Surface of the ground on which the protective surfacing is installed; the subbase for the protective surfacing is installed over the subgrade. 219-1.4 REFERENCE STANDARDS
A. ASTM A123/A123M - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products; 2015.
B. ASTM F1292 - Standard Specification for Impact Attenuation of Surface Systems Under and Around Playground Equipment; 2009.
C. ASTM F1487 - Standard Consumer Safety Performance Specification for Playground Equipment for Public Use; 2011.
160
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-22
D. CPSC Pub. No. 325 - Public Playground Safety Handbook; 2010. 219-1.5 ADMINISTRATIVE REQUIREMENTS
A. Preinstallation Meetings: Convene a meeting one week before starting earthwork for playground to discuss coordination between various installers.
1. Require attendance by personnel responsible for grading and installers of playground equipment, protective surfacing, footings, and adjacent work.
2. Include representatives of Contractor.
3. Notify City’s Authorized Representative at least 2 weeks prior to meeting. 219-1.6 SUBMITTALS
A. Product Data: For manufactured equipment, provide manufacturer's product data showing materials of construction, compliance with specified standards, fall height, installation procedures, safety limitations, and the number of users permitted.
B. Shop Drawings: Detailed scale drawings showing play event layout, Use Zone perimeters, and fall height for each play event.
1. Show locations and dimensions of footings and anchorage points.
2. Contractor to submit engineered / structural drawings for playground Barn footings for approval as a deferred submittal.
3. Show locations of related construction such as walkways and roadways, fences, site furnishings, and plantings.
4. Immediately notify City if a conflict is discovered with component use zones and other site improvements, or with component footings and underground utilities.
C. Maintenance Data: Provide manufacturer's recommended maintenance instructions and list of replaceable parts for each equipment item, with address and phone number of source of supply.
D. Warranty: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.
219-1.7 QUALITY ASSURANCE
A. Maintain one copy of the latest edition of ASTM F1487 and CPSC Pub. No. 325 at project site.
B. Manufacturer Qualifications: Company regularly engaged in manufacturing materials and products specified in this section, with not less than five years of documented experience.
1. Provide certificate of Insurance AA rated for minimum 1,000,000 dollars covering both product and general liability. Refer to Section 15 of the front end specifications for submittal requirements.
2. Manufacturer's Representative: Provide product rep's name, company name and address, and playground safety training certificate.
C. Installer Qualifications: Company that specializes in installation of playgrounds. Provide list of at least seven playgrounds that installer has completed in the last 10 years, including project addresses and owner reference information. Listed projects should be for public agency(s), with components that are similar in scale and type. 219-1.8 DELIVERY, STORAGE, AND HANDLING
A. Deliver, handle, and store equipment to project site in accordance with manufacturer's recommendations.
B. Store materials in a dry, covered area, elevated above grade. 161
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-23
219-2 EQUIPMENT
219-2.1 MANUFACTURERS
A. Refer to plan sheet LC001
219-2.2 PLAYGROUND EQUIPMENT - GENERAL
A. Design Assumptions: Because the safety of the playground depends on strict conformance to the design criteria, this information is provided for Contractor's information.
1. If deviations from specified dimensions, especially fall heights, is required, obtain approval prior to proceeding; follow approval request procedure as specified for substitutions.
B. Mount all equipment on concrete footings, unless otherwise indicated.
1. Playground protective surfacing constitutes a resilient layer installed over a subbase (non-resilient) that is installed over subgrade; top of footings and anchorage devices is to be covered by full depth of resilient portion of protective surfacing.
2. Protective Surfacing Depth: As indicated on drawings.
3. Provide supports as required to mount equipment at proper height above finish and sub-grades to allow installation of sufficient depth of protective surfacing; portion of support below top of surfacing must comply with specified requirements for equipment.
4. Paint the portion of the support that is intended to be installed below the top surface of the protective surfacing a different color, or mark in other permanent way, so that installers and maintainers of protective surfacing can easily determine whether sufficient depth has been installed.
C. Label each equipment item with permanent labels stating age group that equipment was designed for, manufacturer identification, and warning labels in accordance with ASTM F1487.
219-2.3 SIGNAGE
A. Provide signage indicating “Warning – Entering this area can expose you to chemicals known to the State of California to cause cancer, birth defects or other reproductive harm.
For more information go to www.P65warnings.ca.gov”
219-2.3 PLAYGROUND EQUIPMENT
A. Conform to ASTM F1487 and CPSC Pub. No. 325; provide equipment conforming to specific requirements for relevant age group(s).
1. Provide components having factory-drilled holes; do not use components with extra holes that will not be filled by hardware or covered by other components.
B. Certification: For each component. provide International Play Equipment Manufacturers Association (IPEMA) certification that product complies with ASTM F1487.
SECTION 220 - SITE FURNISHINGS
220-1 .1 SECTION INCLUDES
A. Trash receptacles.
B. Benches
C. Pizza Oven
D. Bike Racks
162
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-24
E. Shed
220-1.2 RELATED REQUIREMENTS
A. Greenbook Section 201 – Concrete, Mortar and related materials: Footings for site furnishings
B. Greenbook Section 303 – Concrete and Masonry Construction 220-1.3 SUBMITTALS
A. See Submittals Administrative Requirements for submittal procedures.
B. Product Data: Provide manufacturer's specifications and descriptive literature, installation instructions, and maintenance information.
220-1.4 WARRANTY
A. Provide manufacturer's warranty against defects in materials or workmanship. 220-1.5 SUBSTITUTIONS
A. Substitutions: See requirements in Contract Documents.
220-2.1 Products
A. Refer to Sheet LC001 for a list of site furnishings
220-3.1 EXAMINATION
A. Verify that mounting surfaces, preinstalled anchor bolts, or other mounting devices are properly installed; and ready to receive site furnishing items.
B. Do not begin installation until unacceptable conditions are corrected. 220-3.2 INSTALLATION
A. Install site furnishings in accordance with approved shop drawings, and manufacturer's installation instructions.
B. Provide level mounting surfaces for site furnishing items.
220-4.1 MEASUREMENT
A. Site furnishings shall be measured per unit price.
220-4.2 PAYMENT
B. Payment for each site furnishing will be made at the Contract Unit Price for each Site Furnishing as listed on the Bid Form (ie. Trash Receptacles, Bike Racks, etc) The contract price paid per the unit price for site furnishings shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals and for doing all work involved to place site furnishings, complete in place.
SECTION 221 - PRE-FABRICATED STRUCTURES
163
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-25
221-1 GENERAL
221-1.1 SECTION INCLUDES
A. Manufacturer-engineered, shop-fabricated shade structures. 221-1.2 RELATED REQUIREMENTS
A. Greenbook Section 201 – Concrete, Mortar and related materials: Concrete Pad.
B. Greenbook Section 303 – Concrete and Masonry Construction 221-1.3 DESIGN REQUIREMENTS
A. Where aluminum alloy parts are in contact with dissimilar metals (other than aluminized or galvanized steel) or absorbent building materials, likely to be continuously or intermittently wet, the facing surfaces shall be painted or otherwise separated in accordance with the aluminum design manual section M.7
B. Size and fabricate wall and roof systems free of distortion or defects detrimental to appearance or performance.
221-1.4 ADMINISTRATIVE REQUIREMENTS
A. Preinstallation Meeting: Convene one week before starting work of this section. 221-1.5 SUBMITTALS
A. Provide the following as part of the Submittal requirements B. Shop Drawings: Indicate assembly dimensions, locations of structural members, connections; roof system dimensions, general construction details, anchorages and method of anchorage, footing details, framing anchor bolt settings, sizes, and locations from datum, foundation loads; indicate welded connections with AWS A2.4 welding symbols; indicate net weld lengths; provide professional seal and signature.
C. Samples: Submit two samples of precoated metal panels for each color selected, 2 x 2 inch minimum in size illustrating color and texture of finish.
D. Manufacturer's Instructions: Indicate preparation requirements, and anchor bolt placement.
E. Erection Drawings: Indicate members by label, assembly sequence, and temporary erection bracing.
221-1.6 QUALITY ASSURANCE
A. Not used.
B. Perform welding in accordance with AWS D1.1.
C. Manufacturer Qualifications: Company specializing in the manufacture of products similar to those required for this project.
1. Not less than 3 years of documented experience
D. Erector Qualifications: Company specializing in performing the work of this section with minimum 5 years’ experience.
221-1.7 WARRANTY
A. Provide 10-year manufacturer warranty for defects in materials and workmanship. 221-2 PRODUCTS
221-2.1 PRE-FABRICATED TRELLIS
A. Manufacturer and model: Refer to Sheet LC001 for Manufacturer 164
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-26
B. Substitutions: See requirements in Contract Documents.
221-3 EXECUTION
221-3.1 EXAMINATION
A. Prior to construction, contractor shall coordinate the foundation, floor slab, mechanical and electrical utilities, and placed anchors will be in accordance with manufacturer’s specifications
B. Confirm all measurements in field on site relative to proposed and existing adjacent improvements prior to fabrication. Notify City and Landscape architecture immediately of any discrepancies. Failure to notify the City will result in the Contractor taking ownership of work in conflict.
221-3.2 ERECTION
A. Install in accordance with manufacturer's instructions.
B. Use concealed galvanized, or stainless steel (or better) fasteners.
C. Install sealant and gaskets to prevent weather penetration. 221-3.3 TOLERANCES
A. Framing Members: 1/4 inch from level; 1/8 inch from plumb.
B. Siding and Roofing: 1/8 inch from true position.
221-4 MEASUREMENT AND PAYMENT
A. Payment for Prefabricated garden shade trellis structures will be made at the Contract Lump Sum Unit Price as listed on the Bid Form. The contract price paid shall include full compensation for procuring, shipping, erecting, and installing each component as well as any materials, tools, equipment, incidentals required to perform the work involved complete in place.
SECTION 222 – PRECAST CONCRETE BOARDWALK SYSTEM
222-1 Part 1-General
References
a. “Greenbook” Standard Specifications for Public Works Construction.
222-1.1 Summary
A. These specifications are for a precast concrete boardwalk and shall be regarded as minimum standards for this project. These specifications are based upon products designed and supplied by:
PermaTrak North America LLC
Ph: Choose an item.
P
h: 877-332-7862
165
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-27
Fax: 704-541-3675
www.permatrak.com
Contact: Choose an item.
Choose an item.
This item shall also include the design, specification, and construction of a railing and foundation system that is attached to the proposed boardwalk system.
222-1.2 Alternate Requirements
Alternates are allowed provided that the following
minimum standards and these “Precast Concrete Boardwalk System” specifications are met.
A change in boardwalk material (treads and beams) will not be considered an alternate.
A. “Minimum Standards” as outlined in section 1.3 below must be met.
B. A fully engineered drawing of the precast boardwalk system (including tread layout, structural details designed for the design loads shown on the contract documents, foundation design, full elevation view and layout) must be submitted 2 weeks before the bid date and signed and sealed by a Professional Engineer licensed in the state of the above named project. Approved alternates will be notified by addenda prior to the bid date. Only pre-approved alternates will be considered.
C. Submission of complete design calculations that are signed and sealed by a licensed Professional Engineer in the state of the above named project. The design computations shall include references to all applicable AASHTO code references, documentation of computer programs (including design parameters), and a clearly detailed reinforcement rebar submittal (including sketches of all precast concrete components.
D. Submittal must meet the requirements set forth in section 1.6a.
222-1.3 Minimum Standards
The selected boardwalk shall have the following minimum characteristics:
A. The precast system shall be designed as a modular flexible system allowing a prescribed settlement at pier locations. Joints shall be designed for such movement to occur without damage to the structural integrity of the system.
B. Boardwalk system (beams, treads, and curbs if applicable) must be reinforced precast concrete. A material change, including cast-in-place concrete, is not considered an equal to the design shown on the bid documents.
C. Walking surface (treads) shall be made of reinforced precast concrete, and supported by reinforced precast concrete beams. Where applicable, edges of treads will receive precast concrete curbs.
D. Walking surface (finish) of top surface of treads shall have a formliner finish with one of PermaTrak’s standard textures. Texture must be integral with the concrete and shall not be an applied post pour wearing surface.
E. Precast concrete treads shall be structural load bearing elements and shall interlock with one another via a “tongue and groove” connection.
166
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-28
F. All precast shall consist of integrally colored concrete in a color selected by the owner from one of PermaTrak’s “standard colors”.
G. DESIGN LOADS: Designed for the following live loads:
1. Pedestrian live load of 90 psf.
2. 5000 lb. Maintenance Vehicle with two axles spaced 96 inches apart and equally distributed.
3. H5 Design Truck – 10,000 lbs. total vehicular load (Applicable for boardwalk clearances exceeding 7 ft. but equal to or less than 10 ft.)
4. H10 Design Truck – 20,000 lbs. (Applicable for boardwalk clearance exceeding 10 ft.)
H. Treads shall maintain a “boardwalk appearance”, specifically meaning each tread shall have a width: length ratio ranging from a minimum of 3:1 to a maximum of 14:1. Width is defined as the tread dimension perpendicular to the normal direction of travel. Length is defined as the tread dimension measured in the direction of travel.
I. Tread width shall be as noted on the contract drawings. Alignment should follow the horizontal and vertical alignment shown on the contract plans.
J. Connectors for curbs (if applicable) to treads shall not be visible to boardwalk users while viewed from the top of the walkway.
K. All tread-to-beam connectors shall be non-corrosive, and hidden from view. Metallic tread-to-beam connectors are not acceptable for this project.
L. Boardwalk supplier shall provide a field representative on site for a minimum of 2 days.
Field representative shall be knowledgeable in the installation of precast concrete boardwalks.
222-1.4 Quality Assurance
A. The contractor performing the installation of the pile foundations shall have installed piles of size and length similar to those shown on the plans for a minimum of three (3) years prior to the bid date for this project. The contractor shall submit a list containing at least three (3) projects completed in the last three (3) years on which the contractor has installed piles of a size and length similar to those shown on the plans. The list of projects shall contain names and phone numbers of owner’s representatives who can verify the Contractor’s participation on those projects.
B. Manufacturer Qualifications: Not less than 10 years experience in the actual production of precast products as described below.
1. Components shall be factory fabricated and engineered by single entity. This entity shall be registered to do business in the state of the above named project.
2. Boardwalk supplier (Precaster) for the boardwalk shall have in-house color mixing facilities for color pigmentation.
3. Boardwalk supplier (Precaster) shall have either a minimum experience of 5 years or 50 boardwalk projects in design, production, and field consultation.
4. Boardwalk supplier (Precaster) must be certified by PCI or NPCA. 167
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-29
5. Precast components must be manufactured with the use of hot rolled steel skin in reinforced steel forms. Temporary (i.e., Timber) and/or single use forms are unacceptable unless approved in writing by the Boardwalk Engineer.
C. Acceptability Criteria for Treads and Curbs (if applicable): The finished visible (in the final installed position) surface shall have no obvious imperfections other than minimal color or texture variations from the approved samples or evidence of repairs when viewed in good typical daylight illumination with the unaided naked eye at a 20 ft. viewing distance. Appearance of the surface shall not be evaluated when light is illuminating the surface from an extreme angle as it tends to accentuate the minor surface irregularities.
The following is a list of finish defects that shall be properly repaired, if obvious when viewed at a 20 ft. distance. Patching (by a trained skilled concrete repair person) is an acceptable repair method.
1. Ragged or irregular surfaces.
2. Excessive air voids (commonly called bug holes) larger than ¼ in. evident on the top surface of the tread or curbs (if applicable).
3. Adjacent flat and return surfaces with greater texture and/or color differences than the approved samples or mockups.
4. Casting and/or aggregate segregation lines evident from different concrete placement lifts and consolidation.
5. Visible mold joints or irregular surfaces.
6. Rust stains on exposed surfaces.
7. Units with excessive variation in texture and/or color from the approved samples, within the unit or compared with adjacent units.
8. Blocking stains evident on exposed surfaces.
9. Areas of backup concrete bleeding through the facing concrete.
10. Foreign material embedded in the surface.
11. Visible repairs at a 20 ft. viewing distance.
12. Reinforcement shadow lines.
13. Cracks visible at a 20 ft. viewings distance.
D. Installer Qualifications: Firm with 3 years experience in installation of systems similar in complexity to those required for this Project.
E. Mock-Up: Provide, if required by Architect/ Engineer, a mock-up for evaluation of the boardwalk showing the surface preparation techniques and application workmanship.
1. Finish areas designated by Architect / Engineer.
2. Do not proceed with remaining work until mock-up is accepted by Architect / Engineer.
3. Refinish mock-up area as required to produce acceptable work.
222-1.5 Design
168
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-30
A. For applications requiring minimum disturbance due to tree roots or other existing objects specified by the Owner to be avoided during construction, the Boardwalk Manufacturer requires the Contractor or Engineer/Architect to provide a survey of the proposed boardwalk location identifying items of interest including tree roots that cannot be disturbed per the Owner.
B. The designer of the boardwalk, foundation and railing system shall be a qualified registered Professional Engineer licensed in the state of the above named project and having a minimum of 20 years of experience in the design of concrete structures, foundation and railing systems.
C. The foundation design shown on the boardwalk drawings are based upon recommendations found in the geotechnical report noted on the boardwalk drawings.
D. DESIGN CRITERIA: The design of the boardwalk and railing system shall comply with the following guidelines:
1. AASHTO LRFD Guide Specifications for The Design of Pedestrian Bridges, 2 nd Edition.
2. AASHTO LRFD Bridge Design Specifications, 8th Edition.
3. American Concrete Institute Building Code and Commentary, ACI 318-19 and ACI 318R-19.
4. In addition to the dead loads of the system, the structure shall be designed for the live loads defined in Section 1.3.G above.
222-1.6 Submissions
Prior to the start of fabrication or construction, the Contractor shall submit to the Engineer a design package, which shall include, but is not limited to, the following:
A. For Approval Submissions
Prior to the start of fabrication or construction, the Contractor shall submit to the Engineer a design package, which shall include but not limited to the following:
1. Detailed Plans:
a. REGISTRATION / SEAL: Sealed by a licensed Professional Engineer in the state where the project is located.
b. PLAN VIEW: Full plan view of the boardwalk, foundation and railing system drawn to scale. The plan view must reflect the proposed horizontal alignment as shown on the design plans.
c. ELEVATION VIEW: Partial elevation view of the boardwalk, railing and foundation system drawn to scale which reflect the actual vertical alignment. Elevation or plan view shall indicate the elevation at the top and bottom of the boardwalk and foundation system components, horizontal and vertical break points, and location of the finished grade.
169
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-31
d. DETAILS: Details of all boardwalk and railing system connections such as the length, size and where changes occur.
e. CODE REFERENCE: Design parameters used along with AASHTO references.
2. Design Computations (If Required): computations shall:
a. Be stamped by a licensed Professional Engineer in the state of the above named project.
b. Clearly refer to the applicable AASHTO provisions.
c. Include documentation of computer programs including all design parameters. d. Clearly show that all reinforced precast treads and beams meet AASHTO requirements for the loading per Section 1.3.G.
e. Include sketches of reinforcement in treads and beams, shear and moment diagrams, and all equations used shall be referenced to applicable code.
3. Construction Specifications:
a. Construction methods specific to the boardwalk vendor chosen. Submittal requirements such as certification, quality and acceptance/rejection criteria shall be included. Details on connection of boardwalk units and foundation system such that assurance of uniform load transfer shall be checked.
B. Final Submission
Once a boardwalk, foundation and railing system design has been reviewed and accepted by the Owner, the Contractor shall submit the final plans. The designer of the boardwalk, foundation and railing system is responsible for the review of any drawings prepared for fabrication. In the event the boardwalk designer and railing designer are separate entities, the contractor is responsible for verifying compatibility. One set of all approved shop drawings shall be submitted to the Engineer’s permanent records.
C. Submittals
Product Data: Submit Manufacturer’s technical product data for railing components and accessories.
Manufacturer to supply submittal drawings for approval to include the following:
1. Section-thru details.
2. Mounting methods.
3. Typical Elevations.
4. Key plan layout.
D. SHOP DRAWINGS: Shop drawings shall:
1. Be stamped by a licensed Professional Engineer in the state of the above named project. 170
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-32
2. Show actual field conditions and true elevation and location supplied after field verification.
3. Clearly detail reinforcement in beams, treads and curbs including clear dimension from concrete edge, size and amount of rebar.
4. Clearly state concrete compressive strength, steel type and strength, and a listing of all component weights including lifting locations.
222-1.7 Delivery, Storage, And Handling
A. tore products in manufacturer's unopened packaging until ready for installation.
B. Field Measurements: Where handrails and railings are indicated to fit to other construction, check actual dimensions of other construction by accurate field measurements before fabrication; show recorded measurements on final shop drawings:
1. Where field measurements cannot be made without delaying the railing fabrication and delivery, obtain guaranteed dimensions in writing by the Contractor and proceed with fabrication of products so as not to delay fabrication, delivery and installation.
C. Coordinate fabrication and delivery schedule of handrails with construction progress and sequence to avoid delay of railing installation.
222-1.8 Warranty
A. Contractor will be responsible for installation defects associated with the boardwalk and abutment components, foundation system, and railings for a period of 12 calendar months from the date of final acceptance by the Owner.
B. Boardwalk manufacturer shall warranty all precast concrete components against defects in material and workmanship for a period of 10 years.
C. Railing manufacturer shall warranty the railing against defects in materials and workmanship for a period of 12 months.
222-1.9 Measurement And Payment
A. Precast concrete boardwalk, railings,and foundations shall be paid for at the contract lump sum price as listed in the bid proposal for “Precast Concrete Boardwalk”. This price shall include all materials, equipment, labor and work necessary for and incidental to the design, construction, delivery, unloading, assembly, and placement of the boardwalk and foundation as shown in the contract plans including all railings on the superstructure.
222-2 Part 2-Materials & Testing
171
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-33
222-2.1 Precast Concrete
Shall conform to the following:
A. The minimum compressive strength of the concrete shall be 4000 psi measured at 28 days.
B. All precast concrete shall contain fiber reinforcing as well as structural steel reinforcement as designed by the Engineer of record.
C. All precast concrete components shall be air entrained composed of Portland cement, fine and course aggregates, admixtures and water. The air-entraining feature may be obtained by the use of either an air entraining Portland cement or an air entraining admixture. The entrained air-content shall be not less than four percent or more than seven percent.
D. All reinforcing steel shall be standard uncoated steel conforming to ASTM A615 unless noted otherwise.
222-3 Part 3 - Execution
222-3.1 Precast Concrete Boardwalk
A. Installation of the precast concrete boardwalk system and railings, if applicable, shall be performed in accordance to the approved plans and manufacturers installation instructions.
Boardwalk manufacturer shall provide a field representative to review installation instructions with the Contractor and Engineer and to certify that the installation has been performed according to the approved drawings and manufacturer’s instructions.
222-4 End Section
SECTION 223 – PRECAST CONCRETE UNIT PAVERS
223-1 GENERAL
223-1.1 SECTION INCLUDES
A. Interlocking concrete paver units.
B. Sand setting bed.
C. Polymeric sand joint filler.
223-1.2 REFERENCE STANDARDS
A. ASTM C33/C33M - Standard Specification for Concrete Aggregates 2018.
B. ASTM C144 - Standard Specification for Aggregate for Masonry Mortar 2018.
C. ASTM C936/C936M - Standard Specification for Solid Concrete Interlocking Paving Units 2021b.
223-1.3 SUBMITTALS
172
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path F-34
A. Product Data: Provide characteristics of paver unit, dimensions, and special shapes.
B. Product Data: Provide characteristics of polymeric sand, including base material, additive(s), compressive strength, and color.
223-2 PRODUCTS
223-2.1 MANUFACTURERS
A. Interlocking Permeable Concrete Pavers:
a. Air-Vol Block Pavers.
b. Approved Equal based on an approved submittal
223-2.2 MATERIALS
A. Interlocking Concrete Pavers: Hydraulically pressed concrete, configured for interlocking with adjacent units and complying with ASTM C936/C936M. a. Compressive Strength: 8000 pounds per square inch average, with minimum of 7200 pounds per square inch.
b. Thickness: 2-3/8 inches.
c. Type: 3 piece - Ashlar pattern.
d. Color: Natural.
e. Sand for Setting Bed: Clean washed natural sand or crushed stone complying with gradation requirements of ASTM C33/C33M for fine aggregates.
B. Polymeric Sand: Fine sand complying with ASTM C144 combined with polymer binders for creating semi-solid joints between pavers.
a. Compressive Strength: 750 pounds per square inch.
b. Adhesion by Tensile Load: 100 pounds per square inch. c. Color: As approved from standard color list.
173
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H – Technical Specifications Page 35
174
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 36
PART 3 – CONSTRUCTION METHODS
SECTION 300 - EARTHWORK
ADD: 300-0 GENERAL EARTHWORK REQUIREMENTS.
Contractor shall perform earthwork as required for the Work, including, but not limited to, the following:
1. Perform grading within contract limits, including adjacent transition areas to new elevations, levels, profiles, and contours indicated. Check subgrade surfaces parallel to finished surface grades. Provide uniform levels and slopes between new elevations and existing grades.
2. Grade surfaces to assure areas drain away from structures and to prevent ponding and pockets of surface drainage. Check subgrade surfaces.
Subgrade shall be free from irregular surface changes and as follows:
a. The subgrade at any point shall not vary more than 0.05 foot above or below the grade established by the Improvement Plans if the structural section indicates placing surfacing on native material.
b. The subgrade at any point shall not vary more than 0.05 feet above the grade established by the Improvement Plans if the structural section indicates placing an aggregate base or sub-base material on native materials.
c. Rough Grading: Rough grade surface shall not vary by more than
0.10 feet above or below the grade established by the Improvement Plans. Finish required will be that ordinarily obtained from either blade grader or scraper operations.
d. Fine Grading: Fine grades shall be set to the grades/elevations established by the Plans.
e. Paved Areas: Shape surface of fine grade areas to line, grade, and cross-section indicated. Check compacted subgrade. Subgrade shall be suitable to receive paving base materials, per Standard Specifications. Subgrade tolerance plus 0, minus 1/2".
f. Granular Base: Check subgrade surface. Subgrade surface shall be smooth and even, free of voids, to the required subgrade elevation.
Compacted subgrade shall be suitable to receive granular base materials per Standard Specifications. Tolerance 1/2" in 10'.
3. Uniformly distribute and spread soil. Provide additional imported topsoil, per the Contract Documents to complete the work. Use loose, dry weed-free topsoil. Do not use muddy topsoil. Place during dry weather.
4. Fine grade topsoil eliminating rough and low areas to ensure positive drainage. Maintain levels, profiles, and contours of fine grades.
5. Remove stones, roots, weeds, trash and debris while spreading topsoil materials. Rake surface clean of stones 1" or larger in any dimension and all debris. Provide surfaces suitable for soil preparation provided under lawn 175
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 37
and planting work. Contractor shall be responsible for ‘rock picking’ and removal of all rocks, stones, and boulders one (1) inch in diameter and greater in all areas not requiring concrete paving. Removal of rocks from site shall be in compliance with state and local codes.
6. Perform grading within contract limits, including adjacent transition areas to new elevations, levels, profiles, and contours indicated. Grading within sensitive environmental boundaries shall not occur unless directly authorized by the City’s authorized representative. Any grading authorized in sensitive areas shall be done under direct supervision by the City’s representative.
Grading and earthwork for the new construction shall include excavation of the existing grade as necessary to “key” into existing grade. Spoils from such operations shall be relocated and hauled offsite or stockpiled by the contractor. Provide subgrade surfaces parallel to finished surface grades.
Provide uniform levels and slopes between new elevations and existing grades.
7. DeWatering – Contractor shall provide temporary berms in an approved manner as necessary to hold back water intrusion into excavation operations.
8. Temporary Fencing – Provide 6 ft green mesh temporary construction fencing along property boundaries adjacent to private residences.
Contractor shall supply all equipment, labor, and materials necessary for the performance of the earthwork, including the items listed above. Earthwork, including the items listed above, shall be paid for under the Bid Item for Grading, unless otherwise covered by a separate bid item, and no additional compensation shall be made therefor.
300-1 CLEARING AND GRUBBING.
300-1.1 General. ADD the following:
The Contractor, unless otherwise noted, shall clear, grub, demolish, and remove from the site all existing vegetation in areas demarked on the plans for removal or where otherwise will impact the proposed work. All known existing improvements at the time of the survey are identified on the plans. These improvements include concrete pavement, playground surfacing, irrigation valves, trees, shrubbery, curbs, signs, site furnishings, , etc.
Clearing and Grubbing shall also include the following, with the exception of work otherwise covered by another bid item:
a. Contractor shall haul away from the job site and dispose at a legal landfill deleterious materials (i.e., removal of bushes, removal of trees, etc.).
b. Any existing signs/monuments or similar objects and/or debris not shown on the plans but within the right-of-way or easements at the time of construction, shall be removed and disposed of by the Contractor.
c. Removal and disposal of all miscellaneous concrete, pavement, pipes, hardware, timber, rubble or any other objectionable material encountered beneath the ground surface as a result of grading operations connected with the construction of the project improvements.
176
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 38
d. Removal, relocation, abandoning, adjusting, or salvaging of all existing facilities so indicated on the plans which are not designated as separate bid items or which are not included in other bid items.
e. Removal and transport debris and rubbish in a way that will prevent spillage onto streets or adjacent areas. Cleanup of spillage shall be performed at the Contractor’s expense and to the satisfaction of the City Engineer.
f. Maintaining dust control at all times by watering; including developing water supply and furnishing and placing all water required for work done in the contract, including water used for extra work.
g. Protection and maintenance of utilities, trees. fences, walls, and other facilities within the construction zone, except those specifically directed by the City Inspector to be removed or relocated. Protection of trees shall be in compliance with the City of Goleta.
h. Minor grading for swales and erosion control.
i. Progressive clean-up and maintenance of project appearance.
j. Cleanup of project area upon completion of work.
k. Removal and haul-off of cold plane grindings.
l. Sawcut and removal and haul off of existing concrete sidewalks, driveways, curb and gutter, and asphalt.
m. Provision of temporary drainage facilities when required by demolition operations.
n. Tree Protection
No materials or equipment shall be stored within the dripline of any existing tree to remain.
Grading and trenching within the dripline of existing trees to remain shall be minimized and done with a light (one ton or less) rubber-tired equipment or by hand.
During any grading or excavation adjacent to or beneath the dripline of existing trees to remain, any roots encountered shall be cleanly cut and sealed with a tree-seal compound.
City’s arborist shall be on site during all grading and excavation. Notify the City 48 hours in advance of grading operations.
City’s biologist shall be on site during clearing and grubbing, and demolition for consultation for potential nesting birds. Discovery of nesting birds shall halt construction until further notice by the City. The Contractor shall immediately notify the City of evidence of bird nesting in areas to be disturbed. Refer to the mitigation plan created by Rincon Consultants.
Costs of furnishing equipment, labor, and materials as necessary for compliance with this section shall be paid for under the Bid Item for Clearing and Grubbing, and no additional compensation shall be made therefor.
300-1.2 Preservation of Property. ADD the following:
177
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 39
The contractor shall protect all existing structures and/ or facilities which are adjacent to, or fall within, the limits of the work to be done under this contract in accordance with Section 7-9, Protection and Restoration of Existing Improvements, and Section 300-1 of the Standard Specifications. This item shall also include those structures and facilities which the plans show or these Specifications indicate to be protected. Any structure or facility to be protected that is damaged as a result of the Contractor and/ or construction related activities shall be repaired or replaced at his cost, to the satisfaction of the Engineer.
Contractor shall research all available records and drawings of adjacent work and existing services and utilities which may affect the Work.
300-1.3.2 Requirements.
a. Bituminus Pavement. REVISE the second sentence to read: Sawcutting of edges to be joined shall be mandatory.
300-1.4 Payment. ADD the following:
Unless otherwise specified, payment for clearing and grubbing shall be paid for in one (1) lump sum contract price and no additional compensation will be allowed. Payment shall include full compensations for furnishing all labor, materials, tools, equipment, and mobilization, disposals and doing all work involved in clearing and grubbing as specified and not covered by separate bid items.
ADD 300-1.5 Removal and Relocation. Removal and relocation items shall require the Contractor to remove and relocate the existing improvements as shown on the plans or to the satisfaction of the City Engineer. Existing irrigation valves, valve boxes, mainline, signage, site furnishings will be required to be removed and relocated as part of improvement operations. New materials for relocating piping mainline and lateral relocations shall be considered included as part of the Contractor’s bid price for landscape - irrigation.
All existing water services to be relocated or extended shall be bid as new installations, including the removal of existing service. The Contractor shall inspect and verify that the existing service meets current Agency standards.
Relocated items as shown in the Bid Schedule shall be paid at the contract unit bid price for each, and no additional compensation will be allowed therefor. If no separate bid item for the removal and relocation of an item has been included in the Bid Schedule, that removal and relocation of that item shall be paid for under the Bid Item for Clearing and Grubbing.
Add 300-1.6 TREE REMOVAL
GENERAL
A. Section includes:
1. Remove trees as shown on the plans.
2. General specifications per Greenbook.
178
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 40
3. As approved by the Engineer.
4. As approved by the ISA Certified Arborist.
The following tree protection guidelines adhere to current International Society of Arboriculture (ISA) standards for tree preservation during construction activities:
1. Tree protection shall be established at the Tree Protection Zone (TPZ -canopy and/or root zone) or at the greatest distance possible from all trees.
2. The limits of the TPZ should be staked in the field prior to commencement of construction activities.
3. Any brush clearing or pruning required within the TPZ shall be accomplished with hand operated equipment.
4. All trimming, pruning or removal of trees shall be done by or monitored by an ISA Certified Arborist or Tree Worker and be in accordance with current ISA Standards.
5. No materials, equipment, spoil, waste or washout water shall be deposited, stored or parked within the TPZ.
6. Construction activities shall be completed using the smallest equipment possible and shall operate outside the TPZ.
7. If equipment placement within the TPZ is necessary for construction activities, ground protection shall be placed (2 inches of mulch, plywood) to prevent soil compaction.
8. Any roots over 1inch in diameter exposed during construction activities shall be exposed to sound tissue and cut cleanly with a saw.
9. For any single native tree no more than 20% of live foliage shall be removed or greater than 20% of the ground under a tree be disturbed during the extent of construction activities for this project.
B. Greenbook Related Sections:
Section 300 – Earthwork
Section 300 -1.1 Clearing and Grubbing
Section 301–Treated Soil, Subgrade Preparation and Placement of Base
C. PAYMENT
Payment for remove tree will be made at the contract unit price per each, and shall include
full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in removing tree, complete in place, and no additional compensation will be made.
300-2 UNCLASSIFIED EXCAVATION.
300-2.1 General. ADD the following:
All surplus material including asphalt, concrete, etc. shall be disposed of in a legal manner, in compliance with the City of Goleta Debris Recycling Program and at the expense of the Contractor.
300-5 BORROW MATERIAL
A. Section Includes:
specifications for obtaining local and imported borrow material for embankment construction. 179
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 41
The payment quantity for imported borrow does not include aggregate base placed to fill low areas.
B. Greenbook Related Sections:
Section 300 – Earthwork
Section 300 -1 - Clearing and Grubbing
Section 300-2 0 Unclassified Excavation
Section 300-4 – Unclassified Fill
Section 300-5 Borrow Excavation
Section 301–Treated Soil, Subgrade Preparation and Placement of Base
C Quality Assurance
Notify the Engineer before opening any imported borrow material site so that the Department may test the material.
C. MATERIALS
Borrow material must be:
1. Suitable for the purpose intended
2. Free of unsuitable material including organic matter
Local Borrow
Local borrow shall be in accordance with the provisions of section 300-5.1 in the standard specifications and these technical specifications.
Imported Borrow
Imported borrow must be free of man-made refuse, such as:
1. Concrete
2. Asphalt concrete
3. Residue from grooving and grinding operations
4. Metal
5. Rubber
6. Mixed debris
7. Rubble
D. CONSTRUCTION
1. General
Clear, grub, and strip borrow sites if necessary. Excavate, load, and if necessary haul borrow material. Construct embankments under section 300-4 of the standard specifications and these technical specifications.
2. Local Borrow
Obtain local borrow such that no scar or unsightly appearance is generated.
3. Imported Borrow
Before placing imported borrow in embankments, ensure enough space is available in embankment locations for placing planned or designated excavated material from the job site.
E. PAYMENT
180
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 42
The payment quantity for imported borrow will be made at the contract unit price per cubic yard and per section 300-4.10 of the standard specifications.
The grading factor used for excavated materials for determining payment quantity for imported borrow is 1.0.
SECTION 301 – TREATED SOIL, SUBGRADE PREPARATION AND PLACEMENT OF BASE MATERIALS
301-1 SUBGRADE PREPARATION.
301-1.1 General. ADD the following:
Subgrade soils for concrete and asphalt paving, curbs, playground surfacing, and decomposed granite paving improvements shall be conditioned to a minimum depth of 12-inches, moisture-conditioned, per Project Soils Report and recompacted to a minimum depth of 90 percent relative compaction prior to placement of base materials.
301-1.2 Preparation of Subgrade. After first paragraph, ADD the following:
Subgrade soil shall be prepared in conformance to the geotechnical soils report. Per the report, the upper 12 inches of soil to support pavement, and concrete flatwork shall be removed and replaced with engineered fill.
301-2 UNTREATED BASE.
301-2.4 Measurement and Payment. ADD the following:
The contract price paid per the unit price for Crushed Aggregate Base shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals and for doing all work involved to place Crushed Aggregate Base, complete in place, including scarify six (6) inches, moisture condition, and prepare subgrade to a 90% compaction, as per the Contract Documents and as directed by the Engineer.
301-6.2 Operator's License
The Contractor's operator applying the soil sterilant shall be licensed or Certified Qualified Applicator by the State of California, Department of Food and Agriculture and registered as required by law.
Contractor shall conform application materials and rates to the County of Santa Barbara’s Integrated Pest Management Program (IPMP)
301-6.3 Application
Any soil sterilant which is approved in writing by a licensed pest control advisor (for the purpose to which it will apply) may be used upon acceptance by the Engineer. Contractor shall provide the written recommendation for the soil sterilant to the Engineer in conformance with Section 2.5-3, Submittals.
181
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 43
The dye shall not stain concrete or masonry. Certification shall be furnished to the Engineer showing the purchase receipt and manufacturer’s recommended rate of application of the material in accordance with the requirements in Section 2-5.3, Submittals.
301-6.4 Payment
The Contractor shall supply all labor, materials, and equipment to apply the soil sterilant and shall include the cost for application in the price quoted for Concrete Paving. Payment shall the made as part of the lump sum contract price and no additional compensation will be allowed.
ADD: 301-7 DECOMPOSED GRANITE PAVING. Contractor shall comply with the requirements below:
301-7.1 Installation and Repair. Trail or pathway applications shall be compacted in 2” lifts to a relative compaction of 95% unless noted otherwise. For each 2” lift evenly spread the material over area of concern. Grade and smooth as desired. Thoroughly water entire area so the entire depth of the material is moist. After a period of +/- 6 hours compact the finale lift with a 1,000 – 3,000 lb. static drum roller. Allow for a sufficient curing period of +/- 4 days prior to use.
301-7.2 Color – California Gold. Submit for final approval.
301-7.3 Grades. Garden area shall have a cross-slope of 1.5% and shall not exceed a 2% cross- slope.
301-7.4 Stabilizer. Installation procedures shall be applied per manufacturer’s instructions.
Contractor shall protect stabilized decomposed granite surfacing from ruts, channels, and other damage until Project acceptance. Contractor shall repair damaged areas to match specified requirements prior to acceptance. If surfacing is damaged or discolored, Contractor shall repair in accordance with stabilizer manufacturer’s recommendations.
301-7.5 Payment.
Decomposed Granite Paving shall be included in the contract square foot unit price and shall include full compensation for furnishing all labor, materials, tools and equipment and doing all work required to construct the structure in conformity with the Plans and Specifications.
SECTION 302 – ROADWAY SURFACING
302-5.9 MEASUREMENT AND PAYMENT MODIFY as follows:
Porous Asphalt Concrete Paving shall be paid for at the Contract unit price per cubic yard.
SECTION 303 – CONCRETE AND MASONRY CONSTRUCTION
303-1 CONCRETE STRUCTURES.
182
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 44
303-1.1 General. ADD the following:
Surfaces of all concrete structures shall receive a medium broom finish, unless otherwise specified on the plans.
The Contractor shall furnish all labor, tools and materials to construct reinforced Portland Cement Concrete structures and appurtenant work to grades and dimensions shown on the Plans or staked in the field. The Contractor shall submit method and sequencing for placement of P.C.C. for the Engineer’s approval at least ten (10) working days prior to commencement of work.
Unless otherwise specified, transverse construction joints shall be placed in all reinforced sections at intervals of not less than ten (10) feet or more than fifty (50) feet. The joints shall be in the same plane for the entire structure and, for concrete thickness greater than 6-inches, shall be keyed as directed by the Engineer.
303-1.3 Forms. Eleventh paragraph, DELETE in its entirety and SUBSTITUTE with the following:
Exterior forms are required for structures unless otherwise specified on the Plans or in the Specifications.
ADD the following after the last paragraph:
Forms shall be braced to withstand the pressures developed and shall be tight to prevent the loss of material. Formed wall surface shall be free of any unevenness greater than 1/4-inch when checked with a 10-foot straight edge.
Concrete in walls with side slopes flatter than 3/4:1 shall be placed on suitable material which has been overfilled, compacted, and trimmed to true grade. Backforms shall be used where the side slope is 3/4:1 or steeper.
A clear non-staining form release agent which will not discolor nor affect the surface texture of the concrete and does not react with any ingredients of the concrete shall be used. The cost of Furnishing and Placing Form Release agent shall be included in the cost of Portland Cement Concrete.
All form work for concrete construction (mow curbs, paving, concrete curbs, gutters, walls, etc) shall be reviewed and approved by City prior to pouring of concrete.
303-1.8 Placing Concrete.
303-1.8.1 General. ADD the following:
The Contractor shall exercise caution in placement of concrete in walls and congested areas to ensure proper consolidation and that there are no voids, and protection of waterstops in position.
Adequate provisions shall be made for visual inspection of concrete placement, consolidation and waterstop protection. Pouring of walls in lifts, use of smaller maximum aggregate sizes, or other 183
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 45
methods as necessary may be proposed by the Contractor and will be permitted only after evaluation by the Engineer.
303-1.10 Curing. ADD the following to the first paragraph:
Exposed concrete surfaces shall be sprayed with Type 2 curing compound at a uniform rate of one gallon per 150 square feet.
303-1.11 Payment. ADD the following:
Should the Contractor request and obtain permission to use admixtures for his own benefit, he shall furnish such admixtures and incorporate them in the concrete mixture at his expense, and no additional compensation will be allowed therefore.
Should the Engineer direct the Contractor to incorporate any admixtures in the concrete when their use is not required by these Specifications, furnishing the admixtures and adding them to the concrete will be paid for as Extra Work as provided for in the Contract Documents.
303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.
303-5.1 Requirements.
303-5.1.1 General. The f
irst paragraph, second sentence shall be deleted in the event curb is placed by extrusion machine and concrete mix is approved by the City Engineer.
ADD the following after the first paragraph:
Concrete curbs, ramps, and walks shall conform to the (1) Contract Drawings, (2) Santa Barbara County Standard Drawings, (3) the Standard Drawings, and regulations for accessibility.
Monolithic curb, gutter, and sidewalk shall not be allowed. Expansion Joints shall be provided per details provided on the plans.
In areas where field adjustments to the curb and gutters may be required due to the existing conditions to maintain positive drainage, the Contractor shall contact the Engineer prior to the construction.
The Contractor shall exercise due caution when working around trees not to damage either the trunk or any of its limbs. If damage to a tree occurs, the contractor shall notify the Engineer. Once excavation has occurred, all efforts shall be made to mitigate the exposure of the tree roots to the air.
At the discretion of the Engineer, the angle of the new gutter shall be adjusted to maintain the existing grade or crown of the street and to avoid causing drainage problems. At the discretion of the Engineer, the height of the new curb shall be reduced to match existing conditions and create or 184
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 46
maintain positive drainage away from the property line toward the curb. In areas where the curb height is being adjusted, the transition area shall be a minimum of 6’.
The Contractor shall neatly saw cut all damaged sidewalk, curb and gutter and roadway prior to their removal. The Contractor shall remove all PCC sidewalk, curb and gutter, and tree roots as directed and dispose of said materials at a legal disposal site. The Contractor shall remove any item which exists in the parkway area and will affect the final work product. The Contractor shall exercise due caution when working around trees not to damage either the trunk or any of its limbs. If damage to a tree occurs, the contractor shall notify the Engineer. Once excavation has occurred, all efforts shall be made to mitigate the exposure of the tree roots to the air.
The Contractor shall grade, compact the sub-grade, and form for new curb ramps, sidewalk and/or curb and gutter in accordance with these standard specifications. After final troweling, the PCC sidewalk shall receive a broom finish.
ADD: 303-5.1.5 Existing Surface Improvements. If curb, gutter, or sidewalk are replaced, the Contractor shall duplicate the existing surrounding score pattern and color. The score pattern shall be continued in the same pattern and scale. Jointing shall be approved in advance by the City Engineer.
303-5.2 Forms.
303-5.2.1 Standard Forms. ADD the following:
a. Use flexible metal, 1" lumber or plywood forms to form radius bends.
b. Install, align and level forms, stake, and brace forms in place. Maintain following grade and alignment tolerances except where accessibility concerns would bring non-compliance if tolerances were allowed.
Top of Form: Maximum 1/8” in 10’0”.
Vertical Face: Maximum 1/8” in 10’0”.
c. The Contractor shall include all fine grading and compaction with regard to setting forms during concrete placement.
d. The Contractor shall notify City a minimum of 36 hours in advance of scheduled form board review. All form work for hardscape construction (mow curbs, concrete paving, curbs, gutters, walls, etc.) shall be reviewed and approved by the Engineer prior to pouring of concrete.
Modifications in formwork necessary for alignments to be straight, true to line with well transitioned radial, curved sections shall be provided by the Contractor at no additional cost to the City.
303-5.3 Placing Concrete. ADD the following:
185
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 47
The top and face of the finished concrete surfaces shall be true and straight, of uniform width and free of humps, sags, or other irregularities. The finished concrete surface shall not vary more than
0.02’ (6 mm) from a 10’ (3 meter) straight edge, except at grade changes or curves. No freestanding water will be permitted on slope over 1%. No freestanding water deeper than 1/16” (1.5 mm) will be permitted on slopes of less than 1%.
Concrete placed immediately before rain shall be protected to prevent rainwater from coming in contact with it. Sufficient protective covering shall be kept on hand at all times for this purpose.
303-5.4 Joints.
303-5.4.1 General. ADD the following:
Contractor shall provide expansion joints using pre-molded joint filler at concrete work abutting curbs, walks, and other fixed objects and shall:
a. Locate expansion joints as indicated. When not indicated, provide joints at maximum 24’-0” on center for curbs and walks. Align expansion joints in abutting curbs and walks. Expansion joint material shall be as noted on drawings and shall extend to full depth of concrete section.
b. Install expansion joint fillers full-width and depth of joint. Recess top edge below finish to receive sealants as indicated on the details.
c. Provide joint fillers in single lengths for the full slab width, whenever possible. Fasten joint filler sections together when multiple lengths are required.
d. Where intersecting joints occur, join top edge and continue any spliced joints without deviation of form line or direction.
e. Protect the top edge of the joint filler during concrete placement.
f. Install joint sealant SEKA flex or approved equal. Color to match concrete.
g. Control joints shall be provided to a depth equal to 1/3 the thickness of the concrete pour.
303-5.5 Finishing.
303-5.5.4 Gutter. ADD the following:
All new curb and gutter shall have a minimum of 6” deep Class 2 Aggregate Base placed below it.
Class 2 Aggregate Base shall conform to Section 26 “Aggregate Bases” of the State Standards.
Prior to acceptance of the curb and gutter constructed by the Contractor, a flow test shall be conducted by the Contractor in the presence of the Engineer. Any new work found to be defective shall be repaired or replaced by the Contractor in accordance with Subsection 303-5.7 of the Standard Specifications.
186
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 48
303-5.6 Curing. ADD the following:
Immediately after finishing operations are completed, Type 2 concrete curing compound shall be applied at a rate of one gallon per 150 square feet.
303-5.9 Measurement and Payment.
Payment for concrete curbs, concrete curb edges, and mow curbs shall be at the contract unit price per linear foot , including transition sections where the curb face varies (such as changes in type of curb).
Payment for concrete paving and flat work shall be at the contract unit price per square foot. The thickness of the concrete shall be as indicated on the plans or designated on the Standard Drawing.
Measurement for sidewalk pay quantities will be taken from the back of curb to the back of walk.
Excavation, grading, and backfilling shall be included in the unit price bid for sidewalk, curb ramps or curb and gutter respectively. Payment for removing tree roots, cutting, excavation, disposal, import and backfilling to grade, and pavement construction shall be included in the items of Work for which the subgrade is prepared.
The price bid shall be considered to include full payment for all materials, labor, equipment and incidentals required to construct the concrete improvements in accordance with the Contract Documents.
SECTION 304 – METAL FABRICATION AND CONSTRUCTION
304-3 Chain Link Fence.
304-3.1.1 Materials for Chain Link Fencing items. The Contractor shall comply with the following:
a. Fabrication: Fence work which will be exposed to view shall only be fabricated with materials that are smooth and free of surface blemishes, including, but not limited to, pitting, seam marks, trade names, and roughness. Remove such blemishes by grinding or by welding and grinding prior to cleaning, treating. or applying surface finishes.
b. Shop Assembly: Work shall be fitted, shop assembled, and ready for erection when identified on construction schedule.
c. Workmanship: Form metals to shape and size with sharp lines and angles, and with smooth surfaces and faces free from distortion. Mill fastening to a close fit. Do all fitting true to line.
Bend or form all tubing, pipe, and other members to continuous and true curves with all joints flush and neatly fastened together. All fabrications shall be square, plumb, straight, and true.
d. Jointing and Connections: Jointing and intersections shall be accurately made in true planes and tightly fitted to hairline joints. Connections shall be welded. Do not use screws unless specifically 187
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 49
shown or required - if used, screws shall be countersunk with a metal compatible with the members being joined.
e. Welding: Welding shall conform to the requirements of the "Structural Welding Code" ASW D1.l.
Where welds are exposed to views, bevel members prior to welding and weld full. Grind welds flush, smooth, level with the adjacent surfaces. Grind welds at intersecting members to sharp lines.
f. Holes: Accurately space to centers such that boles are not poorly or carelessly seamed.
g. Anchorage: Fabricate and space anchoring devices to provide adequate support for intended use.
h. Insulation of metals from contact with masonry and different metals from contact with each other shall be provided where necessary to prevent corrosion.
i. Debur and grind smooth all welds and rough spots.
j. Gates – Gate hardware shall be accessible and meet ADA requirements.
304-3.1.2 Installation. The Contractor shall comply with the following:
a. Installation: Chainlink Fencing and gates shall be erected in accordance with the Drawings. All work shall be erected square, plumb, straight, and true. Perform all required cutting, drilling, and filling. Accurately set and properly secure. Attach work in true planes, in alignment, properly reinforced and stiffened.
b. Embedded Items: Provide miscellaneous metal items to be embedded or installed in concrete.
c. Coordination with Related Work: Provide all anchors, sleeves, bolts, and connecting members necessary for securing metal work to other adjacent or adjoining work. Provide and install angles and other reinforcement. Do all cutting, puncturing, drilling, tapping, or modifying of adjacent or adjoining work where necessary for proper installation. Furnish all sockets, bolts, anchors, and other portions of this work to the various trades where needed that are to be built into the structure and be responsible for their accurate spacing and setting.
d. Expansion and Contraction: Assemble and install work with adequate provisions to prevent objectionable distortion and overstressing from expansion and contraction. Construct to be weather-tight where exposed to the weather.
e. Touch-up Coating: Immediately after erection of miscellaneous metal items, all rusted areas, abraded areas, bolts and nuts, and all welds shall be thoroughly cleaned and coated per manufacturer’s instructions for field touch up.
f. Miscellaneous Steel Items: Provide all necessary steel items required which are not specified elsewhere. All necessary supports, guides, brackets, etc., shown or required shall be provided.
188
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 50
304-3.4 Measurement and Payment. REPLACE WITH THE FOLLOWING:
Fencing - Measurement for Chainlink fencing shall be measured parallel to the ground plane. The Contract Unit Price per linear foot for Chainlink Fencing in place shall also be considered full compensation for furnishing and installing the fencing, mesh, concrete foundations, brackets, earthwork, and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in chainlink fencing, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
Gates - The Contract Unit Price per each for Chainlink Gates shall be considered full compensation for installing gates in place including full compensation for furnishing and installing the fencing, mesh, concrete foundations, brackets, earthwork, and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in chainlink gates, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
304-6 METAL WIRE MESH SECURITY FENCING INSTALLATION
304-6.1 Inspection
A. Inspection – Examine the areas and conditions under which gate items are to be installed, and correct conditions detrimental to the proper and timely completion of the work. Do not proceed until unsatisfactory conditions have been corrected. 304-6.2 Preparation
A. Preparation – Follow manufacturer’s recommendations for installation preparations.
Furnish setting drawings, diagrams, templates, instructions, and directions for installation of anchorage, such as steel column, welded angle, and miscellaneous items having integral anchors, which are to be embedded in concrete construction. Coordinate delivery of such items to project site. Verify the gate posts are plumb and gate moves freely. 304-6.3 Gate Swing
A. Verify the gate posts are plum and gate operates freely.
B. Perform any required maintenance before continuing.
C. Verify gate swing direction and layout for each gate on site with City representative prior to fabrication. Gates shall open to the full 180 degree position and shall stage in the open position directly adjacent the next fence panel. Gates shall not obstruct the path of travel in anyway while in open position.
D. Gates receiving panic bars shall have perforated metal panel sheets of same color installed (welded) on both adjacent fence panels to avoid intruders reaching through fence to open gate.
304-6.4 Fencing Installation
A. Fastening to In-Place Construction -- Provide anchorage devices and fasteners as required by drawings for securing miscellaneous metal fabrications to in-place construction.
B. Install system in strict accordance with manufacturer’s instructions.
C. Contractor to arrange fence posts to maximize clearance between fence posts and existing trees. Contractor to use care when digging footings for fence posts to avoid damage to existing tree trunks and roots.
189
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 51
D. Fence locations and mowcurb shall generally be parallel to existing walks, and hardscape.
Install mowcurbs under fencing so that the curb runs directly adjacent existing hardscape improvements.
E. Cutting, Fitting, and Placement
1. Perform cutting, drilling, and fitting required for installation of miscellaneous metal fabrications.
2. Set work accurately in location, alignment, and elevation, and make plumb, level, true and free from rack, measured from established lines and levels.
3. Provide temporary bracing or anchors in formwork for items, which are to be built into concrete or similar construction.
4. Fit exposed connections accurately together to form tight hairline joints.
5. Weld connections, which are not to be left as exposed joints, but cannot be shop welded because of shipping size limitations. 6.Grind exposed joints smooth, and touch up shop paint coat or galvanizing. Do not weld, cut, or abrade the surfaces of exterior units which have been hot-dip galvanized after fabrication and are intended for bolted or screwed field connections.
F. Touch-Up Painting
1. Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with same material as used for shop painting.
Apply or brush or spray to provide minimum dry film thickness of 0.051 mm (2.0 mils).
2. At all galvanized products, clean all damaged areas and re-coat using specified galvanizing coating per manufacturer's criteria.
304-6.5 Instructions
A. Provide operation instructions to District to insure complete understanding of operations. 304-6.6 Warranty
A. Provide the manufacturer's listed warranty for fence materials, finishes, and workmanship.
B. Contractor shall provide their own separate 1 year minimum warranty for installation.
304-6.7 Measurement and Payment
Fencing - The Contract Unit Price per linear foot for Fencing – Wire Mesh in place shall also be considered full compensation for furnishing and installing the fence posts, panels, rails, brackets, and earthwork, haul-off, and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in Wire mesh fencing , complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
Gates - The Contract Unit Price per each for Fencing – Wire Mesh Gate in place shall also be considered full compensation for furnishing and installing the gate posts, panels, rails, brackets, and earthwork, haul-off, and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in wire mesh metal gates, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
SECTION 315 – STORM DRAIN
315-3.4 Measurement. Storm Drain Pipe will be measured by linear foot . 190
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 52
315-3.5 Payment. Payment for Storm Drain pipe will be made at the Contract Unit Price per Linear Foot. The Contract Unit Price shall include all work required to install the pipe, base, subbase, fittings, connection to adjacent pipes, and all required appurtenances.
315-3.4 Measurement. Perforated Pipe will be measured by linear foot.
315-3.5 Payment. Payment for Perforated Pipe will be made at the Contract Unit Price per Linear foot for “PERFORATED PIPE” for each size. The Contract Unit Price shall include all work required to install the pipe, base, subbase, fittings, connection to adjacent pipes, and all required appurtenances.
SECTION 316 – PLAYGROUND SURFACING INSTALLATION
316-1 EXAMINATION
A. Playground equipment installer will perform playground layout prior to installation of footings; verify correctness of layout before starting this work.
B. Verify that playground equipment and site furnishings and irrigation system located within playground area are complete.
C. Verify location of underground utilities and facilities in the playground area. Damage to underground utilities and facilities will be repaired at Contractor's expense.
D. Verify that subgrades are at proper elevations and that smooth grading is complete.
E. Verify that proper depth of surfacing is marked on base supports of playground equipment. 316-2 PREPARATION
A. Correct subgrade irregularities to ensure that required depth of protective surfacing can be installed, and subgrade elevation is in accordance with manufacturer's requirements.
B. Inside Use Zones remove all obstructions that would extend into the resilient protective surfacing.
C. Remove rocks, debris, and other similar items.
D. Install containment curbs with top surface flush with intended elevation of top surface of protective surfacing.
316-3 SUBBASE
A. Install aggregate subbase as indicated on drawings and in Section 32 11 23. Compact aggregate to maximum 95 percent, in accordance with ASTM D1557.
B. Install with top surface of subbase no higher than grades and levels indicated and not more than 1/4 inch lower than grades and levels indicated.
C. Install in true, even plane, sloped to provide positive drainage.
D. Flatness Tolerance: 1/4 inch in 10 feet, maximum.
316-4 RESILIENT SURFACING LAYER
A. Install in accordance with CPSC Pub. No. 325, ASTM F1487, manufacturer's instructions, and requirements of authorities having jurisdiction (AHJ). 191
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 53
B. Install proper thickness throughout Use Zone(s).
C. Clean and dry surface of subbase.
D. Cover aggregate subbase with geotextile fabric:
1. Verify that aggregate is free of ruts or protruding objects.
2. Lap minimum 4 inches width at seams. Adhere seams in accordance with manufacturer's recommendations.
3. Install fabric smooth, and free of tensile stresses, folds, or wrinkles.
4. Protect fabric from clogging, tears, or other damage during surfacing installation.
5. Repair or replace damaged fabric in accordance with manufacturer's recommendations.
E. Poured In Place Surfacing:
1. Mix components mechanically on-site in accordance with manufacturer's directions; do not mix by hand.
2. Install seamlessly; ensure complete bond to subbase.
3. Cover footings and foundations and adhere tightly around penetrating elements.
4. Maintain full thickness of resilient layers within Use Zone; cover or abut containment curbs as indicated on drawings; completely cover tapered transition edges.
5. Hand trowel exposed surface to smooth, even finish.
6. Impact Attenuation Layer: Install entire layer in one continuous pour on the same day unless written City authorization is provided in advance of installation.
7. Wear Surface: Bond wear surface to substrate with adhesive. Apply adhesive in small quantities so that wear surface can be applied before adhesive dries. a. Install surfacing seamlessly. When wear surface is composed of different color patterns, pour surface continuously and seamlessly.
b. When seams are required due to color change or field conditions, place adjacent wear surface as soon as possible, before initial pour has cured. Coat edge of initial pour with adhesive and apply wear surface mixture immediately. c. Add a minimum of 1/16 inch depth to specified surfacing depth to ensure required impact attenuation performance is met.
d. Install wear surface to cover foundations and adhere tightly around elements penetrating the surface.
316-5 FIELD QUALITY CONTROL
A. Owner or Owner's representative will inspect playground surfacing after installation to verify that surfacing is of proper type and depth and that playground meets specified design safety and accessibility requirements.
B. Repair or replace rejected work until compliance is achieved. 316-6 CLEANING AND PROTECTION
A. Restore adjacent existing areas that have been damaged from the construction.
B. Clean playground equipment of construction materials, dirt, stains, filings, and blemishes due to shipment or installation. Clean in accordance with manufacturer's instructions, using cleaning agents as recommended by manufacturer.
C. Clean playground area of excess construction materials, debris, and waste.
D. Remove excess and waste material and dispose of off-site in accordance with requirements of authorities having jurisdiction.
E. Protect installed products until Date of Substantial Completion. 192
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 54
F. Replace damaged products before Date of Substantial Completion.
316-7 MEASUREMENT AND PAYMENT
The Contract Unit Price per square foot for Playground Surfacing installed in place shall be considered full compensation for furnishing and installing the sub-base, earthwork, haul-off, surfacing materials, and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in playground surfacing, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
SECTION 317 – PLAYGROUND EQUIPMENT INSTALLATION
317-1 VERIFICATION OF CONDITIONS
A. Verify that playground equipment footings have been installed in proper locations and at proper elevations.
B. Verify location of underground utilities and facilities in playground area; damage to underground utilities and facilities will be repaired at Contractor's expense. 317-2 PREPARATION
A. Stake location of playground elements, including Use Zone perimeters, perimeter of protective surfacing, access and egress points, hard surfaces, walls, fences, and structures, and planting locations.
B. Stake layout of entire Use Zone perimeter before starting any work and before subbase under resilient surfacing is laid.
1. Verify that Use Zone perimeters do not overlap hard surfaces, whether currently installed or not.
2. Verify that Use Zones are free of obstructions that would extend into resilient portion of protective surfacing.
3. If conflicts or obstructions exist, notify Landscape Architect.
4. Do not proceed until revised drawings have been provided, showing corrected layout, and obstructions have been removed.
317-3 INSTALLATION
A. Coordinate work with preparation for and installation of protective surfacing specified in Section 316; install resilient portion of protective surfacing after playground equipment installation.
B. Install in accordance with CPSC Pub. No. 325, ASTM F1487, manufacturer's instructions, and requirements of authorities having jurisdiction (AHJ).
C. Anchor equipment securely below bottom elevation of resilient surfacing layer.
D. Install without sharp points, edges or protrusions, entanglement hazards, pinch, crush, or shear points.
E. Do not modify play events on site without written approval of manufacturer.
F. Install required signage if not factory-installed.
193
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 55
317-4 FIELD QUALITY CONTROL
A. Owner or Owner's representative will inspect playground equipment after installation to verify that playground meets specified design safety and accessibility requirements.
B. Repair or replace rejected work until compliance is achieved. 317-5 CLEANING
A. Restore adjacent existing areas that have been damaged from the construction.
B. Clean playground equipment of construction materials, dirt, stains, filings, and blemishes due to shipment or installation; clean in accordance with manufacturer's instructions, using cleaning agents as recommended by manufacturer.
C. Clean playground area of excess construction materials, debris, and waste.
D. Remove excess and waste material and dispose of off-site in accordance with requirements of authorities having jurisdiction.
317-6 PROTECTION
A. Protect installed products until Date of Substantial Completion.
B. Replace damaged products before Date of Substantial Completion.
317-7 MEASUREMENT AND PAYMENT
The Contract Lump Sum Unit Price for Playground Equipment installed in place shall be considered full compensation for furnishing and installing the sub-base, earthwork, haul-off, concrete foundations, purchase and delivery of equipment and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in playground equipment, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
SECTION 318 – PRECAST CONCRETE UNIT PAVER INSTALLATION
318-1 EXECUTION
318-1.1 EXAMINATION
A. Verify that substrate is level or to correct gradient, smooth, capable of supporting pavers and imposed loads, and ready to receive work of this Section.
B. Verify gradients and elevations of substrate are correct.
C. Verify dry weather forecast without rain for a minimum of 24 hours with temperatures above 55 degrees Fahrenheit.
D. Verify that pavers are completely dry prior to polymeric sand installation.
318-1.2 PREPARATION
A. Treat soil with herbicide per County IPMP to retard plant growth.
318-1.3 INSTALLATION OF SOLID PAVER UNITS
A. Spread sand bedding evenly over prepared substrate surface to a maximum thickness of 1- 1/2 inch.
194
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 56
B. Dampen and roller compact sand to level and even surface.
C. Screed and scarify top 1 inch to 1 1/2 inch of sand.
D. Place paver units in herringbone pattern creating staggered joints, from straight reference edge.
E. Cut paver units at edges with masonry saw.
F. Place half units at edge and interruptions. Maintain tight joints.
G. Spread polymeric sand uniformly over surface. Use a push broom to fill joints and remove excess while not sweeping long distances. Sweep all excess with a fine bristle brush and remove residues with a leaf blower.
H. Tamp and level paver units with mechanical vibrator until units are firmly bedded, level, and to correct elevation and gradients. Do not tamp unrestrained edges.
I. Using a sprayer set to shower, apply water on specific areas between 100 square feet and 500 square feet to a depth of 1 1/2 inches. Complete one section at a time and avoid flooding the pavers.
318-1.4 CLEANING
A. Do not clean pavers until pavers and mortar are dry.
B. Clean soiled surfaces using cleaning solution. Do not harm pavers, joint materials, or adjacent surfaces.
C. Use non-metallic tools in cleaning operations.
D. Rinse surfaces with clean water.
E. Broom clean paving surfaces. Dispose of excess sand.
318-1.5 PROTECTION
A. Do not permit traffic over unprotected paver surface.
B. Protect paver surface with sheets of plywood.
318-2 MEASUREMENT AND PAYMENT
The Contract Square Foot Unit Price for Interlocking Concrete Pavers installed in place shall be considered full compensation for furnishing and installing the sub-base, earthwork, haul-off, pavers, sand, purchase and delivery of equipment and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in Interlocking Concrete Pavers, complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
PART 4 – EXISTING IMPROVEMENTS
SECTION 400 – PROTECTION AND RESTORATION
ADD the following:
Existing playground components shall be restored as follows:
a. Existing finishes, paints and coatings shall be restored in place where faded, scratched or damaged.
b. Missing brackets and fasteners shall be replaced
195
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 57
c. Notify the City of any existing damaged posts, platforms, and structures.
d. Maintain all manufacturer’s required fall zone protections
The playground will be certified by a certified playground inspector
SECTION 401 – REMOVAL
401-6 Measurement.
ADD the following:
Removal and salvage of existing sign to be measured by each such improvement.
Removal of existing playground surfacing will be measured by “square feet” and shall include removal of surfacing, base material and all related appurtenances as necessary to complete the work.
401-7 Payment.
ADD the following:
Payment for the removal of existing fencing will be made at the Contract unit price for “Demolish Existing Fencing”
Payment for the removal of existing fencing will be made at the Contract unit price for “Demolish Existing Walks”
Payment for the removal of bituminous pavement will be made in accordance with 300-2.9.
Payment for the removal and disposal of playground surfacing shall be made at the Contract Unit Price for "Demolish Existing Play Surfacing."
Payment for the removal, salvage, and transport of existing signs will be made at the Contract Unit Price for “Signage – Relocate Existing Signs”.
PART 8 – LANDSCAPE AND IRRIGATION
SECTION 800 – LANDSCAPE AND IRRIGATION MATERIALS
800-1.1.1 General . REVISE the first sentence to read: Topsoil for planter areas not designated as Bioswales shall be designated as Class B (selected). The Contractor shall perform fertility analysis testing as directed in 800-1.2.3. Topsoil for bioswale planter areas shall be Class “D” as indicated in 800.1.1.5.
ADD 800-1.1.5 Class “D” Topsoil. Biofiltration Planters
196
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 58
Class “D” Topsoil shall be similar to Class “A” Topsoil in that it shall be imported. Soil mix shall comprise of 60-70% sand meeting ASTM C-33 for fine aggregate, 30-40% high quality compost meeting the requirements below:
Compost for bioretention soils shall be analyzed be an accredited lab using #200, ¼ inch, ½ inch, and 1 inch sieves per ASTM D 422 or as approved by the City. The sieve analysis shall conform to the following:
SIEVE SIZE % PASSING BY WEIGHT MIN. MAX.
SAND:
3/8” 100 100
No. 4 90 100
No. 8 70 100
No. 16 40 95
No. 30 15 70
No. 40 5 55
No. 100 0 15
No. 200 0 5
COMPOST
1” 99 100
½” 90 100
¼” 40 90
No. 200 2 10
The materials shall be mechanically blended using a high-speed shredder apparatus and stored on a clean asphalt pad. The material shall be tested to prove infiltration rates greater than 5 inches per hour.
800-1.2.3 Commercial Fertilizers . ADD the following:
Commercial Fertilizers shall be delivered in sacks with the manufacturer’s label showing weight and analysis attached to each sack.
All commercial fertilizers shall comply with the County of Santa Barbara Integrated Pest Management Program (IPMP)
The following commercial fertilizer and soil preparation shall be for bid purposes only. Exact quantities and recommendations will be determined by a soil fertility and agricultural suitability test to be prepared by Soil and Plant Laboratory, Inc. (714) 282-8777 or approved equal testing facility.
Tests of at least two areas of the site shall be provided by the Contractor at no additional cost to the City and shall be included in the base bid. Test shall be performed after final grading has been completed and approved by the City. All areas to be landscaped with a slope of 3:1 or less shall be cross-ripped or otherwise tilled to a depth of 18 to 24 inches. Uniformly spread and cultivate amendments thoroughly by means of mechanical tiller into top 6” of soil in all planting areas.
Application rate per 1,000 square feet:
Commercial Fertilizer 6-20-20 25 pounds
197
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 59
Soil Sulphur 20 pounds
Granular Gypsum 100 pounds
Nitrogen stabilized sawdust (“Greenbook 2018” – Type I Organic Amendment) 6 CY
Planting Tablets: Provide slow-release type with potential acidity of not more than 5 percent by weight containing the following percents by weight of nutrients listed; 20-nitrogen, 10-phosphoric acid, 5-potash, 2.6 combined calcium, 1.6-combined sulphur 0.35-iron (elemental) from ferrous sulfate. Provide in 21 gram tablets manufactured by Agriform, or other approved.
Landscape areas with gradients greater than 3:1 shall receive a uniformity broadcast application of the following:
300 lbs/Acre Nitroform (38-0-0, WIN 27%)
600 lbs/Acre 6-20-20
800-1.2.4 Organic Soil Amendment. DELETE the first paragraph and REPLACE with the following:
Organic Soil amendment material shall conform to Type 1 unless otherwise designated. Delete paragraph references to Type 2 and Type 3 soil amendments.
800-1.2.5 Mulch. ADD the following:
Mulch materials shall be free of seed, debris, and deleterious materials as certified by the Supplier.
DELETE the first sentence of the first paragraph and REPLACE with the following:
For all non-bioswale planter areas, Contractor shall provide and apply pre composted bark mulch to match Jonny D. Wallis Park installation next door, or as approved.
For all bioswale planter areas, Contractor shall provide and apply a 3” layer of decomposed granite mulch loosely compacted. Contractor shall submit samples for approval prior to material delivery to the City in accordance with 2-5.3, Submittals.
ADD: 800-1.2.6 Soil Herbicide. Contractor shall provide and apply a commercially manufactured non-selective herbicide (“Prosecutor” or approved equal) for total control of vegetation products. The non-selective herbicide shall meet County of Santa Barbara IPMP requirements and all federal and state regulations pertaining to the use of such substances.
Application and rate of application shall follow manufacturer’s recommendation and written recommendation from a Pest Control Advisor.
Application shall not be made until obtaining written approval from the Engineer of the Contractor’s submittal for the non-selective herbicide, in accordance with Section 2-5.3, Submittals. Following City approval of Contractor herbicide, Contractor shall apply herbicide to all landscape areas. Such application shall be performed in consideration of overall construction schedule and operation so as not to disrupt or interfere with the project schedule and time line.
198
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 60
800-1.4 PLANTS.
800-1.4.1 General. ADD the following:
A. Trees, Plants, and Ground Cover: Species and size identifiable in plant schedule, grown in climatic conditions similar to those in locality of the Work.
1. Size:
a. Plants shall conform to measurements specified. Measure plants when branches are in their normal position. Height and spread dimensions specified refer to the main body of plant and not branch tip to tip. Take caliper measurements at a point on the trunk 6 inches above natural ground line for trees up to 4 inches in caliper, and at a point 12 inches above the natural ground line for trees over 4 inches in caliper.
b. The measurements specified are the measurements after pruning, where pruning is required. Plants that meet the measurements specified, but do not possess a normal balance between height, spread, and caliper, shall be rejected. c. Plants larger than specified may be used if approved by the Owner, and if provided at no additional cost to the Owner. If larger plants are approved, the root ball shall be increased in proportion to the size of the plant; irrigation system shall also be adjusted as required to accommodate larger plants.
B. Acclimatization: The General Contractor is responsible for supplying plant material that has been grown in a nursery within 25 miles of the project area. Any plants not locally sourced will be rejected unless authorized specifically by the City.
C. Coordination: The Contractor shall coordinate his acclimatization schedule with the Owner as to allow an adequate conditioning period for the plant material prior to the approved date of planting commencement. Notify the Owner in writing prior to proceeding with any acclimatization work if approved work schedule allows insufficient time to acclimate the material.
D. Quality: Plants shall be superior in form, compactness and symmetry; sound, healthy and vigorous, well branched and densely foliated when in leaf; free of disease, insect pests, eggs or larvae, and free from physical damage or adverse conditions that would prevent thriving growth. All plant material shall be reviewed and approved by the City’s authorized representative prior to installation. Rejected material shall be removed from site.
E. Species: Tag one of each plant prior to delivery to the site; label with genus, species and variety. Any plants not so identified will be subject to rejection by the Owner. Plants may be cross referenced with nurseries invoice at the discretion of the Architect.
F. Root Ball:
1. Do not supply any bare root or ball and burlapped stock unless approved by the City.
2. Sizes: As specified on the plans. Where no root ball dimensions have been specified, supply material in container sizes specified.
3. Material: Root ball shall consist of a soil or soil mix that is compatible with the soil or soil mix into which the plant will be planted, and that provides for thorough drainage, aeration, and adequate moisture and nutrient retention. Having sufficient density and firmness that when planted, the plant will stand upright and stable without need for additional support.
4. Containers: All plant material shall have been grown in the containers in which delivered for at least six months, but not over two years. Stock appearing to not have been in their containers for this term shall be rejected. 199
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 61
5. Root Pruning: Where root pruning is required to provide material of the specified size, or for planting in the sloped containers, the pruning is to be done under the direction of a Certified Arborist. No root pruning is to be done within one year of installation unless approved by the Owner.
G. Trunks and Branches: Do not prune plants before delivery. All trunks are to be straight and of uniform taper, larger at the bottom unless otherwise specified. Plants with damaged or crooked leaders, or multiple leaders, unless specified, will be rejected. Plants with abrasions of the bark, sun scalds, disfiguring knots, or fresh cuts of limbs over 3/4 inch, which have not completely callused, will be rejected. Any plant unable to stand upright without support will be rejected.
800-1.5 Headers, Stakes, and Ties.
800-1.5.3 Tree Stakes. DELETE the first paragraph and REPLACE with the following:
Tree stakes shall be sharpened 2" diameter, 10’ long lodgepole pine, treated in accordance with Section 204-2.2. Stake shall be one piece and free from splits. A minimum of two (2) supporting tree ties or three (3) guy anchors shall be used for each tree. Tree ties shall be V.I.T. twist brace Model TB24. Trees installed as 36” box and larger shall be installed with guy anchors (3/tree).
ADD: 212-1.5.5 Root Barriers. Root barriers shall be 36” deep and shall be DeepRoot Corp, (800) 458-7668, OAE. Installation shall occur in locations where trees are within 5 ft of hardscape as per manufacturer’s recommendations.
800-2 IRRIGATION SYSTEM MATERIALS.
ADD: 800-2.0 General. Materials shall be installed as per manufacturer’s recommendations unless specified otherwise in the Contract Documents. Contractor shall immediately notify Engineer upon discovery of any discrepancies between manufacturer recommendations and the Contract Documents.
800-2.1 Pipe and Fittings.
800-2.1.3 Plastic Pipe for Use with Solvent Weld Socket or Threaded Fittings. DELETE the second paragraph and REPLACE with the following:
PVC Class 315 PVC with solvent welded joints for pressure main pipes 2 to 2-1/2” inches.
PVC schedule 40 with solvent welded joints for pressure main piping smaller than 2 inch diameter.
PVC schedule 40 solvent welded piping shall be used for all non-pressure lateral line piping.
PVC used with recycled water shall be purple in color, PVC used with domestic water shall be white in color.
200
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 62
ADD the following:
All PVC pipe must bear the following markings:
1. Manufacturer's name
2. Nominal pipe size
3. Schedule or class
4. Pressure rating in P.S.I.
5. NSF (National Sanitation Foundation) approval
6. Date extrusion
7. U.P.C. shield logo (IAPMO approval)
All fittings shall bear the manufacturer's name or trademark, material designation, size, applicable I.P.S. schedule and NSF seal of approval
Solvent cement and primer for PVC solvent-weld pipe and fittings shall be of the type recommended by the pipe manufacturer and shall be installed according to the instructions by the manufacturer.
800-2.2 Valves and Valve Boxes.
800-2.2.2 Gate Valves. DELETE and REPLACE with the following:
Valves shall be as identified in the Construction Documents and are subject to City review and approval.
800-2.2.4 Remote Control Valves. ADD the following:
Remote control valve manufacturer sizes shall be as per the Drawings. Remote control valve manufacturer shall be as indicated on the Drawings, OAE.
800-2.2.6 Quick-Coupling Valves and Assemblies. DELETE and REPLACE with the following:
Quick-coupling valves shall have a brass two-piece body designed for working pressure of 150 PSI.
The quick-coupling valve shall have a built-in flow control and self-closing valve and shall be supplied in 1-inch (19) size unless otherwise required. The valve shall be equipped with a locking yellow vinyl cover when used with domestic water and a purple locking cover when used with recycled water.
800-2.2.7 Valve Boxes. DELETE the first paragraph and REPLACE with the following:
201
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 63
Valve boxes and lids shall be as detailed on the Plans. The boxes shall be covered with an etched polyethylene face with an ultraviolet inhibitor. The lid shall be plastic, lockable, and embossed with the controller and valve station number on its topside. Sizes and manufacturer of the valve boxes and lids shall be as indicated on the Standard Drawings, OAE.
Valve boxes used with recycled water shall be purple in color. Boxes used with domestic water shall be green in color.
ADD: 800-2.2.8 Master Control Valves. Master control valve sizes shall be as indicated on the Drawings; manufacturer shall be as indicated on the Drawings OAE.
800-2.3 Backflow Preventer Assembly. ADD the following:
Backflow assemblies shall consist of a brass reduced pressure/backflow prevention device with “Wye” strainer and 60 mesh screen as detailed and called out on the Project Plans, unless otherwise required by Ventura water district.
800-2.4 Sprinkler Equipment. DELETE and REPLACE with the following:
Irrigation bodies and nozzles shall be as indicated on the Drawings. Substitutions shall not be allowed unless by written authorization from the Engineer.
Irrigation bodies and nozzles shall feature low head drainage, pressure regulating, and pressure compensating features. Unless otherwise approved, all pop-ups and fixed riser assemblies shall consist of plastic and stainless steel materials.
Smaller radii turf irrigation equipment shall consist of 6-inch pop-ups. All smaller radii shrub and groundcover irrigation equipment shall consist of 12-inch pop-ups, unless otherwise approved by the City. Smaller radii equipment are those components which irrigate within and under a radius of 22 feet.
ADD: 800-2.5 Drip Tubing. Drip tubing shall be as indicated on the Drawings. Substitutions shall not be allowed unless by written authorization from the Engineer.
ADD: 800-2.6 Master Valve. The assembly shall be as indicated on the Drawings.
Substitutions shall not be allowed unless by written authorization from the Engineer.
800-3 ELECTRICAL MATERIALS.
800-3.2.1 Conduit. DELETE and replace with the following:
Conduit shall be Schedule 80 PVC installed per the Drawings. Conduit shall conform to the applicable provisions of Section 800-2.1.3.
202
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 64
800-3.2.2 Conductors. ADD the following:
The electrical system shall be installed in accordance with the National Electrical Code most recently adopted by the City. Connections between the automatic controllers and the electric control valves shall be made with direct burial copper wire AWG-U.F. 600 volt. Pilot wires shall be a different color wire for each automatic controller. Common wires shall be white #12 (min.) with a different color stripe for each automatic controller. Install in accordance with valve manufacture's specifications and wire chart. In no case shall wire size be less than #14.
Wiring shall occupy the same trench and shall be installed along the same route as pressure supply or lateral lines wherever possible. Install wires inside Schedule 40 Conduit anywhere it is not possible to place in pipe trench, or where wires must go under pavement. Conduit size shall be large enough to contain all necessary wires. Minimum conduit size shall be 2”.
Where more than one (1) wire is placed in a trench, the wiring shall be taped together at intervals of ten (10) feet.
An expansion curl should be provided within three (3) feet of each wire connection and at least every one hundred (100) feet of wire length on runs more than one hundred (100) feet in length and also at each change of direction. Expansion curls shall be formed by wrapping at least five (5) ruins of wire around a one-inch diameter pipe, then withdrawing the pipe.
All splices shall be made with Spears DS100 wire connector, or approved equal. Use one splice per connector sealing pack.
Field splices between the automatic controller and electrical control valves will not be allowed without prior approval of the City.
800-3.3 Controls. ADD the following:
Irrigation controller shall operate from a solar power array as indicated on the plans. No site power is available for the controller. Controller shall be housed in a vandal resistant pedestal enclosure as approved by the City.
All irrigation valves serving landscaping shall be connected to the irrigation controller and shall function automatically based on a City approved watering schedule.
All automatic valves controlling hose bibs within the community garden shall be installed on the irrigation controller as well. The valve(s) shall be set on a schedule to allow water during garden hours of operation as determined by the City.
SECTION 801 – LANDSCAPE AND IRRIGATION INSTALLATION
ADD 801-0 INSPECTION FOR LANDSCAPE AND IRRIGATION.
203
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 65
Inspection will be required for the following parts of the work:
a. At completion of rough grade prior to incorporation of soil amendments.
b. Irrigation coverage test prior to initiating planting operations.
c. At completion of incorporation of soil amendments and fine grading.
d. Prior to digging plant pits for trees and shrubs.
e. During backfilling of plant pits with amended backfill.
f. Maintenance period shall not begin until final installation inspection is made, and establishment is verified. City inspector shall approve commencement date of maintenance prior to the commencement of said maintenance.
g. Final review and acceptance at the end of the maintenance period.
801-1 GENERAL. Last paragraph, DELETE in its entirety and SUBSTITUTE with the following:
Work on the irrigation system including hydrostatic tests, backfill and densification of trenches, and other excavations shall be performed before amendments are incorporated into the soil. Preliminary operational tests of the automatic control system and coverage tests shall be performed after soil amendments are incorporated.
Trees or shrubs which have been identified to remain in place as shown on the Plans shall be protected. Construction fencing minimum 5’ high shall be placed around the drip line of the tree or cluster of trees to protect the entire area. No material shall be stored nor shall equipment be permitted within the fenced area. No pruning of the tree canopy shall be permitted without written recommendation of a certified arborist submitted and approved by the Engineer. The Contractor shall be responsible for compliance with the requirements in the City of Ventura. No digging or excavation shall occur under the drip line of the tree unless authorized by the Engineer. Failure to properly protect the identified trees may result in charges against the Contractor’s account based on the assessed value of the tree and other damages once valued by a certified arborist.
801-2 EARTHWORK AND TOPSOIL PLACEMENT.
801-2.1 General. ADD the following:
The Contractor shall apply water as necessary to provide ideal moisture content for tilling and for planting as herein specified.
801-2.2 Trench Excavation and Backfill. DELETE the second and last paragraphs and ADD the following:
The depth of cover over pipelines and conduits shall be per Drawings.
204
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 66
The trenches shall not be backfilled until all required tests are performed. A fine granular material used for bedding and backfill will be placed on all lines. Trenches shall be carefully backfilled with the excavated materials approved for backfilling, consisting of earth, loam, sandy clay, sand, or other approved materials, free from large clods of earth or stones.
The finished surface shall be restored to the grade established prior to excavation. All mounding and divots shall be graded smooth to the satisfaction of the Engineer.
If settlement occurs, and subsequent adjustments in pipe, valves, valve/utility boxes, sprinkler heads, lawn or planting, or other construction are necessary, the Contractor shall make all required adjustments.
ADD 801-2.2.1 Trenching and Backfilling Under Paving. Where irrigation lines are required as per the Drawings to be placed within a sleeve, the sleeve shall be Schedule 40 PVC.
ADD 801-2.2.2 Trenching Adjacent to Existing Trees. Where it is necessary to excavate adjacent to existing trees, the Contractor shall use all possible care to avoid injury to trees and tree roots. Excavation in areas where two (2) inch and larger roots occur shall be done by hand. All roots two (2) inches and larger in diameter, except directly in the path of pipe or conduit, shall be tunneled under and shall be heavily wrapped with burlap, to prevent scarring or excessive drying. Where a ditching machine is run close to trees having roots smaller than two (2) inches in diameter the wall of the trench adjacent to the tree shall be hand trimmed, making clean cuts through. Trenches adjacent to trees should be closed within twenty-four (24) hours; and where this is not possible, the side of the trench adjacent to the free shall be kept shaded with burlap or canvas.
801-2.3 Topsoil Preparation and Conditioning.
801-2.3.2 Fertilizing and Conditioning Procedures. DELETE the first paragraph and REPLACE it with the following:
The planting areas shall be brought to rough grade whereupon Fertilizer and Soil Conditioning required for the native soils for the intended landscape planting shall be added based upon the recommendations of Soils Fertility and Agricultural Suitability Report. (See Section 212) The Contractor, at no additional cost to the City, shall make two additional soils tests for agricultural fertility and suitability and fertilizer and amendment recommendations of all planting areas upon completion of excavation, topsoil backfilling, and grading. The Contractor shall amend it as necessary to comply with the soils test report at no additional cost to the City.
ADD 801-2.3.3 Weed Control. Contractor shall be responsible to kill and remove all existing weeds from site areas utilizing post-emergent herbicide.
Upon completion of the irrigation system and after all designated shrub and ground covers, existing weeds and growth have been removed from the planting areas. All areas shall be watered four (4) times daily until weed seeds have germinated for approximately 21 days or unless otherwise directed by the Engineer. Thereafter, watering shall cease for three (3) days to be followed by the spraying of a systemic herbicide containing the active ingredient glyphosate (Prosecutor, or approved equal).
Spraying shall be at the labeled rate compatible with the eradication rate for the target weed species and shall be performed following the written recommendation from a registered pest control advisor. After allowing sufficient time for the herbicide to kill all remaining weeds (2 weeks 205
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 67
minimum), the areas to be landscaped shall be raked or hoed as directed by the Engineer to remove any remaining weed debris. All areas shall be watered for an additional 14 (fourteen) day period and then receive an additional application of the systemic herbicide per manufacturer’s recommendation and the written recommendation of the Pest Control Advisor.
801-2.4 Finish Grading. Last paragraph, second sentence, DELETE in its entirety and SUBSTITUE with the following:
After the soil has dried out to a workable condition, the planting areas shall be regraded, raked, and smoothed to the required grades and contours. Topsoil shall be mechanically compacted to a minimum relative compaction of 85 percent.
ADD the following:
Except as noted for specimen planting, all planting installation shall take place after the completion of the finish grading and installation of the irrigation system.
Finish grades shall be those indicated on the drawings or as may be controlled by existing installations. Grades not otherwise indicated shall be uniform, and straight graded between points where elevations are noted. Minor modeling of the ground surface may be required. Landscape areas to receive turf shall be rolled with a water drum in a north/south and then east/west direction.
Low spots and high spots in the terrain shall be backfilled and tamped or bladed and spread. The resultant grade shall be smoothly, evenly contoured and compacted to 85%. The gradient shall be as noted on plans.
Grading shall provide for the natural run-off of water without low spots or pockets. Flow lines shall be set by instrument and shall be the maximum gradient possible.
801-2.5 Planter Beds. ADD the following:
Provide imported topsoil for all new planter beds. Fill beds to within 1” of top of bed. Submit fertility analysis of import material for approval. Soil shall be suitable for edibles and flowers.
801-2.5.1 Measurement and Payment. ADD the following:
The Contract Unit Price Per EACH for Raised Garden Beds installed in place shall be considered full compensation for purchasing and fabricating the garden beds per manufacturer instructions and the plans provided, including all equipment and furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in raised garden beds , complete in place, as shown on the Plans, and as specified in the Standard Specifications and these Special Provisions, and as directed by the Engineer
801-3 HEADER INSTALLATION.
ADD 801-3.1 Planter Curb Installation.
Concrete Mow Curbs shall be constructed where shown on the Plans and Specifications. All concrete work shall conform to the requirements of the Contract Documents and the Standard Specifications. 206
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 68
Metal Headers shall be 4” wide x 16 gauge minimum thickness of cor ten steel or as otherwise approved. Stake the header at 18” O.C. Spacing with 12” galv stakes. Additional stakes may be required to provide adequate support for plan layout.
801-4 PLANTING.
801-4.2 Protection and Storage. ADD the following:
Sun sensitive plants, stolons, and stacked or pallet sod shall be stored in the shade or screened from the sun.
801-4.3 Layout and Plant Location. ADD the following:
Quantities for shrubs and groundcovers shown on the legend are for estimate purposes only. Final quantities for plant materials installed shall be governed by the indicated plant spacing. Quantities for trees shall be verified in bid documents and discrepancies between the planting plans and the bid schedule shall be noted on bid schedule by Contractor at the time of bid submittal.
In the event that designated plant location is found in conflict with underground utility or structure during the planting operation an alternate location will be selected by the City. The Contractor shall be responsible to notify utility companies for the spotting of underground facilities prior to plant delivery and to make precautionary potholes where conflicts would be indicated on the plans or by field notations by utility representatives. The cost for utility notification and potholing shall be included in the other work items and no additional compensation will be allowed therefore.
Proposed tree locations, as indicated on plans shall be staked by contractor for review and approval by the City prior to digging of plant pits for planting. Stakes shall minimum of 6’ in length and color coded to indicate variety of proposed tree planting at each of the staked locations. Review and approval of provided color-coded stake locations, with modifications/adjustments as necessary shall be provided by city prior to commencement of tree planting operations.
Container shrubs and groundcovers shall be placed on finish grade at locations indicated on planting plans for review and approval prior to planting. Contractor shall notify City 48 hours prior to scheduled review of containerized shrubs and groundcovers on grade
801-4.4 Specimen Planting.
ADD 801-4.4.1 Specimen Tree Planting.
Tablets shall be installed per the County of Santa Barbara’s IPMP. Set the tablets to be used with each plant on the top of the root ball while the plants are still in their containers so the required number of tablets to be used in each hole can be easily verified.
• tablets per 15 gallon
• tablets per 24 inch box
• tablets per 30 inch box
• tablets per 36 inch box
• tablets per 42 inch box
207
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 69
• tablets per 48 inch and larger boxes
801-4.5 Tree and Shrub Planting. First sentence, DELETE in its entirety and SUBSTITUTE with the following:
a. The Contractor shall amend backfill as necessary per the soils test report at no additional cost to the City. (Refer to Sections 212 and 308-2.3.2). The following soil amendments and fertilizer guidelines shall be used for bid purposes only. Fill holes with backfill mixtures as specified below:
b. The planting pits for trees shall be excavated twice the diameter and the depth of the rootball.
c. The following material shall be thoroughly blended and used as a backfill mix in the surface 12” around trees and shrubs, and the backfill soil, 12” below finish grade should be amended if specified by the soil test report with only gypsum and / or iron sulfate. No mixing for individual planting holes will be permitted. Mix planting soil prior to backfilling and stockpile at the site. The iron sulfate should not contact cement surfaces since severe staining could occur.
• 8 parts by volume screened on-site soil
• 2 parts by volume Nitrogen Stabilized Organic Amendment • 1 ½ lbs. Iron Sulfate per cu. yd. of mix
• 1 lb. 12-12-12 per cu. yd. of mix
• 5 lb. gypsum per cu. yd. of mix
d. Place plants near respective pits. Set the tablets to be used with each plant on the top of the root ball while the plants are still in their containers so the required number of tablets to be used in each hole can be easily verified.
• 1 tablet per 1-gallon container
• 2 tablets per 5-gallon container
• 3 tablets per 15-gallon container
e. Remove all plants from their containers and set in plant pits.
f. Fill to proper height with amended backfill to receive the plant and thoroughly tamp the mixture before setting the plant.
g. Set plant in upright position in the center of the hole and compact the backfill mixture around the ball or roots.
h. Thoroughly water each plant when the hole is one-half filled. After water has completely drained, place planting tablets per detail. The remainder of the hole shall then be backfilled.
i. After watering, tamp the soil in place until the surface of the backfill is level with the surrounding area and the crown of the plant is at the finished grade of the surrounding area. Do not backfill around trunks or stems.
208
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 70
j. After backfilling, an earthen basin shall be constructed around each plant. Each basin shall be of a depth sufficient to hold at least six inches of water. Basins shall be the same size as the container size of each individual plant. The basins shall be constructed of amended backfill material.
k. Immediately after planting, apply water to each tree and shrub by means of a hose. Apply water in a moderate stream in the planting hole until the material about the roots is completely saturated from the bottom of the hole to the top of the ground.
l. Apply water in sufficient quantities and as often as seasonal conditions require to keep the planted areas moist at all times, wet below the root system of trees, turf, and plants. Generally, water once each day for 7 days in cool seasons, for 14 days in hot weather. Berms around shrubs and trees in slopes shall be maintained for 60 days following tree planting and then removed.
m. Pruning - Pruning shall be limited to the minimum necessary to remove injured twigs and branches and to compensate for loss of roots during transplanting, but never to exceed one-third of the branching structure. Upon approval of the City Representative, pruning may be done before delivery of plants but not before plants have been inspected and approved by the City.
n. No trees shall be planted within 6 feet of paved surfaces, unless specifically indicated on plans.
Those trees noted on plans to occur within 6’ of curbs and/or paving shall receive continuous root barriers per Section 212-1.5.5.
o. Upon completion of planting, Contractor to provide a digitized GPS Map indicating the site- specific location of all newly planted trees within the project area. Digital file shall numerically identify all trees with a legend including Botanical and common names. Upon request by the Contractor, the City shall provide AutoCAD file of project base map for Contractors use in preparing this information.
801-4.5 Plant Staking and Guying. DELETE entirety of the subsection and REPLACE with the following:
All staking and guying shall be in accordance with the Drawings and Contract Documents.
801-4.6 Ground Cover and Vine Planting. DELETE the second paragraph and REPLACE with the following:
Ground cover shall be planted in moist soil and spaced as indicated on the Drawings.
801-4.7 EROSION CONTROL PLANTING
1. Seed, mulch and other specified materials shall be applied on slopes by Method B specified in section 801-4.8.2 of the standard specifications.
Seed Mix shall be native seed locally obtained and suitable for riparian environment.
Seed specified in in pounds pure live seed per acre. PLS LBS/ACRE does not equal LBS/Acre. PLS LBS/ACRE is the most accurate way to specify seeds and takes into account both purity and germination. PLS % = % Purity X % Germination. Seed mix shall contain seed produced in California Only. Seed source shall be from S & S Seeds, 209
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 71
Carpentaria (805-684-0436) or approved local source. Measure and mix individual seed species in the presence of the Engineer before applying seed.
The Contractor shall include the following materials as part of the Hydroseeding Slurry:
• Promatrix BFM 2,000 - 3,500 lbs./acre
• Hydropost Premium Compost 1,000 lbs./acre
• Biosol Forte 7-2-1 Organic fertilizer 800 lbs./acre
• AM 120 Mycorrhizal inoculum 60 lbs./acre
• Tri-C Soluble Humate 1 lb./acre
• Seed mix as prescribed by S & S Seeds
Water shall be free of substances harmful to seed growth.
Before applying erosion control measures, verify that finished grades meet the requirements for grade, compaction and finish.
Apply erosion control materials within 24 hours after the final preparation of the erosion control areas. Do not apply hydraulically applied materials under the following conditions:
1. Precipitation
2. Water is standing on or moving across the soil surface
3. Soil is frozen
4. Air temperature is below 40 degrees F during the tackifier curing period unless allowed by the tackifier manufacturer and authorized.
Protect the traveled way, sidewalks, existing vegetation, and San Jose Creek from overspray of hydraulically-applied material. Contractor shall prevent runoff of hydroseed materials from entering into the creek.
Hydromulch and Hydroseed
Apply hyrdomulch with hydraulic spray equipment that mixes fiber, tackifier, fertilizer, and other erosion control materials specified. If applying hydroseed, add seed to hydromulch. Seed may be dry applied to small areas not accessible by hydroseeding equipment if authorized by Engineer.
Add water to hydromulch and hydroseed materials as recommended by the manufacturer and mix sufficiently to ensure an even application.
Equipment must utilize a built-in continuous agitation and discharge system capable of producing a homogeneous mixture and uniform application rate. Begin application within 60 minutes of adding seed to the tank. Apply in successive passes as necessary to achieve the required application rate. Apply all hydromulch or hydroseed materials indicated for a single area within 72 hours. After the final application, do not allow pedestrians or equipment onto the treated areas.
Replace first paragraph of 801-4.9.5 “Watering” with the following:
All seeded and planted areas, including Erosion Control (Hydroseed) areas, shall be kept moist during the plant establishment and/or germination period. Water must be of a quality that promotes germination of seeds and growth of plants.
210
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 72
801-5 IRRIGATION SYSTEM INSTALLATION.
801-5.1 General. ADD the following after paragraph three:
The installation of the irrigation system shall be in accordance with the manufacturer’s instructions unless specified otherwise.
Contractor shall be responsible to notify the City prior to start of construction to coordinate on-site inspections.
Due to the scale of drawings, it is not possible to indicate all offsets, fittings, sleeves, etc., which may be required. The Contractor shall carefully investigate the structural and finished conditions affecting all of his work and plan his work accordingly, furnishing such fittings, etc., as may be required to meet such conditions.
The work shall be installed in such a manner as to avoid conflicts between planting and architectural features, etc.
All work called for in the drawings by notes or details shall be furnished and installed by the contractor whether or not specifically mentioned in the Specifications.
The Contractor shall not willfully install the irrigation system as shown on the Drawings when it is obvious in the field that unknown obstructions, grade differences, or discrepancies in area dimensions exist that might not have been considered in engineering. Such obstructions or differences should be brought to the attention of the Engineer. In the event this notification is not performed, the Irrigation Contractor shall assume full responsibility for any revisions necessary and shall perform such at his own expense.
DELETE the fourth paragraph and REPLACE with the following:
The location of the City’s existing water meter shown is approximate. The Contractor shall do exploration work to verify tie-in location in the field. The Contractor shall contact the utility companies and coordinate the installation of the required electrical and water services. Following coordination with the utility companies, the Contractor shall make all necessary provisions to make the service connections called for on the Drawings at the places indicated or to the nearest acceptable point thereto as approved by the utility companies and the Engineer. Verification of the point of connections with the utility companies and the Engineer shall be obtained by the Contractor prior to the start of work.
ADD the following:
Temporary Repairs. The City reserves the right to make temporary repairs as necessary to keep the irrigation system in operating condition. The exercise of this right by the City shall not relieve the Contractor of his responsibilities under the terms of the guarantee as herein specified.
801-5.3 Irrigation Pipeline Installation.
211
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 73
801-5.3.1 General. ADD the following:
A minimum of twelve (12) inches clearance shall be maintained between “recycled” irrigation pipelines and non-irrigation pipelines/conduits.
PVC Sleeves shall be required under areas where all hardscape materials shall be installed. Sleeving shall be done per detail on Project Plans (Minimum sleeve dimension shall be twice the diameter of pipe size.
801-5.3.3 Plastic Pipeline.
ADD the following:
PVC to metal connections shall only be accomplished by PVC male adapters screwed into metal fittings. Teflon tape shall be used on all threaded PVC to PVC, and on all threaded PVC to metal joints.
Handling of PVC Pipe and Fittings. The Contractor is cautioned to exercise care in handling, loading, unloading, and storing of PVC pipe and fittings. All PVC pipe are to lie flat and not to be subjected to undue bending or concentrated external load at any point. Any section of pipe that has been dented or damaged will be discarded and, if installed, shall be replaced with new piping. Pipe and fittings shall not be stored in direct sunlight.
801-5.4 Installation of Valves, Valve Boxes, and Special Equipment . DELETE paragraphs three, four, five, and six.
801-5.5 Sprinkler Head Installation and Adjustment.
801-5.5.1 General. ADD the following:
Mains and laterals, including risers, shall be flushed and pressure tested before installing swing joints and sprinkler heads, after which a water coverage test shall be performed.
801-5.5.2 Location, Elevation, and Spacing. AMEND the third paragraph to read as follows:
Sprinkler heads shall be installed 6 inches from the adjacent vertical elements projecting above grade such as walls, planter boxes, curbs, and fences in shrub areas. Sprinkler heads shall be installed 24 inches from adjacent vertical elements projecting above grade such as walkways where drainage moves away from the landscape area.
801-5.6 Automatic Control System Installation. DELETE the first sentence of the fourth paragraph and REPLACE with:
All service wiring shall be installed at the minimum depth specified in 308-2.2 in electrical PVC conduit from the service point to the controller.
All valve wires shall be unique colors. No two colors shall match.
801-5.7 Flushing and Testing.
212
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 74
801-5.7.1 General. ADD the following to the beginning of the subsection:
Flushing of the lines shall be done before quick coupling valves and remote control valves are in place. All open ends shall be piped (temporarily to exhaust flushing water up and out of the trenches.)
No water will be permitted to fall into the trench. Flushing procedure will be to first open the ports nearest the source, then recap, and move progressively towards the end of the line, with only one open port flushing at any one time.
ADD the following paragraphs to the end of the subsection:
When the irrigation system is completed, a coverage test shall be performed by City to determine if the water coverage for planting areas is complete, adequate, and avoids overspray onto walks, roadways, and buildings as much as possible. The Contractor shall furnish all materials and perform all work required to correct any inadequacies of coverage due to deviations from the Drawings, or where the system has been willfully installed as indicated on the Drawings when it is obviously inadequate, without bringing this to the attention of the City inspector. This test shall be accomplished before any ground cover is planted.
The Contractor shall request the presence of the City in writing at least forty-eight (48) hours in advance of testing. The Contractor shall flush and adjust all sprinkler heads for optimum performance and to prevent overspray onto walks, roadways, and buildings as much as possible.
801-5.7.2 Pipeline Pressure Test. Testing shall be performed under Method A. AMEND the constant test pressure and the duration of the test as follows:
• Mains: 6 hours at 150 PSI
• Laterals: 2 hours at 100 PSI
801-6 MAINTENANCE AND PLANT ESTABLISHMENT. First paragraph, ADD the following:
Maintenance shall be performed weekly or as directed by the Engineer and include irrigation inspection and repair, Site cleanup, pruning of groundcover, shrubs, and trees, mowing, weed control, fertilization every 6 weeks, pest and fungi control, plant replacement, and mulch replenishment.
Fourth paragraph, DELETE in its entirety and SUBSTITUTE with the following:
After all planting and related work has been completed in accordance with the Contract Documents; the Contractor shall request a pre-maintenance inspection from the Engineer. The Punchlist items shall be completed prior to the start of the Plant Establishment Period (PEP).
Fifth paragraph, DELETE in its entirety and SUBSTITUTE with the following:
After planting is completed, a field notification will be issued to the Contractor to establish the effective beginning date of the PEP. The PEP shall be for a period of 120 days for ornamental shrubs, trees and ground covers. A follow-up walk shall be scheduled on or near the 60 th day into the PEP to
review plants and identify plants needing replacement. PEP may be extended by the Engineer if the 213
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 75
planted areas are improperly maintained, appreciable plant replacement is required, or other corrective work becomes necessary. Unhealthy plant materials shall be replaced within 2 weeks from the Engineer’s notification. For temporarily irrigated native plantings, the acceptance of the PEP by the Engineer shall begin the 90-day plant maintenance period, unless otherwise specified.
The Contractor shall be responsible for detecting diseases and pests (including rabbits, gophers, groundhogs, rodents) as soon as they are present and shall take immediate action to identify, control, and remove the disease or pest within the job-site. Pest control programs of all mammals shall be done without extermination and as approved by the City’s Authorized Representative. Plants shall be maintained in a disease and pest free condition. A licensed pest control operator shall be maintained to recommend and apply pesticide, herbicides, and fungicides. Contractor shall be responsible for removal of gophers and moles from site and repair any and all damage attributed to their presence. Damaged plant material due to vertebrate pests (rabbits, gophers, groundhogs, etc.) shall be replaced immediately by Contractor at no cost to City. Dead dying and damaged plant material shall be removed at no cost to the City.
Maintain all planting starting with the planting operations and continuing for 90 calendar days after all planting is complete and the Plant Establishment Period ending has been approved by the City in writing. The maintenance period will not commence until all planting has been approved in writing by the City.
Maintenance shall include, but not be limited to, all watering, irrigation repair, weeding, mowing, edging, cultivating, spraying, and pruning necessary to keep the plant materials in a healthy growing condition and to keep the planted areas neat and attractive throughout the maintenance period.
The Contractor will be relieved from maintenance work when the plant establishment and maintenance work has been completed to the satisfaction of the City.
The costs for the maintenance period shall include all costs for water (from the new water meter installed only), watering, irrigation repair, weeding, mowing, edging, cultivating, spraying, and pruning necessary to keep the plant materials in a healthy growing condition and to keep the plant areas neat and attractive throughout the maintenance period, and shall be included in the costs for installation of the plant material.
The Contractor shall:
a. Provide all equipment and means for proper application of water to those planted areas not equipped with an irrigation system.
b. Protect all planted areas against damage, including erosion and trespassing, by providing and maintaining proper safeguards.
c. During the maintenance period, all plants and planted areas shall be kept properly watered and weed-free at all times. Irrigation schedule shall comply with AB325 and Certified Irrigation Auditor’s parameters.
d. In order to expedite the plant establishment work, the Contractor shall maintain a sufficient number of workers and adequate equipment to perform the work herein specified from the time any planting is done until the end of the final maintenance period. 214
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 76
e. Damage to planting areas shall be replaced immediately when seen by Contractor.
Damage observed by the City shall be replaced within 24 hours of notification to the Contractor.
f. Depressions caused by vehicles, bicycles, or foot traffic, are to be filled and leveled.
Replant damaged areas.
g. Apply a pelletized fertilizer blend of 15-15-15 at the beginning and at every 30-day maintenance interval at the rate 350 lbs. per acre until the designated end of the maintenance period. A 90-day maintenance program shall consist of three fertilizer periods.
h. Apply 25 lbs Gro-Power Plus (OAE) per 1,000 square feet at 25th and 55th day of 90 day maintenance period. All applications shall be in accordance with the County’s IPMP programs
i. Contractor shall be responsible for removal of rodents, slugs, snails, and cutworms from site as required and repair damage as above.
j. All paved areas will be broom cleaned and/or washed and maintained in a neat and clean condition at all times, as directed by the City. AQMD and WQMP practices shall be observed. Air blowers shall not be allowed.
k. During the maintenance period, should the appearance of any plant indicate weakness and probability of dying, immediately replace that plant with a new and healthy plant of the same type and size without additional cost to the City. At the end of the maintenance period, all plant material shall be in a healthy growing condition.
l. All trees shall be guaranteed by the Contractor to live and grow in an acceptable upright position for a period of one year after completion and final acceptance by the City.
m. The Contractor, within ten (10) days of notification by the City, shall remove and replace all guaranteed plant materials which for any reason fail to meet the requirements of the guarantee. Replacement shall be made with plant materials as indicated or specified for the original planting, and all such replacement materials shall be guaranteed as specified for the original guaranteed materials.
ADD 801-6.1 Charts, Manuals, and Drawings.
801-6.1.1 As-Built Drawings.
Contractor shall provide the Engineer with Landscape Architect signed “as-built” heavy weight drafting film originals of all project construction document plans, reflecting all “as-built” conditions for all project elements and two (2) sets of edge bound plots at the completion of the project at no additional cost to the City.
Contractor shall provide two (2) sets of surveyed electronic files in CAD and PDF format. One (1) set shall be delivered to the City for permanent recordkeeping purposes. 215
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 77
Contractor shall dimension from two (2) permanent points of reference, building corners, sidewalk or road intersections, etc., the location of the following items:
1. Gate valves
2. Sprinkler control valves
3. Routing of control wiring
4. Rain gauge
5. Quick coupling valves
6. Point of connection components (meters, backflow preventors, etc.)
7. Other related equipment as directed by the City
8. Significant changes in routing of lateral lines from those indicated on the plans
On or before the date of the final inspection, the Contractor shall deliver the corrected and completed design documents to the City. Delivery of the final heavy weight drafting film will not relieve the Contractor of the responsibility of furnishing required information that maybe omitted from the prints.
801-6.1.2 Controller Charts.
As-built drawings shall be approved by the City before the Contractor prepares the controller charts.
Contractor shall provide two (2) controller charts for each controller supplied.
The chart shall show the area controlled by the automatic controller and shall be the maximum size which the controller door will allow.
The chart is to be a reduced drawing of the actual “as-built” system. However, in the event the controlled sequence is not legible when the drawing is reduced, it shall be enlarged to a size that will be readable when reduced.
The chart shall be on an 11x17 print and a different color shall be used to indicate the area of coverage for each station.
When completed and approved, the Contractor shall hermetically seal the chart between two pieces of plastic, each piece being a minimum of 10 mils thick.
These charts shall be completed and approved prior to final inspection of the irrigation system.
801-6.1.3 Manuals of All Equipment and Certificate of Substantial Completion.
216
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 78
Contractor shall prepare and deliver to the City within ten calendar days after substantial completion of the project, three hard cover binders with three rings containing the following information:
a. Index sheet stating Contractor's and subcontractor’s license numbers, address, and telephone number and list of equipment with name and address of al local supplier’s and manufacturer's representatives.
b. Catalog and specification ‘cut’ sheets materials for all hardscape and softscape and equipment installed under this contract.
c. Guarantee statement. The guarantee for the sprinkler irrigation system shall be made in accordance with the enclosed form. The Contractor shall file a complete copy of all substantial completion forms and irrigation guarantee prior to the acceptance of project by the City. The guarantee shall be included in the operations and maintenance manual of all equipment throughout the park. The guarantee shall be typed onto the Contractor’s letterhead.
d. Complete operating and maintenance instructions on all major equipment.
In addition to the above mentioned maintenance manuals, provide the City's maintenance personnel with instructions for major equipment and show evidence in writing to the City at the conclusion of the project that this service has been rendered.
ADD 801-6.2 Equipment.
801-6.2.1 Loose Equipment to be Furnished.
The Contractor shall supply as a part of this contract the following tools:
1. One (1) quick coupler key and matching hose swivel for every five (5) of each type of quick coupling valve installed.
2. Two (2) keys each for controller and controller enclosure doors.
The above-mentioned equipment shall be turned over to the City at the conclusion of the project.
Before final inspection can occur, evidence that the City has received material must be shown to the City Representative.
801-7 PAYMENT.
The payment for the irrigation system and all appurtenant installations indicated on the drawings and described in these specifications shall be included as part of the Lump Sum Contract Price in the Proposal Bid Form.
The payment for maintenance of the work per the drawings and the specifications shall be included in the price for Landscape – Maintenance Period. No further payment will be provided.
217
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 79
The payment for the planting and installation of trees, shrubs, and ground cover shall be included in the prices for the various plant items. The cost of soil amendments, fertilizing and soil conditioning, weed control, and finish grading shall be included in the price for the various plant items.
ADD 801-8 GUARANTEE.
The guarantee period shall begin upon written notice by City of substantial compliance with plans and specifications have been achieved by Contractor.
Upon acceptance, all construction shall be guaranteed by the Contractor for a period of one year against defects in materials and workmanship.
Any settling of backfill trenches which may occur during the one year guarantee period shall be backfilled, compacted, and transitioned smoothly with adjacent gradients to the City's satisfaction by the Contractor without expense to the City, including the complete restoration of damaged planting, paving, or other improvements of any kind.
The Contractor, within ten (10) days of notification by the City Representative, shall remove and replace all guaranteed plant materials which, for any reason, fail to meet the requirements of the guarantee. Replacement shall be made with plant materials as indicated or specified for the original planting and all such replacement materials shall be guaranteed as specified for the original guaranteed materials.
801-8.1 Guarantee Certificate for Irrigation System.
GUARANTEE FOR IRRIGATION SYSTEM
We hereby guarantee that the irrigation system we have furnished and installed is free from defects in materials and workmanship, and the work has been completed in accordance with the drawings and specifications, ordinary wear and tear, and unusual abuse, or neglect accepted. We agree to repair or replace any defects in material or workmanship, including settling of backfilled areas below grade which may develop during the period of one year from date of acceptance and also to repair or replace any damage resulting from the repairing or replacing of such defects at no additional cost to the City. We shall make such repairs or replacements within 72 hours after receipt of written notice.
In the event of our failure to make such repairs upon written notice from the City, we authorize the City to proceed to have said repairs or replacements made at our expense and we will pay the costs and charge therefore upon demand.
PROJECT: Armitos Community Garden
LOCATION: Armitos Drive
AGENCY: City of Goleta
CONTRACTOR SIGNATURE: _____________________________
ADDRESS: _____________________________
PHONE: _____________________________
218
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 80
DATE OF ACCEPTANCE: _____________________________
SECTION 901 – LOW WATER CROSSING
901-1 GENERAL
A. Includes:
1. Construction of Low Water Crossing improvements as shown on the plans.
2. 1’x6’ openings with concrete backfill
3. ¼”x18” metal plate with approved non-slip surface
4. 2” long anchor bolt welded to bottom of plate (2 feet on center – both sides)
5. Galvanize after fabrication and assembly
6. As approved by the Engineer
B. Greenbook Related Sections:
1. Section 201 – Concrete Mortar and Related Materials Section 206 – Miscellaneous Metal Items
2. Section 211 – Soils and Aggregate Tests Section 300 – Earthwork
3. Section 301–Treated Soil, Subgrade Preparation and Placement of Base Material
4. Section 303 – Concrete and Masonry Construction
B. PAYMENT
Payment for Low Water Crossing will be made by the contract lump sum price, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in constructing low water crossing, complete in place, and no additional compensation will be made.
SECTION 902 – REMOVABLE BOLLARD
902-1 GENERAL
A. SECTION INCLUDES:
1. Construction of Removable Bollards.
2. Bollard Model #B-3 As Manufactured by Fairweather Site Furnishings and Accessories, Port Orchard Washington, 1-800-323-798 or Equal approved by the Engineer.
3. Install Bollards Per Manufacturers Recommendations and as shown on the plans.
4. Concrete Footing.
5. Gravel for Drain.
B. GREENBOOK RELATED SECTIONS:
1. SECTION 201 – Concrete Mortar And Related Materials
2. SECTION 206 – Miscellaneous Metal Items
3. SECTION 300 – Earthwork
219
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 81
4. SECTION 301–Treated Soil, Subgrade Preparation And Placement Of Base Material
5. SECTION 303 – Concrete And Masonry Construction
C. PAYMENT
Payment for removable bollard will be made by the contract unit price per each, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing bollard, complete in place, and no additional compensation will be made.
SECTION 903 – SLOPE PROTECTION
A. Section Includes:
1. Specifications for constructing rock slope protection (RSP).
2. Use the class of rock and the method for placement described.
B. GREENBOOK RELATED SECTIONS:
1. Section 200 – Rock Materials
3. Section 300 – Earthwork
4. Section 301–Treated Soil, Subgrade Preparation And Placement Of Base Material
C. MATERIALS
1. General
unless otherwise specified, fabric must be class 8 rsp fabric.
2. Rock
For method a and b placement and the class of rsp described, comply with the rock gradation shown in the following table:
Rock Gradation
Nominal RSP class
by median particle
diameterb
Nominal
median
particle
weight
W50c,d
d15c (inches)
d50c (inches) d100c
(inches)
Placement
Classa
Diameter
(inches) Min Max Min Max Max Method
I 6 20 lb 3.7 5.2 5.7 6.9 12.0 B
II 9 60 lb 5.5 7.8 8.5 10.5 18.0 B
III 12 150 lb 7.3 10.5 11.5 14.0 24.0 B
IV 15 300 lb 9.2 13.0 14.5 17.5 30.0 B
V 18 1/4 ton 11.0 15.5 17.0 20.5 36.0 B
VI 21 3/8 ton 13.0 18.5 20.0 24.0 42.0 A or B
VII 24 1/2 ton 14.5 21.0 23.0 27.5 48.0 A or B
VIII 30 1 ton 18.5 26.0 28.5 34.5 48.0 A or B
IX 36 2 ton 22.0 31.5 34.0 41.5 52.8 A
X 42 3 ton 25.5 36.5 40.0 48.5 60.5 A
XI 46 4 ton 28.0 39.4 43.7 53.1 66.6 A
aFor RSP Classes I–VIII, use Class 8 RSP fabric. For RSP Classes IX–XI, use Class 10 RSP fabric. bIntermediate or B dimension (i.e., width) where A dimension is length and C dimension is thickness. cd%, where % denotes the percentage of the total weight of the graded material. 220
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 82
dValues shown are based on the minimum and maximum particle diameters shown and an average specific gravity of 2.65. Weight will vary based on specific gravity of rock available for the project.
Rock material must comply with the requirements show n in the following table:
Rock Material Requirements
Quality characteristic Test method Requirement
Apparent specific gravity
(min)
California Test
206
2.5 Absorption (max, %) California Test
206
4.2 Durability index (min) California Test
229
52 Notes:
Durability absorption ratio (DAR) = course durability index/(percent absorption + 1)
If the DAR is greater than 10, the absorption may exceed 4.2 percent.
If the DAR is greater than 24, the durability index may be less than 52.
Select rock such that the shapes provide a stable st ructure for the required section. If the slope is steeper than 2:1, do not use rounded boulders and cobbles. Angular shaped rock may be used on any planned slope. Flat or needle-shaped rock must not be used unless the individual rock thickness is greater than 0.33 times the length.
3. Fabric
Fabric must be RSP fabric that complies with the class shown in the following table:
Fabric Class
Class Largest rock gradation class used in slope protection 8 Classes I–VIII
10 Classes IX–XI
F. CONSTRUCTION
GENERAL
Excavate the footing trench along the toe of the slope.
Local surface irregularities of the RSP must not vary from the planned slope by more than 1 foot as measured at right angles to the slope.
At the completion of slope protection work, fill voids in the footing trench with excavated material.
Compaction is not required.
PLACEMENT METHOD A
Do not place rocks by dumping.
Place larger rocks in the footing trench.
Place rocks on the slope such that their longitudinal axis is normal to the face of the embankment.
Place foundation course rocks such that they are in contact with the ground surface.
For rocks above the foundation course, place them such that each rock has a 3-point bearing on underlying rocks; do not bear them on smaller rocks which may be used for chinking voids.
PLACEMENT METHOD B
221
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 83
Rocks may be placed by dumping and may be spread in layers by bulldozers or other suitable equipment.
Place rocks such that:
a. There is a minimum of voids
b. Larger rocks are in the toe course and on the outside surface of the slope protection
Earthwork must comply with section 300 of the standard specifications.
If placement of fabric is required, place the fabric before placing slope protection, slope paving, and gabions.
Before placing the fabric, the surface of the slope must be free of loose or extraneous material and sharp objects that may damage the fabric.
Handle and place the fabric under manufacturer's instructions. Place the fabric loosely on the slope such that it conforms to the surface without damage to the fabric when the cover material is placed.
Join the edges of the fabric with either overlapped joints or stitched seams.
If the fabric is joined with overlapped joints, the adjacent borders of the fabric must be overlapped by at least 24 inches. Overlap in the same direction that the cover material is placed.
If the fabric is joined by stitched seams, stitch with contrasting colored yarn. Use the size and composition of yarn that is recommended by the fabric manufacturer. Use 5 to 7 stitches per inch of seam. The strength of a stitched seam must be the same as that specified for the fabric, except if the stitched seams are oriented up and down a slope, the strength may be reduced to a value that it is at least 80 percent of that specified for the fabric.
Do not operate equipment or drive vehicles directly on the fabric.
If the fabric is damaged and the Engineer determines that it cannot be repaired, replace the fabric.
If the Engineer determines that the fabric can be repaired, then repair it by covering the damaged area with new fabric. If the repair is made using overlapped joints, the overlap must be at least 3 feet.
3. Rock Slope Protection Fabric
RSP fabric must be a permeable, nonwoven, needle-punched geotextile. The fabric must be manufactured from one of the following:
1. Polyester
2. Polypropylene
3. Combined polyester and polypropylene
Polymers must be either virgin compounds or clean reworked material. Do not subject virgin compounds to use or processing other than required for initial manufacture. Clean reworked material must be previously processed material from the processor's own production that has been reground, pelletized, or solvated. The fabric must not contain more than 20 percent of clean reworked material by weight. Do not use recycled materials from either post-consumer or post- industrial sources.
RSP fabric must comply with the requirements shown in the following table:
RSP Fabric
Quality characteristic Test method Requirement
Class 8 Class 10
222
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 84
Mass,(min, oz/sq yd) ASTM D5261 7.5 9.5
Grab breaking load, 1 inch grip in each direction, (min, lb) ASTM D4632 200 250 Apparent elongation in each direction, (min, percent) ASTM D4632 50 50 Permittivity, (min, sec-1) ASTM D4491 1.0 0.70
Apparent opening size, (min and max, US Standard sieve
size) ASTM D4751 70–100 70–100
UV resistance, retained grab breaking load, 500 hours, (min, percent) ASTM D4355 70 70
PAYMENT
If RSP is paid by the ton, the payment quantity is the weight determined from scale weighings.
If RSP is paid by the cubic yard, the payment quantity is the volume determined from the dimensions shown or ordered.
Payment for rock slope protection fabric is not included in the payment for rock slope protection. Rock slope protection fabric is paid by the square yard.
Payment for RSP and RSP fabric shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing RSP and fabric, complete in place, and no additional compensation will be made.
The City does not pay for additional fabric used for overlaps.
SECTION 904 – BARRICADES
A. Section Includes:
1. Specifications for placing barricades.
2. Barricades must comply with the California MUTCD.
B. General
Barricades must be placed where shown on the plans or as approved by the Engineer.
Wood members must be either Redwood or Douglas Fir. Douglas Fir must be treated with a wood preservative in conformance with the State Specifications.
A fully reflectorized sign, as shown on plans, must be placed on the barricade with bolts, nuts, and washers, and must face oncoming traffic to designate dead end streets. All barricades must be painted white, with 2 applications of a latex base paint formulated for use on exterior wood.
C. Payment
Payment for barricade will be made at the contract unit per each, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing barricades, complete in place, and no additional compensation will be made.
SECTION 905 – ROADSIDE SIGNS
A. Section Includes:
1. specifications for constructing roadside signs.
2. Roadside signs include Type N (CA), Type P (CA), and Type R (CA) marker panels.
3. Signs and markers must comply with the California MUTCD. 223
Armitos Park Improvements, Community Garden, & San Jose Creek Multi-Purpose Path
SECTION H: Technical Specifications Page 85
B. GREENBOOK RELATED SECTIONS:
1. Section 206 – Miscellaneous Metal Items
2. Section 210 - Paint And Protective Coatings
2. Section 304 – Metal Fabrication And Construction
C. QUALITY ASSURANCE
When delivered to the job site, treated posts must comply with the specified grading requirements and have a moisture content of not more than 25 percent when tested under ASTM D4444 with an authorized moisture meter.
D. MATERIALS
GENERAL
A roadside sign includes sign panels, fastening hardware, back braces, straps and saddle brackets, and frame assemblies for multiple sign panels.
METAL POSTS
A mounting for a roadside sign to be installed on a barrier or railing must be fabricated from (1) welded or seamless steel pipe complying with ASTM A53/A53M, Grade B, and (2) structural steel complying with ASTM A36/A36M.
Bolted connections and concrete anchorage devices must comply with the standard specifications.
Footing concrete must comply with the standard specifications.
After fabrication, all metal parts for mounting a roadside sign must be galvanized.
WOOD POSTS
A wood post must be the allowable grade and species for the sizes shown in the following table:
Nominal post sizea Allowable grades and species
4 by 4 inches
Select heart redwood
No. 1 heart structural redwood, 1050f
No. 2 heart structural redwood, 900f
No. 1 structural light framing Douglas fir, free of heart center No. 1 structural light framing Hem-Fir, free of heart center No. 1 structural light framing Southern yellow pine, free of heart center
4 by 6 inches
Select heart grade redwood
Select heart structural grade redwood, 1100f
No. 1 heart structural redwood, 950f
No. 2 structural joists and planks, Douglas fir, free of heart center No. 1 structural joists and planks Hem-Fir, free of heart center No. 2 structural joists and planks Southern yellow pine
Greater than 4 by 6 inches
Select heart redwood
No. 1 heart structural redwood, 950f
No. 1 posts and timbers, also known as no. 1 structural, Douglas fir, free of heart center
Select structural posts and timbers Hem-Fir, free of heart center; and no. 1 timbers Southern yellow pine, free of heart center
aSizes shown are minimum dressed dry sizes
The posts must be graded per the standard specificat ions. The sweep must not exceed
0.08 foot in 10 feet.
When tested under ASTM D4444 with an authorized moisture meter, the moisture content of Douglas fir, Hem-Fir, and Southern yellow pine posts 224
must be not more than 25 percent in the outer 1 inch at the post's midpoint before preservative treatment.
Douglas fir and Hem-Fir posts must be treated per the standard specifications and under AWPA U1, Use Category UC4A, Commodity Specification A. Posts must be incised, and the minimum retention of preservative must comply with AWPA requirements.
SIGN PANEL FASTENING AND MOUNTING HARDWARE
Frame assemblies for multiple sign installations must be fabricated from an aluminum alloy or structural steel complying with ASTM A36/A36M. Frames fabricated from structural steel must be hot-dip galvanized after fabrication.
Back braces for a sign must be made of commercial-quality, mild steel and hot- dip galvanized after fabrication.
Straps and saddle brackets for mounting sign panels on lighting standards, sign structure posts, and traffic signal standards must be stainless steel complying with ASTM A167, Type 302B. Theft-proof bolts must be stainless steel with a chromium content of at least 17 percent and a nickel content of at least 8 percent.
Bolts, except theft-proof bolts, lag screws, metal washers, and nuts must be made of commercial-quality steel and hot-dip galvanized after fabrication.
Fiber washers must be commercial quality.
Galvanizing must comply with the standard specifications.
CONSTRUCTION
1. General
You may cut the ends of wood posts at the job site. If cutting or boring is performed after treating posts with preservative, manually apply preservative to the cuts and holes per the standard specifications.
Treat wood block spacers inserted between the post and sign panel on single-post installations with wood preservative per the standard specifications.
If you do not immediately use laminated wood box posts, neatly stack them on dunnage. Do not paint wood posts and block spacers unless described otherwise.
Drill 2 holes in each wood post to provide the breakaway feature shown.
Make breakaway saw cuts and holes for the saw cuts in laminated wood box posts after installation of the posts. Do not splice the posts. You may make 1 trim cut at the bottom of the post.
The line between the center of the top of a post and the center of the post at ground level must not deviate from a plumb line by more than 0.02 foot in 10 feet.
Backfill the space around wood posts with earth or sand that is free of rocks or other deleterious material. Backfill around laminated wood box posts with granular material.
Place the backfill material in layers approximately 1/3 foot thick. Moisten and thoroughly compact each layer.
225
Backfill the space around metal posts with minor concrete that contains at least 470 pounds of cementitious material per cubic yard.
Unless surplus excavated material is hazardous, uniformly spread it along the adjacent roadway where designated by the Engineer.
2. Sign Panel Installation
Install lag screws by turning the lag screw into pilot holes using a wrench. Bore the pilot holes with a bit diameter equal to the root diameter of the lag screw thread.
Apply PVC tape, polyethylene tape, or other authorized corrosion-resistant barrier to the areas on metal sign surfaces or hardware that will be in contact with treated wood. Before inserting bolts, fill the bolt holes with the hardware manufacturer's recommended corrosion-protection grease that will not melt or run at a temperature of 150 degrees F. The corrosion-resistant barrier and grease is not required if wood posts and blocks are treated with pentachlorophenol in hydrocarbon solvent.
PAYMENT
An installed roadside sign consisting of one or more sign panels attached to:
1. 1 post is 1 measurement unit of roadside sign - one post
2. 2 posts is 1 measurement unit of roadside sign - two post
3. 1 or 2 laminated wood box posts is 1 measurement unit of install roadside sign (laminated wood box post)
Payment for roadside sign will be made at the contract unit price for each, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing sign, complete in place, and no additional compensation will be made.
Payment for furnishing sign panels is not included in the payment for roadside signs.
Payment for furnishing sign panel will be made at the contract unit price per square- foot, and no additional compensation will be made.
Payment for object marker will be made at the contract unit price for each, and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in furnishing and installing object marker, complete in place, and no additional compensation will be made.
226