Agenda Item C.3

DISCUSSION/ACTION ITEM
Meeting Date: December 6, 2022

TO: Mayor and Councilmembers

FROM: Peter Imhof, Planning and Enviro nmental Review Director

CONTACT: Dana Murray, Sustainability Manager
Angeline Foshay, Sustainability Management Assistant

SUBJECT: Approval of the City Ha ll Electric Vehicle Charging Infrastructure and SCE Charge Ready Project, Finding the Project to be Categorically Exempt from CEQA under Guideline Sections 15311 and 15304, and Direction to Staff to File Notice of Exemption

RECOMMENDATION:

A. Authorize participation in the Southern California Edis on Charge Ready program and authorize the City Manager to sign the Participation Agreement;

B. Find the work performed under the Partic ipation Agreement is exempt from the California Environmental Quality Act (CEQA) under CEQA Guideline Sections 15311 and 15304 and direct staff to file a Notice of Exemption;

C. Approve a budget appropriation amount of $50,000 from the General Fund Unassigned Balance for an Electric Vehicl e Supply Equipment vendor to install 17 Electric Vehicle Supply Equipment charging ports as part of a “turn-key” package; and

D. Authorize staff to apply for $12,325 in incentives through the SCE Charge Ready Program and seek additional funding opportunities to reduce project costs.

BACKGROUND:

Investing in the development and installati on of electric vehicle (EV) charging infrastructure is identified in the City’s budget priorities and Strategic Plan as a means of supporting environmental vitality and supporting the City’s transition to a clean energy future. Additionally, ‘Electrical Vehicle Readiness Planning’ is a top priority in the City’s adopted Planning & Environmental Review Department’s Annual Work Program for FY 22/23. The City Council adopted an Electric Vehicle Charging Station Permit Streamlining Ordinance in April 2020.

1 Meeting Date: December 6, 2022

Page 2 of 8 ends

In September 2020, Governor Newsom issued an executive or der requiring sales of all new passenger vehicles to be zero-emissi on by 2035 and additi onal measures to eliminate harmful emissions fr om the transportation sector. Transportation accounts for just over half of the greenhouse gas (GHG) em issions in Santa Barbara County. One of the key strategies to reducing emissions and meeting the ambitious climate goals of the State is encouraging the us e of EVs and expanding EV charging infrastructure. The executive order directs the California Air Resources Board (CARB), California Energy Commission (CEC), California Public Utilities Commission (CPUC), other State agencies, and local agencies to accelerate deployment of affordable fueling and charging options for zero-emission vehicles (ZEVs) in ways that serve all communities, and specifically in low income and disadvantaged communities.

California has a statewide goal to install 250,000 EV chargers to support 1.5 million ZEVs by 2025 and infrastructure to support 5 mill ion ZEVs by 2030. Based on information provided by the Santa Barbara County Air Po llution Control District, the CEC estimates that jurisdictions within Santa Barbara County will need to support an additional 10,333 EVs by 2025. Supporting that number of EVs by 2025 requires significant investment in public Level 2 EV chargers, which are characterized by a 208-240 Volt, 40 Amp circuit and can deliver on average 7.6 kW of power. CEC’s estimated projection of the number of public Level 2 EV charging stations needed to support the 2025 ZEV goal is 972 chargers in Santa Barbara County. The to tal number of public Level 2 EV charging stations in the County as of January 31, 2022, is 328, leaving an EV charging station gap of 644 to meet CEC’s 2025 ZEV projection over the next few years.

To help achieve EV goals and in acknowledgement of the existing gaps in local EV charging infrastructure, over the last year Sustainability Program staff has been pursuing various funding opportunities to offset the costs of installing EV charging stations at City facilities. Staff has submitted applications to the Southern California Edison (SCE) Charge Ready Program, the CEC’s CALeVIP Program, the VW Light Duty EV Infrastructure Program, and the Santa Barbara County Air Pollution Control District’s Clean Air Grants Infrastructure Program. Additionally, EV-capable conduits have been installed as part of the solar photovoltaic project at City Hall to allow for easy installation of at least three dual port EV chargers providing six public EV spaces. Of the programs applied to, the City was selected to participate in SCE’s Charge Ready Program.

SCE’s Charge Ready Program assists property owners, including local jurisdictions, with deploying the infrastructure and equipment nec essary to support EV charging stations.

Specifically designed for li ght-duty passenger vehicles, t he program helps cities by providing financial incentives, infrastructu re, and technical support to facilitate the installation and maintenance of EV chargers . The Charge Ready Program is a “make ready” program, in which SCE provides progr am-funded infrastructure upgrades (e.g., underground conduit, wiring and stub-outs needed to install EV chargers), as well as an incentive for the purchase of new EV charging stations. Once enrolled in Charge Ready, the City is responsible for the purchase and installation of the EV charging stations, to be selected from SCE’s approved product list. The terms of the program include an easement for the installation of electrical equipment, SCE access to EV charger use data, and EV charger participation in SCE’s future demand response events. These “demand 2 Meeting Date: December 6, 2022

Page 3 of 8 ends

response events” essentially scale back charging when the need and cost of energy is high during peak demand hours and are part of local grid resiliency efforts. Additionally, the City would be responsible for maintenance, operation and networking of all installed chargers for a minimum of 10 years to ensure equipment is in good working order.

During the February, March, and October 2022 Green Committee meetings, staff solicited feedback on the proposed conceptual desi gn and EVSE features. The Committee and key City staff reviewed SCE’s conc eptual design and recommended pursuing participation in SCE’s Charge Ready Program. In February and Marc h, staff presented an option to increase the number of charging ports in the conceptual design from 12 to 17, with the Committee recommending 17 EV ports that would extend further east along the southern stretch of parki ng spaces outside of City Hall. Key discussion points centered on the number of c hargers proposed and a potentia l increase in ports, the inclusion of a cable retractors, ADA cons iderations, and the proposed location of the project. At the October 2022 Green Co mmittee meeting, the Committee again recommended proceeding with par ticipation in the SCE C harge Ready Program and expressed support for allocating $65,000 towards the project.

DISCUSSION:

The City of Goleta has been selected as a pot ential participant in SCE’s Charge Ready Program for the Goleta City Hall site, whic h will provide ‘make ready’ EV infrastructure and EV equipment rebate support for the installation of 17 EV chargers at City Hall. Staff recommends that the City pr oceed in the Charge Ready pr ogram process by approving the Participation Agreement for 17 Level 2 EV charging stations at City Hall and allocating an additional $50,000 in funds for the purchase and installation of charging equipment (in addition to the $15,000 already allocated). SCE’s ‘make ready’ work includes but is not limited to: all the electrical work up to the stub-out, pedestals, bollards, 600 amp panel, ADA signs, installation of ADA pathway, landscape moving, painting and restriping, trenching, and asphalt work. The estimated in-kind value of SCE’s work for the City is about $250,000, which the City woul d be receiving for free for participating in the SCE Charge Ready program. In addition to the ‘make ready’ electrical work and infrastructure being free to the City, the City will receive a rebate incentive of $725 per charging port, totaling $12,325, from SCE once EV stations are installed. The Charge Ready program has no restrictions on the use of EVSE, so chargers may be used for future City electric fleet vehicles, employees, and the public as determined by the City. SCE’s determination of location does not preclude t he City from pursuing installa tion of EV chargers in other locations around City Hall.

SCE Charge Ready Program Process & Conceptual Design

Immediately after the launch of the current SCE Charge Ready Program in August 2021, the City submitted program applications to SCE requesting multiple sites for consideration for EV charging infrastructure. After conducting site visits, SCE notified the City in November 2021 that the Goleta City Hall site had been selected by SCE as the location approved for the program’s EV Charging Infrastructure and Re bate offering. SCE then began developing a conceptual design plan for the City. 3 Meeting Date: December 6, 2022

Page 4 of 8 ends

In December 2021, SCE presented a conceptual design plan to staff. The initial site plan proposed EV infrastructure installation on the south side of City Hall to accommodate six dual-port Level-2 chargers, totaling 12 EV spaces. The initial conceptual design included one ADA-compliant, van-accessible EVSE par king space and one standard accessible, unreserved EVSE parking space in compliance with the California Building Code (Table 11B-228.3.2.1). Charger location s were identified primarily fo r proximity to an existing transformer as well as ease of improving AD A EV access, which is required to ensure accessible pathways from the ADA EV spaces to the building. The conceptual design meets SCE’s cost-effectiveness feasibility criteria for the project.

On February 24 and March 21, 2022, the Cit y’s Energy & Green Issues Standing Committee reviewed SCE’s conceptual design and recommended pursuing participation in SCE’s Charge Ready Program as well as increasing the number of charging ports in the conceptual design from 12 to 17 EV ports that would extend further east along the southern stretch of parking spaces outside of City Hall. The updated conceptual design with the increased port count was received in early July 2022 for staff analysis and review (Attachment 1). The conceptual design has been reviewed by staff and the City has provided feedback to SCE from the City’s Planning, Public Works, General Services, and Neighborhood Services Departm ents as well as the City Manager’s Office. Staff also sought feedback from the City’s Energy & Green Issues Standing Committee.

Key elements of the updated conceptual design include infrastructure to accommodate 8 dual port and 1 single port EV charger (17 EV spaces total), the installation of a 200-amp service meter, the installation of a 600-amp distribution subpanel, and an ADA accessible pathway to the south entranc e of City Hall. Anticipated im pacts from the project are expected to be minimal, with minor vegetation removal for the installation of the pathway.

Along the drive aisle and proposed projec t area, the anticipated restriping to accommodate ADA improvements and EVSE equipment will result in a loss of 7 parking stalls across the 24 that currently exist. This loss of parking will not br ing City Hall out of compliance with parking minimum requirement s for government build ings pursuant to Title 17, as there are an ample number of spaces for parking onsite.

The increase in ports in the conceptual design from 12 to 17 will help the City maximize project cost efficiencies and increase EV infr astructure at City Hall while meeting the necessary ADA improvements for providing EV charging. The City’s Building Department has confirmed that one van accessible and one standard accessible EV charging station spaces are required when 5 to 25 EV charging stations are provided on a site.

EVSE Vendors and Cost Estimates

While SCE is responsible for all the ‘mak e-ready' electrical infrastructure and ADA improvements, the City is responsible for the purchase and installation of EVSE connecting to this electrical infrastructure as well as the netwo rking, operations and maintenance for the 10-year program period. Upon rece iving the updated conceptual design, the City solicited informal proposals from vendors and conducted multiple site visits with EVSE vendors on SCE’s approved product list. Staff then used the information 4 Meeting Date: December 6, 2022

Page 5 of 8 ends

gathered from this informal process to identify the estimated cost for the project for the City, as well as used the information to help staff develop a thorough and detailed Request for Proposals (RFP). Staff issued the RFP on September 30, 2022 with a closing date of November 6, 2022. The City received eight proposals from EVSE vendors, which are currently under review and contract negotiation.

During the March 2022 Green Committee meeting, staff presented the potential upfront and ongoing costs at the time for the proposed EVSE from SCE’s initial conceptual design. This financial analysis was drawn fr om a proposal from a single vendor, who applied on the City’s behalf for CALeVIP funds for the City Hall site to supplement any potential charging project. Following this initial assessment and the March Green Committee meeting, a few factors have impact ed the cost of the EV charging stations, charger networking, and maintenance. The primary factor is the requested increase in the number of stations - from 12 to 17 - which ultimately increases the purchasing price of EVSE and the ongoing networking and maintenance costs. Additionally, the initial proposal received from the vendor did not include details and estimates regarding shipping, installation, and potential operations and maintenance warranties necessary to keep the stations in compliance SCE’s Charge Ready program.

Upon further research in discussing operations and maintenance with other jurisdictions, EV charging stations are prone to service disruption and need regul ar maintenance. In evaluating vendors, staff considered more comprehensive options for operations, maintenance, and warranties for EVSE that woul d ensure consistent operation. Staff included this provision in the RFP. Another factor driving up costs of EVSE is inflation, with the Consumer Price Index rising by nearly 4% since March 2022. Since receiving the updated conceptual design, staff’s initial outreach to vendors to receive informal proposals on the project for evaluation has rev ealed an increase in costs and a suite of networking, operations, and maintenance options that will ultimately impact the final costs of any EVSE project.

While estimates vary on the brand and the capacit y of the chargers, t he cost of Level 2 EV charging equipment ranges from $1,550 to $2,400 per port, with the total for 17 ports averaging close to $35,550. The cost of networking EVSE averages around $260 per port and $4,400 per year for the to tal number of proposed chargers. Some vendors offer the option of waiving networking fees in exchange for Low Carbon Fuel Standard credits and operations and maintenance models that handle the upkeep of EVSE in the event of service disruption. Staff is currently revi ewing eight proposals fr om vendors through an RFP process and are evaluating the diffe rent operations and maintenance package approaches, while keeping in mind reliability, co st, and service. Should the City Council approve participating in SCE Charge Ready, st aff is requesting a budget allocation of $50,000 from the General Fund Unassigned Balance for the purchase and installation of 17 EVSE, in addition to the $15,000 already approved earlier in 2022. This request has changed since the Committee meeting in March from 12 ports to 17 ports, and from about $30,000 to about $65,000. The Green Committee re-affirmed their support for participation in the SCE Charge Ready program and recommended that Council approve the budget allocation request at the Oct ober 2022 meeting. Following Program Participation signing, the City has 45 days to demonstrate the proof of purchase of EVSE. 5 Meeting Date: December 6, 2022

Page 6 of 8 ends

Next Steps, Timing, & Additional Funding

For the City to proceed with the SCE Charge Ready program, staff requests that City Council approve the Program Pa rticipation Agreement (Attachment 1). The City’s legal team has reviewed the Agreement and notes that participation does add some risk to the City in that it requires the City to waive any claims associated with the quality and safety of the products associated with the Charging Equipment as well as the workmanship of third parties used by SCE to install the Charging Equipment. SCE makes no warranties regarding the merchantability and fitness for any particular purpose, use or application of the products and services under the Program. In other words, if the Charging Equipment fails and causes injury to the City or another third party who then files a claim against the City, the City could not look to SCE for com pensation. However, knowing that SCE has installed similar facilities in other cities and counties, staff is not aware of any injuries associated with these facilities. This SCE Agreement is the same for all cities and counties participating in the SCE Charge Ready program. Given this record, the low risk of injury associated with the Charging Equipment, and the benefits of the Charge Ready program, staff recommends that Council approve the Program Participation Agreement.

Following City Council approval and signing of the Participat ion Agreement by both parties, the City is required to provide proof of purchase for all vehicle charging equipment designated for the project within 45 calendar days of the date funds are reserved. Staff is timing the RFP process to sele ct a vendor for the project concurrent with bringing this item before City Council, so the City can be prepared to complete a purchase order for the EV charging equipment wit hin 45 days of Council’s Participation Agreement authorization.

The approximate timeline according to SCE Charge Ready staff once they receive our purchase order for the EV charger s is 9 to 12 months for c onstruction to be complete.

During this time, SCE will complete the detailed design work, prepare and deliver easements for the City’s signature, secure any necessary permits, procure materials, and manage the construction of the make-ready infrastructure work. After SCE’s construction is complete, the City will then move forwar d with installing the EV charging equipment.

When the EV chargers have been installed, the City will provid e documentation and verification of completed work to SCE. Once the work is verified, SCE will process rebate payments. The City estimates rebate payments from SCE to be $12,325, which will offset the City’s budget allocation for the project.

In addition to EV charger rebates from SCE, staff has identif ied other potential funding sources to help offset the cost of EV chargers to the City. Staff has already met with our City’s community choice energy provider, Central Coast Community Energy (CCCE), to discuss EV charger rebate programs available to Goleta as a Member Agency. CCCE’s Light Duty Vehicle Electrific ation program has available funding to supplement EV charging equipment with ext ended benefits being offered to it s Member Agencies. Staff plans to apply for and pursue the reservati on of funds through this program after the vendor and equipment is selected, which can provide the City up to $10,000 of funding from CCCE for the purchase of EV charging stations as part of this project. If approved, 6 Meeting Date: December 6, 2022

Page 7 of 8 ends

reservation of CCCE funds will be committed th rough a Letter of Intent provided to the City.

In addition to SCE and CCCE, staff intends to pursue other funding sources to further offset the cost of EV chargers. In August 2022, staff applied for a competitive Clean Air Grant through the Santa Barbara County Air Pollution Control District to further offset the cost of the EV chargers. Once the EVSE equipment is selected and purchased, staff will work with APCD to provide updated cost info rmation as part of the grant application package.

ENVIRONMENTAL REVIEW
This project qualifies for a Categorical Exemption, under Section 15311 and Section 15304 of the CEQA Guidelines, as the project calls for the construction of minor structures accessory to existing facilities. The Class 11 exemption applies as the project calls for the construction of minor structures accessory to existing facilities that do not result in a significant environmental impact (§ 15311) and § 15304(f), Minor Alterations to Land, “Class 4 consists of minor public or private alterations in the condition of land, water, and/or vegetation which do not involve remova l of healthy, mature, scenic trees except for forestry or agricultural purposes. Exampl es include but are not limited to: Minor trenching and backfilling where the surface is restored.” The project will not result in a significant environmental impact.

GOLETA STRATEGIC PLAN:

City-Wide Strategy: Support Environmental Vitality
Strategic Goal : Promote renewable energy, energy conservation and local energy resiliency
Objectives:
 Encourage renewable ener gy generation and use thr ough installation of solar panels, battery energy storage, electric vehicle charging stat ions and similar measures, including at City-owned faciliti es and complete installation of solar panels and electric vehicle charging stations at City Hall.

FISCAL IMPACTS:

Should the City proceed with SCE Charge Ready, staff is requesting a one-time budget appropriation of $50,000 from the General F und Unassigned Balance for the purchase and installation of 17 EVSE. Following the signing, the City has 45 days to demonstrate the proof of purchase of EVSE. This request is in anticipation of quick timelines and the estimated costs for EVSE, installation, and initial setup fees. 7 Meeting Date: December 6, 2022

Page 8 of 8 ends

Goleta City Hall EV Charger Project, FY 22/23
Fund Type Account FY 22/23
Current
Budget
YTD
Actuals
Appropriation Total
Available
Budget
General Fund 101-40-
4500-57010
$15,000 $0 $50,000 $65,000
Total $15,000 $0 $50,000 $65,000
Since available funding str eams are rebates or reimbursements, staff is requesting an allocation of $50,000 in funds to cover the EVSE “turn-key” package. In addition to the ‘make ready’ electrical work and infrastructure being free to the City, the City will receive a rebate incentive of $725 per charging port, totaling $12,325 from SCE, and staff plans to apply for an additional $10,000 of funding from CCCE - for a total of $22,325. With this approach, staff anticipates offsetting the cost of EV chargers for the City by about half.

ALTERNATIVES:

The City Council may elect not to pursue participation in the SCE Charge Ready program and to fully-fund the project with City budget, or to not allocate funding to the project until the vendor contract is completed. City Council may also elect not to pursue participation in the SCE Charge Ready Program as presented and provide staff alternate direction.

Reviewed By: Legal Review By: Approved By:
___________________ ______ _____________ _________ ________ Kristine Schmidt Megan Garibaldi Robert Nisbet
Assistant City Manager City Attor ney City Manager ATTACHMENTS:

1. SCE Charge Ready Conceptual Design – Goleta City Hall

2. SCE Charge Ready Participation Agreement

3. Staff Presentation
8 ATTACHMENT 1

SCE Charge Ready Conceptual Design – Goleta City Hall
9 E V
S E
E V
S E
E V
S E
E V
S E
E V
S E
ONLY

EV CHARGING
ONLY

EV CHARGING

PARKING
NO
BO BO

EXISTING TRANSFORMER
P5317536, 277/480, 3P, 16 KV,
750 KVA
5'
(TYP)
8'
(TYP) 12'
5'
9'
5'
(TYP)
8'
(TYP)
18'
(TYP)
4'
LPLP
E V
S E
A
C
E
D E
F
G
K
W
R
Q U
T
U
AD
AC
AE
AF
AG
SEB
(TYP)
(TYP)
F
(TYP)
A
18'
(TYP)
DR
T
AB
C
T
8'
SEB
SEB
SEBSEB
SEBSEB

BO BOBO BOBO BOBO BO
AD

AF (TYP)
CATCH
BASIN

REMOVE AND RELOCATE
SIGNS
3'-2"
E V

S EBO BO E V
S E
18'
(TYP)

BO BOBO BOE V
S E
A
P
DQ
XZ
H
A
V
AB
M
Drawing: P:\221-0223\Site\00001349006_CG\DD Phase\CP and SLD\00001349006_CG_cp.dwg; Layout1 Plot by: crios Jun 10, 2022 - 10:17am SCALE: AS NOTEDOF SHEETS
SHEET NO. CH. BY
DR. BY
DATE

CONSULTANT

SCE CHARGE READY PROGRAM
00001349006 CITY OF GOLETA

EVSE SITE IMPROVEMENTS
AE
CR
06-09-2022
2 SYMBOL LEGEND:

EXISTING SIGN

EXISTING LIGHT POLE

PROPOSED BOLLARD

PROPOSED SERVICE EQUIPMENT

BOLLARD

PROPOSED WHEELSTOP

PROPOSED SIGN

PROPOSED PULL BOX

PROPOSED SERVICE METER

PROPOSED STEP DOWN

TRANSFORMER

PROPOSED DISTRIBUTION SUBPANEL

DUAL PORT EVSE

SINGLE PORT EVSE

EXISTING SCE TRANSFORMER

SCE ELECTRICAL SERVICE SUPPLY TO

METER, BY T&D

LIMITS OF WORK
ELECTRICAL CONDUIT (+2")
ELECTRICAL CONDUIT (<2")

PROPOSED ACCESSIBLE STRIPING

PROPOSED ACCESSIBLE ROUTE

PROPOSED STRIPING

PROPOSED ASPHALT CONCRETE

PAVEMENT

PROPOSED CONCRETE

PROPOSED TRUNCATED DOMES
LP
BO
SEB
P
E V
S E
E V
S E
T
CONCEPTUAL PLAN - REV 1
1 0 5 10 2040

SCALE IN FEET

CUSTOMER INFRASTRUCTURE

IMPROVEMENTS
CONSTRUCTION NOTESE.Q.

REMOVAL OF HARDEN SURFACING610 SF
REMOVE VEGETATION115 SF
2' WIDE UTILITY TRENCH230 LF

PROPOSED ASPHALT CONCRETE
PAVEMENT560 SF
PROPOSED CONCRETE270 SF
INSTALL 600 AMP DISTRIBUTION
SUBPANEL1 UNIT
INSTALL 200 AMP SERVICE METER (NO
PANELBOARD)1 UNIT
INSTALL 150 KVA STEP DOWN
TRANSFORMER1 UNIT
INSTALL PULL BOX1 UNIT
INSTALL BELOW GRADE PVC CONDUIT +2"55 LF
INSTALL BELOW GRADE PVC CONDUIT <2"1815 LF
#8 WIRE CONDUCTOR2775 LF
#6 WIRE CONDUCTOR1455 LF
#4 WIRE CONDUCTOR625 LF
3/0 WIRE CONDUCTOR85 LF
2/0 WIRE CONDUCTOR60 LF
350 MCM WIRE CONDUCTOR230 LF
DATA CAT5E CABLE1005 LF
STRIPING FOR ADA STALLS1 UNIT
INSTALL ACCESSIBLE EVSE SIGNAGE1 UNIT
INSTALL TRUNCATED DOMES15 SF
INSTALL SITE BOLLARDS23 UNITS
INSTALL WHEELSTOPS2 UNITS
A
C
D
E
F
G
H
K
M
Q
R
T
U
V
W
X
Z
AB
AC
AD
AE
AF
AG
NOTES:

1.UTILITY DISTRIBUTION INFRASTRUCTURE SHOWN IN RED BUILT

BY OTHERS AND SHOWN ONLY FOR PROJECT CLARITY AND
COORDINATION.

2.IMPACTED EXISTING PARKING = 24 TOTAL SPACES; 24
STANDARD SPACES, NET LOSS OF STALLS = 7

3.PROPOSED CHARGING = 17 TOTAL SPACES; 1 VAN ACCESSIBLE EVSE, 1 STANDARD ACCESSIBLE UNRESERVED EVSE, 15

STANDARD EVSE

4.EVSE LAYOUT BASED ON USE OF DUAL AND SINGLE PORT

STYLE CHARGERS

5.PULL BOXES TO BE INSTALLED AS NEEDED

6.PROPOSED SERVICE PANEL MAY BE STANDARD OR 100%
RATED. SEE SINGLE LINE FOR CLARIFICATION.
*LINEAR FOOTAGE QUANTITIES INCLUDE VERTICAL TRAVEL
10 Y Δ
16kV 750kVA,
480Y/277V, 3Ø, 4W

EXISTING UTILITY

TRANSFORMER
P5317536 (kVA

RATING PER SCE)
(NEMA 3R)

PULL SECTIONMETERING

SECTION

LANDING
LUGS
M

PROPOSED SERVICE METER AND MAIN BREAKER,
200A BUS, 200A MAIN,
480Y/277V, 3Ø, 4W, 30kAIC MINIMUM
200A
3P
Y Δ
150.0kVA,
480-208Y/120V
3Ø, 4W (NEMA 3R)

PROPOSED STEP DOWN

TRANSFORMER
2" U.G. PVC WITH
(3) 3/0 Cu AND
(1) #6 Cu GND
(2) 3" U.G. PVC WITH
(4) 350 MCM Cu AND
(1) 2/0 Cu GND

IN EACH CONDUIT
12 PROPOSED DISTRIBUTION PANEL "A", 600 AMP BUS, 600 AMP MAIN 208Y/120V, 3Ø, 4W, 22 kAIC MINIMUM
40A
2P
40A
2P
1112
40A
2P
40A
2P
(NEMA 3R)
600A
3P
MAIN
TO EVSE-1
CHARGE PORTS 1 & 2
(32 FLA + 32 FLA)
TO EVSE-6
CHARGE PORTS 11 & 12
(32 FLA + 32 FLA)
1" U.G. PVC WITH
(4) #8 Cu AND
(2) #8 Cu GND
(TYP FOR EVSE-1
THROUGH EVSE-6)
1314
40A
2P
40A
2P
1516
40A
2P
40A
2P
TO EVSE-7
CHARGE PORTS 13 & 14
(32 FLA + 32 FLA)
TO EVSE-8
CHARGE PORTS 15 & 16
(32 FLA + 32 FLA)
1" U.G. PVC WITH
(4) #6 Cu AND
(2) #6 Cu GND
(TYP FOR EVSE-7
AND EVSE-8)
17 2P
40A
TO EVSE-9
CHARGE PORT 17
(32 FLA)
1" U.G. PVC WITH
(2) #4 Cu AND
(1) #4 Cu GND
Drawing: P:\221-0223\Site\00001349006_CG\DD Phase\CP and SLD\00001349006_CG_SLD.dwg; Layout1 Plot by: crios Jun 10, 2022 - 10:18am SCALE: AS NOTEDOF SHEETS
SHEET NO. CH. BY
DR. BY
DATE

CONSULTANT

SCE CHARGE READY PROGRAM
00001349006 CITY OF GOLETA

EVSE SITE IMPROVEMENTS
AE
CR
06-09-2022
2 SINGLE LINE DIAGRAM - REV 1
2 #
####
NOTES:

1.TOTAL CONNECTED 3-PH KVA: 119.11 KVA AT 0.95 PF

2.STANDARD RATED SERVICE PANELS, OVER CURRENT PROTECTION DEVICES AND WIRE SIZES BASED ON CEC/NEC REQUIREMENTS AT 125% CONTINUOUS LOAD. 100% RATED SERVICE PANELS, OVER CURRENT PROTECTION DEVICES AND WIRE SIZES BASED ON CEC/NEC REQUIREMENTS AT 100% CONTINUOUS LOAD.

3.TRANSFORMER LOADING BASED ON KVA REQUIREMENTS OF CHARGER AT 0.95 PF PER SCE (6.7 KVA/CHARGER).
4 , INDIVIDUAL CHARGE PORT NUMBER. THIS IS NOT BREAKER SPACE OR EVSE NUMBER. LOAD SCHEDULE INDICATES BREAKER SPACE FOR EACH CHARGE PORT.

5. , INDIVIDUAL CHARGE PORT NUMBER TYPICAL FOR PORTS THROUGH .

6. PER CEC/NEC 210.19 (A) INFORMATIONAL NOTE #4, "CONDUCTORS FOR BRANCH CIRCUITS AS DEFINED IN ARTICLE 100, SIZED TO PREVENT A VOLTAGE DROP EXCEEDING 3 PERCENT AT THE FARTHEST OUTLET OF

POWER, HEATING, AND LIGHTING LOADS, OR COMBINATION OF SUCH LOADS, AND WHERE THE MAXIMUM

TOTAL VOLTAGE DROP ON BOTH FEEDERS AND BRANCH CIRCUITS TO THE FARTHEST OUTLET DOES NOT EXCEED 5%."

7.ELECTRIC VEHICLE SUPPLY EQUIPMENT (EVSE) CAN BE DUAL CHARGE OR SINGLE CHARGE PORT DEPENDANT ON LOCATION SEE CONCEPTUAL PLAN AND SINGLE LINE FOR NUMBER OF CHARGE PORTS.

8. MAXIMUM VOLTAGE DROP FOR CONDUCTORS: #8 WIRE = 2.6%, #6 WIRE = 2.8%, #4 WIRE = 2.0%, 3/0 WIRE (480V) = 0.1%, 350 MCM WIRE (208V) = 0.2%

9.DIAGRAM ASSUMES CHARGER AND CONTROLLER ARE ONE (1) SELF CONTAINED UNIT. 11 ATTACHMENT 2

SCE Program Participation Agreement
12 Page | 1

9-2-2021 V2.7
Charge Ready
Charging Infrastructure and Rebate
Participation Agreement
This Charge Ready Charging Infrastructure and Rebate Participation Agreement (Agreement) sets forth the terms and conditions for Program Participant to participate in the Program. Pursuant to the terms of this Agreement, SCE will (1) install the Infrastructure (as defined herein) at no cost to the Program Participant; and, (2) if applicable, remit the Charging Equipment Rebate, and/or the Maintenance and Networking Rebate after all terms and conditions have been met by the Program Participant.

All Program Participants are eligible for no-cost installation of the utility-side and Customer-Side Make-Ready Infrastructure.

Program Participant hereby agrees to the following terms and conditions of the Charge Ready Charging Infrastructure and Rebate Program (the “Program”).

APPROVED CHARGING PORTS

1. Total Number of Approved Charging Ports:

The
commitment to procure and install the number of approved Charging Ports applies whether or not the Program Participant is eligible to also receive a rebate for the installed charging equipment, as SCE will design and install the Infrastructure based on
this commitment.

The Program Participant is required to install the quantity and power level of approved Charging Ports set forth in this Agreement. Failure to procure and install the agreed upon number may lead to termination of this Agreement, at SCE’s discretion.

Number of Charging Ports and Power Levels approved by SCE.

Power Level (L1) Port count: 0
Power Level (L2) Port count: 17
Power Level (DCFC)
Port count: 0

2. Rebates (if applicable):

2.1. Charging Equipment Rebate
13 Page | 2

9-2-2021 V2.7
If Program Participant is eligible to receive a rebate for the purchase and installation of charging equipment, the rebate amount paid to the Program Participant will be reduced to ensure that when combined with any other third- party rebates or incentives, the total rebate received by Program Participant does not exceed the Program Participant’s total costs for procuring and installing the equipment. Following the successful installation of the Charging Equipment, the
Program Participant will certify whether it has received any other third-party rebates or incentives, so that SCE can determine the appropriate rebate payment.

The following table reflects that rebate values in effect at the time this agreement was
issued:

Charging Infrastructure and
Rebate
DAC
Excluding
Fortune 1000* Multi-Family
Others
Including
Fortune 1000*
L2 $2,900 $1,450 $725

2.2. Maintenance and Networking Rebate
This rebate option is only available to Multi-Family Property sites located in a designated top quartile DAC. The rebate provides a one-time payment intended to offset the maintenance
, networking and warranty costs associated with owning
and operating L2 charging equipment. This rebate is intended to cover most of the costs associated with 10 years of the equipment’s operation . The total rebate
received by Program Participant will not exceed the Program Participant’s actual costs
.

APPROVED SITE LOCATION AND DESIGN

3. Description of Approved Location at the Site:

Brief description of the mutually approved location on the Program Participant’s Site where Infrastructure will be installed.

Site Description: City of Goleta City Hall (Charging Infrastructure and Rebate Application; NOT Turn-Key Installation)
Site Address: 130 CREMONA DR, GOLETA, CA, 93117

14 Page | 3

9-2-2021 V2.7

4. Conceptual Design of the Infrastructure deployment at Program Participant’s Site:

Program participant has reviewed and approved the Conceptual Design, as provided by SCE, showing the location within the Site where SCE will deploy the charging infrastructure. MAKE-READY INFRASTRUCTURE WORK

5. The Make-Ready Infrastructure:

If the Program Participant elects to have SCE install the entire Make-Ready Infrastructure, SCE will do so at no cost to the Program Participant. In this case, the Make-Ready Infrastructure will be part of the “Infrastructure” as defined in this Agreement.

SCE-installed Customer-Side Make-Ready Infrastructure.

PROGRAM PARTICIPATION TERMS AND CONDITIONS
Program Participant agrees that its participation in the Program is subject to the following terms and conditions:

6. Definitions:

6.1. AHJ – Authority
Having Jurisdiction: The responsible government
entity having geographically-based jurisdiction that typically approves, inspects, and permits construction projects (e.g., City, County, Fire, Division of State Architect, etc.).

6.2. Approved Product List: The list of Charging Equipment qualified by SCE and meeting SCE’s technical requirements. Program Participant must select Charging Equipment
from the Approved Product List to
receive applicable Charging Equipment Rebate (if available).

6.3. Disadvantaged Communities as defined by CalEPA: see Disadvantaged Communities.

6.4. Charging Equipment: Qualifying Charging Equipment that meets the technical specifications set forth by SCE. Charging Equipment that qualif
ies for the Rebate, if available, are listed in the Approved Product List, which can be found on SCE’s website at www.SCE.com/APL. See also Power Levels.

6.5. Charging Equipment Supplier: The entity from which the Charging Equipment is purchased.
15 Page | 4

9-2-2021 V2.7

6.6. Charging Equipment Rebate: Financial reimbursement paid to an eligible Program Participant, or its designee, pursuant to this Agreement, to off-set a portion of the purchase of approved Charging Equipment.

6.7. Charging Ports: See Charging Stations.

6.8. Charging Stations – EV Charging Equipment: EV Charging Equipment interconnects with the electricity grid at a charging site to an electric vehicle, whether using alternating current (AC) or direct current (DC). An individual charging station unit may contain one or more charging ports for the purpose of connecting the electric vehicle to a grid connected power source capable of recharging the vehicle’s battery pack. The individual connectors of the Charging Station are referred to as ports (referred to in this agreement as Charging Ports). Each charging station may charge one or more vehicles depending on the number of ports with which each unit is equipped. For dual-port stations, power cannot be throttled during non-DR events and each port must be able to deliver full power to both vehicles that are charging simultaneously. For example, a dual-port L2 station rated at 7.2 kW must be able to deliver 7.2 kW of
power to both vehicles when two vehicles are charging simultaneously.

6.9. Commitment Period: The ten (10) year period where Program Participant must maintain all Charging Equipment in working order at the Site
. The Commitment Period will commence on the In-Service Date of the Charging Equipment.

6.10. Conceptual Design: Map and related documents, as applicable, that show the proposed layout of the Infrastructure and Charging Equipment, including but not limited to, conduit routing and equipment placement.

6.11. California Public Utilities Commission (CPUC): The California state regulatory agency that is responsible for regulating privately owned electric, natural gas, telecommunications, water, railroad, rail transit, and passenger transportation
companies.

6.12. CPUC’s Transportation Electrification Safety Requirements Checklist: The Safety Requirements Checklist applies to CPUC- Approved Transportation Electrification Programs and can be downloaded from:
www.cpuc.ca.gov/WorkArea/DownloadAsset.aspx?
id=6442458882

6.13. Customer-Side Infrastructure: See “Make-Ready Infrastructure.” 16 Page | 5

9-2-2021 V2.7

6.14. Customer-Side Make-Ready Rebate: The rebate intended to offset a portion of the Participant’s costs if Participant elects to perform the C
ustomer-Side Make-Ready Infrastructure work, following the completed installation of the Make-Ready Infrastructure and submission of required documentation.

6.15. Demand Response: Demand Response (DR) programs encourage a reduction of electricity use during certain time periods, typically during on-peak hours or when demand for electricity is high, and/or can provide incentives to use electricity during periods of excess generation or when demand for electricity is lower.

6.16. Disadvantaged Communities (DACs)
: Census tracts in SCE’s service
territory with a top quartile score according to California Environmental Protection Agency’s California Communities Environmental Health Screening Tool. SCE will use the current applicable version of the CalEnviroScreen tool to verify site status.

6.17. Enrollment Portal: The website where Program Participants can apply for the Program, check application status, and upload most required documents.

6.18. Electric Vehicle Infrastructure Training Program (EVITP) Certification
: The document certifying an electrician has gone through the Electric Vehicle Infrastructure Training Program process. For more information, please visit https://www.evitp.org
.

6.19. Fortune 1000: Fortune 1000 companies include companies listed on the Fortune 1000 list, subsidiaries of Fortune 1000 companies, corporate stores of Fortune 1000 companies, and international companies with annual revenue at or above the lowest cutoff point in Fortune 1000.

6.20. Final Design:

Map and related documents, as applicable, that show the proposed layout of the Infrastructure and Charging Equipment, including but not limited to, conduit routing and equipment placement. The Final Design is the engineered construction drawing submitted for permitting and will be completed
after this Agreement is executed and prior to start
of construction.

6.21. Final Invoice: Statement of the total amount paid by Program Participant to Charging Equipment Supplier(s) for the purchase, and installation of
the Charging Equipment.
17 Page | 6

9-2-2021 V2.7

6.22. Grant of Easement: A contractual agreement to grant right of way for SCE to construct, maintain, operate, and repair any SCE-installed infrastructure.

6.23. In-Service Date: The earliest date on which the EV Charging Equipment is installed and operational.

6.24. Infrastructure: The necessary Infrastructure on both the utility-side and customer-side of the electric meter (i.e., “make-ready”) that SCE will design, construct, and install at no cost to the Program Participant pursuant to this Program. Infrastructure, as defined herein, does NOT include (1) purchase or installation of the Charging Equipment; or (2) the customer-side portion of the Make-Ready Infrastructure, if the Program Participant elects the self-installed Customer-Side Make-Ready Infrastructure option.

6.25. Make-Ready Infrastructure: Infrastructure located on both the utility-side and customer-side of the meter is also referred to as the Make-Ready Infrastructure. The Utility-Side Infrastructure includes all infrastructure work from SCE’s distribution system to a new circuit panel that will be installed to support EV charging. SCE will always be responsible for designing, procuring, installing, and maintaining the necessary infrastructure located on the utility side of the meter. The Customer-Side Make-Ready Infrastructure includes all infrastructure from the new panel that will be set as part of the Utility-
Side Infrastructure work, up to the
first point of interconnection with the Participant’s Charging Equipment.

Participants will have the option to have SCE perform the Customer-Side
Make-Ready Infrastructure work or perform that work themselves and qualify to receive the Customer-Side Make-Ready Rebate.

6.26. Make-Ready Rebate: See Customer-Side Make-Ready Rebate.

6.27. Multi-Family Property (also referred to as multi-unit dwelling, or MUD).

The definition for enhance rebate qualifying sites include:

6.27.1.Residential properties – Structures that are designed to accommodate two or more tenants with shared parking areas.

6.27.2.Apartment Buildings – Structure(s) containing two or more dwelling units that may also include common areas and facilities, e.g., entrances, lobby, elevators or stairs, mechanical space, walks, grounds, recreational facilities, and parking both covered and open. 18 Page | 7

9-2-2021 V2.7

6.27.3.Retirement Communities, Townhomes, Condominiums – Residential communities with shared parking areas managed by an HOA or an equivalent association.

6.27.4.Mobile Home Parks
– Residential mobile home communities with
shared parking areas.

6.27.5.University & Military Housing – Student or military housing units or apartments with individual cooking facilities (except conventional dormitories and barracks with cafeteria type kitchens).

6.27.6.Timeshares
– Vacation property communities with shared parking
areas managed by an HOA or an equivalent association.

6.27.7.Public Parking with Dedicated Overnight Resident Passes – Public parking lots designated for nearby multi-family residents for overnight parking. Charging Stations can be open for public use during day-time hours.

6.28. Network Service Provider: The third-party entity that will provide Network Services for the Charging Equipment. The Network Service Provider will be required to transmit port level data and other information to SCE complying with Program requirements.

6.29. Ports:

See Charging Stations.

6.30. Power Levels: Charging Equipment Power Levels.

Level 1 (L1) Charging: Low power charging, typically at or below 120 volts.

Level 2 (L2) Charging: Medium power charging, typically delivered between 220 and 240 volts.

Direct Current Fast Charging (DCFC): Charging equipment that provide a high-power DC current, and for this program at least 50 kW, to the electric vehicle's battery without passing through any onboard AC/DC converter, which means the current is connected directly to the battery.

6.31. Preliminary Design:

The set of engineered, working drawings of the
Infrastructure. The design includes project specifications, conduit routing, electrical equipment specifications and calculations, project related Site improvements and construction details

6.32. Program:

Also referred to as the Charge Ready Charging Infrastructure and Rebate Program. This Program is designed to help Program 19 Page | 8

9-2-2021 V2.7
Participants install the charging infrastructure needed to enable drivers to refuel their light-duty electric vehicles.

6.33. Program Guidelines: Program reference documents developed by SCE that provide program information, including but not limited to the program participation requirements.

6.34. Program Participant: The SCE non-residential
entity that enters into this
Agreement.

6.35. Property Owner/Site Owner: Individual or entity authorized representative of entity holding title in the Site where the Charging Equipment and Infrastructure will be located.

6.36. Rebate Payment: The payment made by SCE to Program Participant, or its designated assignee, after the eligible Program Participant procures and installs the Charging Equipment, meets the qualification requirements for the Customer-Side Make-Ready Rebate, and/or the Maintenance and Networking Rebate, in accordance with this Agreement, as verified by SCE, in SCE’s sole discretion.

6.37. Site:

The premises, owned, leased or operated by Program Participant, where the Charging Equipment will be installed.

6.38. Time-of-Use (TOU) Rate Plans: Rate plans which feature energy charges that vary based on the time of day, the day of the week, and the season. Some plans also include demand charges that are based on the maximum amount of electricity your business uses at once.

6.39. Utility
-Side Infrastructure: See Make-Ready Infrastructure.

7. Eligibility.

Program Participant certifies that it meets, and will continue to meet throughout its participation in the Program, all eligibility requirements of the Program, including, but not limited to:

7.1. Program Participant is a non-residential SCE entity with at least one active service account.

7.2. T
he installation site is located in SCE’s service territory.

7.3. Program Participant agrees to provide, or cause the Site Owner to provide, SCE with the rights of way across public or private property (as applicable) and to obtain any necessary permits to install Charging Equipment, without cost to SCE
.

7.4. Program Participant will comply with all Program requirements outlined in the Charge Ready
Program Guidelines.
20 Page | 9

9-2-2021 V2.7

8. Additional Representations of Program Participant during the Term of the Agreement.

Program Participant:

8.1. Program Participant agrees to purchase and install the Charging Equipment, as set forth in this Agreement. Program Participant agrees that the number of Charging Ports and their charging power level set forth in Section 1 cannot
be modified after execution of this Agreement, without
express written consent of SCE, at SCE’s discretion.

8.2. All charging equipment must be selected from SCE’s Approved Product List (APL) or otherwise approved by SCE for installation under this Program, in a quantity approved by SCE.

8.3. Program Participant agrees to have APL listed charging equipment installed by a qualified C-10 licensed and insured contractor.

8.4. Agrees to ensure their EVSE equipment installer follows all relevant State and local codes, and AHJ permitting requirements. All installed equipment must be correctly rated for the location where it will be installed (outdoor rated if applicable, conforming with ventilation requirements). The EV charging current shall not exceed 80% of the branch circuit rating. All EVSE installations must comply with the SB350 safety requirement checklist.

8.5. Agrees to ensure their EVSE equipment installer will not install and energize any EVSE or associated equipment capable of generation or bidirectional operation without Permission to Operate from SCE .

8.6. Agrees to procure, own, install, operate, and maintain the Charging Equipment in good working order at the site for a minimum of ten (10)
years from the In-Service Date of Charging Equipment (“Commitment Period”).

8.7. Agrees that, if at any time during the Commitment Period the Charging Equipment is replaced, only SCE approved EVSE will be installed and all associated costs will be the responsibility of the Program Participant.

8.8. Agrees to contract with a qualified electric vehicle charging equipment Network Service Provider
approved by SCE to record and transmit EV
charging usage and other data to SCE.

8.9. Program Participant authorizes SCE to act on Program Participant’s behalf to voluntarily grant a Third Party access to receive information
21 Page | 10

9-2-2021 V2.7
relating to Charging Station data, billing records, billing history, pricing information, and all meter usage data used for bill calculation for all meters participating in this Program. This authorization expires ten (10) years from the Charging Equipment’s In-Service Date.

8.10. Program participant authorizes the use of the collected Charging Station and related meter and billing data for regulatory reporting, program evaluation, industry forums, case studies or other similar activities, in accordance with applicable laws and regulations.

8.11. Acknowledges and agrees that the actual Make-Ready Infrastructure may vary from the Conceptual Design, if, in SCE’s sole discretion, actual Site conditions or AHJ direction requires such changes.

8.12. Acknowledges that funding pursuant to this Agreement is only reserved after SCE receives a copy of this Agreement signed by Program Participant and Property Owner (if different from Program Participant) .

The Program Participant also acknowledges that reserved funding may be withdrawn, and SCE may terminate this Agreement, both in SCE’s sole discretion, if Program Participant breaches the Agreement.

8.13. Agrees to comply with the established timelines and required documentation set forth in the Program Guidelines.

8.14. Represents and warrants that if Program Participant has applied for or received any other incentives or rebates for the Charging Equipment, Customer-Side Make-Ready
Infrastructure, or Charging Equipment
Maintenance and Networking program Participant shall notify SCE of any such incentives or rebates as soon as reasonably practicable. In the event that any such incentives or rebates, when combined with Program rebates,
would reimburse Program Participant for more than 100 percent of their costs, SCE shall decrease the issued rebate amount if not yet paid, or if already paid, submit a reimbursement request to the Program Participant for the amount of the Rebate Payment exceeding 100 percent of the Participants costs.

8.15. Program Participant agrees that the electricity meter(s) associated with the EV charging equipment will be provided service under a TOU rate plan.

8.16. Participants must enroll in at least one qualifying Demand Response
Program.
22 Page | 11

9-2-2021 V2.7

8.17. Agrees to ensure information of newly installed Charging Equipment, if accessible to the general public, will be registered with the US Department of Energy’s Alternative Fuel Data Center (https:// afdc.energy.gov/stations/#/analyze), and with the US Department of Energy’s EV Charging Station Locations mapping tool, accessible at (
https://www.afdc.energy.gov/fuels/electricity_locations.html#/find/ nearest?fuel=ELEC), and that only one set of information is reported between the Program Participant and Charging Equipment Supplier.

8.18. Agrees to submit a completed IRS tax form W-9, and California Franchise Tax Board form 590 if applicable, or to provide line items from those forms as SCE may request,
in order for SCE to process any Rebate
Payment.

8.19. Represents and warrants that the execution and delivery of this Agreement, and the performance by Program Participant of its obligations under this Agreement, have been duly and validly authorized, and this Agreement is a legal, valid and binding obligation of Program Participant.

8.20. SCE, at its sole discretion and in accordance with its applicable tariffs, design standards, and AHJ permitting requirements, will locate, design, and install the
utility-side, and possibly the customer-side Infrastructure depending on the Participants choice. SCE is responsible for all costs associated with Infrastructure deployed by SCE pursuant to this Agreement.

8.21. SCE will pay the Charging Equipment Rebate, if applicable, after SCE has verified correct installation of the Charging Equipment, consistent with this Agreement, subject to Program Participant meeting all Program requirements. The actual Charging Equipment Rebate Payment amount shall not exceed the actual reasonable costs of the Charging Equipment, and
its installation, as set forth in the Final Invoice(s) and consistent with the Program Participant’s contract with the Charging Equipment Supplier(s)
and installers.

8.22. SCE will pay the Maintenance and Networking Rebate to qualifying participants following the installation of the Charging Equipment and subject to Program Participant meeting all Program requirements .

8.23. For sites that qualify to participate under the Multi-Family Property sites definition by providing Public Parking with Dedicated Overnight Resident Passes, Participant agrees to ensure that overnight parking will be 23 Page | 12

9-2-2021 V2.7
reserved and dedicated for nearby multi-family residents for the duration of the commitment period.

8.24. Agrees to participate in SCE sponsored customer satisfaction and other surveys following completion of the Project, upon request of SCE.

9. Term and Termination:

9.1. Term: The term of this Agreement shall begin upon the date that both Parties have signed the Agreement and end ten (10) years from the In- Service Date of the Charging Equipment, unless otherwise terminated earlier pursuant to this Agreement (“Term”).

9.2. Termination: If the Program Participant fails to comply with any of the terms and conditions of this Agreement, SCE, in its sole discretion, may terminate this Agreement after sending Program Participant a notice of default that remains uncured for five (5) business days from receipt, except in the case of a safety or security violation, in which case, SCE may terminate the Agreement immediately and take all other necessary actions, including but not limited to, disconnecting power to the Charging Equipment, in SCE’s sole discretion, to cure such safety or security violation(s).

9.3. Termination Costs: If this Agreement is terminated prior to the end of the Term because (1) Program Participant terminates its participation in this Program, (2) Program Participant, prior to the end of the Commitment Period, fails to install, or removes without replacing, the Charging Equipment or Program Participant-owned make-ready infrastructure, if applicable; or (3) SCE terminates this Agreement due to Program Participant’s failure to comply with the terms and conditions of the Agreement, in accordance with Section 9.b. (Termination) hereof, the Program Participant shall pay (a) all costs actually incurred, or committed to be incurred, by SCE, as of the termination date, in connection with designing and deploying the Infrastructure at the Site; and (b) the Rebate Payment (if already paid). If the Charging Equipment or the Make-Ready Infrastructure, if applicable, are installed, the amount due to SCE for both (a) and (b) above will be prorated over a ten-year period, beginning from the In-Service Date of the Charging Equipment. SCE will invoice the Program Participant for such costs, and Program Participant shall pay such invoice within sixty (60
) days of receipt.

10. Indemnification and Liability; No Representations or Warranties 24 Page | 13

9-2-2021 V2.7

10.1. Program Participant understands that SCE makes no representations regarding manufacturers, dealers, contractors, materials or workmanship of the Charging Equipment. Further, SCE makes no warranty, whether express or implied, including without limitation the implied warranties of merchantability and fitness for any particular purpose, use, or application of the products and services under the Program. Program Participant agrees that SCE has no liability whatsoever concerning (1) the quality, safety or installation of such products, including their fitness for any purpose, (2) the workmanship of any third parties, (3) the installation or use of the products. Program Participant hereby waives any and all claims against SCE, its parent companies, directors, officers, employees, or agents, arising out of activities conducted by or on behalf of SCE under the Program. Without limiting the generality of the foregoing, Neither SCE nor Program Participant shall be liable hereunder for any type of damages, whether direct, or indirect, incidental, consequential, exemplary, reliance, punitive or special damages, including damages for loss of use, regardless of the form of action, whether in contract, indemnity, warranty, strict liability or tort, including negligence of any kind.

10.2. Indemnification of SCE. To the fullest extent permitted by law, Program Participant shall, at SCE’s request,
indemnify, defend, and hold harmless
SCE, and its parent company, subsidiaries, affiliates, and their respective shareholders, officers, directors, employees, agents, representatives, successors, and assigns (collectively, the “Indemnified Parties”), from and against any and all claims, actions, suits, proceedings, losses, liabilities, penalties, fines, damages, costs, or expenses, including without limitation reasonable attorneys’ fees (a “Claim”), resulting from (a) any breach of the representations, warranties, covenants, or obligations of Program Participant under this Agreement, (b) any act or omission of Program Participant, whether based upon Program Participant’s negligence, strict liability, or otherwise, in connection with the performance of this Agreement, or (c) any third
-party claims of any kind, whether based upon
negligence, strict liability, or otherwise, arising out of or connected in any way to Program Participant’s performance or nonperformance under this Agreement. This indemnification obligation shall not apply to the extent that such injury, loss, or damage is caused by the sole negligence or willful misconduct of SCE.
25 Page | 14

9-2-2021 V2.7

10.3. Responsibility for Repairs. If Participant -installed equipment damages SCE-owned Infrastructure, Participant will be responsible for any costs associated with making any necessary repairs. If SCE identifies an improper installation of Participant-installed equipment, Participant agrees to pay for and be responsible for making any necessary corrections in the manner requested by SCE.

10.4. Defense of Claim. If any Claim is brought against the Indemnified Parties, Program Participant, at SCE’s request, shall assume the defense of such Claim, with counsel reasonably acceptable to the Indemnified Parties, unless in the opinion of counsel
for the Indemnified Parties a conflict
of interest between the Indemnified Parties and Program Participant may exist with respect to such Claim. If a conflict precludes Program Participant from assuming the defense, then Program Participant shall reimburse the Indemnified Parties on a monthly basis for the Indemnified Parties’ defense costs through separate counsel of the Indemnified Parties’ choice. If Program Participant assumes the defense of the Indemnified Parties with acceptable counsel, the Indemnified Parties, at their sole option and expense, may participate in the defense with counsel of their own choice without relieving Program Participant of any of its obligations hereunder.

11. Miscellaneous
All Applicable Tariffs Apply. All applicable SCE tariffs apply to service provided pursuant to this Agreement, with the following exceptions:

11.1. Rules 15 and 16. Distribution Line and Service Extensions: Because SCE will design and install the Infrastructure at no cost to Program Participant, sections in Rules 15 and 16 that address applicant responsibilities or options are not applicable to Program Participants while participating in the
Charge Ready Charging Infrastructure and Rebate Program. This may include, but is not limited to, allowances, contributions or advances, payments, refunds, and design and installation options. This exception does not apply to certain responsibilities found in Rule 16, such as, but not limited to, Section A.10, providing rights of way or easements; Section A.11, providing access to the location; and Section D.1, providing a clear route for the Service Extension.
26 Page | 15

9-2-2021 V2.7

11.2. Survival. Program Participant’s obligation to pay Termination Costs and to indemnify the Indemnified Parties shall survive the expiration or termination of this Agreement.

11.3. Assignment. Program Participant shall not assign this Agreement without the prior written consent of SCE; to be granted or denied in SCE’s sole discretion.

Any assignment and assumption shall be in a form acceptable to SCE, in SCE’s sole discretion.

11.4. All applicable SCE tariffs apply to service provided pursuant to this Agreement including, but not limited to, the applicable provisions of SCE’s Charge Ready Program (CRP) Tariff Schedule filed with the California Public Utilities Commission. This Agreement shall be subject to such changes or modifications by the Public Utilities Commission of the State of California, as said Commission may, from time to time, direct in the exercise of its jurisdiction.

11.5. Should a conflict exist between the Charge Ready Program Guidelines and this Agreement
, then this Agreement shall control with respect to
such conflict.

11.6. Incentives and Rebates are taxable and if greater than $600 will be reported to the IRS unless the payee is exempt. SCE will report the rebate as income on IRS Form 1099. The payee should consult its tax advisor concerning the taxability of the Rebate
Payment.

This Agreement can be signed electronically. If wet signature required, this Agreement can be downloaded and signed. Following signature, the Program Participant can upload the completed Agreement. SCE will verify for completeness and accuracy and will execute the Agreement and reserve funding accordingly.

AGREEMENT BY PROGRAM PARTICIPANT
By signing this document, you represent that the information provided in this Agreement is true, accurate and complete, and that you will comply with the terms and conditions set forth in this Agreement. You also represent and warrant that you are a duly authorized representative of Program Participant with the requisite authority to enter into this Agreement. For federal government Program Participants, you must be a Contracting Officer authorized to enter into this Agreement.

Name of Program Participant
: GOLETA, CITY OF
27 Page | 16

9-2-2021 V2.7
Name of Program Participant Representative:
______________________________________________

Title of Program Participant Representative:
_______________________________________________

I certify that the information provided is accurate and complete and that I have authority to sign this Agreement on behalf of Applicant.
________________________________________________
Signature
Date: ______________
AGREEMENT BY PROPERTY OWNER (If Program Participant is the Property Owner, no separate signature is required.)
By signing this document, you represent and warrant that you are a duly authorized representative of the owner of the property on which the Site is located and that you have the requisite authority to consent to the use of the property in the manner set forth in this Agreement. You also represent that Property Owner hereby approves the installation and operation of the Infrastructure and the Charging Equipment, as well as any other necessary equipment to deploy the Charging Equipment pursuant to the Program as described in this Agreement. You further agree to execute the Easement Agreement within thirty (30) calendar days after Easement Agreement is provided by SCE
.

Name of Property Owner Representative:
___________________________________________
Title of Property Owner Representative:
___________________________________________
I certify that I have authority to sign this Agreement on behalf of the Property Owner. ________________________________________
Signature

28 Page | 17

9-2-2021 V2.7
Date:

Endnotes

29 ATTACHMENT 3

Staff Presentation
30 City Hall Electric Vehicle
Charging Infrastructure:

SCE Charge Ready
Presentation to the Goleta City Council
September 6, 2022
Presentation by:

Dana Murray, Sustainability Manager
Angeline Foshay, Sustainability Management Assistant
31 Presentation Overview
September 6th, 2022 Goleta City Council Meeting 2

1. Timeline &
History

2. Program
Participation

3. Conceptual
Design
32 1. Timeline & History
September 6th, 2022 Goleta City Council Meeting 3
33 City Strategic Goals
Support for EV infrastructure at
City facilities
demonstrated in
Strategic Plan Goal 1.1.3
EV Readiness Planning a top
curren
t projects priority for 22-
23 PER Annual Work Program
September 6th, 2022 Goleta City Council Meeting 4
34 Demand for EV Infrastructure
Transportation accounts for over half of County's
emissions
State goal: 250,000 EV Chargers to support 1.5 million ZEV
s by 2025
Santa Barbara County estimated need for public Level
2 Charg
ers by 2025: 972
Current Level 2 Chargers: 328
September 6th, 2022 Goleta City Council Meeting 5
35 Timeline
August 2021 – Staff submitted applications to SCE
November 2021 – Preliminary approval for City Hall site December 2021 – Initial conceptual design
February 2022 – Presented conceptual design to Green
Committe
e
March 2022 – Approval from Green Committee with port
increase
July 2022 – Updated conceptual design received
September 6th, 2022 Goleta City Council Meeting 6
36 2. Program Participation – SCE Charge
Ready
September 6th, 2022 Goleta City Council Meeting 7
37 Charge Ready Program Terms
10-Year Participation Agreement
Grant of Easement
SCE Charge Ready Provides:
 Designs and installs the "make-ready" infrastructure for free  Addresses ADA compliance
 Rebates for EVSE per port
City Responsibilities
 Purchase and installation of EVSE
 Networking for all chargers for program term
 Operations and maintenance for program term
 Enrollment in Demand Response Program
September 6th, 2022 Goleta City Council Meeting 8
38 Program Process
September 6th, 2022 Goleta City Council Meeting 9
39 Next Steps
 Program Participation
Agreemen
t
 Upon execution, 45 days to
demonstr
ate proof of purchase
of EVSE
Staff currently evaluating
vendor
s via informal bid
process
September 6th, 2022 Goleta City Council Meeting 10
40 3. Conceptual Design
September 6th, 2022 Goleta City Council Meeting 11
41 Key Elements
 17 EV Chargers – 8 Dual Port & 1 Single Port
 2 ADA Accessible Spaces – 1 Van & 1 Standard
 ADA accessibility improvements to the south
entr
ance to City Hall
 Restriping will result in a net loss of 7 parking stalls September 6th, 2022 Goleta City Council Meeting 12
42 Conceptual Design
September 6th, 2022 Goleta City Council Meeting 13
43 14
Recommendation:

A. Authorize the City Manager to negotiate and
execute the necessary documents for the City of
Goleta to participate in the SCE Charge Ready Program.

B. Approve a budget appropriation for a total not-to
exceed amount of $50,000 from General Fund
Unassigned Balance for the purchase and installation
of 17 Level 2 Electric Vehicle chargers and software.

C. Authorize staff to apply for $12,325 in incentives
through the SCE Charge Ready Program and seek
additional funding opportunities to reduce project
costs.
44