Miscellaneous Park Improvement Project Notice of Completion

Goleta City Council
March 7, 2023

Document
Miscellaneous Park Improvement Project Notice of Completion
Meeting
March 7, 2023
Body
Goleta City Council
Pages
4
Original file
877 KB
Text extracted from the city's file for reading and search. Open the original on goleta.legistar1.com. That file is the official record.

Agenda Item B.8

CPMS CONSENT CALENDAR
Meeting Date: March 7, 2023
____________________________________________________________ TO: Mayor and Councilmembers
FROM: Jaime A Valdez, Neighborhood Services Director
CONTACT: JoAnne Plummer, Parks and Recreation Manager
SUBJECT: Miscellaneous Park Improvement Project Notice of Completion RECOMMENDATION:

A. Adopt Resolution No. 23-__ entitled “A Resolution of the City Council of the City of Goleta, California, Authorizing the Filing of a Notice of Completion for the Miscellaneous Park Improvement Project (CIP 9066)”, and B. Direct the City Clerk to file a Notice of Completion with County Recorder’s Office.

BACKGROUND:

In 2015, the adopted Recreation Needs Assessment identified improvement needed at a variety of parks in the City of Goleta. The parks were prioritized, and three parks emerged as needing playgrounds replaced and access improved: Andamar Park, Winchester 1 Park and Winchester 2 Park. This Project was approved in the 2016 CIP Project as CIP No. 9066.

In 2017, an evaluation of existing playgrounds was completed and a swing set at Berkeley Park was identified as dangerous and recommended for replacement. The damaged equipment was immediately removed in the interest of public safety. During the following budget process, playground replacement for this park was added to CIP No. 9066.

In 2019, the City Council received two separate reports to discuss the possible layouts for the playground equipment at Winchester 2 Park. Neighbors had reported problems with a lack of tree maintenance, flooding, and drainage at this location. Concerns were expressed related to how the playground may impact the other uses in the park such as soccer, picnicking and t-ball. Prior to the meeting on February 19, 2019, staff had reached out to the neighborhood in the vicinity of the park and posted signs about the meeting in the park to make sure that all of those impacted by the improvements had the opportunity to express their concerns. Numerous letters and emails were received, most expressing concerns with a layout at the north side of the property, close to the busy Calle Real traffic.

Council r eviewed multiple layouts of the playground and chose Option D as the final 1 Meeting Date: March 7, 2023

Page 2 of 4 ends

layout. In the motion, staff was asked to re -evaluate the site due to recent fallen trees to determine if the layout could be flipped, moving the taller elements to the north side of the design. Due to the trees lost in a storm earlier that year, the layout for Option D was able to be flipped, placing the swings at the south side of the layout and the taller play features further north in the design. Additionally, the Americans with Disabilities Act (ADA) compliant walkway would run from the sidewalk on Calle Real to the playground.

The concerns that were raised regarding Winchester 2 Park’s drainage would need to be evaluated by an outside agency before construction would begin. No t knowing if the challenges at Winchester 2 Park would be significant, staff requested that Winchester 2 Park be placed as its own project in the Fiscal Years 2019 -20 and 2020-21 CIP Budget as CIP No. 9108. In late July of 2019, the City contracted with St antec for engineering and surveying services. Over the next few months, Stantec conducted evaluations on this site to include percolation tests. The result was a finding that the natural flow of the property does flow towards Warwick Place and clay was fou nd in the soils, which can slow percolation after heavy rains. In early 2020, questions were raised related to the ADA accessibility requirements at all the locations. The plan was to ensure that there was at least one ADA pathway leading to the new featur es and the surfacing material would include a unitary product that was compliant with ADA access. While it is ideal to have multiple accessible pathways, only one is required at the time of the park improvements.

As other improvements are considered, such as addressing drainage in the picnic area, additional access pathways will be evaluated for inclusion with those projects and has been included in a separate Capital Improvement Project (9108).

DISCUSSION:

In December of 2020, the City Council authorized staff to advertise for construction and installation of the equipment and ADA pathways for four park locations including Andamar Park, Winchester 1 Park, Winchester 2 Park and Berkeley Park. Staff filed the Notices of Exemption with the County of Santa Barbara for all four locations per the CEQA guidelines in January of 2021.

These park improvement locations have benefited the health and quality of life for young people and families in the community by improving the accessibility and safety surfacing and expanding the exploration opportunities through play. The improvements at Winchester 1 Park also provides a positive experience for physical fitness for old er children, adults and seniors.

In June of 2021, the City Council awarded a contract to R.E. Shultz Construction, Inc. for the construction of the project and to Filippin Engineering for the construction management, inspections and materials testing related to this project.

In September of 2021, the City issued a notice to proceed to R.E. Shultz Construction, Inc to begin construction of the Park. The work consisted of grading, installation of sidewalks, driveways, fencing, drains, recreation amenities to include playground equipment, fitness equipment, benches, shade structures, picnic table, and curbing per the project plans, specifications and change orders.
2 Meeting Date: March 7, 2023

Page 3 of 4 ends

The work by the contractor was completed by June of 202 2. Over the past number of months, the Neighborhood Services Department ha s finalized construction invoices and project closeout activities.

The Neighborhood Services Department is recommending adoption of the proposed resolution to facilitate the final close -out of this project (Attachment 1). A Notice of Completion pursuant to Public Contract Code §20854 is recommended for approval and direction requested for the City Clerk to file it with the County of Santa Barbara, County Recorder Office (Attachment 2).

FISCAL IMPACTS:

The actual cost for construction, including quantity changes, equipment, and construction management, totaled $924,407.30 including the $15,080 in change orders for construction.

The project was funded with Park DIF. The budget worksheet for the construction and the overall project costs are shown in the tables below.

TOTAL PROJECT COST SUMMARY

PLAYGROUND IMPROVEMENT PROJECT

Purchasing of Equipment 379,111.00
Construction Contract 492,133.80
Construction Change Order Costs 15,080.00
CMIT Contract 38,082.50
TOTAL $924,407.30

ALTERNATIVES:

The Council may elect to direct staff not to file a Notice of Completion for the project. If a Notice of Completion is not filed, the time period for subcontractor claims and the associated release of final retention on the Project would be extended from 30 to 90 days.

Reviewed By: Legal Review By: Approved By:

___________________ ___________________ _________________ Kristine Schmidt Megan Garibaldi Robert Nisbet
Assistant City Manager City Attorney City Manager

3 Meeting Date: March 7, 2023

Page 4 of 4 ends

ATTACHMENTS:

1. A Resolution of the City Council of the City Goleta, California Authorizing the Filing of a Notice of Completion of the Miscellaneous Park Improvement Project

2. Notice of Completion for the Miscellaneous Park Improvement Project (CIP 9066) 4 ATTACHMENT 1

Resolution No. 23-__ entitled “A Resolution of the City Council of the City of Goleta, California, Authorizing the Filing of a Notice of Completion for the Miscellaneous Park Improvement Project (9066)”
5 Resolution No.19-__ Notice of Completion for the Crosswalk at South Kellogg Avenue Project

RESOLUTION NO. 23 - ___

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

GOLETA, CALIFORNIA AUTHORIZING THE FILING OF A NOTICE

OF COMPLETION FOR THE MISCELLANEOUS PARK

IMPROVEMENT PROJECT

WHEREAS, on June 15, 2021 , the City of Goleta authorized award of a construction contract to R.E. Schultz Construction, Inc, for the Construction of the Miscellaneous Park Improvement Project; and

WHEREAS, the City Engineer has evaluated the work and has determined that the work was satisfactorily completed within the City extended contract period and within budget; and

WHEREAS, the City Engineer recommends the filing of a Notice of Completion pursuant to Government Code section 20854.

NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF GOLETA AS FOLLOWS:

SECTION 1.

The work required to be performed by said Contractor has been completed.

SECTION 2.

The work is hereby accepted and approved based on the recommendation of the City Engineer.

SECTION 3.

The Finance Department is directed to release retention posted for the completion of the project as required by the California Civil Code.

SECTION 4.

The City Clerk is directed to forthwith forward a Notice of Completion to the Recorder of the County of Santa Barbara for recording.

6 Resolution No.19-__ Notice of Completion for the Crosswalk at South Kellogg Avenue Project SECTION 5.

The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED, APPROVED, AND ADOPTED this 7th day of March, 2023.

__________________________

PAULA PEROTTE,
MAYOR

ATTEST: APPROVED AS TO FORM:

_________________________ __________________________
DEBORAH S. LOPEZ MEGAN GARIBALDI

CITY CLERK CITY ATTORNEY

7 Resolution No.19-__ Notice of Completion for the Crosswalk at South Kellogg Avenue Project

STATE OF CALIFORNIA )
COUNTY OF SANTA BARBARA ) ss.

CITY OF GOLETA )

I, DEBORAH S. LOPEZ, City Clerk of the City of Goleta, California, DO HEREBY CERTIFY that the foregoing Resolution No. 23-___ was duly adopted by the City Council of the City of Goleta at a regular meeting held on the 7th day of March, 2023, by the following vote of the Council:

AYES:

NOES:

ABSENT:

(SEAL)

___________________________
DEBORAH S. LOPEZ

CITY CLERK

8 ATTACHMENT 2

Notice of Completion for the Miscellaneous Park Improvement Project (9066) 9 RECORDING REQUESTED BY:

WHEN RECORDED RETURN TO:

City of Goleta
130 Cremona Drive, Suite B
Goleta, CA 93117
ATTN: CITY CLERK
__________________________________________________________________ SPACE ABOVE THIS LINE FOR RECORDER’S USE

Exempt from recording fee, per Government Code
Section 27383

CITY OF GOLETA, CALIFORNIA

By: __Deborah S. Lopez______
City Clerk

NOTICE OF COMPLETION

NOTICE IS HEREBY GIVEN that a contract was heretofore awarded by the City Council of the City of Goleta, California, to R.E. Shultz Construction, Inc., Rick Schultz, 1767 North Batavia Street, Orange, CA 92965 for the performance of the following work:

CONSTRUCTION OF MISCELLANEOUS PARK IMPROVEMENT PROJECT

Said work was substantially completed on June 30, 2022 , by said company; was completed in accordance with City standards and to the satisfaction of the City Engineer of the City of Goleta; and was accepted by the City Council of the City of Goleta, owner, at a regular meeting thereof held on the 7th day of March, 2023, by Resolution No. 23-__.

DATED this 7th day of March, 2023, at Goleta, California.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

______________________________
DEBORAH S. LOPEZ,

CITY CLERK
10 STATE OF CALIFORNIA )
COUNTY OF SANTA BARBARA ) ss

CITY OF GOLETA )

I, Deborah S. Lopez, City Clerk of the City of Goleta, California, do hereby certify that the foregoing Notice of Completion is true and correct, and that said Notice of Completion was duly and regularly ordered to be recorded in the Office of the Santa Barbara County Recorder by said City Council.

DATED this 7th day of March, 2023, at Goleta, California.

________________________________
DEBORAH S. LOPEZ

CITY CLERK