Agenda Item C.1

CPMS PUBLIC HEARING
Meeting Date: April 18, 2023
____________________________________________________________ TO: Mayor and Councilmembers
FROM: Charles W. Ebeling, Public Works Director
CONTACT: Teresa Lopes, Senior Project Manager
SUBJECT: Measure A Five-Year Program of Projects for FY 2023-2028 RECOMMENDATION:

A. Conduct a public hearing on the Measure A Five-Year Program of Projects for Fiscal Years 2023-2028; and
B. Adopt Resolution No. 23-___, entitled “A Resolution of the City Council of the City of Goleta, California, Adopting the Measure A Five -Year Local Program of Projects for FY 2023-2024 through FY 2027-2028.”
BACKGROUND:

In 2008 the voters of Santa Barbara County approved Local Transportation Authority Ordinance No. 5 (Ordinance), the Road Repair, Traffic Relief, and Transportation Safety Measure or “Measure A,” which established the Santa Barbara Transportation Improvement Program. Measure A i s funded through a local one -half percent sales tax for a period of 30 years. The Santa Barbara County Association of Government s (SBCAG) is the designated Local Transportation Authority and is responsible for the administration of the Measure A program an d the allocation of revenues to the local agencies.

Measure A is estimated to provide more than $1 billion in local sales tax revenues for transportation projects in Santa Barbara County over 30 years. The tax generated revenues are split between North a nd South areas of the County ( approximately 43.3% each) and the Highway 101 Widening Project (Carpinteria to Santa Barbara approximately 13.4%). Revenues to the North and South County areas are further divided up between various regional transportation pro jects and other local transportation programs identified in the adopted Measure A expenditure plan.

SBCAG has provided a five -year estimate of Measure A revenues (Attachment 1) and has calculated each jurisdiction’s allocation amounts in accordance with t he Ordinance.

To receive its annual allocation of Measure A funds, the City of Goleta is required to prepare and adopt a five-year capital expenditure program, also known as a Program of Projects (POP) for Measure A tax revenues. City Council approval of t he City’s POP must follow a noticed public hearing. The approved POP is then forwarded to SBCAG 1 Meeting Date: April 18, 2023

Page 2 of 4 ends

and is then presented to the SBCAG Board for review in April and adopt ion in May. A copy of the Measure A Local Allocation Rules Manual is located in the City C lerk’s office.

DISCUSSION:

Public Works has prepared a draft POP based on SBCAG’s estimated Measure A revenue projections (Exhibit A to Attachment 2). This year's proposed five-year program of projects is similar to the previous year's program. The transit programs continue to receive a direct allocation of Measure A funding off the top (see Attachment 1). A brief description of each category of the proposed Measure A Five-Year POP is as follows:

Maintenance, Improvement or Construction of Roadways & Bridges: This category provides for a portion of the costs associated with the City’s annual pavement program, street maintenance , and other eligible improvements included in the City’s Capital Improvement Program (CIP).

Urban Forestry Street Tree Program: This category covers a portion of the City’s annual street tree maintenance program.

Storm Damage Repair to Transportation Facilities: This category covers improvements and repairs to transportation facilities due to storm damage.

Roadway Drainage Facilities: This category covers the costs associated with developing and improving the City’s storm drain projects and programs.

Traffic Signal Coordination, Intersection Channelization: This category covers the costs associated with maintaining and improving the City’s signalized intersections.

Landscaping Maintenance: This category covers the costs associated with maintaining and improving the City’s landscaped medians and street rights-of-way.

Matching Funds f or State and Regional Programs and Projects: This category covers the costs associated with matching funding sources for upcoming and existing CIP projects.

Maintenance, Repair, Construction & Improvement of Bike & Pedestrian Facilities: This category provides for a portion of the cost s associated with the City’s annual sidewalk repair program and the maintenance and improvements to the City’s bicycle and pedestrian facilities.

Safe Routes to School Improvements: This category covers a portion of the cost s associated with improving school zone safety and other safe routes to schools’ improvements.

Reduced Transit Fares for Seniors & Disabled: This category covers the City’s share of an operations subsidy for transportation services provided by Easy Lift Transportation. 2 Meeting Date: April 18, 2023

Page 3 of 4 ends

The last three items listed above meet the City’s requirement to direct a minimum of 10% of the City’s Measure A funding to Alternative Transportation projects. For FY 2023-24 through FY 2027-28, the City anticipates exceeding the minimum requirement by projecting a total of approximately 44% on Alternative Transportation qualifying projects.

The table included in Attachment 1 shows the estimated amount of Measure A revenues the City will rec eive for FY 20 23-24 through FY 2027-28. These annual amounts were used to determine the future scope of projects listed in the five -year POP. The estimated apportionment, minus the South Coast Transit Operations amount, for FY 2023-24, is approximately $2.2 million.

The adoption of a five-year POP is a requirement included in the Ordinance. Adoption of a five -year POP does not necessarily bind the Council to the projects listed. The program can be modified at any time by the Council if changes to the plann ed expenditures are warranted. Measure A funds are intended to be flexible and adoption of the program is not meant to hinder Council policy with regard to street maintenance and project priorities. Staff is recommending the Council adopt the Measure A Five-Year Local Program of Projects for FY 20 23-24 through FY 2027-28 (Exhibit A to Attachment 2).

FISCAL IMPACTS:

The City will receive Measure A allocation of approximately $2,202,877 in FY 202 3-24 based on SBCAG’s estimates of future sales tax revenues.

Maintenance of Effort:

The Ordinance includes a Maintenance of Effort (MOE) provision requiring the City to continue to expend discretionary funds (e.g. General Fund) on eligible street expenditures equal to or greater than the amount spent before the Ord inance was adopted. Measure A revenues were meant to supplement the discretionary funds that local agencies had historically expended on transportation purposes. The purpose of the MOE provision is to discourage local agencies from reducing the amount of discretionary funds expended on transportation purposes after initiation of the Measure A program.

The SBCAG Board approves the MOE amounts annually. The Ordinance allows for the MOE expenditure to be averaged over five years instead of being required to b e expended on an annual basis. The table below lists the MOE five-year compliance period of FY 2020-21 through FY 2024-25. This is the third year of the five -year compliance period , the City exceeded the MOE amount for the prior five -year compliance period FY 2015-16 through FY 2019-20.

FISCAL YEAR
MOE Required Estimated Expenditures
Estimated
Total
FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25
$797,958 $913,859 $1,066,573 TBD TBD $2,778,390
3 Meeting Date: April 18, 2023

Page 4 of 4 ends

* Estimated, actual expenditures unknown at this time.

ALTERNATIVES:

While adoption of a five -year program of projects is required to receive allocated Measure A funds, the Council may adopt a modified five -year program of projects for submittal to SBCAG. Any modifications directed by the Council would be included in the information submitted to SBCAG.

Reviewed By: Legal Review By: Approved By:

___________________ ___________________ _________________ Kristine Schmidt Megan Garibaldi Robert Nisbet
Assistant City Manager City Attorney City Manager

ATTACHMENTS:

1. SBCAG Five-Year Estimate of Measure A Apportionments

2. Resolution No. 2 3-___ entitled “A Resolution of the City Council of the City of Goleta, California, Adopting the Measure A Five -Year Local Program of Projects for FY 2023-2024 through FY 2027-2028”

3. Measure A POP Presentation

FISCAL YEAR
MOE Actual Expenditures
Total
Expended
% of
MOE
FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25
$2,986,033 $7,625,643 $2,500,000* TBD TBD $13,111,676* 472%* 4 ATTACHMENT 1

SBCAG Five-Year Estimate of Measure A Apportionments
5 Jurisdiction Population Population % FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 TOTAL Alternative
Mode
Percentage
Total North County Estimates 237,924 100.000% $16,395,900 $16,834,567 $15,614,975 $16,298,420 $16,912,398 $82,056,260 Buellton 5,055 2.125% $435,604 $444,924 $419,012 $433,533 $446,577 $2,179,649 5% Guadalupe 8,544 3.591% $667,240 $682,993 $639,196 $663,739 $685,788 $3,338,956 5% Lompoc 43,845 18.428% $3,010,889 $3,091,727 $2,866,979 $2,992,925 $3,106,070 $15,068,591 15% Santa Maria 109,910 46.195% $7,396,974 $7,599,618 $7,036,223 $7,351,942 $7,635,572 $37,020,328 15% Solvang 5,709 2.400% $479,023 $489,549 $460,285 $476,684 $491,416 $2,396,957 15% Co. of Santa Barbara (unincorporated North County) 64,861 27.261% $4,406,170 $4,525,757 $4,193,280 $4,379,596 $4,546,975 $22,051,779 10% Total South Coast Estimates 207,240 100.000% $15,898,253 $16,323,606 $15,141,031 $15,803,732 $16,399,075 $79,565,696 Carpinteria 12,963 6.255% $1,069,427 $1,096,034 $1,022,063 $1,063,515 $1,100,754 $5,351,793 % of Gross Allocation for SC Transit Operations 7.96% $85,126 $87,244 $81,356 $84,656 $87,620 $426,003 Carpinteria $984,301 $1,008,789 $940,706 $978,859 $1,013,134 $4,925,790 10% Goleta 32,591 15.726% $2,537,292 $2,604,184 $2,418,209 $2,522,427 $2,616,052 $12,698,163 % of Gross Allocation for SC Transit Operations 13.18% $334,415 $343,231 $318,720 $332,456 $344,796 $1,673,618 Goleta $2,202,877 $2,260,952 $2,099,489 $2,189,971 $2,271,256 $11,024,545 10% Santa Barbara City 86,591 41.783% $6,575,638 $6,753,363 $6,259,247 $6,536,144 $6,784,896 $32,909,289 % of Gross Allocation for SC Transit Operations 26.05% $1,712,954 $1,759,251 $1,630,534 $1,702,666 $1,767,465 $8,572,870 Santa Barbara City $4,862,684 $4,994,112 $4,628,714 $4,833,478 $5,017,431 $24,336,419 10% Co. of Santa Barbara (unincorporated South Coast) 75,095 36.236% $5,715,896 $5,870,026 $5,441,512 $5,681,646 $5,897,372 $28,606,452 % of Gross Allocation for SC Transit Operations 11.12% $635,608 $652,747 $605,096 $631,799 $655,788 $3,181,037 Co. of Santa Barbara (unincorporated South Coast) $5,080,289 $5,217,279 $4,836,416 $5,049,847 $5,241,585 $25,425,415 10% South Coast Transit Operations Program TOTAL $2,768,103 $2,842,474 $2,635,706 $2,751,576 $2,855,669 $13,853,528 Population estimates reflect California Department of Finance (DOF) figures for January 2022. https://dof.ca.gov/forecasting/de mographics/estimates-e1/ North/South unincorporated split is based on 2020 US Census, 2020 American Community Survey, 5 year estimates All local jurisdictions receive a $100,000 base allocation Table 3 - Local Agency Apportionments
Five Year Measure A Revenue Estimate
FY 2023/24 to FY 2027/28
11/16/2022
6 ATTACHMENT 2

Resolution 23-____, entitled “A Resolution of the City Council of the City of Goleta, California, Adopting the Measure A Five-Year Local Program of Projects for FY 2023- 2024 through FY 2027-2028”
7 RESOLUTION NO. 23-___

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

GOLETA, CALIFORNIA, ADOPTING THE MEASURE A FIVE-
YEAR LOCAL PROGRAM OF PROJECTS FOR FY 2023-2024
THROUGH 2027-2028

WHEREAS, on November 8, 2008, the voters of Sa nta Barbara County approved Local Transportation Authority Ordinance No. 5, the Road Repair, Traffic Relief and Transportation Safety Measure (“Measure A”); and

WHEREAS, Measure A provides that the Santa Barbara County Local Transportation Authority shall annually approve a program of projects submitted by local jurisdictions identifying those transportation projects eligible to use Measure A funds during the succeeding five-year program; and

WHEREAS, the City of Goleta was provided with an estimate of annual Measure A local revenues for Fiscal Years 2023-2024 through 2027-2028; and

WHEREAS, the City of Goleta has held a public hearing in accordance with Section 18 of the Measure A.

NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF GOLETA, AS FOLLOWS:

SECTION 1.

That the attached Five-Year Program of Projects, attached hereto as Exhibit A, to be funded in part, by Measure A revenues is approved.

SECTION 2.

That the City of Goleta will include in its FY 20 23-24 budget an amount of local discretionary funding for local streets and roads sufficient to comply with the Maintenance of Effort requirements contained in Section 27 of Measure A.

SECTION 3.

That the City of Goleta will not use Measure A revenues to replace private developer funding that has been committed to transportation projects or would otherwise by required under current City policies.

SECTION 4.

That the City of Goleta has complied with all other applicable provisions and requirements of Measure A.

8 SECTION 5.

The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED, APPROVED AND ADOPTED this 18th day of April 2023.

__________________________

PAULA PEROTTE, MAYOR

ATTEST: APPROVED AS TO FORM:

_________________________ __________________________
DEBORAH S. LOPEZ MEGAN GARIBALDI

CITY CLERK CITY ATTORNEY

9 STATE OF CALIFORNIA )
COUNTY OF SANTA BARBARA ) ss.

CITY OF GOLETA )

I, DEBORAH S. LOPEZ, City Clerk of the City of Goleta, California, DO HEREBY CERTIFY that the foregoing Resolution No. 23-__ was duly adopted by the City Council of the City of Goleta a t a regular meeting held on the 18th day of April 2023, by the following vote of the Council:

AYES:

NOES:

ABSENT:

(SEAL)

_________________________
DEBORAH S. LOPEZ

CITY CLERK

10 Local Street & Transportation Improvements Total Project Cost
For Santa Barbara County
Only
Project Descriptions
FY 2021/22
Actual
Expenditures
Carry-over
from FY
21/22
Carry-over
from FY
22/23
FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 TOTAL Measure A Revenues Local State Federal TOTAL Non-Measure A
Revenues
Class 2 Bikeway Maintenance
Expenditure - Count as
Alternative Transportation
Expenditure
Maintainance, Improvement or Construction of Roadways & Bridges Pavement Rehabilitation (5800-51073) $19 $821 $817 $300 $300 $300 $300 $300 $2,317 $4,040 $4,040 $6,357 Pavement Maintenance (5800-51062) $43 $94 $118 $75 $75 $75 $75 $75 $493 $550 $550 $1,043 Striping and Signage (5800-51074) $6 $117 $191 $75 $75 $75 $75 $75 $566 $125 $125 $691 Ekwill Street & Fowler Road Extensions (9002) $0 $17,900 $11,300 $29,200 $29,200 Goleta 101 Overcrossing (9027) $0 $41,000 $50,000 $50,000 Hollister Avenue Bridge Project (9033) $9 $57 $57 $57 $3,110 $15,300 $18,410 $18,467 Hollister Avenue Widening - Storke to 280 feet west of Glen Annie (9044) $0 $14 $14 $14 $3,088 $3,088 $3,102 Safety Improvements
$0 $0 $0
Urban Forestry Street Tree Program
Street Tree Maintenance (5800-51067) $63 $317 $659 $300 $300 $300 $300 $300 $2,159 $0 $2,159 Storm Damage Repair to Transportation Facilities
Cathedral Oaks Crib Wall (9053) $0 $0 $0 $521 $200 $721 $17,600 $17,600 $18,321 Old Town S. Fairview Ave Drainage Improvements (9107) $350 Roadway Drainage Facilities
Old Town Goleta Drainage Study (9085) $0 $0 $100 $100 $1,000 $1,000 $1,100 Traffic Signal Coordination, Intersection Channelization Traffic Signal Maintenance (5700-51076) $31 $556 $334 $250 $250 $100 $150 $200 $1,284 $0 $1,284 Traffic Signal Upgrades (9083) $0 $95 $95 $95 $3,120 $3,120 $3,215 Traffic Management
$0 $0 $0
Landscaping Maintenance
Median and Parkway Maintenance (5800-51066) $88 $29 $110 $120 $120 $120 $100 $100 $670 $0 $670 Highway Improvements
$0 $0 $0
Matching Funds for State and Regional Programs and Projects Misc. Capital Improvement Projects $0 $0 $0 $100 $100 $200 $200 $600 $0 $600 TOTAL $259 $2,100 $2,495 $1,120 $1,741 $1,270 $1,200 $1,250 $9,076 $88,763 $14,420 $15,300 $127,133 $136,209 $0 Alternative Transportation Expenditures Total Project
Cost
Project Descriptions
FY 2021/22
Actual
Expenditures
Carry-over
from FY
21/22
Carry-over
from FY
22/23
FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 TOTAL Measure A Revenues Local State Federal TOTAL Non-Measure A
Revenues
Maintenance, Repair, Construction & Improvement of Bike & Ped Facilities $0 Concrete Maintenance and Access Ramps (5800-51071) $2 $219 $366 $220 $220 $220 $220 $220 $1,466 $3,604 $3,604 $5,070 Hollister Avenue Complete Streets (9001) $0 $25 $24 $24 $600 $236 $836 $860 San Jose Creek Multipurpose Path [ATP] (9006) $1 $24 $494 $500 $250 $1,244 $10,000 $4,270 $15,910 $30,180 $31,424 San Jose Creek Middle - Segment 1 (9007) $0 $130 $160 $160 $868,600 $868,600 $868,760 Old Town Sidewalk [ATP] (completed) (9031) $18 $307 $306 $306 $1,721 $1,721 $2,027 RRFB at Chapel/ PHB at Kingston (completed) (9058) $6 $42 $42 $42 $133 $237 $370 $412 Storke Road Transit, Bicycle, Pedestrian Improvements (9062) $0 $1,900 Fairview Sidewalk Infill at Calle Real/US 101 (completed) (9070) $0 $18 $18 $18 $79 $79 $97 Vision Zero Plan (9086) $0 $10 $10 $227 $501 $738 $1,205 $1,205 $1,943 Crosswalk PHB on Calle Real near Encina Lane (completed) (9087) $89 $84 $84 $84 $180 $180 $264 RRFB at School Zone Crossing (completed) (9088) $232 $96 $96 $96 $344 $344 $440 Goleta Traffic Safety Study [GTSS] (9089) $0 $46 $46 $46 $45 $278 $323 $369 Fairview Corridor Study (9097) $0 $90 $90 $300 $390 $530 $530 $920 Crosswalk at S. Kellogg Ave (completed) (9098) $0 $30 $30 $30 $100 $100 $130 Crosswalk at Calle Real/Fairview Center - PHB (9099) $24 $130 $223 $223 $330 $300 $630 $853 Storke Road Corridor Study (9102) $0 $54 $54 $54 $506 $506 $560 Citywide School Zones Signage & Striping Evaluation (9103) $0 $20 $20 $20 $197 $197 $217 Citywide Evaluation of Existing Traffic Signals (9104) $0 $69 $69 $69 $100 $100 $169 Hollister Ave Class I Bike Path - Lighting (9110) $20 $244 $244 $244 $480 $480 $724 Hollister Avenue Old Town Interim Striping Project (9114) $72 $78 $115 $312 $427 $2,558 $2,558 $2,985 Cathedral Oaks Class I Multipurpose Path (9061) $0 $20,260 $20,260 $20,260 Hollister Avenue Sidewalk Improvement at Ellwood School $0 $1,043 Rectangular Rapid Flashing Beacons (RRFBs) Calle Real @ Jenna (90125) $0 $318 Fairview Ave and Stowe Canyon Intersection Improvements (90124) $332 $720 $1,052 $1,538 $1,538 $2,590 Safe Routes to School Improvements
Safe Routes to School Improvements - Street Striping (5800-51081) $0 $25 $50 $25 $25 $25 $25 $150 $0 $150 Reduced Transit Fares for Seniors & Disabled
Paratransit/Easy Lift (5800-51308) $25 $0 $25 $25 $25 $25 $25 $125 $0 $125 Bus and Rail Transit Services and Facilties
$0 $0 $0
Programs, Education, & Incentives to Reduce Single Occupant Auto Trips or Transportation Demand
$0 $0 $0
TOTAL ALTERNATIVE TRANSPORTATION EXPENDITURES $489 $1,741 $2,566 $1,082 $520 $829 $990 $1,021 $7,008 $914,650 $6,569 $16,383 $934,341 $941,349 TOTAL EXPENDITURES $748 $3,841 $5,061 $2,202 $2,261 $2,099 $2,190 $2,271 $16,084 $1,003,413 $20,989 $31,683 $1,061,474 $1,077,558 Alternative Transportation Summary
TOTAL MEASURE A ALLOCATION (FY 2023/24 TO 2027/28) $16,084

MINIMUM ALTERNATIVE PERCENTAGE PRESCRIBED BY INVESTMENT PLAN TO BE MET BY FY 2024/25 FOR FISCAL YEARS 2020/21 THROUGH 2024/25 10% TOTAL MEASURE A ALLOCATION TO ALTERNATIVE TRANSPORTATION $7,008

PERCENTAGE OF MEASURE A ALLOCATION TO ALTERNATIVE
TRANSPORTATION 43.6%
Non-Measure A Revenues
City of Goleta
Five Year Measure A Program of Projects (FYs 23/24 to 27/28) Measure A Local Street and Transportation Improvements Submittal Form (Figures in $1000's)
Measure A Revenues Non-Measure A Revenues
11 ATTACHMENT 3

Measure A POP Presentation
12 Measure A Program of
Projects Overview
April 18, 2023
Public Works Department
Teresa Lopes, Sr. Project Manager
13 Adopted in 2008
Local one-half percent sales tax over 30 years
Generate approx. $1.05 billion over 30 years
Administered by Santa Barbara County
Association of Governments (SBCAG)
Measure A - Overview
April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 2 14 Estimated $252.9 million – next five years
FY2023/24 to 2027/28
$197 million – Local Agencies
$56 million – Hwy 101 and Named Projects
Goleta –
$11 million over five years
Alternative Transportation Percentage – ~44%
Measure A – Local Impacts
April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 3 15 Program of Projects (POP)
 Required annually
 Identify all projects during five-year period
 Projects listed by categories
 Projects and revenues similar to last year
San Jose Creek Bike Path – Northern and Southern
Segments
Hollister Interim Striping Project
Bicycle and Pedestrian focused projects
Measure A POP
April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 4 16 5April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 17  Projects Recently Completed
 Pavement Rehabilitation Project 20/21
 RRFB at School Zone Crossings (Project No. 9088)
 Goleta Traffic Safety Study (Project No. 9089)
 Projects in Final Design/Construction
 Pavement Rehabilitation Project (22 Construction, 23 Design)  Miscellaneous Concrete Repair Project (Final Design)
 Crosswalk at Calle Real / Fairview Center – PHB (9099) (Construction)  San Jose Creek Bike Path - Middle Extent (Project No. 9007) (Construction)  Ekwill & Fowler Extensions/Hollister Roundabouts (Project No. 9002) (Construction)
 Hollister Avenue Bridge (Project No. 9033) (Construction)  Hollister Avenue Old Town Interim Striping (Project No. 9114) (Construction)  Hollister Avenue Class 1 Bike Path Lighting (Project No. 9110) (Final Design)  San Jose Creek Multipurpose Path Northern and Southern Segments (9006) (Design)
List of Projects
April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 6 18 Questions?
April 18, 2023, City Council Meeting – Measure A Program of Projects Overview 7 19