Agenda Item A.3

CPMS CONSENT CALENDAR
Meeting Date: May 7, 2024
TO: Mayor and Councilmembers
SUBMITTED BY: Luz “Nina” Buelna, Interim Public Works Director PREPARED BY: Michael Winnewisser, Assistant Engineer
SUBJECT: Ratification of Agreements for 202 4 Emergency Storm Repair Projects
RECOMMENDATION:

A. Ratify the Professional Design Services Agreement with RRM Design Group, Inc. executed by the City Manager, for the 2024 Emergency Storm Repair Projects for a total not-to-exceed of $200,000 for a term ending June 30, 2025; B. Ratify the Professional Services Agreement with Pacific Materials Laboratory executed by the City Manager for the 2024 Emergency Storm Repair Projects for a total not-to-exceed of $100,000 for a term ending June 30, 2025; C. Ratify the Public Works Contract with Toro Enterprise s Inc. for Evergreen Storm Drain Repair, for a total not-to-exceed amount of $388,024.13; D. Ratify the Public Works Contract with Toro Enterprise s Inc. for Newport Creek Culvert Repair Project, for a total not-to-exceed amount of $794,117; E. Ratify the Public Works Contract with Toro Enterprises Inc. for Camino Venturoso Debris Removal, for a total not-to-exceed amount of $82,225; F. Ratify the Public Works Contract with Bob’s Backhoe and Trucking, for Ellwood Mesa Emergency Access Road Repair Project, for a total not -to-exceed amount of $157,068; and
G. Ratify the Public Works Contract with Bob’s Backhoe and Trucking, for San Pedro Creek and Storm Drain Repair Project, for a total not -to-exceed amount of $296,616.
1 Meeting Date: May 7, 2024

Page 2 of 6 ends

BACKGROUND:

In early February 2024, City of Goleta (City) staff began monitoring the potential for heavy rains to impact Santa Barbara County, particularly portions of the more densely populated areas of South County.

On February 4, 2024, an atmospheric river storm struck California. The significant rainfall caused flooding on public streets, watersheds, creeks, open spaces, wetlands, and other property in the City; damage to public rights-of-way; downed trees blocking sidewalks and streets; road closures; and disruption of public service s. The storm prompted the City of Goleta to declare a local emergency on February 4, 2024.

Pursuant to City of Goleta Municipal Code Section 3.05.120 for Urgencies, Public Works staff engaged in immediate emergency operations by securing necessary contractors and consultants to permit the continued performance of the City's operations and services and avoid the immediate danger to life, health, or property caused by the storm.

DISCUSSION:

As a result of the storm, a wide range of damage occurred throughout the City of Goleta.

Public Works staff created a list of damages and consolidated them into the Public Works February 2024 Storm Damage List, which names each project and describes the damage caused by the storm , as well as needed repairs. The emergency agreements and amendments referenced in this report are necessary to cover services for one or more projects included on this list, as well as emergency clean-up and maintenance measures.

The current list is outlined below in Table 1.

Table 1: Public Works February 2024 Storm Damage List

Project Name Project Description
Ellwood Mesa Emergency
Access Road
The service roadway to Ellwood Mesa was
irreparably damaged. Repairs include installing
and reinforcing a new culvert and restoring the
access road overtop.

San Pedro Creek and
Storm Drain Repair
The storm drain's concrete collar was exposed
and separated from a pipe in the high storm
flows. Repairs include excavating the existing
pipe and installing the new c ollar, headwall,
and footing. Nearby downed trees must also be
removed.

Ellwood Beach Dr. Drain
Repair
High flows caused erosion of the nearby slope
past the end o f the roadway , repaired outlet
has been plugged by debris and sediment .

Repairs include the installation of a drainage
system to mitigate flows.
2 Meeting Date: May 7, 2024

Page 3 of 6 ends

San Rossano & Padova
Drain Replacement
A sinkhole developed in the parkway near the
curb drain inlet by Evergreen Park due to pipe
erosion. Repairs include excavatio n,
replacement of eroded pipe, back fill, and soil
compaction.

Cathedral Oaks Road
Due to the heavy rains, further erosion of the
underground voids has been anticipated,
resulting in the closure of the westbound lane .

Based on the geotechnical report, The lane has
been reopened, and staff i s working to hire a
design consultant to perform the final design.

Ellwood Mesa Trail
Erosion and Beach
Access Erosion
Due to the heavy rainfall, the coastal bluffs
eroded at two locations , and several beach
access trails were damaged . Repairs include
regrading trail segments to redirect runoff water
away from the bluff and cleaning up eroded
areas.

Newport Creek Culvert
The southern end of the culvert is severely
undermined. Repairs include stabilization of
culvert and creek bed with concrete foam an d
rip rap.

Camino Venturoso Debris
Removal
The drainage pipe has been plugged with
debris and sediment. The repairs include
excavating and clearing debris.

Brandon Open Space
The v-ditch has been undermined, a sinkhole
has formed in the channel and hillside, and the
hillside has begun to slump. Repairs include
backfill and compacting of damaged areas.

Tree Damage
93 trees across a ll parks and open spaces
were damaged or destroyed. Debris clearing,
chipping, and tree felling will be performed
under t he direction of certified arborists and
biologists.

Beach Debris Cleanup
Debris (trees, trash, sediment, etc.) washed up
onto City beaches throughout the storm event
and must be removed and disposed of.

Evergreen Drainage
Repair Project
The drainage pipe has corroded and caused
erosion of the hillside.

Emergency Services Agreements
RRM Design Group, Inc. (RRM)
RRM has been selected to enter into a Professional Design Service Agreement to provide design support for the Ellwood Mesa Beach Access Erosion Repair Project and any future anticipated Ellwood Mesa erosion projects . Table 2 provides the estimated cost and 3 Meeting Date: May 7, 2024

Page 4 of 6 ends

funding source for the contract. The Professional Design Services Agreement with RRM has a total not -to-exceed of $ 200,000 and an expiration date of June 30, 2025, and is included as Attachment 1.

Pacific Materials Laboratory (PML)
PML has been selected to enter into a Professional Service Agreement to provide materials testing and geotechnical testing services for the various 2024 Emergency Storm Repair Projects listed in Table 1. Table 2 provides the estimated cost and funding source for the contract. The Professional Services Agreement with PML has a total not-to-exceed of $100,000 and an expiration date of June 30, 2025, and is included as Attachment 2.

Toro Enterprises, Inc. (Toro)
Toro was selected to enter into a Public Works Contract to repair the Evergreen Drainage Repair Project listed in Table 1. The repairs for this project consist of replacing the existing corrugated metal pipe from the existing catch basin on San Rosano to the v -ditch in Evergreen Park, installing a new energy dissipation structure at the discharge point of the storm drain, and filling in the erosion area. Table 2 provides the estimated costs and funding source for the contract. The Public Works Contract has a total not -to-exceed of $388,024.13 and is included as Attachment 3.

Toro Enterprises, Inc. (Toro)
Toro was selected to enter into a Public Works Contract to repair the Newport Creek Culvert Repair Project listed in Table 1. The repairs for this project consist of replacing the existing corrugated metal pipe from the existing catch basin on San Rosano to the v- ditch in Evergreen Park, installing a new energy dissipator structure at the discharge point of the storm drain, and filling in the erosion area. Table 2 provides the estimated costs and funding source for the contract. The Public Works Contract has a total not-to-exceed of $794,117 and is included as Attachment 4.

Toro Enterprises, Inc. (Toro)
Toro was selected to enter into a Public Works Contract for the Camino Venturoso Debris Removal listed in Table 1. Th is project is to remove the debris build up in the existing storm drain and channel. Table 2 provides the estimated costs and funding source for the contract. The Public Works Contract has a total not-to-exceed of $82,225 and is included as Attachment 5.

Bob’s Backhoe and Trucking
Bob’s Backhoe and Trucking was selected to enter into a Public Works Contract to repair the Ellwood Mesa Emergency Access Road Project listed in Table 1. The repairs for this project consist of installing a new 72 -inch storm drainpipe, backfill, and placing asphalt.

Table 2 provides the estimated costs and funding source for the cont ract. The Public Works Contract has a total not-to-exceed of $157,068 and is included as Attachment 6. 4 Meeting Date: May 7, 2024

Page 5 of 6 ends

Bob’s Backhoe and Trucking
Bob’s Backhoe and Trucking was selected to enter into a Public Works Contract to repair San Pedro Creek and Storm Drain Rep air listed in Table 1. The repairs for this project consist of installing a new storm drainpipe, backfill, and erosion protection. Table 2 provides the estimated costs and funding source for the contract. The Public Works Contract has a total not-to-exceed of $296,616 and is included in Attachment 7.

FISCAL IMPACTS:

There is an available balance of $1,846,808 in account 101-50-5200-54004 – Emergency Response to be used to fund the emergency projects. Budget for the RRM and PML agreements will be encumbered on a task order basis due to the limited available funding for the various storm damaged projects. If no budget is available, a task order should not be issued, as both budget authority and contract authority are needed to move forward with services.

Table 2 – Estimated Costs and Funding for Storm Damages Projects Storm
Year
Consultant Project
Components
Not-to-
Exceed
Amount
Funding Source Funding
Amounts
2024 RRM Design Services
(On-Call)
$200,000 General Fund (101-
50-5200-54004)
$1,760,982
2024 PML Construction
Services Materials
Testing Services
(On-Call)
$100,000 General Fund (101-
90-9120-57071)
$100,000
2024 Toro Evergreen Storm
Drain Repair
$388,024 MBHMP (322-90-
9112-57071)
$157,068
2023 Toro Newport Creek
Culvert Repair
$794,117
2024 Toro Camino
Venturoso Debris
Removal
$82,225
2024 Bob’s
Backhoe
Ellwood Mesa
Access Road
Repair
$157,068
2023 Bob’s
Backhoe
San Pedro Creek
and Storm Drain
Repair
$296,616
Total $2,018,050 Total $2,018,050
ALTERNATIVES:
5 Meeting Date: May 7, 2024

Page 6 of 6 ends

The City Council can elect not to approve the amendments and agreements discussed herein; however, this would result in significant delays to the initiation and completion of the work associated with these emergency storm projects. This delay would result in many of these locations being inaccessible and hazardous to the public.

LEGAL REVIEW BY: Megan Garibaldi, City Attorney

APPROVED BY: Robert Nisbet, City Manager

ATTACHMENTS:

1. Professional Design Services Agreement with RRM Design Group, Inc.

2. Professional Services Agreement with Pacific Materials Laboratory, Inc.

3. Public Works Contract with Toro Enterprises, Inc. Evergreen

4. Public Works Contract with Toro Enterprises, Inc. Newport

5. Public Works Contract with Toro Enterprises, Inc. Camino Venturoso

6. Public Works Contract with Bob’s Backhoe Ellwood Mesa

7. Public Works Contract with Bob’s Backhoe San Pedro

6 ATTACHMENT 1

Professional Design Services Agreement with RRM Design Group, Inc.

7 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 1 of 27 ends

Project Name: 2024 Emergency Repair Projects

AGREEMENT FOR PROFESSIONAL DESIGN SERVICES

BETWEEN THE CITY OF GOLETA
AND
RRM DESIGN GROUP, INC.

This AGREEMENT FOR PROFESSIONAL DESIGN SERVICES (herein referred to as “AGREEMENT”) is made and entered into this ________ day of ______ , 20____, by and between the CITY OF GOLETA , a municipal corporation (herein referred to as "CITY"), and RRM DESIGN GROUP, INC., a California Corporation (herein referred to as "CONSULTANT").

SECTION A. RECITALS

1. The CITY has a need for professional design services for the 2024 Emergency Repair Projects; and

2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for professional services to accomplish this work; and

3. Goleta Municipal Code Section 2.10.040(A)(6)(a) allows the City Manager (referenced as “Director of Emergency Services”) to “make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency; provided however, such rules and regulations must be confirmed at the earliest practicable time by the City Council”; and

4. An emergency exists in the CITY due to the severe storms of February 2024 which caused significant damage to roadways and CITY infrastructure. Therefore, it is necessary to the public health and safety that the City Manager immediately authorize the start of work on emergency mitigation measures, subject to ratification by City Council; and

5. The City Manager authorized this agreement pursuant to Goleta Municipal Code Section 2.10.040(A)(6)(a) and the City Council ratified this agreement at its next public meeting.

8 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 2 of 27 ends

SECTION B. TERMS

1. RETENTION AS CONSULTANT
CITY hereby retains CONSULTANT, and CONSULTANT hereby accepts such engagement, to perform the services described in Section 2.

CONSULTANT warrants it has the qualifications, experience, and facilities to properly and timely perform said services.

2. DESCRIPTION OF SERVICES
The services to be performed by CONSULTANT are as follows:

Professional Design Services in conjunction with the 2024 Emergency Storm Repair Projects shall generally include coordination, permitting, design development, landscape and civil development, topographic surveys, and soils engineering as more particularly set forth in the Scope of Work, attached as Exhibit “A,” and incorporated herein.

3. COMPENSATION AND PAYMENT
(a) Maximum and Rate . The total compensation payable to CONSULTANT by CITY for the services under this AGREEMENT SHALL NOT EXCEED the sum of $200,000 (herein "not to exceed amount"), and shall be earned as the work progresses on the following basis:

Hourly at the hourly rates and with reimbursement to
CONSULTANT for those expenses set forth in CONSULTANT's Schedule of Fees marked Exhibit "B," attached and incorporated herein. The rates and expenses set forth in that exhibit shall be binding upon CONSULTANT until June 30, 2025 after which any change in said rates and expenses must be approved in writing by CITY's Project Manager as described in Section 5 (CITY is to be given 60 days notice of any rate increase request), provided the not to exceed amount is the total compensation due CONSULTANT for all work described under this AGREEMENT.
(b) Payment . CONSULTANT shall provide CITY with written verification of the actual compensation earned, which written verification shall be in a form satisfactory to CITY's Project Manager, as described in Section 5.

Invoices shall be made no more frequently than on a monthly basis, and describe the work performed (including a list of hours worked by personnel classification).

All payments shall be made within 30 days after CITY’s approval of the invoice.

4. EXTRA SERVICES
9 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 3 of 27 ends

CITY shall pay CONSULTANT for those CITY authorized extra services, not reasonably included within the services described in Section 2, as mutually agreed to writing in advance of the incurrence of extra services by CONSULTANT. Unless CITY and CONSULTANT have agreed in writing before the performance of extra services, no liability and no right to claim compensation for such extra services or expenses shall exist. The applicable hourly rates for extra services shall be at the hourly rates set forth in Exhibit B, if one is included as part of this agreement. Any compensation for extra services shall be part of the total compensation and shall not increase the not to exceed amount identified in Section 3.

5. CITY PROJECT MANAGER AND SERVICES BY CITY
The services to be performed by CONSULTANT shall be accomplished under the general direction of, and coordinate with, CITY's "Project Manager", as that staff person is designated by CITY from time to time, and who presently is George Thomson. Project Manager shall have the authority to act on behalf of the CITY in administering this AGREEMENT but shall not be authorized to extend the term of the AGREEMENT or increase the not to exceed amount.

6. TERM, PROGRESS AND COMPLETION
The term of this AGREEMENT is from the date first written above to June 30, 2025, unless term of this AGREEMENT is extended, or the AGREEMENT is terminated as provided for herein.

CONSULTANT shall not commence work on the services to be performed until (i) CONSULTANT furnishes proof of insurance as required by Section 10 below, and (ii) CITY gives written authorization to proceed with the work provided by CITY's Project Manager.

7. OWNERSHIP OF DOCUMENTS
All drawings, designs, data, photographs, reports and other documentation (other than CONSULTANT's drafts, notes and internal memorandum), including duplication of same prepared by CONSULTANT in the performance of these services, are the property of CITY. CITY shall be entitled to immediate possession of the same upon completion of the work under this AGREEMENT, or at any earlier or later time when requested by CITY. CITY agrees to hold CONSULTANT harmless from all damages, claims, expenses, and losses arising out of any reuse of the plans and specifications for purposes other than those described in this AGREEMENT, unless written authorization of CONSULTANT is first obtained.
10 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 4 of 27 ends

8. PERSONAL SERVICES/NO ASSIGNMENT/SUBCONTRACTOR
This AGREEMENT is for professional services which are personal to CITY. Michael Hamilton is deemed to be specially experienced and is a key member of CONSULTANT's firm, and shall be directly involved in the performance of this work. This key person shall communicate with, and periodically report to, CITY on the progress of the work. Should any such individual be removed from assisting in this contracted work for any reason, CITY may terminate this AGREEMENT. This AGREEMENT may not be assigned or subcontracted without the City Manager’s prior written consent.

9. HOLD HARMLESS AND INDEMNITY
(a) Indemnification and Defense for Professional Service. To the fullest extent permitted by law, Consultant shall indemnify, defend and hold harmless the CITY and any and all of its officials, employees and agents (“Indemnified Parties”) from and against any and all claims, losses, liabilities, damages, costs and expenses, including attorney’s fees and costs, to the extent they arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the CONSULTANT.

CONSULTANT’s duty to defend shall consist of reimbursement of defense costs incurred by CITY in direct proportion to the CONSULTANT’s proportionate percentage of fault. CONSULTANT’s percentage of fault shall be determined, as applicable, by a court of law, jury or arbitrator. In the event any loss, liability or damage is incurred by way of settlement or resolution without a court, jury or arbitrator having made a determination of the CONSULTANT’s percentage of fault, the parties agree to mediation with a third party neutral to determine the CONSULTANT’s proportionate percentage of fault for purposes of determining the amount of indemnity and defense cost reimbursement owed to the CITY.
(b) For All Other Liabilities. Notwithstanding the foregoing and without diminishing any rights of CITY, for any liability, claim, demand, allegation against CITY arising out of, related to, or pertaining to any act or omission of CONSULTANT, but which is not a design professional service, CONSULTANT shall defend, indemnify, and hold harmless CITY, its officials, employees, and agents (“Indemnified Parties”) from and against any and all damages, costs, expenses (including reasonable attorney fees and expert witness fees), judgments, settlements, and/or arbitration awards, whether for personal or bodily injury, property damage, or economic injury, and arising out of, related to, any concurrent or contributory negligence on the part of the CITY, except for the sole or active negligence of, or willful misconduct of the CITY. (c) No Waiver. ClTY does not waive, nor shall be deemed to have waived, any indemnity, defense or hold harmless rights under this section 11 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 5 of 27 ends

because of the acceptance by CITY, or the deposit with CITY, of any insurance certificates or policies described in Section 10.

10. INSURANCE
CONSULTANT shall, at CONSULTANT's sole cost and expense, provide insurance as described herein. All insurance is to be placed with insurers authorized to do business in the State of California with an A.M. Best and Company rating of A- or better, Class VII or better, or as otherwise approved by CITY.

Insurance shall include the following (or broader) coverage:
a) Insurance Services Office Commercial Liability coverage “occurrence” form CG 00 01 or its exact equivalent with an edition date prior to 2004 and with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate.

b) Insurance Services Office form number CA 00 01 or equivalent covering Automobile Liability, including hired and non-owned automobile liability with a minimum limit of $1,000,000 per accident. If the Service Provider owns no vehicles, this requirement may be satisfied by a non-owned and hired auto endorsement to Service Provider’s commercial general liability policy.

c) Workers’ Compensation insurance complying with California worker’s compensation laws, including statutory limits for workers’ compensation and an Employer’s Liability limit of $1,000,000 per accident or disease.

d) Professional liability insurance that covers the services to be performed in connection with this agreement, in the minimum amount of $1,000,000 per claim.

Liability insurance policies required to be provided by CONSULTANT hereunder shall contain or be endorsed to contain the following provisions:

a) Except for professional liability insurance, CITY, its employees, officials, agents and member agencies shall be covered as additional insureds. Coverage shall apply to any and all liability arising out of the work performed or related to the contract. Additional insured status under the general liability requirement shall be provided on Insurance Services Office Form CG 20 10, with an edition date prior to 2004, or its equivalent. Additional insured status for completed operations shall be provided either in the additional insured form or through another endorsement such as CG 20 37, or its equivalent. 12 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 6 of 27 ends

b) General and automobile liability insurance shall apply separately to each insured against whom a claim is made or suit is brought, except with respect to the limits of the insurer’s liability. Coverage will not be limited to CITY’s vicarious liability.
c) Professional liability insurance policies inception date, continuity date, or retroactive date must be before the effective date of this agreement. CONSULTANT agrees to maintain continuous coverage through a period no less than three years after completion of the services required by this agreement.
d) Except for professional liability insurance, liability coverage shall be primary and non-contributing with any insurance maintained by CITY.

e) Evidence of coverage (including the workers’ compensation and employer’s liability policies) shall provide that coverage shall not be suspended, voided, canceled or reduced in coverage or in limits except after 30 days’ prior written notice has been given to CITY.

Such provision shall not include any limitation of liability of the insurer for failure to provide such notice.

f) No liability insurance coverage provided to comply with this AGREEMENT shall prohibit CONSULTANT, or CONSULTANT’s
employees, or agents, from waiving the right of recovery prior to a loss. CONSULTANT waives its right of recovery against CITY.

g) CONSULTANT agrees to deposit with CITY within fifteen days of Notice to Proceed of the Contract certificates of insurance and required endorsements.

h) There shall be no recourse against CITY for payment of premiums or other amounts with respect to the insurance required to be provided by CONSULTANT hereunder. Any failure, actual or alleged, on the part of CITY to monitor compliance with these requirements will not be deemed as a waiver of any rights on the part of CITY. CITY has no additional obligations by virtue of requiring the insurance set forth herein. In the event any policy of insurance required under this AGREEMENT does not comply with these requirements or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONSULTANT or CITY will withhold amounts sufficient to pay premium from CONSULTANT payments.

13 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 7 of 27 ends

i) CONSULTANT agrees to provide immediate notice to CITY of any claim or loss against CONSULTANT arising out of the work performed under this AGREEMENT. CITY assumes no obligation or liability by such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve CITY.

11. RELATIONSHIP OF CONSULTANT TO CITY
The relationship of the CONSULTANT to CITY shall be that of an independent contractor and that in no event shall CONSULTANT be considered an officer, agent, servant or employee of CITY. CONSULTANT shall be solely responsible for any workers compensation insurance, withholding taxes, unemployment insurance, and any other employer obligations associated with the described work.

12. CORRECTIONS
In addition to the above indemnification obligations, CONSULTANT shall correct, at its expense, all errors in the work that may be disclosed during CITY's review of CONSULTANT's report or plans. Should CONSULTANT fail to make such correction in a reasonably timely manner, such correction shall be made by CITY, and the cost thereof shall be charged to CONSULTANT or withheld from any funds due to CONSULTANT hereunder.

13. TERMINATION BY CITY
CITY, by notifying CONSULTANT in writing, may upon 10 calendar days notice, terminate without cause any portion or all of the services agreed to be performed under this AGREEMENT. If termination is for cause, no notice period need be given. In the event of termination, CONSULTANT shall have the right and obligation to immediately assemble work in progress for the purpose of closing out the job. All compensation for actual work performed and charges outstanding at the time of termination shall be payable by CITY to CONSULTANT within 30 days following submission of a final statement by CONSULTANT unless termination is for cause. In such event, CONSULTANT shall be compensated only to the extent required by law.

14. ACCEPTANCE OF FINAL PAYMENT CONSTITUTES RELEASE
The acceptance by CONSULTANT of the final payment made under this AGREEMENT shall operate as and be a release of CITY from all claims and liabilities for compensation to CONSULTANT for anything done, furnished, or relating to CONSULTANT'S work or services. Acceptance of payment shall be any negotiation of CITY's check or the failure to make a written extra compensation claim within 10 calendar days of the receipt of that check.

However, approval or payment by CITY shall not constitute, nor be deemed, a 14 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 8 of 27 ends

release of the responsibility and liability of CONSULTANT, its employees, subcontractors, agents and CONSULTANTs for the accuracy and competency of the information provided and/or work performed; nor shall such approval or payment be deemed to be an assumption of such responsibility or liability by CITY for any defect or error in the work prepared by CONSULTANT, its employees, subcontractors, agents and consultants.

15. AUDIT OF RECORDS
At any time during normal business hours and as often as it may deem necessary, CONSULTANT shall make available to a representative of CITY for examination of all its records with respect to all matters covered by this AGREEMENT and will permit CITY to audit, examine and/or reproduce such records. CONSULTANT will retain such financial records, time sheets, work progress reports, invoices, bills and project records for at least two years after termination or final payment under this AGREEMENT.

16. WAIVER; REMEDIES CUMULATIVE
Failure by a party to insist upon the strict performance of any of the provisions of this AGREEMENT by the other party, irrespective of the length of time for which such failure continues, shall not constitute a waiver of such party's right to demand strict compliance by such other party in the future. No waiver by a party of a default or breach of the other party shall be effective or binding upon such party unless made in writing by such party, and no such waiver shall be implied from any omissions by a party to take any action with respect to such default or breach. No express written waiver of a specified default or breach shall affect any other default or breach, or cover any other period of time, other than any default or breach and/or period of time specified. All of the remedies permitted or available to a party under this AGREEMENT, or at law or in equity, shall be cumulative and alternative, and invocation of any such right or remedy shall not constitute a waiver or election of remedies with respect to any other permitted or available right of remedy.

17. CONFLICT OF INTEREST
CONSULTANT is unaware of any CITY employee or official that has a financial interest in CONSULTANT'S business. During the term of this AGREEMENT and/or as a result of being awarded this AGREEMENT, CONSULTANT shall not offer, encourage or accept any financial interest in CONSULTANT'S business by any CITY employee or official.

18. CONSTRUCTION OF LANGUAGE OF AGREEMENT
The provisions of this AGREEMENT shall be construed as a whole according to its common meaning of purpose of providing a public benefit and not strictly for or against any party. It shall be construed consistent with the 15 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 9 of 27 ends

provisions hereof, in order to achieve the objectives and purposes of the parties.

Wherever required by the context, the singular shall include the plural and vice versa, and the masculine gender shall include the feminine or neutral genders or vice versa.

19. MITIGATION OF DAMAGES
In all situations arising out of this AGREEMENT, the parties shall attempt to avoid and minimize the damages resulting from the conduct of the other party.

20. GOVERNING LAW
This AGREEMENT, and the rights and obligations of the parties, shall be governed and interpreted in accordance with the laws of the State of California.

Should litigation occur, venue shall be in Superior Court of Santa Barbara County.

21. NONDISCRIMINATION
CONSULTANT shall not discriminate on the basis of race, color, gender, gender identity/expression, pregnancy, sexual orientation, disability, marital status, or any other characteristic protected under applicable federal or state law.

22. TAXPAYER IDENTIFICATION NUMBER
CONSULTANT shall provide CITY with a complete Request for Taxpayer Identification Number and Certification, Form W-9 (Rev. October 2018), as issued by the Internal Revenue Service.

23. NON-APPROPRIATION OF FUNDS
Payments due and payable to CONSULTANT for current services are within the current budget and within an available, unexhausted and unencumbered appropriation of CITY funds. In the event CITY has not appropriated sufficient funds for payment of CONSULTANT services beyond the current fiscal year, this AGREEMENT shall cover only those costs incurred up to the conclusion of the current fiscal year.

24. MODIFICATION OF AGREEMENT
The tasks described in this AGREEMENT and all other terms of this AGREEMENT may be modified only upon mutual written consent of CITY and CONSULTANT.

25. USE OF THE TERM “CITY”
Reference to “CITY” in this AGREEMENT includes City Manager or any authorized representative acting on behalf of CITY.
16 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 10 of 27 ends

26. PERMITS AND LICENSES
CONSULTANT, at its sole expense, shall obtain and maintain during the term of this AGREEMENT, all appropriate permits, licenses, and certificates that may be required in connection with the performance of services under this AGREEMENT.

27. CAPTIONS
The captions or headings in this AGREEMENT are for convenience only and in no other way define, limit or describe the scope or intent of any provision or section of the AGREEMENT.

28. AUTHORIZATION
Each party has expressly authorized the execution of this AGREEMENT on its behalf and bind said party and its respective administrators, officers, directors, shareholders, divisions, subsidiaries, agents, employees, successors, assigns, principals, partners, joint venturers, insurance carriers and any others who may claim through it to this AGREEMENT.

29. ENTIRE AGREEMENT BETWEEN PARTIES
Except for CONSULTANT'S proposals and submitted representations for obtaining this AGREEMENT, this AGREEMENT supersedes any other agreements, either oral or in writing, between the parties hereto with respect to the rendering of services, and contains all of the covenants and agreements between the parties with respect to said services.

30. PARTIAL INVALIDITY
If any provision in this AGREEMENT is held by a court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions will nevertheless continue in full force without being impaired or invalidated in any way.

31. NOTICES
Any notice required to be given hereunder shall be deemed to have been given by depositing said notice in the United States mail, postage prepaid, and addressed as follows:

TO CITY: Attention: Robert Nisbet, City Manager
City of Goleta
130 Cremona Drive, Suite B
Goleta, CA 93117
TO CONSULTANT: Attention: Michael Hamilton
17 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 11 of 27 ends

RRM Design Group
3765 S Higuera St Ste 102,
San Luis Obispo, CA 93401

32. COUNTERPARTS AND ELECTRONIC/FACSIMILE SIGNATURES
This Agreement may be executed in several counterparts, which may be facsimile or electronic copies. Each counterpart is fully effective as an original, and together constitutes one and the same instrument.

33. FEDERAL REQUIREMENTS
FEMA financial assistance will be used to fund all or a portion of this contract.

The Consultant shall comply with all federal requirements including, but not limited to, the following:

1. 2 C.F.R. Part 200 – Uniform Administrative Requirements, Cost Principles,
and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.

2. Federal Contract Provisions attached hereto as Exhibit “C” and incorporated
herein by reference.

Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, 2 C.F.R.

Part 200 and the Federal Contract Provisions.

With respect to any conflict between such federal requirements and the terms of this contract and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.
18 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 12 of 27 ends

In concurrence and witness whereof , this AGREEMENT has been executed by the parties effective on the date and year first above written.

CITY OF GOLETA CONSULTANT

_____________________________ _____________________________ Robert Nisbet, City Manager Jeff Ferber, Senior Vice President, Principal

ATTEST

_____________________________ _____________________________ Deborah Lopez, City Clerk Michael Hamilton, Vice President, Principal

APPROVED AS TO FORM:

MEGAN GARIBALDI, CITY ATTORNEY
_____________________________
Scott Shapses, Deputy City Attorney
19 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 13 of 27 ends

EXHIBIT A

SCOPE OF WORK
Scope of Work (SOW) for an emergency services agreement between the City of Goleta and RRM Design:

1. Project Coordination and Meetings:
o Coordinate with relevant stakeholders, including city officials, RRM Design, and other involved parties.
o Schedule and facilitate regular project meetings to discuss progress, address issues, and ensure alignment.

2. Coastal Development Permitting:
o Prepare and submit a comprehensive coastal development permit package.
o Include all necessary documentation, plans, and environmental impact assessments required for permit approval.
o Collaborate with regulatory agencies and address any feedback or revisions.

3. Design Development:
o Develop detailed design plans for the vertical beach access. o Consider safety, accessibility, aesthetics, and environmental impact.
o Incorporate habitat restoration elements into the design. o Provide 2D and 3D visualizations as needed.

4. Landscape Construction:
o Oversee the implementation of the approved design.
o Coordinate with contractors and subcontractors.
o Ensure compliance with design specifications and environmental regulations.
o Monitor progress and address any construction-related challenges.

5. Civil Construction:
o Execute civil engineering aspects of the project.
o Address grading, drainage, utilities, and infrastructure. o Collaborate with surveyors and geotechnical engineers. o Ensure adherence to safety standards.

6. Topographic Survey:
o Conduct a detailed topographic survey of the project site. o Capture accurate elevation data.
o Use advanced surveying techniques to inform design decisions.

7. Soils Engineering:
o Perform soil testing and analysis.
o Assess soil stability, bearing capacity, and suitability for construction.
o Provide recommendations for foundation design and soil improvement measures.
20 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 14 of 27 ends

EXHIBIT B

SCHEDULE OF FEES
21 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 15 of 27 ends

EXHIBIT D

FEDERAL CONTRACT PROVISIONS
During the performance of this contract, RRM Design Group, Inc. (the “Consultant”) shall comply with all applicable federal laws and regulations including but not limited to the federal contract provisions in this Exhibit. In this Exhibit, the term “Agency” shall mean the local agency entering into this contract with the Consultant.

1. CONTRACTING WITH SMALL AND MINORITY FIRMS, WOMEN’S
BUSINESS ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2
C.F.R. § 200.321)
A. Consultant shall be subject to 2 C.F.R. § 200.321 and will take affirmative steps to assure that minority firms, women’s business enterprises, and labor surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.

B. Affirmative steps shall include:
i. Placing qualified small and minority businesses and
women's business enterprises on solicitation lists;
ii. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are
potential sources;
iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business
enterprises;
iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and
v. Using the services/assistance of the Small Business
Administration (SBA), and the Minority Business
Development Agency (MBDA) of the Department of
Commerce.

Consultant shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.

Notwithstanding the foregoing, the affirmative steps requirements detailed above do not apply in the case of a noncompetitive procurement made 22 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 16 of 27 ends

under the emergency exception/exigency exception to competitive procurements.

2. COST PRINCIPLES (2 C.F.R. PART 200, SUBPART E)
A. If any indirect costs will be charged to the Agency under this contract, such costs must conform to the cost principles set forth under the Uniform Rules at 2 C.F.R. Part 200, subpart E (“Cost Principles”). In general, costs must (i) be necessary and reasonable; (ii) allocable to the grant award; (iii) conform to any limitations or exclusions set forth in the Cost Principles; (iv) be adequately documented; and (v) be determined in accordance with generally accepted accounting principles (“GAAP”), except, for state and local governments and Indian tribes only, as otherwise provided for in 2 C.F.R. Part 200, subpart E. 2 C.F.R. § 200.403.

Costs that are determined unallowable pursuant to a federal audit are subject to repayment by Consultant.

3. ACCESS TO RECORDS & RECORD RETENTION (2 C.F.R. 200.336) A. Consultant shall comply with 2 C.F.R. § 200.336 and provide the Federal Agency, Inspectors General, the Comptroller General of the United States, Agency, and the State of California or any of their authorized representatives access, during normal business hours, to documents, papers, books and records which are directly pertinent to this contract for the purposes of making and responding to audits, examinations, excerpts, and transcriptions. The right also includes timely and reasonable access to the Consultant personnel for the purpose of interview and discussion related to the books and records.

B. The Consultant agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

C. The Consultant agrees to provide the Federal Agency or its authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

4. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH
APPENDIX II TO PART 200 – CONTRACT PROVISIONS FOR NON-
FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS (2
C.F.R. § 200.326)
23 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 17 of 27 ends

A. Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract is in excess of $10,000 and the contract does not include provisions for both termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract is for more than the simplified acquisition threshold (see 2 C.F.R. § 200.88) at the time the contract is executed and does not provide for administrative, contractual, or legal remedies in instances where Contractor violates or breaches the terms of the contract, then the following termination clauses shall apply and have precedence over the contract. Otherwise, the following termination clauses shall not be applicable to the contract. i. Termination for Convenience. The Agency may, by written notice to Consultant, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Consultant of such termination, and specifying the effective date thereof (“Notice of Termination for Convenience”). If the termination is for the convenience of the Agency, the Agency shall compensate Provider for work or materials fully and adequately provided through the effective date of
termination. No amount shall be paid for unperformed work or materials not provided, including anticipated profit.

Consultant shall provide documentation deemed adequate
by the Agency to show the work actually completed or
materials provided by Consultant prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination.
ii. Termination for Cause. If Consultant fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to Consultant specifying the default (“Notice of Default”). If Consultant does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause. If Consultant fails to cure a default as set forth above, the Agency may, by written notice to Consultant , terminate this contract for cause, in whole or in part, and specifying the effective date thereof (“Notice of Termination for Cause”). If the termination is for cause, Consultant shall be
compensated for that portion of the work or materials
24 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 18 of 27 ends

provided which has been fully and adequately completed
and accepted by the Agency as of the date the Agency
provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems
necessary to complete the project and correct Consultant’s deficiencies and charge the cost thereof to Consultant, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.
iii. Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work rendered or materials provided and shall be entitled to withhold compensation for defective work or other damages caused by Consultant performance of the work.

iv. Additional Termination Provisions. Upon receipt of a Notice of Termination, either for cause or for convenience,
Consultant shall promptly discontinue the work unless the Notice directs to the contrary. Consultant shall deliver to the Agency and transfer title (if necessary) to all provided materials and completed work, and work in progress
including drafts, documents, plans, forms, maps, products, graphics, computer programs and reports. The rights and remedies of the parties provided in this Section are in addition to any other rights and remedies provided by law or under this contract. Consultant acknowledges the Agency’s right to terminate this contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the Agency’s
termination of this contract. The Agency shall not be liable for any costs other than the charges or portions thereof which are specified herein. Consultant shall not be entitled to payment for unperformed work or materials not provided and shall not be entitled to damages or compensation for termination of work or supply of materials. If Agency
terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a
termination for convenience. In such event, Consultant shall be entitled to receive only the amounts payable under this 25 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 19 of 27 ends

Section, and Consultant specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance.

B. Appendix II to Part 200 (C) – Equal Employment Opportunity:

Except as otherwise provided under 41 C.F.R. Part 60, Consultant shall comply with the following equal opportunity clause, in accordance with Executive Order 11246 of September 24, 1965 entitled “Equal Employment Opportunity,” as amended by
Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:
i. Consultant will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. Consultant will take affirmative action to insure that applicants are employed and that employees are treated equally during employment, without regard to race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following: employment upgrading, demotion, transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training including
apprenticeship. Consultant agrees to post in conspicuous places, available to employees and applicants for
employment, notices to be provided by the Agency setting forth the provisions of this nondiscrimination clause.
ii. Consultant will, in all solicitations or advertisements for employees placed by or on behalf of Consultant , state that all qualified applicants will receive consideration for employment without regard to their race, color, religion, sex, or national origin.
iii. Consultant will not discharge or in any other manner discriminate against any employee or applicant for
employment because such employee or applicant has
inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant.

This provision shall not apply to instances in which an 26 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 20 of 27 ends

employee who has access to the compensation information of other employees or applicants as a part of such
employee's essential job functions discloses the
compensation of such other employees or applicants to
individuals who do not otherwise have access to such
information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an
investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with Consultant‘s legal duty to furnish information.
iv. Consultant will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of
September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
v. Consultant will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
vi. Consultant will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
vii. In the event of Consultant’s noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the
contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in
Executive Order No.11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as
provided in Executive Order No.11246 of September 24,
27 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 21 of 27 ends

1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
viii. Consultant will include the provisions of paragraphs (i) through (viii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of September 24,1965, so that such provisions will be binding upon each subcontractor or Consultant. Consultant will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, that in the event Consultant becomes involved in, or is threatened with,
litigation with a subcontractor or Consultant as a result of such direction, Consultant may request the United States to enter into such litigation to protect the interests of the United States.

C. Appendix II to Part 200 (D) – Davis-Bacon Act; Copeland Act: Not applicable to this contract.

D. Appendix II to Part 200 (E) – Contract Work Hours and Safety Standards Act:
i. If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Consultant shall
comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to
compute the wages of every mechanic and laborer on the
basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and
provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.
28 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 22 of 27 ends

ii. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives
compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
iii. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any
subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and
subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section. iv. The Agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Consultant or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other
federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be
necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.
v. The Consultant or subcontractor shall insert in any
subcontracts the clauses set forth in paragraph (ii) through 29 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 23 of 27 ends

(v) of this Section and also a clause requiring the
subcontractors to include these clauses in any lower tier subcontracts. The Contractor shall be responsible for
compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.

E. Appendix II to Part 200 (F) – Rights to Inventions Made Under a Contract or Agreement:
i. If the Federal award meets the definition of “funding agreement” under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental,
developmental, or research work under that “funding
agreement,” the non-Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative
Agreements), and any implementing regulations issued by the Agency.

ii. The regulation at 37 C.F.R. § 401.2(a) currently defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or
research work funded in whole or in part by the Federal government. This term also includes any assignment,
substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.

iii. This requirement does not apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management
Assistance Grant Program, Crisis Counseling Assistance
and Training Grant Program, Disaster Case Management
Grant Program, and Federal Assistance to Individuals and Households – Other Needs Assistance Grant Program, as
FEMA awards under these programs do not meet the
definition of “funding agreement.”
30 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 24 of 27 ends

F. Appendix II to Part 200 (G) – Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Consultant shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401- 7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387).
i. Pursuant to the Clean Air Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the
appropriate Environmental Protection Agency Regional
Office, and (3) Consultant agrees to include these
requirements in each subcontract exceeding $150,000.
ii. Pursuant to the Federal Water Pollution Control Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Consultant
agrees to include these requirements in each subcontract exceeding $150,000.

G. Appendix II to Part 200 (H) – Debarment and Suspension: A contract award (see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 C.F.R. part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.
31 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 25 of 27 ends

i. This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Consultant is required to verify that none of the Consultant, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. §
180.940) or disqualified (defined at 2 C.F.R. § 180.935). ii. Consultant must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into.
iii. This certification is a material representation of fact relied upon by Agency. If it is later determined that Consultant did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available
remedies, including but not limited to suspension and/or debarment.
iv. Consultant warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs. Consultant also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from
participation in accordance with the requirements above.

Consultant further agrees to notify the Agency in writing immediately if Consultant or its subcontractors are not in compliance during the term of this contract.

H. Appendix II to Part 200 (I) – Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Consultant shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Consultant shall file with the Agency the Federal Standard Form LLL titled “Disclosure Form to Report Lobbying.” Consultants that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 32 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 26 of 27 ends

U.S.C. 1352. Each tier must also disclose any lobbying with non- Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.

I. Appendix II to Part 200 (J) – Procurement of Recovered Materials:
i. Consultant shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation
and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the
Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered
materials practicable, consistent with maintaining a
satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity
acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement.
ii. In the performance of this contract, the Consultant shall make maximum use of products containing recovered
materials that are EPA-designated items unless the product cannot be acquired: Competitively within a timeframe
providing for compliance with the contract performance
schedule; Meeting contract performance requirements; or At a reasonable price.
iii. Information about this requirement, along with the list of EPA-designate items, is available at EPA’s Comprehensive Procurement Guidelines web site,
https://www.epa.gov/smm/comprehensive-procurement-
guideline-cpg-program.

5. MISCELLANEOUS PROVISIONS
A. The Consultant shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA preapproval.

B. This is an acknowledgement that FEMA financial assistance will be used to fund the contract only. The Consultant will comply with all 33 City of Goleta
Department of Public Works and RRM Design Group, Inc.

Page 27 of 27 ends

applicable federal law, regulations, executive orders, FEMA policies, procedures, and directives.

C. Consultant acknowledges that 31 U.S.C. Chapter 38
(Administrative Remedies for False Claims and Statements) applies to the Consultant’s actions pertaining to this contract.

D. The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the Agency, Consultant, any subcontractors or any other party pertaining to any matter resulting from the contract.

E. General and Administrative Expenses And Profit For Time And Materials Contracts/Amendments.
i. General and administrative expenses shall be negotiated and must conform to the Cost Principles.
ii. Profit shall be negotiated as a separate element of the cost.

To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the Consultant , the Consultant’s investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.

iii. Any agreement, amendment or change order for work
performed on a time and materials basis shall include a ceiling price that Consultant exceeds at its own risk.
34 ATTACHMENT 2

Professional Services Agreement with Pacific Materials Laboratory, Inc.

35 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 1 of 27 ends

Project Name: Various February 2024 Storm Emergency Projects

AGREEMENT FOR PROFESSIONAL SERVICES

BETWEEN THE CITY OF GOLETA
AND
PACIFIC MATERIALS LABORATORY INC.

This AGREEMENT FOR PROFESSIONAL SERVICES (herein referred to as “AGREEMENT”) is made and entered into this ________ day of ______ , 2024, by and between the CITY OF GOLETA, a municipal corporation (herein referred to as "CITY"), and PACIFIC MATERIALS LABORATORY, INC., a California Corporation (herein referred to as "CONSULTANT").

SECTION A. RECITALS

1. The CITY has a need for professional on-call geotechnical and materials testing services for various February 2024 Storm Emergency Projects in the City of Goleta; and

2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for professional services to accomplish this work; and

3. Goleta Municipal Code Section 2.10.040(A)(6)(a) allows the City Manager (referenced as “Director of Emergency Services”) to “make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency; provided however, such rules and regulations must be confirmed at the earliest practicable time by the City Council”; and

4. An emergency exists in the CITY due to the severe storms of February 2024 which caused significant damage to roadways and CITY infrastructure. Therefore, it is necessary to the public health and safety that the City Manager immediately authorize the start of work on emergency mitigation measures, subject to ratification by City Council; and

5. The City Manager authorized this agreement pursuant to Goleta Municipal Code Section 2.10.040(A)(6)(a) and the City Council ratified this agreement at its next public meeting.

36 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 2 of 27 ends

SECTION B. TERMS

1. RETENTION AS CONSULTANT
CITY hereby retains CONSULTANT, and CONSULTANT hereby accepts such engagement, to perform the services described in Section 2.

CONSULTANT warrants it has the qualifications, experience, and facilities to properly and timely perform said services.

2. DESCRIPTION OF SERVICES
The services to be performed by CONSULTANT are as follows:

Professional Services in conjunction with on-call geotechnical and materials testing services shall generally include compaction testing, concrete strength testing, concrete slump and yield testing, structural steel testing, and any other tasks as more particularly set forth in the Scope of Work, attached as Exhibit “A,” and incorporated herein.

CONSULTANT shall deliver to CITY the deliverables defined in Exhibit “A.”

3. COMPENSATION AND PAYMENT
(a) Maximum and Rate . The total compensation payable to CONSULTANT by CITY for the services under this AGREEMENT SHALL NOT EXCEED the sum of $100,000 (herein "not to exceed amount"), and shall be earned as the work progresses on the following basis:

Hourly at the hourly rates and with reimbursement to
CONSULTANT for those expenses set forth in CONSULTANT's Schedule of Fees marked Exhibit "B," attached and incorporated herein. The rates and expenses set forth in that exhibit shall be binding upon CONSULTANT until June 30, 2025, after which any change in said rates and expenses must be approved in writing by CITY's Project Manager as described in Section 5 (CITY is to be given 60 days notice of any rate increase request), provided the not to exceed amount is the total compensation due CONSULTANT for all work described under this AGREEMENT.
(b) Payment . CONSULTANT shall provide CITY with written verification of the actual compensation earned, which written verification shall be in a form satisfactory to CITY's Project Manager, as described in Section 5.

Invoices shall be made no more frequently than on a monthly basis, and describe the work performed (including a list of hours worked by personnel classification).

All payments shall be made within 30 days after CITY’s approval of the invoice. 37 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 3 of 27 ends

4. EXTRA SERVICES
CITY shall pay CONSULTANT for those CITY authorized extra services, not reasonably included within the services described in Section 2, as mutually agreed to writing in advance of the incurrence of extra services by CONSULTANT. Unless CITY and CONSULTANT have agreed in writing before the performance of extra services, no liability and no right to claim compensation for such extra services or expenses shall exist. The applicable hourly rates for extra services shall be at the hourly rates set forth in Exhibit B, if one is included as part of this agreement. Any compensation for extra services shall be part of the total compensation and shall not increase the not to exceed amount identified in Section 3.

5. CITY PROJECT MANAGER AND SERVICES BY CITY
The services to be performed by CONSULTANT shall be accomplished under the general direction of, and coordinate with, CITY's "Project Manager", as that staff person is designated by CITY from time to time, and who presently is John Plummer. Project Manager shall have the authority to act on behalf of the CITY in administering this AGREEMENT but shall not be authorized to extend the term of the AGREEMENT or increase the not to exceed amount.

6. TERM, PROGRESS AND COMPLETION
The term of this AGREEMENT is from the date first written above to June 30, 2025, unless term of this AGREEMENT is extended, or the AGREEMENT is terminated as provided for herein.

CONSULTANT shall not commence work on the services to be performed until (i) CONSULTANT furnishes proof of insurance as required by Section 10 below, and (ii) CITY gives written authorization to proceed with the work provided by CITY's Project Manager.

7. OWNERSHIP OF DOCUMENTS
All drawings, designs, data, photographs, reports and other documentation (other than CONSULTANT's drafts, notes and internal memorandum), including duplication of same prepared by CONSULTANT in the performance of these services, are the property of CITY. CITY shall be entitled to immediate possession of the same upon completion of the work under this AGREEMENT, or at any earlier or later time when requested by CITY. CITY agrees to hold CONSULTANT harmless from all damages, claims, expenses, and losses arising out of any reuse of the plans and specifications for purposes other than those described in this AGREEMENT, unless written authorization of CONSULTANT is first obtained.
38 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 4 of 27 ends

8. PERSONAL SERVICES/NO ASSIGNMENT/SUBCONTRACTOR
This AGREEMENT is for professional services which are personal to CITY. Ron Pike is deemed to be specially experienced and is a key member of CONSULTANT's firm, and shall be directly involved in the performance of this work. This key person shall communicate with, and periodically report to, CITY on the progress of the work. Should any such individual be removed from assisting in this contracted work for any reason, CITY may terminate this AGREEMENT. This AGREEMENT may not be assigned or subcontracted without the City Manager’s prior written consent.

9. HOLD HARMLESS AND INDEMNITY
(a) Hold Harmless for CONSULTANT's Damages. CONSULTANT
holds CITY, its elected officials, officers, agents, and employees, harmless from all of CONSULTANT's claims, demands, lawsuits, judgments, damages, losses, injuries or liability to CONSULTANT, to CONSULTANT's employees, to CONSULTANT’s contractors or subcontractors, or to the owners of CONSULTANT's firm, which damages, losses, injuries or liability occur during the work required under this AGREEMENT, or occur while CONSULTANT is on CITY property, or which are connected, directly or indirectly, with CONSULTANT's performance of any activity or work required under this AGREEMENT.
(b) Defense and Indemnity of Third Party Claims/Liability.

CONSULTANT shall investigate, defend, and indemnify CITY, its elected officials, officers, agents, and employees, from any claims, lawsuits, demands, judgments, and all liability including, but not limited to, monetary or property damage, lost profit, personal injury, wrongful death, general liability, automobile, infringement of copyright/patent/trademark, or professional errors and omissions arising out of, directly or indirectly, an error, negligence, or omission of CONSULTANT or any of CONSULTANT’s officers, agents, employees, representatives, subconsultants, or subcontractors, or the willful misconduct of CONSULTANT or any of CONSULTANT’s officers, agents, employees, representatives, subconsultants, or subcontractors, in performing the services described in, or normally associated with, this type of contracted work. The duty to defend shall include any suits or actions concerning any activity, product or work required under this AGREEMENT, and also include the payment of all court costs, attorney fees, expert witness costs, investigation costs, claims adjusting costs and any other costs required for and related thereto. (c) No Waiver. CITY does not waive, nor shall be deemed to have waived, any indemnity, defense or hold harmless rights under this section because of the acceptance by CITY, or the deposit with CITY, of any insurance certificates or policies described in Section 10.
39 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 5 of 27 ends

10. INSURANCE
CONSULTANT shall, at CONSULTANT's sole cost and expense, provide insurance as described herein. All insurance is to be placed with insurers authorized to do business in the State of California with an A.M. Best and Company rating of A- or better, Class VII or better, or as otherwise approved by CITY.

Insurance shall include the following (or broader) coverage:
a) Insurance Services Office Commercial Liability coverage “occurrence” form CG 00 01 or its exact equivalent with an edition date prior to 2004 and with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate.

b) Insurance Services Office form number CA 00 01 or equivalent covering Automobile Liability, including hired and non-owned automobile liability with a minimum limit of $1,000,000 per accident. If the Service Provider owns no vehicles, this requirement may be satisfied by a non-owned and hired auto endorsement to Service Provider’s commercial general liability policy.

c) Workers’ Compensation insurance complying with California worker’s compensation laws, including statutory limits for workers’ compensation and an Employer’s Liability limit of $1,000,000 per accident or disease.

d) Professional liability insurance that covers the services to be performed in connection with this agreement, in the minimum amount of $1,000,000 per claim.

Liability insurance policies required to be provided by CONSULTANT hereunder shall contain or be endorsed to contain the following provisions:

a) Except for professional liability insurance, CITY, its employees, officials, agents and member agencies shall be covered as additional insureds. Coverage shall apply to any and all liability arising out of the work performed or related to the contract. Additional insured status under the general liability requirement shall be provided on Insurance Services Office Form CG 20 10, with an edition date prior to 2004, or its equivalent. Additional insured status for completed operations shall be provided either in the additional insured form or through another endorsement such as CG 20 37, or its equivalent.

b) General and automobile liability insurance shall apply separately to each insured against whom a claim is made or suit is brought, except 40 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 6 of 27 ends

with respect to the limits of the insurer’s liability. Coverage will not be limited to CITY’s vicarious liability.
c) Professional liability insurance policies inception date, continuity date, or retroactive date must be before the effective date of this agreement. CONSULTANT agrees to maintain continuous coverage through a period no less than three years after completion of the services required by this agreement.
d) Except for professional liability insurance, liability coverage shall be primary and non-contributing with any insurance maintained by CITY.

e) Evidence of coverage (including the workers’ compensation and employer’s liability policies) shall provide that coverage shall not be suspended, voided, canceled or reduced in coverage or in limits except after 30 days’ prior written notice has been given to CITY.

Such provision shall not include any limitation of liability of the insurer for failure to provide such notice.

f) No liability insurance coverage provided to comply with this AGREEMENT shall prohibit CONSULTANT, or CONSULTANT’s
employees, or agents, from waiving the right of recovery prior to a loss. CONSULTANT waives its right of recovery against CITY.

g) CONSULTANT agrees to deposit with CITY within fifteen days of Notice to Proceed of the Contract certificates of insurance and required endorsements.

h) There shall be no recourse against CITY for payment of premiums or other amounts with respect to the insurance required to be provided by CONSULTANT hereunder. Any failure, actual or alleged, on the part of CITY to monitor compliance with these requirements will not be deemed as a waiver of any rights on the part of CITY. CITY has no additional obligations by virtue of requiring the insurance set forth herein. In the event any policy of insurance required under this AGREEMENT does not comply with these requirements or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONSULTANT or CITY will withhold amounts sufficient to pay premium from CONSULTANT payments.

i) CONSULTANT agrees to provide immediate notice to CITY of any claim or loss against CONSULTANT arising out of the work performed under this AGREEMENT. CITY assumes no obligation or liability by 41 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 7 of 27 ends

such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve CITY.

11. RELATIONSHIP OF CONSULTANT TO CITY
The relationship of the CONSULTANT to CITY shall be that of an independent contractor and that in no event shall CONSULTANT be considered an officer, agent, servant or employee of CITY. CONSULTANT shall be solely responsible for any workers compensation insurance, withholding taxes, unemployment insurance, and any other employer obligations associated with the described work.

12. CORRECTIONS
In addition to the above indemnification obligations, CONSULTANT shall correct, at its expense, all errors in the work that may be disclosed during CITY's review of CONSULTANT's report or plans. Should CONSULTANT fail to make such correction in a reasonably timely manner, such correction shall be made by CITY, and the cost thereof shall be charged to CONSULTANT or withheld from any funds due to CONSULTANT hereunder.

13. TERMINATION BY CITY
CITY, by notifying CONSULTANT in writing, may upon 10 calendar days notice, terminate without cause any portion or all of the services agreed to be performed under this AGREEMENT. If termination is for cause, no notice period need be given. In the event of termination, CONSULTANT shall have the right and obligation to immediately assemble work in progress for the purpose of closing out the job. All compensation for actual work performed and charges outstanding at the time of termination shall be payable by CITY to CONSULTANT within 30 days following submission of a final statement by CONSULTANT unless termination is for cause. In such event, CONSULTANT shall be compensated only to the extent required by law.

14. ACCEPTANCE OF FINAL PAYMENT CONSTITUTES RELEASE
The acceptance by CONSULTANT of the final payment made under this AGREEMENT shall operate as and be a release of CITY from all claims and liabilities for compensation to CONSULTANT for anything done, furnished, or relating to CONSULTANT'S work or services. Acceptance of payment shall be any negotiation of CITY's check or the failure to make a written extra compensation claim within 10 calendar days of the receipt of that check.

However, approval or payment by CITY shall not constitute, nor be deemed, a release of the responsibility and liability of CONSULTANT, its employees, subcontractors, agents and CONSULTANTs for the accuracy and competency of the information provided and/or work performed; nor shall such approval or 42 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 8 of 27 ends

payment be deemed to be an assumption of such responsibility or liability by CITY for any defect or error in the work prepared by CONSULTANT, its employees, subcontractors, agents and consultants.

15. AUDIT OF RECORDS
At any time during normal business hours and as often as it may deem necessary, CONSULTANT shall make available to a representative of CITY for examination of all its records with respect to all matters covered by this AGREEMENT and will permit CITY to audit, examine and/or reproduce such records. CONSULTANT will retain such financial records, time sheets, work progress reports, invoices, bills and project records for at least two years after termination or final payment under this AGREEMENT.

16. WAIVER; REMEDIES CUMULATIVE
Failure by a party to insist upon the strict performance of any of the provisions of this AGREEMENT by the other party, irrespective of the length of time for which such failure continues, shall not constitute a waiver of such party's right to demand strict compliance by such other party in the future. No waiver by a party of a default or breach of the other party shall be effective or binding upon such party unless made in writing by such party, and no such waiver shall be implied from any omissions by a party to take any action with respect to such default or breach. No express written waiver of a specified default or breach shall affect any other default or breach, or cover any other period of time, other than any default or breach and/or period of time specified. All of the remedies permitted or available to a party under this AGREEMENT, or at law or in equity, shall be cumulative and alternative, and invocation of any such right or remedy shall not constitute a waiver or election of remedies with respect to any other permitted or available right of remedy.

17. CONFLICT OF INTEREST
CONSULTANT is unaware of any CITY employee or official that has a financial interest in CONSULTANT'S business. During the term of this AGREEMENT and/or as a result of being awarded this AGREEMENT, CONSULTANT shall not offer, encourage or accept any financial interest in CONSULTANT'S business by any CITY employee or official.

18. CONSTRUCTION OF LANGUAGE OF AGREEMENT
The provisions of this AGREEMENT shall be construed as a whole according to its common meaning of purpose of providing a public benefit and not strictly for or against any party. It shall be construed consistent with the provisions hereof, in order to achieve the objectives and purposes of the parties.

Wherever required by the context, the singular shall include the plural and vice 43 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 9 of 27 ends

versa, and the masculine gender shall include the feminine or neutral genders or vice versa.

19. MITIGATION OF DAMAGES
In all situations arising out of this AGREEMENT, the parties shall attempt to avoid and minimize the damages resulting from the conduct of the other party.

20. GOVERNING LAW
This AGREEMENT, and the rights and obligations of the parties, shall be governed and interpreted in accordance with the laws of the State of California.

Should litigation occur, venue shall be in Superior Court of Santa Barbara County.

21. NONDISCRIMINATION
CONSULTANT shall not discriminate on the basis of race, color, gender, gender identity/expression, pregnancy, sexual orientation, disability, marital status, or any other characteristic protected under applicable federal or state law.

22. TAXPAYER IDENTIFICATION NUMBER
CONSULTANT shall provide CITY with a complete Request for Taxpayer Identification Number and Certification, Form W-9 (Rev. October 2018), as issued by the Internal Revenue Service.

23. NON-APPROPRIATION OF FUNDS
Payments due and payable to CONSULTANT for current services are within the current budget and within an available, unexhausted and unencumbered appropriation of CITY funds. In the event CITY has not appropriated sufficient funds for payment of CONSULTANT services beyond the current fiscal year, this AGREEMENT shall cover only those costs incurred up to the conclusion of the current fiscal year.

24. MODIFICATION OF AGREEMENT
The tasks described in this AGREEMENT and all other terms of this AGREEMENT may be modified only upon mutual written consent of CITY and CONSULTANT.

25. USE OF THE TERM “CITY”
Reference to “CITY” in this AGREEMENT includes City Manager or any authorized representative acting on behalf of CITY.
44 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 10 of 27 ends

26. PERMITS AND LICENSES
CONSULTANT, at its sole expense, shall obtain and maintain during the term of this AGREEMENT, all appropriate permits, licenses, and certificates that may be required in connection with the performance of services under this AGREEMENT.

27. CAPTIONS
The captions or headings in this AGREEMENT are for convenience only and in no other way define, limit or describe the scope or intent of any provision or section of the AGREEMENT.

28. AUTHORIZATION
Each party has expressly authorized the execution of this AGREEMENT on its behalf and bind said party and its respective administrators, officers, directors, shareholders, divisions, subsidiaries, agents, employees, successors, assigns, principals, partners, joint venturers, insurance carriers and any others who may claim through it to this AGREEMENT.

29. ENTIRE AGREEMENT BETWEEN PARTIES
Except for CONSULTANT'S proposals and submitted representations for obtaining this AGREEMENT, this AGREEMENT supersedes any other agreements, either oral or in writing, between the parties hereto with respect to the rendering of services, and contains all of the covenants and agreements between the parties with respect to said services.

30. PARTIAL INVALIDITY
If any provision in this AGREEMENT is held by a court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions will nevertheless continue in full force without being impaired or invalidated in any way.

31. NOTICES
Any notice required to be given hereunder shall be deemed to have been given by depositing said notice in the United States mail, postage prepaid, and addressed as follows:

TO CITY: Attention: Robert Nisbet, City Manager
City of Goleta
130 Cremona Drive, Suite B
Goleta, CA 93117
45 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 11 of 27 ends

TO CONSULTANT: Attention: Ron Pike
35 South La Patera Lane
Goleta, CA 93117

32. COUNTERPARTS AND ELECTRONIC/FACSIMILE SIGNATURES
This Agreement may be executed in several counterparts, which may be facsimile or electronic copies. Each counterpart is fully effective as an original, and together constitutes one and the same instrument.

33.FEDERAL REQUIREMENTS
FEMA financial assistance will be used to fund all or a portion of this contract.

The Consultant shall comply with all federal requirements including, but not limited to, the following:

1. 2 C.F.R. Part 200 – Uniform Administrative Requirements, Cost Principles,
and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.

2. Federal Contract Provisions attached hereto as Exhibit “C” and incorporated
herein by reference.

Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, 2 C.F.R.

Part 200 and the Federal Contract Provisions.

With respect to any conflict between such federal requirements and the terms of this contract and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.

46 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 12 of 27 ends

In concurrence and witness whereof , this AGREEMENT has been executed by the parties effective on the date and year first above written.

CITY OF GOLETA CONSULTANT

_____________________________ _____________________________ Robert Nisbet, City Manager Ronald J. Pike, President ATTEST
_____________________________ _____________________________ Deborah Lopez, City Clerk Karl F. Buchmiller, Board Member

APPROVED AS TO FORM:

MEGAN GARIBALDI, CITY ATTORNEY
_____________________________
Scott Shapses, Deputy City Attorney
47 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 13 of 27 ends

EXHIBIT A

SCOPE OF WORK
Consultant shall go to any project site within the City of Goleta as requested to extract samples or cores as needed for any requested test. Tests include but are not limited to the following:

Task 1: Soil Compaction Testing
Task 2: Concrete Compressive Strength Test
Task 3: Concrete Slump and Yield Testing

Task 4: Structural Steel and Reinforcing (Rebar) Tests

Deliverables:
- Laboratory test results shall be submitted to the City within 5 (five) days after completion.

Any other tasks within Consultant’s range of services may be requested as a part of this agreement.

48 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 14 of 27 ends

EXHIBIT B

SCHEDULE OF FEES
Staff/Project Role Rates
Soil Technician $135 (2 hour minimum)
No annual escalation will be allowed
Reimbursables + 10% markup
No mileage will be reimbursed
49 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 15 of 27 ends

EXHIBIT C

FEDERAL CONTRACT PROVISIONS
During the performance of this contract, Pacific Materials Laboratory, Inc. (the “Consultant”) shall comply with all applicable federal laws and regulations including but not limited to the federal contract provisions in this Exhibit. In this Exhibit, the term “Agency” shall mean the local agency entering into this contract with the Consultant.

1. CONTRACTING WITH SMALL AND MINORITY FIRMS, WOMEN’S
BUSINESS ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2
C.F.R. § 200.321)

A. Consultant shall be subject to 2 C.F.R. § 200.321 and will take affirmative steps to assure that minority firms, women’s business enterprises, and labor surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.

B. Affirmative steps shall include:

i. Placing qualified small and minority businesses and
women's business enterprises on solicitation lists;
ii. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are
potential sources;
iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business
enterprises;
iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and
v. Using the services/assistance of the Small Business
Administration (SBA), and the Minority Business
Development Agency (MBDA) of the Department of
Commerce.

Consultant shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.

Notwithstanding the foregoing, the affirmative steps requirements detailed above do not apply in the case of a noncompetitive procurement made 50 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 16 of 27 ends

under the emergency exception/exigency exception to competitive procurements.

2. COST PRINCIPLES (2 C.F.R. PART 200, SUBPART E)
A. If any indirect costs will be charged to the Agency under this contract, such costs must conform to the cost principles set forth under the Uniform Rules at 2 C.F.R. Part 200, subpart E (“Cost Principles”). In general, costs must (i) be necessary and reasonable; (ii) allocable to the grant award; (iii) conform to any limitations or exclusions set forth in the Cost Principles; (iv) be adequately documented; and (v) be determined in accordance with generally accepted accounting principles (“GAAP”), except, for state and local governments and Indian tribes only, as otherwise provided for in 2 C.F.R. Part 200, subpart E. 2 C.F.R. § 200.403.

Costs that are determined unallowable pursuant to a federal audit are subject to repayment by Consultant.

3. ACCESS TO RECORDS & RECORD RETENTION (2 C.F.R. 200.336) A. Consultant shall comply with 2 C.F.R. § 200.336 and provide the Federal Agency, Inspectors General, the Comptroller General of the United States, Agency, and the State of California or any of their authorized representatives access, during normal business hours, to documents, papers, books and records which are directly pertinent to this contract for the purposes of making and responding to audits, examinations, excerpts, and transcriptions. The right also includes timely and reasonable access to the Consultant personnel for the purpose of interview and discussion related to the books and records.

B. The Consultant agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

C. The Consultant agrees to provide the Federal Agency or its authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

4. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH
APPENDIX II TO PART 200 – CONTRACT PROVISIONS FOR NON-
FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS (2
C.F.R. § 200.326)
51 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 17 of 27 ends

A. Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract is in excess of $10,000 and the contract does not include provisions for both termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract is for more than the simplified acquisition threshold (see 2 C.F.R. § 200.88) at the time the contract is executed and does not provide for administrative, contractual, or legal remedies in instances where Contractor violates or breaches the terms of the contract, then the following termination clauses shall apply and have precedence over the contract. Otherwise, the following termination clauses shall not be applicable to the contract. i. Termination for Convenience. The Agency may, by written notice to Consultant, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Consultant of such termination, and specifying the effective date thereof (“Notice of Termination for Convenience”). If the termination is for the convenience of the Agency, the Agency shall compensate Provider for work or materials fully and adequately provided through the effective date of
termination. No amount shall be paid for unperformed work or materials not provided, including anticipated profit.

Consultant shall provide documentation deemed adequate
by the Agency to show the work actually completed or
materials provided by Consultant prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination.
ii. Termination for Cause. If Consultant fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to Consultant specifying the default (“Notice of Default”). If Consultant does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause. If Consultant fails to cure a default as set forth above, the Agency may, by written notice to Consultant, terminate this contract for cause, in whole or in part, and specifying the effective date thereof (“Notice of Termination for Cause”). If the termination is for cause, Consultant shall be
compensated for that portion of the work or materials
52 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 18 of 27 ends

provided which has been fully and adequately completed
and accepted by the Agency as of the date the Agency
provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems
necessary to complete the project and correct Consultant’s deficiencies and charge the cost thereof to Consultant, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.

iii. Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work rendered or materials provided and shall be entitled to withhold compensation for defective work or other damages caused by Consultant performance of the work.

iv. Additional Termination Provisions. Upon receipt of a Notice of Termination, either for cause or for convenience,
Consultant shall promptly discontinue the work unless the Notice directs to the contrary. Consultant shall deliver to the Agency and transfer title (if necessary) to all provided materials and completed work, and work in progress
including drafts, documents, plans, forms, maps, products, graphics, computer programs and reports. The rights and remedies of the parties provided in this Section are in addition to any other rights and remedies provided by law or under this contract. Consultant acknowledges the Agency’s right to terminate this contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the Agency’s
termination of this contract. The Agency shall not be liable for any costs other than the charges or portions thereof which are specified herein. Consultant shall not be entitled to payment for unperformed work or materials not provided and shall not be entitled to damages or compensation for termination of work or supply of materials. If Agency
terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a
termination for convenience. In such event, Consultant shall be entitled to receive only the amounts payable under this 53 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 19 of 27 ends

Section, and Consultant specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance.

B. Appendix II to Part 200 (C) – Equal Employment Opportunity:

Except as otherwise provided under 41 C.F.R. Part 60, Consultant shall comply with the following equal opportunity clause, in accordance with Executive Order 11246 of September 24, 1965 entitled “Equal Employment Opportunity,” as amended by
Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:
i. Consultant will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. Consultant will take affirmative action to insure that applicants are employed and that employees are treated equally during employment, without regard to race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following: employment upgrading, demotion, transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training including
apprenticeship. Consultant agrees to post in conspicuous places, available to employees and applicants for
employment, notices to be provided by the Agency setting forth the provisions of this nondiscrimination clause.
ii. Consultant will, in all solicitations or advertisements for employees placed by or on behalf of Consultant, state that all qualified applicants will receive consideration for employment without regard to their race, color, religion, sex, or national origin.

iii. Consultant will not discharge or in any other manner discriminate against any employee or applicant for
employment because such employee or applicant has
inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant.

This provision shall not apply to instances in which an 54 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 20 of 27 ends

employee who has access to the compensation information of other employees or applicants as a part of such
employee's essential job functions discloses the
compensation of such other employees or applicants to
individuals who do not otherwise have access to such
information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an
investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with Consultant‘s legal duty to furnish information.
iv. Consultant will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of
September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
v. Consultant will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
vi. Consultant will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
vii. In the event of Consultant’s noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the
contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in
Executive Order No.11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as
provided in Executive Order No.11246 of September 24,
55 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 21 of 27 ends

1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
viii. Consultant will include the provisions of paragraphs (i) through (viii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of September 24,1965, so that such provisions will be binding upon each subcontractor or Consultant. Consultant will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, that in the event Consultant becomes involved in, or is threatened with,
litigation with a subcontractor or Consultant as a result of such direction, Consultant may request the United States to enter into such litigation to protect the interests of the United States.

C. Appendix II to Part 200 (D) – Davis-Bacon Act; Copeland Act: Not applicable to this contract.

D. Appendix II to Part 200 (E) – Contract Work Hours and Safety Standards Act:
i. If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Consultant shall
comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to
compute the wages of every mechanic and laborer on the
basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and
provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.
56 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 22 of 27 ends

ii. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives
compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
iii. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any
subcontractor responsible therefore shall be liable for the unpaid wages. In addition, such contractor and
subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section. iv. The Agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Consultant or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other
federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be
necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.
v. The Consultant or subcontractor shall insert in any
subcontracts the clauses set forth in paragraph (ii) through 57 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 23 of 27 ends

(v) of this Section and also a clause requiring the
subcontractors to include these clauses in any lower tier subcontracts. The Contractor shall be responsible for
compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.

E. Appendix II to Part 200 (F) – Rights to Inventions Made Under a Contract or Agreement:
i. If the Federal award meets the definition of “funding agreement” under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental,
developmental, or research work under that “funding
agreement,” the non-Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative
Agreements), and any implementing regulations issued by the Agency.

ii. The regulation at 37 C.F.R. § 401.2(a) currently defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or
research work funded in whole or in part by the Federal government. This term also includes any assignment,
substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.

iii. This requirement does not apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management
Assistance Grant Program, Crisis Counseling Assistance
and Training Grant Program, Disaster Case Management
Grant Program, and Federal Assistance to Individuals and Households – Other Needs Assistance Grant Program, as
FEMA awards under these programs do not meet the
definition of “funding agreement.”
58 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 24 of 27 ends

F. Appendix II to Part 200 (G) – Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Consultant shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401- 7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387).
i. Pursuant to the Clean Air Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the
appropriate Environmental Protection Agency Regional
Office, and (3) Consultant agrees to include these
requirements in each subcontract exceeding $150,000.

ii. Pursuant to the Federal Water Pollution Control Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Consultant
agrees to include these requirements in each subcontract exceeding $150,000.

G. Appendix II to Part 200 (H) – Debarment and Suspension: A contract award (see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 C.F.R. part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.
59 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 25 of 27 ends

i. This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Consultant is required to verify that none of the Consultant, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. §
180.940) or disqualified (defined at 2 C.F.R. § 180.935). ii. Consultant must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into.
iii. This certification is a material representation of fact relied upon by Agency. If it is later determined that Consultant did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available
remedies, including but not limited to suspension and/or debarment.
iv. Consultant warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs. Consultant also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from
participation in accordance with the requirements above.

Consultant further agrees to notify the Agency in writing immediately if Consultant or its subcontractors are not in compliance during the term of this contract.

H. Appendix II to Part 200 (I) – Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Consultant shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Consultant shall file with the Agency the Federal Standard Form LLL titled “Disclosure Form to Report Lobbying.” Consultants that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 60 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 26 of 27 ends

U.S.C. 1352. Each tier must also disclose any lobbying with non- Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.

I. Appendix II to Part 200 (J) – Procurement of Recovered Materials:
i. Consultant shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation
and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the
Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered
materials practicable, consistent with maintaining a
satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity
acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement.
ii. In the performance of this contract, the Consultant shall make maximum use of products containing recovered
materials that are EPA-designated items unless the product cannot be acquired: Competitively within a timeframe
providing for compliance with the contract performance
schedule; Meeting contract performance requirements; or at a reasonable price.
iii. Information about this requirement, along with the list of EPA-designate items, is available at EPA’s Comprehensive Procurement Guidelines web site,
https://www.epa.gov/smm/comprehensive-procurement-
guideline-cpg-program.

5. MISCELLANEOUS PROVISIONS
A. The Consultant shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA preapproval.

B. This is an acknowledgement that FEMA financial assistance will be used to fund the contract only. The Consultant will comply with all 61 City of Goleta
Department of Public Works and Pacific Materials Laboratory Inc.

Page 27 of 27 ends

applicable federal law, regulations, executive orders, FEMA policies, procedures, and directives.

C. Consultant acknowledges that 31 U.S.C. Chapter 38
(Administrative Remedies for False Claims and Statements) applies to the Consultant’s actions pertaining to this contract.

D. The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the Agency, Consultant, any subcontractors or any other party pertaining to any matter resulting from the contract.

E. General and Administrative Expenses And Profit For Time And Materials Contracts/Amendments.
i. General and administrative expenses shall be negotiated and must conform to the Cost Principles.
ii. Profit shall be negotiated as a separate element of the cost.

To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the Consultant, the Consultant’s investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.

iii. Any agreement, amendment or change order for work
performed on a time and materials basis shall include a ceiling price that Consultant exceeds at its own risk.
62 ATTACHMENT 3

Public Works Contract with Toro Enterprise Inc. Evergreen

63 64
65 66
67 68
69 70
71 72
73 74
75 76
77 78
79 80
81 82
83 84
85 86
87 88
89 90
91 92
93 94
95 96
97 98
99 100
101
ATTACHMENT 4

Public Works Contract with Toro Enterprise Inc. Newport

102

PUBLIC WORKS CONTRACT

BETWEEN THE CITY OF GOLETA
AND

TORO ENTERPRISES, INC

This Public Works Contract CONTRACT
and entered into by and between the CITY OF GOLETA, a municipal corporation (herein referred to as "CITY"), and TORO ENTERPRISES, INC. , a California Corporation (he CONTRACTOR ).

SECTION A. RECITALS

1. The CITY has a need for emergency repairs to public property, trees, parks, and other infrastructure caused by severe storms in 2023 and 2024; and

2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for construction services to accomplish this work; and

3. Goleta Municipal Code Section 2.10.040(A)(6)(a) allows the City Manager make and issue rules and
regulations on matters reasonably related to the protection of life and property as affected by such emergency; provided however, such rules and regulations must be confirmed at the earliest practicable time by the City Council

4. An emergency exists in the CITY due to the severe storms of March 2023 and February 2024 which caused significant damage to roadways and CITY infrastructure. Therefore, it is necessary to the public health and safety that the City Manager immediately authorize the start of work on emergency mitigation measures, subject to ratification by City Council; and

5. The City Manager authorized this agreement pursuant to Goleta Municipal Code Section 2.10.040(A)(6)(a) and the City Council ratified this agreement at its next public meeting.

NOW, THEREFORE , in consideration of the foregoing and the mutual covenants herein contained, it is agreed:

SECTION B. TERMS

1. GENERAL SCOPE OF WORK: CITY agrees to engage CONTRACTOR and CONTRACTOR agrees to furnish all necessary labor, tools, materials, appliances, and equipment for and do the work for the Newport Creek Culvert Project in the City of Goleta as described in Exhibit A. The work shall be performed in accordance with the instructions of the City Engineer
designee.

103
Public Works Contract

TORO ENTERPRISES, INC

Page 2 of 37 ends

2. COMPENSATION: CONTRACTOR agrees to receive and accept the prices set forth in its Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder (Contract Price). Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid contract documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.

3. TIME OF PERFORMANCE: CONTRACTOR agrees to complete the work within 25 working days in the timeframe specified in the Notice to Proceed Letter (Contract Time). By signing this CONTRACT, CONTRACTOR represents to CITY that the Contract Time is reasonable for completion of the work and that CONTRACTOR will complete such work within the Contract Time. In accordance with Government Code Section 53069.85, CONTRACTOR agrees to forfeit and pay CITY as liquidated damages, not as a penalty, the sum of $750 per day for each and every day of unauthorized delay beyond the completion date, which amount shall be deducted from any payments due or to become due the CONTRACTOR.

4. PREVAILING WAGES:

A. Pursuant to Labor Code Sections §§1720 et seq., including but not limited to sections 1771, 1774 and 1775, and as specified in Title 8, California Code of Regulations, Section 16000 et seq., CONTRACTOR must pay its workers prevailing wages.
implement any prevailing wage requirements and CONTRACTOR agrees to pay any penalty or civil damages resulting from a violation of the prevailing wage laws.

B. In accordance with Labor Code Section 1773.2, copies of the prevailing rate Division or the website for State of California Prevailing wage determination at http://www.dir.ca.gov/DLSR/PWD. CONTRACTOR must post a copy of the prevailing rate of per diem wages at the job site.

C. CITY directs CONTRACT Sections 1777.5,
1777.6 and 3098 concerning the employment of apprentices by CONTRACTOR or any subcontractor.

D. Labor Code Section 1777.5 requires CONTRACTOR or subcontractor 104
Public Works Contract

TORO ENTERPRISES, INC

Page 3 of 37 ends

employing tradesmen in any apprenticeship occupation to apply to the joint apprenticeship committee nearest the site of the public works project and which administers the apprenticeship program in that trade for a certificate of approval. The certificate must also fix the ratio of apprentices to journeymen that will be used in the performance of the contract. The ratio of apprentices to journeymen in such cases will not be less than one to five except:

(1) When employment in the area of coverage by the joint appren- ticeship committee has exceeded an average of 15 percent in the 90 days before the request for certificate, or

(2) When the number of apprentices in training in the area exceeds a ratio of one to five, or

(3) When the trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally, or

(4) When assignment of an apprentice to any work performed under a public works contract would create a condition that would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large, or the specific task to which the apprentice is to be assigned is of a nature that training cannot be provided by a journeyman.

Pursuant to Labor Code § 1776, CONTRACTOR shall comply with all Department of Industrial Relations registration requirements.

E. CONTRACTOR is required to make contributions to funds established for the administration of apprenticeship programs if CONTRACTOR employs registered apprentices or journeymen in any apprentice able trade on such contracts and if other contractors on the public works site are making such contributions.

F. CONTRACTOR and any subcontractor must comply with Labor Code Sections 1777.5 and 1777.6 in the employment of apprentices.

G. Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations (DIR), ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

H. CONTRACTOR and its subcontractors must keep an accurate certified payroll records showing the name, occupation, and the actual per diem 105
Public Works Contract

TORO ENTERPRISES, INC

Page 4 of 37 ends

wages paid to each worker employed in connection with this CONTRACT.

The record will be kept open at all reasonable hours to the inspection of the body awarding the contract and to the Division of Labor Law Enforcement.

If requested by CITY, CONTRACTOR must provide copies of the records at its cost.

5. LEGAL HOURS OF WORK: CONTRACTOR agrees to comply with the provisions of California Labor Code Section 1813 concerning penalties for workers who work excess hours. Except as provided by Labor Code Section 1815, the CONTRACTOR shall, as a penalty to the CITY, forfeit twenty five dollars ($25) for each worker employed in the execution of the Contract by the CONTRACTOR or by any Subcontractor for each calendar day during which such worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2, Part 7, Chapter 1, Article 3 (commencing at Section 1810) of the California Labor Code.

6. TRAVEL AND SUBSISTENCE PAY : CONTRACTOR agrees to pay travel and subsistence pay to each worker needed to execute the work required by this CONTRACT as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed in accordance with Labor Code Section 1773.8.

7. CONTRACTOR'S LIABILITY: The CITY and its officers, agents and employees Indemnitees ) shall not be answerable or accountable in any manner for any loss or damage that may happen to the work or any part thereof, or for any of the materials or other things used or employed in performing the work; or for injury or damage to any person or persons, either workers or employees of CONTRACTOR, of its subcontractors or the public, or for damage to adjoining or other property from any cause whatsoever arising out of or in connection with the performance of the work. CONTRACTOR shall be responsible for any damage or injury to any person or property resulting from defects or obstructions or from any cause whatsoever.

CONTRACTOR will indemnify Indemnities against and will hold and save Indemnitees harmless from any and all actions, claims, damages to persons or property, penalties, obligations or liabilities that may be asserted or claimed by any person, firm, entity, corporation, political subdivision, or other organization arising out of or in connection with the work, operation, or activities of CONTRACTOR, its agents, employees, subcontractors or invitees provided for herein, whether or not there is concurrent passive negligence on the part of CITY. In connection therewith:

106
Public Works Contract

TORO ENTERPRISES, INC

Page 5 of 37 ends

a. CONTRACTOR will defend any action or actions filed in connection with any such claims, damages, penalties, obligations or liabilities and will pay all costs and expenses, including attorneys' fees, expert fees and costs incurred in connection therewith.

b. CONTRACTOR will promptly pay any judgment rendered against CONTRACTOR or Indemnitees covering such claims, damages, penalties, obligations and liabilities arising out of or in connection with such work, operations or activities of CONTRACTOR hereunder, and CONTRACTOR agrees to save and hold the Indemnitees harmless therefrom.

c. In the event Indemnitees are made a party to any action or proceeding filed or prosecuted against CONTRACTOR for damages or other claims arising out of or in connection with the work, operation or activities hereunder, CONTRACTOR agrees to pay to Indemnitees and any all costs and expenses incurred by Indemnitees in such action or proceeding together with reasonable attorneys' fees.

CONTRACTOR'S obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this CONTRACT, Contractor shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City.

So much of the money due to CONTRACTOR under and by virtue of the contract as shall be considered necessary by CITY may be retained by CITY until disposition has been made of such actions or claims for damages as aforesaid.

It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California.

This indemnity provision shall survive the termination of the CONTRACT and is in addition to any other rights or remedies which Indemnitees may have under the law.

107
Public Works Contract

TORO ENTERPRISES, INC

Page 6 of 37 ends

This indemnity is effective without reference to the existence or applicability of any insurance coverage which may have been required under this CONTRACT or any additional insured endorsements which may extend to Indemnitees.

CONTRACTOR, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the Indemnitees, while acting within the scope of their duties, from all claims, losses and liabilities arising out of or incident to activities or operations performed by or on behalf of the CONTRACTOR regardless of any prior, concurrent, or subsequent passive negligence by the Indemnitees.

8. THIRD PARTY CLAIMS: In accordance with Public Contracts Code Section 9201, CITY will promptly inform CONTRACTOR regarding third-party claims against CONTRACTOR, but in no event later than ten (10) business days after CITY receives such claims. Such notification will be in writing and forwarded in CONTRACT. CONTRACTOR agrees
to indemnify, hold harmless and defend the City against any third-party claim.

9. WORKERS COMPENSATION: In accordance with California Labor Code Sections 1860 and 3700, CONTRACTOR and each of its subcontractors will be required to secure the payment of compensation to its employees. In accordance with the provisions of California Labor Code Section 1861, CONTRACTOR, by signing this c I am aware of the provisions of Section
3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

10. INSURANCE: With respect to performance of work under this CONTRACT, CONTRACTOR shall maintain and shall require all of its subcontractors to maintain insurance as required in the Standard Specifications.

11. ASSIGNMENT: This CONTRACT is not assignable nor the performance of either party's duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations of either party without the prior written consent of the other shall be void and of no force and effect.

12. INDEPENDENT CONTRACTOR: CONTRACTOR is and shall at all times remain as to the CITY, a wholly independent contractor. Neither the CITY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR'S employees, except as herein set forth. CONTRACTOR shall not 108
Public Works Contract

TORO ENTERPRISES, INC

Page 7 of 37 ends

at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of CITY.

13. TAXES: CONTRACTOR is responsible for paying all retail sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes and operations incidental to or involved in this contract. CONTRACTOR is responsible for ascertaining and arranging to pay them. The prices established in the contract shall include compensation for any taxes CONTRACTOR is required to pay by laws and regulations in effect at the notice to proceed.

14. LICENSES: CONTRACTOR represents and warrants to CITY that it has all licenses, permits, qualifications, insurance, and approvals of whatsoever nature which are legally required of CONTRACTOR to practice its profession.

CONTRACTOR represents and warrants to CITY that CONTRACTOR shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this CONTRACT any licenses, permits, insurance, and approvals which are legally required of CONTRACTOR to practice its profession. CONTRACTOR shall maintain a City of Goleta business license, if required under CITY ordinance.

15. RECORDS: CONTRACTOR shall maintain accounts and records, including personnel, property, and financial records, adequate to identify and account for all costs pertaining to this CONTRACT and such other records as may be deemed necessary by CITY or any authorized representative, and will be retained for three years after the expiration of this CONTRACT. All such records shall be made available for inspection or audit by CITY at any time during regular business hours.

16. SEVERABILITY: If any portion of these contract documents are declared by a court of competent jurisdiction to be invalid or unenforceable, then such portion will be deemed modified to the extent necessary in the opinion of the court to render such portion enforceable and, as so modified, such portion and the balance of this CONTRACT will continue in full force and effect provided that it does not frustrate the mutual intent of the parties herein.

17. WHOLE AGREEMENT: This CONTRACT supersedes any and all other agreements either oral or written, between the parties and contains all of the covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this contract acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statements or promise not 109
Public Works Contract

TORO ENTERPRISES, INC

Page 8 of 37 ends

contained in this contract shall not be valid or binding. Any modifications of this contract will be effective only if signed by the party to be charged.

18. AUTHORITY: CONTRACTOR affirms that the signatures, titles, and seals set forth hereinafter in execution of this CONTRACT represent all individuals, firm members, partners, joint ventures, and/or corporate officers having a principal interest herein. Each party warrants that the individuals who have signed this CONTRACT have the legal power, right, and authority to make this CONTRACT and to bind each respective party. This CONTRACT may be modified by written amendment.
anager may execute any su
behalf.

19. NOTICES: All notices permitted or required under this CONTRACT shall be in representative as provided in this CONTRACT. Additionally, such notices may be given to the respective parties at the following addresses, or at such other addresses as the parties may provide in writing for this purpose.

Such notices shall be deemed made when personally delivered or when mailed forty-eight (48) hours after deposit in the U.S. mail, first-class postage prepaid, and addressed to the party at its applicable address. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.

CITY OF GOLETA
130 Cremona Drive, Suite B
Goleta, CA 93117
Attn: City Manager

CONTRACTOR
Toro Enterprise, Inc
P.O Box 6285
Oxnard, CA 93031
Attn: Sean Castillo

20. DISPUTES: Disputes arising from this contract will be determined in accordance with the contract documents.

21. NON-DISCRIMINATION: The CITY reaffirms its ongoing commitment to equality in the conduct of City business, and prohibits any policy, plan, program, custom or practice, including harassment, in the conduct of City business. No discrimination or discriminatory practice shall occur in either employment of persons for, or completion of, the work contemplated by this CONTRACT, when such 110
Public Works Contract

TORO ENTERPRISES, INC

Page 9 of 37 ends

discrimination is based on race, color, national origin, or ancestry; religion; sex; gender, gender identity, gender expression, or gender transitioning status; physical disability, mental disability, medical condition, or genetic information; marital or domestic partner status; citizenship status; age; sexual orientation; exercising a legally protected right to an employment leave of absence; status as a victim of domestic violence, sexual assault, or stalking; reproductive health decision-making, or any other classification protected under state or federal law.

Among other possible violations of law, a violation of this section exposes CONTRACTOR to the penalties provided for in Labor Code Section 1735.

22. PAPER PRODUCTS AND PRINTING REQUIREMENTS: To the extent this contract provides paper products, and printing and writing paper for the City, CONTRACTOR must meet quality standards and criteria specified in SB 1383, Sections 22150-22154 of the Public Contract Code and 16 Code of Federal by:
a. If fitness and quality are equal, provide recycled products, instead of nonrecycled products whenever recycled products are available at the same or a lesser total cost than nonrecycled items.
b. Provide paper products and printing and writing paper that meet Federal Trade Commission recyclability standard as defined in 16 CFR

c. Certify in writing, under penalty of perjury, the minimum percentage of postconsumer material in the paper products and printing and writing paper offered or sold to the City. This certification requirement may be waived if the percentage of postconsumer material in the paper products, printing and writing paper, or both can be verified by a product label, catalog, invoice, or a manufacturer or vendor internet website. d. Certify in writing, on invoices or receipts provided, that the paper products and printing and writing paper offered or sold to the City is eligible to be labeled with an unqualified recyclable label as defined in

e. Comply with any other requirements in Goleta Municipal Code Section

8.10.900(B).

23. ORGANIC WASTE USE REQUIREMENTS: To the extent this contract provides landscaping maintenance, renovation, and construction services, CONTRACTOR must:
a. Use compost and SB 1383 eligible mulch, as practicable, produced from recovered organic waste, for all landscaping renovations, construction, or maintenance performed for the City, whenever available, and capable 111
Public Works Contract

TORO ENTERPRISES, INC

Page 10 of 37 ends

of meeting quality standards and criteria specified. SB 1383 eligible mulch used for land application must comply with 14 CCR Section 18993.1 - 18993.4, and must meet or exceed the physical contamination, maximum metal concentration and pathogen density standards specified in 14 CCR Sections 17852(a)(24.5)(A)(1) through (3).
b. Keep and provide records of procurement of recovered organic waste Designated Representative, upon completion of projects. Information to be provided must include:
i. General description of how and where the product was used and if applicable, applied;
ii. Source of product, including name, physical location, and contact information for each entity, operation, or facility from whom the recovered organic waste products were procured; iii. Type of product;
iv. Quantity of each product; and,
v. Invoice or other record demonstrating purchase or
procurement.
c. Comply with all requirements in Goleta Municipal Code Section

8.10.900(A).

24. NO THIRD-PARTY BENEFICIARY: This CONTRACT and every provision herein is for the exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of the or the obligations under this Contract.

25. TIME IS OF ESSENCE: Time is of the essence for each and every provision of the Contract Documents.

26. ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES: The Parties agree that this CONTRACT, agreements ancillary to this CONTRACT, and related documents to be entered into in connection with this CONTRACT will be considered signed when the signature of a party is delivered by facsimile transmission or scanned and delivered via electronic mail. Such facsimile or electronic mail copies will be treated in all respects as having the same effect as an original signature.

27. GOVERNING LAW: This CONTRACT shall be governed by the laws of the State of California, and exclusive venue for any action involving this CONTRACT will be in Santa Barbara County.
112
Public Works Contract

TORO ENTERPRISES, INC

Page 11 of 37 ends

28. FEDERAL REQUIREMENTS
FEMA financial assistance will be used to fund all or a portion of this contract.

The Contractor shall comply with all federal requirements including, but not limited to, the following:

1. 2 C.F.R. Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.

2. Federal Contract Provisions attached hereto as Exhibit B and incorporated herein by reference.

Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, 2 C.F.R. Part 200 and the Federal Contract Provisions.

With respect to any conflict between such federal requirements and the terms of this contract and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.

IN WITNESS WHEREOF, the parties hereto have executed this CONTRACT with all the formalities required by law on the respective dates set forth opposite their signatures.

This CONTRACT is executed on this ________ day of ___________ , at Goleta, California, and effective as of _____ ______, 20____.

CITY OF GOLETA:

___________________________________
Robert Nisbet, City Manager

ATTEST:

___________________________________
Deborah Lopez, City Clerk

APPROVED AS TO FORM:

MEGAN GARIBALDI, CITY ATTORNEY

___________________________________
Scott Shapses, Deputy City Attorney
113
Public Works Contract

TORO ENTERPRISES, INC

Page 12 of 37 ends

CONTRACTOR:

_____________________________________
Sean Castillo, Owner

State of California License No.

__710580_____________________________
Department of Industrial Relations Registration
No.

_____________________________________

Business Phone No.

__ (805) 483 4515_____________________

which contractor can be reached at any time

_Dann White_- (805) 620 8966 _______ _

_____________________________________

______ _
Dann White, Superintendent

114
Public Works Contract

TORO ENTERPRISES, INC

Page 13 of 37 ends

EXHIBIT A

SCOPE OF WORK

At the cost of $721,924 CONTRACTOR shall perform the following work:

A. Head Wall

1. Remove unsuitable material and any standing water at the base of the headwall.

Any deleterious material shall be removed on a T&M basis.

2. Perform as shown on detailed design drawing (DDD) dated 12/31/2023 (no revisions shown) grading within downstream channel for subgrade preparation necessary to install rock slope protection (i.e. stone rip rap).

3. Install a Class VIII, 1 Ton Rock Slope Protection (i.e. stone rip rap) downstream of headwall as shown on DDD dated 12/31/2023 (no revisions shown). This includes installation of Rock Slope Protection Fabric and Rock Slope Protection.

4. Protect existing head wall structure in place during construction.

B. Wing Walls:

1. Remove existing wing walls, excavate materials behind wing walls and install temporary shoring.

2. Install six cast in drilled hole (CIDH) piles, new wing walls, and structural connections to existing headwalls as shown on DDD dated 12/31/2023 (no revisions shown).

3. Backfill and compact materials behind wing walls.

C. Sidewalk:

1. Backfill - backfill shall be done per DDD

2. Remove and replace concrete sidewalk
D. Galvanized Pipe Handrail

1. Remove Galvanized Pipe Handrail and replace with cable railing along the top of the new wing walls and existing headwall structure.

115
116
Public Works Contract

TORO ENTERPRISES, INC

Page 14 of 37 ends

117
Public Works Contract

TORO ENTERPRISES, INC

Page 15 of 37 ends

118
Public Works Contract

TORO ENTERPRISES, INC

Page 16 of 37 ends

119
Public Works Contract

TORO ENTERPRISES, INC

Page 17 of 37 ends

The following optional services shall be directed by the CITY to be conducted on an as needed basis and up to a not to exceed the amount of $72,193. The CONTRACTOR shall from the Engineer before conducting any of the
following services. If the CONTRACTOR performs the work without prior approval from the Engineer, the Contractor shall be responsible for the cost of the work performed.

The following services will also become a part of the work if directed by the City. 120
Public Works Contract

TORO ENTERPRISES, INC

Page 18 of 37 ends

EXHIBIT B

SCHEDULE OF FEES

121
Public Works Contract

TORO ENTERPRISES, INC

Page 19 of 37 ends

122
Public Works Contract

TORO ENTERPRISES, INC

Page 20 of 37 ends

123
Public Works Contract

TORO ENTERPRISES, INC

Page 21 of 37 ends

EXHIBIT C

FEDERAL CONTRACT PROVISIONS
During the performance of this contract, Toro Enterprise, Inc. comply with all applicable federal laws and regulations including but not limited to the the local agency entering into this contract with the Contractor.

1. ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2 C.F.R. § 200.321)

A. Contractor shall be subject to 2 C.F.R. § 200.321 and will take affirmative surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.

B. Affirmative steps shall include:

i. Placing qualified small and minority businesses and women's business enterprises on solicitation lists;
ii. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are potential sources; iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business enterprises;
iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and
v. Using the services/assistance of the Small Business Administration (SBA), and the Minority Business Development Agency (MBDA) of the Department of Commerce.

Contractor shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.

Notwithstanding the foregoing, the affirmative steps requirements detailed above do not apply in the case of a noncompetitive procurement made under the emergency exception/exigency exception to competitive procurements.

2. COST PRINCIPLES (2 C.F.R. PART 200, SUBPART E)

A. If any indirect costs will be charged to the Agency under this contract, such costs must conform to the cost principles set forth under the Uniform Rules 124
Public Works Contract

TORO ENTERPRISES, INC

Page 22 of 37 ends

(i) be necessary and reasonable; (ii) allocable to the grant award; (iii) conform to any limitations or exclusions set forth in the Cost Principles; (iv) be adequately documented; and (v) be determined in accordance with generally accepted accounting princ
local governments and Indian tribes only, as otherwise provided for in 2 C.F.R. Part 200, subpart E. 2 C.F.R. § 200.403. Costs that are determined unallowable pursuant to a federal audit are subject to repayment by Contractor.

3. ACCESS TO RECORDS & RECORD RETENTION (2 C.F.R. 200.336)

A. Contractor shall comply with 2 C.F.R. § 200.336 and provide the Federal Agency, Inspectors General, the Comptroller General of the United States, Agency, and the State of California or any of their authorized representatives access, during normal business hours, to documents, papers, books and records which are directly pertinent to this contract for the purposes of making and responding to audits, examinations, excerpts, and transcriptions. The right also includes timely and reasonable access to the Contractor personnel for the purpose of interview and discussion related to the books and records.

B. The Contractor agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

C. The Contractor agrees to provide the Federal Agency or its authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

4. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH APPENDIX II TO PART 200

CONTRACT PROVISIONS FOR NON-FEDERAL ENTITY
CONTRACTS UNDER FEDERAL AWARDS (2 C.F.R. § 200.326)

A. Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract is in excess of $10,000 and the contract does not include provisions for both termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract is for more than the simplified acquisition threshold (see 2 C.F.R. § 200.88) at the time the contract is executed and does not provide for administrative, contractual, or legal remedies in instances where Contractor violates or breaches the terms of the contract, then the following termination clauses shall apply and have 125
Public Works Contract

TORO ENTERPRISES, INC

Page 23 of 37 ends

precedence over the contract. Otherwise, the following termination clauses shall not be applicable to the contract.

i. Termination for Convenience. The Agency may, by written notice to Contractor, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Contractor of such Termination for C
convenience of the Agency, the Agency shall compensate Provider for work or materials fully and adequately provided through the effective date of termination. No amount shall be paid for unperformed work or materials not provided, including anticipated profit. Contractor shall provide documentation deemed adequate by the Agency to show the work actually completed or materials provided by Contractor prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination.

ii. Termination for Cause. If Contractor fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause.

If Contractor fails to cure a default as set forth above, the Agency may, by written notice to Contractor, terminate this contract for cause, in whole or in part, and specifying the effective date thereof Contractor shall be compensated for that portion of the work or materials provided which has been fully and adequately completed and accepted by the Agency as of the date the Agency provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems necessary to complete the project o
Contractor, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.

iii. Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work rendered or materials provided and shall be entitled to withhold compensation for defective work or other damages caused by Contractor performance of the work.

126
Public Works Contract

TORO ENTERPRISES, INC

Page 24 of 37 ends

iv. Additional Termination Provisions. Upon receipt of a Notice of Termination, either for cause or for convenience, Contractor shall promptly discontinue the work unless the Notice directs to the contrary. Contractor shall deliver to the Agency and transfer title (if necessary) to all provided materials and completed work, and work in progress including drafts, documents, plans, forms, maps, products, graphics, computer programs and reports. The rights and remedies of the parties provided in this Section are in addition to any other rights and remedies provided by law or under this contract. contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the for any costs other than the charges or portions thereof which are specified herein. Contractor shall not be entitled to payment for unperformed work or materials not provided and shall not be entitled to damages or compensation for termination of work or supply of materials. If Agency terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a termination for convenience. In such event, Contractor shall be entitled to receive only the amounts payable under this Section, and Contractor specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance.

B. Appendix II to Part 200 (C) Equal Employment Opportunity: Except as otherwise provided under 41 C.F.R. Part 60, Contractor shall comply with the following equal opportunity clause, in accordance with Executive Order amended by Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:

i. Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin.

Contractor will take affirmative action to insure that applicants are employed and that employees are treated equally during
employment, without regard to race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following:
127
Public Works Contract

TORO ENTERPRISES, INC

Page 25 of 37 ends

employment upgrading, demotion, transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training including apprenticeship. Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the Agency setting forth the provisions of this nondiscrimination clause.

ii. Contractor will, in all solicitations or advertisements for employees placed by or on behalf of Contractor, state that all qualified applicants will receive consideration for employment without regard to their race, color, religion, sex, or national origin.

iii. Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the information.

iv. Contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

v. Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.

vi. Contractor will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, 128
Public Works Contract

TORO ENTERPRISES, INC

Page 26 of 37 ends

regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.

vii.
nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order No.11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order No.11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.

viii. Contractor will include the provisions of paragraphs (i) through (viii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of September 24,1965, so that such provisions will be binding upon each subcontractor or Contractor. Contractor will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, that in the event Contractor becomes involved in, or is threatened with, litigation with a subcontractor or Contractor as a result of such direction, Contractor may request the United States to enter into such litigation to protect the interests of the United States.

C. Appendix II to Part 200 (D) Davis-Bacon Act; Copeland Act: Not applicable to this contract.

D. Appendix II to Part 200 (E) Contract Work Hours and Safety Standards Act:

i. If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Contractor shall comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor
regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work 129
Public Works Contract

TORO ENTERPRISES, INC

Page 27 of 37 ends

in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

ii. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.

iii. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any subcontractor responsible therefore shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section.

iv. The Agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be 130
Public Works Contract

TORO ENTERPRISES, INC

Page 28 of 37 ends

necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.

v. The Contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (ii) through (v) of this Section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The Contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.

E. Appendix II to Part 200 (F) Rights to Inventions Made Under a Contract or Agreement:

i.
under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work -Federal entity must comply
with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements), and any implementing regulations issued by the Agency.

ii.
entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or research work funded in whole or in part by the Federal government. This term also includes any assignment, substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.

iii. This requirement does not apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management Assistance Grant Program, Crisis Counseling Assistance and Training Grant Program, Disaster Case Management Grant Program, and Federal Assistance to Individuals and Households Other Needs Assistance Grant Program, as FEMA awards under these programs do not meet the

131
Public Works Contract

TORO ENTERPRISES, INC

Page 29 of 37 ends

F. Appendix II to Part 200 (G) Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Contractor shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387).

i. Pursuant to the Clean Air Act, (1) Contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Contractor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Contractor agrees to include these requirements in each subcontract exceeding $150,000.

ii. Pursuant to the Federal Water Pollution Control Act, (1) Contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Contractor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Contractor agrees to include these requirements in each subcontract exceeding $150,000.

G. Appendix II to Part 200 (H)
Debarment and Suspension: A contract award
(see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.

i. This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Contractor is required to verify that none of the Contractor, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded 132
Public Works Contract

TORO ENTERPRISES, INC

Page 30 of 37 ends

(defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935).

ii. Contractor must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into. iii. This certification is a material representation of fact relied upon by Agency. If it is later determined that Contractor did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment.

iv. Contractor warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs.

Contractor also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from participation in accordance with the requirements above. Contractor further agrees to notify the Agency in writing immediately if Contractor or its subcontractors are not in compliance during the term of this contract.

H. Appendix II to Part 200 (I) Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Contractor shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Contractor shall file with the Agency the Federal Standard Form LLL titled award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.

I. Appendix II to Part 200 (J) Procurement of Recovered Materials:

i. Contractor shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and 133
Public Works Contract

TORO ENTERPRISES, INC

Page 31 of 37 ends

Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement.

ii. In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired:

Competitively within a timeframe providing for compliance with the contract performance schedule; Meeting contract performance requirements; or at a reasonable price.

iii. Information about this requirement, along with the list of EPA- Guidelines web site, https://www.epa.gov/smm/comprehensive- procurement-guideline-cpg-program.

5. MISCELLANEOUS PROVISIONS

A. The Contractor shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA preapproval.

B. This is an acknowledgement that FEMA financial assistance will be used to fund the contract only. The Contractor will comply with all applicable federal law, regulations, executive orders, FEMA policies, procedures, and directives.

C. Contractor acknowledges that 31 U.S.C. Chapter 38 (Administrative actions pertaining to this contract.

D. The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the Agency, Contractor, any subcontractors or any other party pertaining to any matter resulting from the contract.

E. General and Administrative Expenses And Profit For Time And Materials Contracts/Amendments.
134
Public Works Contract

TORO ENTERPRISES, INC

Page 32 of 37 ends

i. General and administrative expenses shall be negotiated and must conform to the Cost Principles.

ii. Profit shall be negotiated as a separate element of the cost. To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the Contractor
subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.

iii. Any agreement, amendment or change order for work performed on a time and materials basis shall include a ceiling price that Contractor exceeds at its own risk.

135
Public Works Contract

TORO ENTERPRISES, INC

Page 33 of 37 ends

EXHIBIT D

DISPUTE RESOULTION
Section 10 Potential Claims and Dispute Resolution

Section 10-1 Potential Claim
Any demand or assertion by the Contractor seeking an adjustment of Contract Price and/or Contract Time, or other relief, for any reason whatsoever, must be in strict compliance with the requirements of the Contract Documents. For purposes of this Section 10-1, any and all work relating to any such demand or assertion shall be referred from an interpretation of the Contract Documents, an action or inaction of the Contractor, the Engineer, or the City, or any other event, issue, or circumstance. The Contractor shall bear all costs incurred in complying with the provisions of this Section 10-1.

Promptly upon becoming aware of any event, issue, or circumstance including, but not limited to, disputes arising under the Contract, the acts or omissions of the Engineer or City or by operation of law, which the Contractor believes, in whole or in part, provides a performance is excused, or other relief, Contractor shall provide a signed written Initial Notice of Potential Claim to the Engineer in a format acceptable to the City. Contractor shall provide a signed written initial notice of potential claim to the Engineer within 5 days from the date the dispute first arose and before commencing any disputed work. The initial notice of potential claim shall provide the nature and circumstances involved in the dispute which shall remain consistent through the dispute. The initial notice of potential be certified with reference to the California False Claims Act, Government Code Sections 12650 12655. Assign an exclusive identification number for each dispute, determined by chronological sequencing, based on the date of the dispute.

The exclusive identification number for each dispute shall be used on the following corresponding documents:

1. Initial notice of potential claim.

2. Supplemental notice of potential claim.

3. Full and final documentation of potential claim.

4. Corresponding claim included in the Contractor's written statement of claims.

Provide the Engineer the opportunity to examine the site of work within 5 days from the date of the initial notice of potential claim. Proceed with the performance of contract work unless otherwise specified or directed by the Engineer.

Throughout the disputed work, maintain records that provide a clear distinction between the incurred direct costs of disputed work and that of undisputed work. Allow the Engineer access to your project records deemed necessary by the Engineer to evaluate the potential claim within 20 days of the date of the Engineer's written request. 136
Public Works Contract

TORO ENTERPRISES, INC

Page 34 of 37 ends

Within 15 days of submitting the initial notice of potential claim, submit a signed supplemental notice of potential claim to the Engineer that provides the following information:

1. The complete nature and circumstances of the dispute which caused the potential claim.

2. The contract provisions that provide the basis of claim.

3. The estimated cost of the potential claim, including an itemized breakdown of individual costs and how the estimate was determined.

4. A time impact analysis of the project schedule that illustrates the effect on the scheduled completion date due to schedule changes or disruptions where a request for adjustment of Contract Time is made.

Include your complete reasoning for additional compensation or adjustments.

Submit the supplemental notice of potential claim on Form CEM 6201B furnished by the Department and certify with reference to the California False Claims Act, Government Code Sections 12650 12655. The Engineer will evaluate the information presented in the supplemental notice of potential claim and provide a written response within 20 days of receipt. If the estimated cost or effect on the scheduled completion date changes, update information in items 3 and 4 above as soon as the change is recognized and submit this information to the Engineer.

Within 30 days of the completion of work related to the potential claim, submit the full and final documentation of potential claim to the Engineer that provides the following information:

(1.) A detailed factual narration of events fully describing the nature and circumstances that caused the dispute, including, but not limited to, necessary dates, locations, and items of work affected by the dispute.
(2.) The specific provisions of the contract that support the potential claim and a statement of the reasons these provisions support and provide a basis for entitlement of the potential claim.
(3.) When additional monetary compensation is requested, the exact amount requested calculated in conformance with the Contract Documents including an itemized breakdown of individual costs. These costs shall be segregated into the following cost categories:

3.1. Labor
A listing of individuals, classifications, regular hours and overtime hours worked, dates worked, and other pertinent information related to the requested reimbursement of labor costs.

3.2. Materials Invoices, purchase orders, location of materials either stored or incorporated into the work, dates materials were transported to the project or incorporated into the work, and other pertinent information related to the requested reimbursement of material costs.

3.3. Equipment Listing of detailed description (make, model, and serial number), hours of use, dates of use, and equipment rates. Equipment rates shall be at the applicable State rental rate as listed in the Department of Transportation 137
Public Works Contract

TORO ENTERPRISES, INC

Page 35 of 37 ends

publication entitled "Labor Surcharge and Equipment Rental Rates," in effect when the affected work related to the dispute was performed.

3.4. Other categories as specified by the Contractor or the Engineer.

(4.) When an adjustment of Contract Time is requested, include the following:

4.1.The specific dates for which contract time is being requested.

4.2.The specific reasons for entitlement to a Contract Time adjustment.

4.3. The specific provisions of the contract that provide the basis for the requested Contract Time adjustment.

4.4. A detailed time impact analysis of the project schedule. The time impact analysis shall show the effect of changes or disruptions on the scheduled completion date to demonstrate entitlement to a Contract Time adjustment.

(5.) The identification and copies of documents and the substance of oral communications that support the potential claim.

The full and final documentation of the potential claim shall be submitted on Form CEM 6201C furnished by the Department and shall be certified with reference to the California False Claims Act, Government Code Sections 12650 12655.

Pertinent information, references, arguments, and data to support the potential claim shall be included in the full and final documentation of potential claim. Information submitted subsequent to the full and final documentation submittal will not be considered.

Information required in the full and final documentation of potential claim, as listed in items 1 to 5 above, that is not applicable to the dispute may be exempted as determined by the Engineer. No full and final documentation of potential claim will be considered that does not have the same nature and circumstances, and basis of claim as those specified on the initial and supplemental notices of potential claim.

If you, in conjunction with or subsequent to the assertion of a potential claim, request inspection and copying of documents or records in the possession of the City that pertain to the potential claim, you must make your records of the project, as deemed by the City to be pertinent to the potential claim, available to the City for inspection and copying."

Unless otherwise specified, the Engineer will evaluate the information presented in the full and final documentation of potential claim and provide a written response within 30 days of receipt. The Engineer's receipt of the full and final documentation of potential claim shall be evidenced by postal receipt or the Engineer's written receipt if delivered by hand. If you submit full and final documentation of potential claim after acceptance of the work by the City, the Engineer need not provide a written response.

Section 10-2 Dispute Resolution
All disputes and claims arising under or by virtue of this contract shall be directed to and appealed to City Manager or their designee. The determination by the City Manager or their designee of disputes and claims shall constitute the decision of the City of Goleta; provided, however, that Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 138
Public Works Contract

TORO ENTERPRISES, INC

Page 36 of 37 ends

3 of Division 2 of the Public Contract Code shall apply to the public works claim of $375,000 or less.

Section 10-3 Dispute Resolution - Claims exceeding $375,000 Any claim, dispute, or other matter in question arising out of or related to the Contract or Project exceeding three-hundred seventy-five thousand dollars ($375,000.00) that cannot be resolved between the City and the Contractor shall be resolved by the Santa Barbara County Superior Court.

Section 10-4 Claims Procedures as a Prerequisite to Filing Suit Contractor acknowledges and agrees that its failure to submit any notice of potential claim or claim arising under this Contract in accordance with Section 10, shall constitute a ime. Failure
right to receive any additional time or money as a result of any event giving rise to a claim or request for change order. Notwithstanding any other provisions in the Contract relating to any additional time or money which Contractor may be entitled to upon the occurrence of any directive or other event, or any other circumstance, Contractor must comply with the provisions of Section 10 to avoid a waiver of any such entitlement to any additional compensation or adjustments to Contract Time. Such failure, neglect, or refusal failure, neglect, or refusal prevent the timely analysis of requests for adjustment of Contract Time, and whether such adjustments may be warranted. Contractor hereby waives all rights to additional compensation or adjustments of Contract Time due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of Section 10.

Section 10-5 Government Code Claims.
obligation to present a written Government Code claim in accordance with Section 900 et al of the California Government Code, which is a prerequisite to filing a lawsuit for money or damages against the City. Contractor further acknowledges that notwithstanding in the
with the claims procedures set forth in Government Code sections 900 et al prior to filing a lawsuit against the City for any such claim. Failure to submit a Government Code claim, or comply with the claims provision contained in Section 10 or in the City Special Provisions, shall bar Contractor from bringing and maintaining a valid lawsuit against the City.

Section 10-6 Participation in Dispute Resolution Proceedings.

Contractor and the City agree that all parties necessary to resolve a claim or dispute should be parties to the same dispute resolution proceeding. Contractor agrees upon esence
is required if complete relief is to be accorded and to prevent the possibility of conflicting 139
ATTACHMENT 5

Public Works Contract with Toro Enterprise Inc. Camino Venturoso

140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
ATTACHMENT 6

Public Works Contract with Bob’s Backhoe Ellwood Mesa
183

PUBLIC WORKS CONTRACT

BETWEEN THE CITY OF GOLETA
AND
HEARN CONSTRUCTION INC. DBA BOB’S BACKHOE & TRUCKING
This Public Works Contract (herein referred to as “CONTRACT”) is made and entered into by and between the CITY OF GOLETA, a municipal corporation (herein referred to as "CITY"), and HEARN CONSTRUCTION INC. dba BOB’S BACKHOE & TRUCKING (hereinafter referred to as “CONTRACTOR”).

SECTION A. RECITALS

1. The CITY has a need for emergency repairs to public property, trees, parks, and other infrastructure caused by severe storms in 2024; and

2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for construction services to accomplish this work; and

3. Goleta Municipal Code Section 2.10.040(A)(6)(a) allows the City Manager (referenced as “Director of Emergency Services”) to “make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency; provided however, such rules and regulations must be confirmed at the earliest practicable time by the City Council”; and

4. An emergency exists in the CITY due to the severe storms of 2024 which caused significant damage to roadways and CITY infrastructure. Therefore, it is necessary to the public health and safety that the City Manager immediately authorize the start of work on emergency mitigation measures, subject to ratification by City Council; and

5. The City Manager authorized this agreement pursuant to Goleta Municipal Code Section 2.10.040(A)(6)(a) and the City Council ratified this agreement at its next public meeting.

NOW, THEREFORE , in consideration of the foregoing and the mutual covenants herein contained, it is agreed:

SECTION B. TERMS

1. GENERAL SCOPE OF WORK: CITY AGREES TO ENGAGE CONTRACTOR and CONTRACTOR agrees to furnish all necessary labor, tools, materials, appliances, and equipment for and do the work for the Ellwood Mesa Emergency Access Road Project in the City of Goleta as described in Exhibit A. The work shall be performed in accordance with the instructions of the City Engineer, or City’s Manager’s designee.
184
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 2 of 33 ends

2. COMPENSATION: CONTRACTOR agrees to receive and accept the prices set forth in its Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder (Contract Price). Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid contract documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.

3. TIME OF PERFORMANCE: CONTRACTOR agrees to complete the work within 10 working days in the timeframe specified in the Notice to Proceed Letter (Contract Time). By signing this CONTRACT, CONTRACTOR represents to CITY that the Contract Time is reasonable for completion of the work and that CONTRACTOR will complete such work within the Contract Time. In accordance with Government Code Section 53069.85, CONTRACTOR agrees to forfeit and pay CITY as liquidated damages, not as a penalty, the sum of $$750 per day for each and every day of unauthorized delay beyond the completion date, which amount shall be deducted from any payments due or to become due the CONTRACTOR.

4. PREVAILING WAGES:

A. Pursuant to Labor Code Sections §§1720 et seq., including but not limited to sections 1771, 1774 and 1775, and as specified in Title 8, California Code of Regulations, Section 16000 et seq., CONTRACTOR must pay its workers prevailing wages. It is CONTRACTOR’s responsibility to interpret and implement any prevailing wage requirements and CONTRACTOR agrees to pay any penalty or civil damages resulting from a violation of the prevailing wage laws.

B. In accordance with Labor Code Section 1773.2, copies of the prevailing rate of per diem wages are available upon request from CITY’s Engineering Division or the website for State of California Prevailing wage determination at http://www.dir.ca.gov/DLSR/PWD. CONTRACTOR must post a copy of the prevailing rate of per diem wages at the job site.

C. CITY directs CONTRACTOR’s attention to Labor Code Sections 1777.5, 1777.6 and 3098 concerning the employment of apprentices by CONTRACTOR or any subcontractor.
185
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 3 of 33 ends

D. Labor Code Section 1777.5 requires CONTRACTOR or subcontractor employing tradesmen in any apprenticeship occupation to apply to the joint apprenticeship committee nearest the site of the public works project and which administers the apprenticeship program in that trade for a certificate of approval. The certificate must also fix the ratio of apprentices to journeymen that will be used in the performance of the contract. The ratio of apprentices to journeymen in such cases will not be less than one to five except:

(1) When employment in the area of coverage by the joint appren- ticeship committee has exceeded an average of 15 percent in the 90 days before the request for certificate, or

(2) When the number of apprentices in training in the area exceeds a ratio of one to five, or
(3) When the trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally, or

(4) When assignment of an apprentice to any work performed under a public works contract would create a condition that would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large, or the specific task to which the apprentice is to be assigned is of a nature that training cannot be provided by a journeyman.

Pursuant to Labor Code § 1776, CONTRACTOR shall comply with all Department of Industrial Relations registration requirements.

E. CONTRACTOR is required to make contributions to funds established for the administration of apprenticeship programs if CONTRACTOR employs registered apprentices or journeymen in any apprentice able trade on such contracts and if other contractors on the public works site are making such contributions.

F. CONTRACTOR and any subcontractor must comply with Labor Code Sections 1777.5 and 1777.6 in the employment of apprentices.

G. Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations (DIR), ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

186
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 4 of 33 ends

H. CONTRACTOR and its subcontractors must keep an accurate certified payroll records showing the name, occupation, and the actual per diem wages paid to each worker employed in connection with this CONTRACT.

The record will be kept open at all reasonable hours to the inspection of the body awarding the contract and to the Division of Labor Law Enforcement.

If requested by CITY, CONTRACTOR must provide copies of the records at its cost.

5. LEGAL HOURS OF WORK: CONTRACTOR agrees to comply with the provisions of California Labor Code Section 1813 concerning penalties for workers who work excess hours. Except as provided by Labor Code Section 1815, the CONTRACTOR shall, as a penalty to the CITY, forfeit twenty five dollars ($25) for each worker employed in the execution of the Contract by the CONTRACTOR or by any Subcontractor for each calendar day during which such worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2, Part 7, Chapter 1, Article 3 (commencing at Section 1810) of the California Labor Code.

6. TRAVEL AND SUBSISTENCE PAY : CONTRACTOR agrees to pay travel and subsistence pay to each worker needed to execute the work required by this CONTRACT as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed in accordance with Labor Code Section 1773.8.

7. CONTRACTOR'S LIABILITY: The CITY and its officers, agents and employees (“Indemnitees”) shall not be answerable or accountable in any manner for any loss or damage that may happen to the work or any part thereof, or for any of the materials or other things used or employed in performing the work; or for injury or damage to any person or persons, either workers or employees of CONTRACTOR, of its subcontractors or the public, or for damage to adjoining or other property from any cause whatsoever arising out of or in connection with the performance of the work. CONTRACTOR shall be responsible for any damage or injury to any person or property resulting from defects or obstructions or from any cause whatsoever.

CONTRACTOR will indemnify Indemnities against and will hold and save Indemnitees harmless from any and all actions, claims, damages to persons or property, penalties, obligations or liabilities that may be asserted or claimed by any person, firm, entity, corporation, political subdivision, or other organization arising out of or in connection with the work, operation, or activities of CONTRACTOR, its agents, employees, subcontractors or invitees provided for herein, whether or not 187
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 5 of 33 ends

there is concurrent passive negligence on the part of CITY. In connection therewith:

a. CONTRACTOR will defend any action or actions filed in connection with any such claims, damages, penalties, obligations or liabilities and will pay all costs and expenses, including attorneys' fees, expert fees and costs incurred in connection therewith.

b. CONTRACTOR will promptly pay any judgment rendered against CONTRACTOR or Indemnitees covering such claims, damages, penalties, obligations and liabilities arising out of or in connection with such work, operations or activities of CONTRACTOR hereunder, and CONTRACTOR agrees to save and hold the Indemnitees harmless therefrom.

c. In the event Indemnitees are made a party to any action or proceeding filed or prosecuted against CONTRACTOR for damages or other claims arising out of or in connection with the work, operation or activities hereunder, CONTRACTOR agrees to pay to Indemnitees and any all costs and expenses incurred by Indemnitees in such action or proceeding together with reasonable attorneys' fees.

CONTRACTOR'S obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this CONTRACT, Contractor shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City.

So much of the money due to CONTRACTOR under and by virtue of the contract as shall be considered necessary by CITY may be retained by CITY until disposition has been made of such actions or claims for damages as aforesaid.

It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California.

This indemnity provision shall survive the termination of the CONTRACT and is in 188
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 6 of 33 ends

addition to any other rights or remedies which Indemnitees may have under the law.

This indemnity is effective without reference to the existence or applicability of any insurance coverage which may have been required under this CONTRACT or any additional insured endorsements which may extend to Indemnitees.

CONTRACTOR, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the Indemnitees, while acting within the scope of their duties, from all claims, losses and liabilities arising out of or incident to activities or operations performed by or on behalf of the CONTRACTOR regardless of any prior, concurrent, or subsequent passive negligence by the Indemnitees.

8. THIRD PARTY CLAIMS: In accordance with Public Contracts Code Section 9201, CITY will promptly inform CONTRACTOR regarding third-party claims against CONTRACTOR, but in no event later than ten (10) business days after CITY receives such claims. Such notification will be in writing and forwarded in accordance with the “Notice” section of this CONTRACT. CONTRACTOR agrees to indemnify, hold harmless and defend the City against any third-party claim.

9. POTENTIAL CLAIMS AND DISPUTE RESOLUTION: Refer to Exhibit C for potential claims and dispute resolution information.

10. WORKERS COMPENSATION: In accordance with California Labor Code Sections 1860 and 3700, CONTRACTOR and each of its subcontractors will be required to secure the payment of compensation to its employees. In accordance with the provisions of California Labor Code Section 1861, CONTRACTOR, by signing this contract, certifies as follows: “I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.”

11. INSURANCE: With respect to performance of work under this CONTRACT, CONTRACTOR shall maintain and shall require all of its subcontractors to maintain insurance as required in the Standard Specifications.

12. ASSIGNMENT: This CONTRACT is not assignable nor the performance of either party's duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations 189
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 7 of 33 ends

of either party without the prior written consent of the other shall be void and of no force and effect.

13.INDEPENDENT CONTRACTOR: CONTRACTOR is and shall at all times remain as to the CITY, a wholly independent contractor. Neither the CITY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR'S employees, except as herein set forth. CONTRACTOR shall not at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of CITY.

14.TAXES: CONTRACTOR is responsible for paying all retail sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes and operations incidental to or involved in this contract. CONTRACTOR is responsible for ascertaining and arranging to pay them. The prices established in the contract shall include compensation for any taxes CONTRACTOR is required to pay by laws and regulations in effect at the notice to proceed.

15. LICENSES: CONTRACTOR represents and warrants to CITY that it has all licenses, permits, qualifications, insurance, and approvals of whatsoever nature which are legally required of CONTRACTOR to practice its profession.

CONTRACTOR represents and warrants to CITY that CONTRACTOR shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this CONTRACT any licenses, permits, insurance, and approvals which are legally required of CONTRACTOR to practice its profession. CONTRACTOR shall maintain a City of Goleta business license, if required under CITY ordinance.

16. RECORDS: CONTRACTOR shall maintain accounts and records, including personnel, property, and financial records, adequate to identify and account for all costs pertaining to this CONTRACT and such other records as may be deemed necessary by CITY or any authorized representative, and will be retained for three years after the expiration of this CONTRACT. All such records shall be made available for inspection or audit by CITY at any time during regular business hours.

17. SEVERABILITY: If any portion of these contract documents are declared by a court of competent jurisdiction to be invalid or unenforceable, then such portion will be deemed modified to the extent necessary in the opinion of the court to render such portion enforceable and, as so modified, such portion and the balance of this CONTRACT will continue in full force and effect provided that it does not frustrate the mutual intent of the parties herein.
190
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 8 of 33 ends

18.WHOLE AGREEMENT: This CONTRACT supersedes any and all other agreements either oral or written, between the parties and contains all of the covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this contract acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statements or promise not contained in this contract shall not be valid or binding. Any modifications of this contract will be effective only if signed by the party to be charged.

19. AUTHORITY: CONTRACTOR affirms that the signatures, titles, and seals set forth hereinafter in execution of this CONTRACT represent all individuals, firm members, partners, joint ventures, and/or corporate officers having a principal interest herein. Each party warrants that the individuals who have signed this CONTRACT have the legal power, right, and authority to make this CONTRACT and to bind each respective party. This CONTRACT may be modified by written amendment. CITY’s City Manager may execute any such amendment on CITY’s behalf.

20. NOTICES: All notices permitted or required under this CONTRACT shall be in writing, and shall be deemed made when delivered to the applicable party’s representative as provided in this CONTRACT. Additionally, such notices may be given to the respective parties at the following addresses, or at such other addresses as the parties may provide in writing for this purpose.

Such notices shall be deemed made when personally delivered or when mailed forty-eight (48) hours after deposit in the U.S. mail, first-class postage prepaid, and addressed to the party at its applicable address. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.

CITY OF GOLETA
130 Cremona Drive, Suite B
Goleta, CA 93117
Attn: City Manager

CONTRACTOR

Hearn Construction Inc dba Bob’s Backhoe & Trucking
5775 Thornwood Drive
Goleta, CA 93117
191
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 9 of 33 ends

21.DISPUTES: Disputes arising from this contract will be determined in accordance with the contract documents.

22. NON-DISCRIMINATION: The CITY reaffirms its ongoing commitment to equality in the conduct of City business, and prohibits any policy, plan, program, custom or practice, including harassment, in the conduct of City business. No discrimination or discriminatory practice shall occur in either employment of persons for, or completion of, the work contemplated by this CONTRACT, when such discrimination is based on race, color, national origin, or ancestry; religion; sex; gender, gender identity, gender expression, or gender transitioning status; physical disability, mental disability, medical condition, or genetic information; marital or domestic partner status; citizenship status; age; sexual orientation; exercising a legally protected right to an employment leave of absence; status as a victim of domestic violence, sexual assault, or stalking; reproductive health decision-making, or any other classification protected under state or federal law.

Among other possible violations of law, a violation of this section exposes CONTRACTOR to the penalties provided for in Labor Code Section 1735.

23. PAPER PRODUCTS AND PRINTING REQUIREMENTS: To the extent this contract provides paper products, and printing and writing paper for the City, CONTRACTOR must meet quality standards and criteria specified in SB 1383, Sections 22150-22154 of the Public Contract Code and 16 Code of Federal by:
a. If fitness and quality are equal, provide recycled products, instead of nonrecycled products whenever recycled products are available at the same or a lesser total cost than nonrecycled items.
b. Provide paper products and printing and writing paper that meet Federal Trade Commission recyclability standard as defined in 16 CFR

c. Certify in writing, under penalty of perjury, the minimum percentage of postconsumer material in the paper products and printing and writing paper offered or sold to the City. This certification requirement may be waived if the percentage of postconsumer material in the paper products, printing and writing paper, or both can be verified by a product label, catalog, invoice, or a manufacturer or vendor internet website. d. Certify in writing, on invoices or receipts provided, that the paper products and printing and writing paper offered or sold to the City is eligible to be labeled with an unqualified recyclable label as defined in

192
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 10 of 33 ends

e. Comply with any other requirements in Goleta Municipal Code Section

8.10.900(B).

24. ORGANIC WASTE USE REQUIREMENTS: To the extent this contract provides landscaping maintenance, renovation, and construction services, CONTRACTOR must:
a. Use compost and SB 1383 eligible mulch, as practicable, produced from recovered organic waste, for all landscaping renovations, construction, or maintenance performed for the City, whenever available, and capable of meeting quality standards and criteria specified. SB 1383 eligible mulch used for land application must comply with 14 CCR Section 18993.1 - 18993.4, and must meet or exceed the physical contamination, maximum metal concentration and pathogen density standards specified in 14 CCR Sections 17852(a)(24.5)(A)(1) through (3).
b. Keep and provide records of procurement of recovered organic waste products (either through purchase or acquisition) to the City’s Designated Representative, upon completion of projects. Information to be provided must include:
i. General description of how and where the product was used and if applicable, applied;
ii. Source of product, including name, physical location, and contact information for each entity, operation, or facility from whom the recovered organic waste products were procured; iii. Type of product;
iv. Quantity of each product; and,
v. Invoice or other record demonstrating purchase or
procurement.
c. Comply with all requirements in Goleta Municipal Code Section

8.10.900(A).

25. NO THIRD PARTY BENEFICIARY: This CONTRACT and every provision herein is for the exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of the CONTRACTOR’s or the CITY’s obligations under this Contract.

26. TIME IS OF ESSENCE:Time is of the essence for each and every provision of the Contract Documents.
193
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 11 of 33 ends

27.ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES: The Parties agree that this CONTRACT, agreements ancillary to this CONTRACT, and related documents to be entered into in connection with this CONTRACT will be considered signed when the signature of a party is delivered by facsimile transmission or scanned and delivered via electronic mail. Such facsimile or electronic mail copies will be treated in all respects as having the same effect as an original signature.

28.GOVERNING LAW: This CONTRACT shall be governed by the laws of the State of California, and exclusive venue for any action involving this CONTRACT will be in Santa Barbara County.

29. FEDERAL REQUIREMENTS
FEMA financial assistance will be used to fund all or a portion of this contract.

The Contractor shall comply with all federal requirements including, but not limited to, the following:

1. 2 C.F.R. Part 200 – Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.

2. Federal Contract Provisions attached hereto as Exhibit B and incorporated herein by reference.

Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, 2 C.F.R. Part 200 and the Federal Contract Provisions.

With respect to any conflict between such federal requirements and the terms of this contract and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.

IN WITNESS WHEREOF, the parties hereto have executed this CONTRACT with all the formalities required by law on the respective dates set forth opposite their signatures.

This CONTRACT is executed on this ________ day of ___________ , at Goleta, California, and effective as of _____ ______, 20____.

CITY OF GOLETA:

194
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 12 of 33 ends

___________________________________
Robert Nisbet, City Manager
ATTEST:
___________________________________
Deborah Lopez, City Clerk

APPROVED AS TO FORM:

MEGAN GARIBALDI, CITY ATTORNEY

___________________________________
Scott Shapses, Deputy City Attorney

CONTRACTOR:

_____________________________________
Toni Hearn, President
State of California License No.
2553457______________________________
Department of Industrial Relations Registration
No.
1000017993___________________________
Business Phone No.
_____(805) 967-5849____________________
CONTRACTOR’S Emergency Phone No. at
which contractor can be reached at any time
_____________________________________
_____________________________________
195
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 13 of 33 ends

____________________________________
Mike Hearn, Owner

196
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 14 of 33 ends

EXHIBIT A

PROPOSAL

Repairs include but are not limited to:

197
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 15 of 33 ends

198
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 16 of 33 ends

EXHIBIT B

FEDERAL CONTRACT PROVISIONS
During the performance of this contract, Hearn Construction Inc dba Bob’s Backhoe & Trucking. (the “Contractor”) shall comply with all applicable federal laws and regulations including but not limited to the federal contract provisions in this Exhibit. In this Exhibit, the term “Agency” shall mean the local agency entering into this contract with the Contractor.

1. CONTRACTING WITH SMALL AND MINORITY FIRMS, WOMEN’S BUSINESS ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2 C.F.R. § 200.321)

A. Contractor shall be subject to 2 C.F.R. § 200.321 and will take affirmative steps to assure that minority firms, women’s business enterprises, and labor surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.

B. Affirmative steps shall include:

i. Placing qualified small and minority businesses and women's business enterprises on solicitation lists;
ii. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are potential sources; iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business enterprises;
iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and
v. Using the services/assistance of the Small Business Administration (SBA), and the Minority Business Development Agency (MBDA) of the Department of Commerce.

Contractor shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.

Notwithstanding the foregoing, the affirmative steps requirements detailed above do not apply in the case of a noncompetitive procurement made under the emergency exception/exigency exception to competitive procurements.

2. COST PRINCIPLES (2 C.F.R. PART 200, SUBPART E)

199
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 17 of 33 ends

A. If any indirect costs will be charged to the Agency under this contract, such costs must conform to the cost principles set forth under the Uniform Rules at 2 C.F.R. Part 200, subpart E (“Cost Principles”). In general, costs must (i) be necessary and reasonable; (ii) allocable to the grant award; (iii) conform to any limitations or exclusions set forth in the Cost Principles; (iv) be adequately documented; and (v) be determined in accordance with generally accepted accounting principles (“GAAP”), except, for state and local governments and Indian tribes only, as otherwise provided for in 2 C.F.R. Part 200, subpart E. 2 C.F.R. § 200.403. Costs that are determined unallowable pursuant to a federal audit are subject to repayment by Contractor.

3. ACCESS TO RECORDS & RECORD RETENTION (2 C.F.R. 200.336)

A. Contractor shall comply with 2 C.F.R. § 200.336 and provide the Federal Agency, Inspectors General, the Comptroller General of the United States, Agency, and the State of California or any of their authorized representatives access, during normal business hours, to documents, papers, books and records which are directly pertinent to this contract for the purposes of making and responding to audits, examinations, excerpts, and transcriptions. The right also includes timely and reasonable access to the Contractor personnel for the purpose of interview and discussion related to the books and records.

B. The Contractor agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

C. The Contractor agrees to provide the Federal Agency or its authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

4. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH APPENDIX II TO PART 200 – CONTRACT PROVISIONS FOR NON-FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS (2 C.F.R. § 200.326)

A. Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract is in excess of $10,000 and the contract does not include provisions for both termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract is for more than the simplified acquisition threshold (see 2 C.F.R. § 200.88) at the time the 200
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 18 of 33 ends

contract is executed and does not provide for administrative, contractual, or legal remedies in instances where Contractor violates or breaches the terms of the contract, then the following termination clauses shall apply and have precedence over the contract. Otherwise, the following termination clauses shall not be applicable to the contract.

i. Termination for Convenience. The Agency may, by written notice to Contractor, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Contractor of such termination, and specifying the effective date thereof (“Notice of Termination for Convenience”). If the termination is for the convenience of the Agency, the Agency shall compensate Provider for work or materials fully and adequately provided through the effective date of termination. No amount shall be paid for unperformed work or materials not provided, including anticipated profit. Contractor shall provide documentation deemed adequate by the Agency to show the work actually completed or materials provided by Contractor prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination.
ii. Termination for Cause. If Contractor fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to Contractor specifying the default (“Notice of Default”). If Contractor does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause.

If Contractor fails to cure a default as set forth above, the Agency may, by written notice to Contractor , terminate this contract for cause, in whole or in part, and specifying the effective date thereof (“Notice of Termination for Cause”). If the termination is for cause, Contractor shall be compensated for that portion of the work or materials provided which has been fully and adequately completed and accepted by the Agency as of the date the Agency provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems necessary to complete the project and correct Contractor’s deficiencies and charge the cost thereof to Contractor, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.
iii. Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work 201
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 19 of 33 ends

rendered or materials provided and shall be entitled to withhold compensation for defective work or other damages caused by Contractor performance of the work.
iv. Additional Termination Provisions. Upon receipt of a Notice of Termination, either for cause or for convenience, Contractor shall promptly discontinue the work unless the Notice directs to the contrary. Contractor shall deliver to the Agency and transfer title (if necessary) to all provided materials and completed work, and work in progress including drafts, documents, plans, forms, maps, products, graphics, computer programs and reports. The rights and remedies of the parties provided in this Section are in addition to any other rights and remedies provided by law or under this contract.

Contractor acknowledges the Agency’s right to terminate this contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the Agency’s termination of this contract. The Agency shall not be liable for any costs other than the charges or portions thereof which are specified herein. Contractor shall not be entitled to payment for unperformed work or materials not provided and shall not be entitled to damages or compensation for termination of work or supply of materials. If Agency terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a termination for convenience. In such event, Contractor shall be entitled to receive only the amounts payable under this Section, and Contractor specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance.

B. Appendix II to Part 200 (C) – Equal Employment Opportunity: Except as otherwise provided under 41 C.F.R. Part 60, Contractor shall comply with the following equal opportunity clause, in accordance with Executive Order 11246 of September 24, 1965 entitled “Equal Employment Opportunity,” as amended by Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:
202
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 20 of 33 ends

i. Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin.

Contractor will take affirmative action to insure that applicants are employed and that employees are treated equally during
employment, without regard to race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following:
employment upgrading, demotion, transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training including apprenticeship. Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the Agency setting forth the provisions of this nondiscrimination clause.

ii. Contractor will, in all solicitations or advertisements for employees placed by or on behalf of Contractor, state that all qualified applicants will receive consideration for employment without regard to their race, color, religion, sex, or national origin.

iii. Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with Contractor‘s legal duty to furnish information.
iv. Contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
203
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 21 of 33 ends

v. Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
vi. Contractor will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
vii. In the event of Contractor’s noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order No.11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order No.11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.

viii. Contractor will include the provisions of paragraphs (i) through (viii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of September 24,1965, so that such provisions will be binding upon each subcontractor or Contractor. Contractor will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, that in the event Contractor becomes involved in, or is threatened with, litigation with a subcontractor or Contractor as a result of such direction, Contractor may request the United States to enter into such litigation to protect the interests of the United States.

C. Appendix II to Part 200 (D) – Davis-Bacon Act; Copeland Act: Not applicable to this contract.

D. Appendix II to Part 200 (E) – Contract Work Hours and Safety Standards Act:
204
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 22 of 33 ends

i. If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Contractor shall comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor
regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

ii. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.

iii. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section.

205
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 23 of 33 ends

iv. The Agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.
v. The Contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (ii) through (v) of this Section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The Contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.

E. Appendix II to Part 200 (F) – Rights to Inventions Made Under a Contract or Agreement:

i. If the Federal award meets the definition of “funding agreement” under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the non-Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements), and any implementing regulations issued by the Agency.

ii. The regulation at 37 C.F.R. § 401.2(a) currently defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or research work funded in whole or in part by the Federal government. This term also includes any assignment, substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or 206
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 24 of 33 ends

research work under a funding agreement as defined in the first sentence of this paragraph.

iii. This requirement does not apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management Assistance Grant Program, Crisis Counseling Assistance and Training Grant Program, Disaster Case Management Grant Program, and Federal Assistance to Individuals and Households – Other Needs Assistance Grant Program, as FEMA awards under these programs do not meet the definition of “funding agreement.”

F. Appendix II to Part 200 (G) – Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Contractor shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387).
i. Pursuant to the Clean Air Act, (1) Contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Contractor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Contractor agrees to include these requirements in each subcontract exceeding $150,000.
ii. Pursuant to the Federal Water Pollution Control Act, (1) Contractor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Contractor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Contractor agrees to include these requirements in each subcontract exceeding $150,000.

G. Appendix II to Part 200 (H) – Debarment and Suspension: A contract award (see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement 207
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 25 of 33 ends

Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 C.F.R. part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. i. This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Contractor is required to verify that none of the Contractor, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935).
ii. Contractor must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into. iii. This certification is a material representation of fact relied upon by Agency. If it is later determined that Contractor did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment.
iv. Contractor warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs.

Contractor also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from participation in accordance with the requirements above. Contractor further agrees to notify the Agency in writing immediately if Contractor or its subcontractors are not in compliance during the term of this contract.

H. Appendix II to Part 200 (I) – Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Contractor shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Contractor shall file with the Agency the Federal Standard Form LLL titled “Disclosure Form to Report Lobbying.” Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of 208
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 26 of 33 ends

Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.

I. Appendix II to Part 200 (J) – Procurement of Recovered Materials:
i. Contractor shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement.

ii. In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired:

Competitively within a timeframe providing for compliance with the contract performance schedule; Meeting contract performance requirements; or At a reasonable price.
iii. Information about this requirement, along with the list of EPA- designate items, is available at EPA’s Comprehensive Procurement Guidelines web site, https://www.epa.gov/smm/comprehensive- procurement-guideline-cpg-program.

5. MISCELLANEOUS PROVISIONS

A. The Contractor shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA preapproval.

B. This is an acknowledgement that FEMA financial assistance will be used to fund the contract only. The Contractor will comply with all applicable federal 209
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 27 of 33 ends

law, regulations, executive orders, FEMA policies, procedures, and directives.

C. Contractor acknowledges that 31 U.S.C. Chapter 38 (Administrative Remedies for False Claims and Statements) applies to the Contractor’s actions pertaining to this contract.

D. The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the Agency, Contractor, any subcontractors or any other party pertaining to any matter resulting from the contract.

E. General and Administrative Expenses And Profit For Time And Materials Contracts/Amendments.
i. General and administrative expenses shall be negotiated and must conform to the Cost Principles.
ii. Profit shall be negotiated as a separate element of the cost. To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the Contractor , the Contractor’s investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.

iii. Any agreement, amendment or change order for work performed on a time and materials basis shall include a ceiling price that Contractor exceeds at its own risk.
210
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 28 of 33 ends

EXHIBIT C

DISPUTE RESOLUTION
Section 10 – Potential Claims and Dispute Resolution
Section 10-1 Potential Claim
Any demand or assertion by the Contractor seeking an adjustment of Contract Price and/or Contract Time, or other relief, for any reason whatsoever, must be in strict compliance with the requirements of the Contract Documents. For purposes of this Section 10-1, any and all work relating to any such demand or assertion shall be referred to as “Disputed Work,” regardless of whether the basis of the demand or assertion arises from an interpretation of the Contract Documents, an action or inaction of the Contractor, the Engineer, or the City, or any other event, issue, or circumstance. The Contractor shall bear all costs incurred in complying with the provisions of this Section 10-1.

Promptly upon becoming aware of any event, issue, or circumstance including, but not limited to, disputes arising under the Contract, the acts or omissions of the Engineer or City or by operation of law, which the Contractor believes, in whole or in part, provides a basis for an adjustment of Contract Price and/or Contract Time. Or that Contractor’s performance is excused, or other relief, Contractor shall provide a signed written Initial Notice of Potential Claim to the Engineer in a format acceptable to the City. Contractor shall provide a signed written initial notice of potential claim to the Engineer within 5 days from the date the dispute first arose and before commencing any disputed work. The initial notice of potential claim shall provide the nature and circumstances involved in the dispute which shall remain consistent through the dispute. The initial notice of potential claim shall be submitted on Form CEM 6201A available on Caltrans’ website and shall be certified with reference to the California False Claims Act, Government Code Sections 12650 12655. Assign an exclusive identification number for each dispute, determined by chronological sequencing, based on the date of the dispute.

The exclusive identification number for each dispute shall be used on the following corresponding documents:

1. Initial notice of potential claim.

2. Supplemental notice of potential claim.

3. Full and final documentation of potential claim.

4. Corresponding claim included in the Contractor's written statement of claims.

Provide the Engineer the opportunity to examine the site of work within 5 days from the date of the initial notice of potential claim. Proceed with the performance of contract work unless otherwise specified or directed by the Engineer.

Throughout the disputed work, maintain records that provide a clear distinction between the incurred direct costs of disputed work and that of undisputed work. Allow the Engineer 211
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 29 of 33 ends

access to your project records deemed necessary by the Engineer to evaluate the potential claim within 20 days of the date of the Engineer's written request.

Within 15 days of submitting the initial notice of potential claim, submit a signed supplemental notice of potential claim to the Engineer that provides the following information:

1. The complete nature and circumstances of the dispute which caused the potential claim.

2. The contract provisions that provide the basis of claim.

3. The estimated cost of the potential claim, including an itemized breakdown of individual costs and how the estimate was determined.

4. A time impact analysis of the project schedule that illustrates the effect on the scheduled completion date due to schedule changes or disruptions where a request for adjustment of Contract Time is made.

Include your complete reasoning for additional compensation or adjustments.

Submit the supplemental notice of potential claim on Form CEM 6201B furnished by the Department and certify with reference to the California False Claims Act, Government Code Sections 12650 12655. The Engineer will evaluate the information presented in the supplemental notice of potential claim and provide a written response within 20 days of receipt. If the estimated cost or effect on the scheduled completion date changes, update information in items 3 and 4 above as soon as the change is recognized and submit this information to the Engineer.

Within 30 days of the completion of work related to the potential claim, submit the full and final documentation of potential claim to the Engineer that provides the following information:

(1.) A detailed factual narration of events fully describing the nature and circumstances that caused the dispute, including, but not limited to, necessary dates, locations, and items of work affected by the dispute.
(2.) The specific provisions of the contract that support the potential claim and a statement of the reasons these provisions support and provide a basis for entitlement of the potential claim.
(3.) When additional monetary compensation is requested, the exact amount requested calculated in conformance with the Contract Documents including an itemized breakdown of individual costs. These costs shall be segregated into the following cost categories:

3.1. Labor – A listing of individuals, classifications, regular hours and overtime hours worked, dates worked, and other pertinent information related to the requested reimbursement of labor costs.

3.2. Materials – Invoices, purchase orders, location of materials either stored or incorporated into the work, dates materials were transported to the project or incorporated into the work, and other pertinent information related to the requested reimbursement of material costs.
212
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 30 of 33 ends

3.3. Equipment – Listing of detailed description (make, model, and serial number), hours of use, dates of use, and equipment rates. Equipment rates shall be at the applicable State rental rate as listed in the Department of Transportation publication entitled "Labor Surcharge and Equipment Rental Rates," in effect when the affected work related to the dispute was performed.

3.4. Other categories as specified by the Contractor or the Engineer. (4.) When an adjustment of Contract Time is requested, include the following:

4.1.The specific dates for which contract time is being requested.

4.2.The specific reasons for entitlement to a Contract Time adjustment.

4.3. The specific provisions of the contract that provide the basis for the requested Contract Time adjustment.

4.4. A detailed time impact analysis of the project schedule. The time impact analysis shall show the effect of changes or disruptions on the scheduled completion date to demonstrate entitlement to a Contract Time adjustment.

(5.) The identification and copies of documents and the substance of oral communications that support the potential claim.

The full and final documentation of the potential claim shall be submitted on Form CEM 6201C furnished by the Department and shall be certified with reference to the California False Claims Act, Government Code Sections 12650 12655.

Pertinent information, references, arguments, and data to support the potential claim shall be included in the full and final documentation of potential claim. Information submitted subsequent to the full and final documentation submittal will not be considered.

Information required in the full and final documentation of potential claim, as listed in items 1 to 5 above, that is not applicable to the dispute may be exempted as determined by the Engineer. No full and final documentation of potential claim will be considered that does not have the same nature and circumstances, and basis of claim as those specified on the initial and supplemental notices of potential claim.

If you, in conjunction with or subsequent to the assertion of a potential claim, request inspection and copying of documents or records in the possession of the City that pertain to the potential claim, you must make your records of the project, as deemed by the City to be pertinent to the potential claim, available to the City for inspection and copying."

Unless otherwise specified, the Engineer will evaluate the information presented in the full and final documentation of potential claim and provide a written response within 30 days of receipt. The Engineer's receipt of the full and final documentation of potential claim shall be evidenced by postal receipt or the Engineer's written receipt if delivered by hand. If you submit full and final documentation of potential claim after acceptance of the work by the City, the Engineer need not provide a written response.

Section 10-2 Dispute Resolution
All disputes and claims arising under or by virtue of this contract shall be directed to and be determined by the Public Works Director. The Director’s determination can be 213
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 31 of 33 ends

appealed to City Manager or their designee. The determination by the City Manager or their designee of disputes and claims shall constitute the decision of the City of Goleta; provided, however, that Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3 of Division 2 of the Public Contract Code shall apply to the public works claim of $375,000 or less.

Section 10-3 Dispute Resolution - Claims exceeding $375,000 Any claim, dispute, or other matter in question arising out of or related to the Contract or Project exceeding three-hundred seventy-five thousand dollars ($375,000.00) that cannot be resolved between the City and the Contractor shall be resolved by the Santa Barbara County Superior Court.

Section 10-4 Claims Procedures as a Prerequisite to Filing Suit Contractor acknowledges and agrees that its failure to submit any notice of potential claim or claim arising under this Contract in accordance with Section 10, shall constitute a waiver of Contractor’s right to additional compensation and/or extension of time. Failure to follow the provisions set forth in this Contract shall constitute a waiver of Contractor’s right to receive any additional time or money as a result of any event giving rise to a claim or request for change order. Notwithstanding any other provisions in the Contract relating to any additional time or money which Contractor may be entitled to upon the occurrence of any directive or other event, or any other circumstance, Contractor must comply with the provisions of Section 10 to avoid a waiver of any such entitlement to any additional time or money. Contractor’s failure, neglect, or refusal to comply with the requirements of Section 10, or any portion thereof, shall bar Contractor’s request for additional compensation or adjustments to Contract Time. Such failure, neglect, or refusal prejudices the City’s and the Engineer’s ability to recognize and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for adjustment of Contract Time, and whether such adjustments may be warranted. Contractor hereby waives all rights to additional compensation or adjustments of Contract Time due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of Section 10.

Section 10-5 Government Code Claims.

Notwithstanding Contractor’s participation in dispute resolution proceedings or other claims procedures under the Contract, such proceedings are in addition to Contractor’s obligation to present a written Government Code claim in accordance with Section 900 et al of the California Government Code, which is a prerequisite to filing a lawsuit for money or damages against the City. Contractor further acknowledges that notwithstanding Contractor’s compliance with the claims procedures set forth in Section 10or in the Contract Documents, such procedures are in addition to Contractor’s obligation to comply with the claims procedures set forth in Government Code sections 900 et al prior to filing a lawsuit against the City for any such claim. Failure to submit a Government Code claim, or comply with the claims provision contained in Section 10 or in the City Special Provisions, shall bar Contractor from bringing and maintaining a valid lawsuit against the City.

Section 10-6 Participation in Dispute Resolution Proceedings. 214
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 32 of 33 ends

Contractor and the City agree that all parties necessary to resolve a claim or dispute should be parties to the same dispute resolution proceeding. Contractor agrees upon request of the City to be joined in any mediation or arbitration when Contractor’s presence is required if complete relief is to be accorded and to prevent the possibility of conflicting rulings on a common issue of law or fact and otherwise to prevent the risk of the parties being subjected to inconsistent obligations or decisions.

Section 10-7 Contractor’s Continuing Obligations.

At all times during the processing of the Contractor’s potential Claim, including, but not limited to, in response to a work directive issued by the Engineer, the Contractor shall diligently proceed with the performance of the Disputed Work and other Work, unless otherwise specified or directed by the Engineer.

The Contractor shall provide the Engineer the opportunity to examine the site of the Disputed Work as soon as reasonably possible, and in no event later than five (5) days from the date of the Initial Notice of Potential Claim. Throughout the processing of the Contractor’s potential Claim, the Contractor shall provide the Engineer a reasonable opportunity to examine the site of the Disputed Work within five (5) days of the date of Engineer’s written request therefor.

The Contractor shall promptly respond to any requests for further information or documentation regarding the Contractor’s potential Claim.

Although not to be construed as proceeding with force account work, throughout the performance of the Disputed Work, the Contractor shall maintain daily records in accordance with the Contact Documents that provide a clear distinction between the incurred direct costs of Disputed Work and other Work. The Contractor shall allow the Engineer access to its project records deemed necessary by the Engineer to evaluate the potential Claim within fifteen (15) days of the date of the Engineer's written request.

All Subcontractor’s and material supplier’s claims of any type shall be brought only through Contractor pursuant to the provisions of this Section 10 and Contractor’s prior good faith review pursuant to the Contract Documents. Under no circumstances shall any Subcontractor or material supplier make any direct claim against City.

Except where provided by law, or elsewhere in these Contract Documents, THE CITY

SHALL NOT BE LIABLE FOR SPECIAL OR CONSEQUENTIAL DAMAGES AND THE CONTRACTOR SHALL NOT INCLUDE THEM IN ITS CLAIMS. Contractor shall be limited in its recovery on any Claim(s) to the adjustments allowed in the Contract Documents.

During each step in the processing of the Contractor’s Claim, each notice shall be accompanied by the Contractor’s written statement that the adjustment or relief claimed is the entire adjustment or relief to which the claimant believes it is entitled as a result of the event, issue, or circumstance giving rise to the Claim.

Under no circumstances may the Contractor submit an Initial Notice of Potential Claim, Supplemental Notice of Potential Claim, or Notice of Final Claim after the date of final payment.

Section 10-8 Notice of Third-Party Claims.
215
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 33 of 33 ends

The City shall provide Contractor with prompt written notice of the receipt of any third- party claim relating to the Contract in accordance with Public Contract Code section 9201 by sending a copy of the third-party claim to Contractor at the address indicated in the Agreement via first class.
216
ATTACHMENT 7

Public Works Contract with Bob’s Backhoe San Pedro
217

PUBLIC WORKS CONTRACT

BETWEEN THE CITY OF GOLETA
AND
HEARN CONSTRUCTION INC. DBA BOB’S BACKHOE & TRUCKING
This Public Works Contract (herein referred to as “CONTRACT”) is made and entered into by and between the CITY OF GOLETA, a municipal corporation (herein referred to as "CITY"), and HEARN CONSTRUCTION INC. dba BOB’S BACKHOE & TRUCKING (hereinafter referred to as “CONTRACTOR”).

SECTION A. RECITALS

1. The CITY has a need for emergency repairs to public property, trees, parks, and other infrastructure caused by severe storms in 2024; and

2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for construction services to accomplish this work; and

3. Goleta Municipal Code Section 2.10.040(A)(6)(a) allows the City Manager (referenced as “Director of Emergency Services”) to “make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency; provided however, such rules and regulations must be confirmed at the earliest practicable time by the City Council”; and

4. An emergency exists in the CITY due to the severe storms of 2024 which caused significant damage to roadways and CITY infrastructure. Therefore, it is necessary to the public health and safety that the City Manager immediately authorize the start of work on emergency mitigation measures, subject to ratification by City Council; and

5. The City Manager authorized this agreement pursuant to Goleta Municipal Code Section 2.10.040(A)(6)(a) and the City Council ratified this agreement at its next public meeting.

NOW, THEREFORE , in consideration of the foregoing and the mutual covenants herein contained, it is agreed:

SECTION B. TERMS

1. GENERAL SCOPE OF WORK: CITY AGREES TO ENGAGE CONTRACTOR and CONTRACTOR agrees to furnish all necessary labor, tools, materials, appliances, and equipment for and do the work for the San Pedro Creek and Westmoreland Place Project in the City of Goleta as described in Exhibit A. The work shall be performed in accordance with the instructions of the City Engineer, or City’s Manager’s designee.

218
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 2 of 34 ends

2. COMPENSATION: CONTRACTOR agrees to receive and accept the prices set forth in its Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder (Contract Price). Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid contract documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.

3. TIME OF PERFORMANCE: CONTRACTOR agrees to complete the work within 10 working days in the timeframe specified in the Notice to Proceed Letter (Contract Time). By signing this CONTRACT, CONTRACTOR represents to CITY that the Contract Time is reasonable for completion of the work and that CONTRACTOR will complete such work within the Contract Time. In accordance with Government Code Section 53069.85, CONTRACTOR agrees to forfeit and pay CITY as liquidated damages, not as a penalty, the sum of $750 per day for each and every day of unauthorized delay beyond the completion date, which amount shall be deducted from any payments due or to become due the CONTRACTOR.

4. PREVAILING WAGES:

A. Pursuant to Labor Code Sections §§1720 et seq., including but not limited to sections 1771, 1774 and 1775, and as specified in Title 8, California Code of Regulations, Section 16000 et seq., CONTRACTOR must pay its workers prevailing wages. It is CONTRACTOR’s responsibility to interpret and implement any prevailing wage requirements and CONTRACTOR agrees to pay any penalty or civil damages resulting from a violation of the prevailing wage laws.

B. In accordance with Labor Code Section 1773.2, copies of the prevailing rate of per diem wages are available upon request from CITY’s Engineering Division or the website for State of California Prevailing wage determination at http://www.dir.ca.gov/DLSR/PWD. CONTRACTOR must post a copy of the prevailing rate of per diem wages at the job site.

C. CITY directs CONTRACTOR’s attention to Labor Code Sections 1777.5, 1777.6 and 3098 concerning the employment of apprentices by CONTRACTOR or any subcontractor.
219
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 3 of 34 ends

D. Labor Code Section 1777.5 requires CONTRACTOR or subcontractor employing tradesmen in any apprenticeship occupation to apply to the joint apprenticeship committee nearest the site of the public works project and which administers the apprenticeship program in that trade for a certificate of approval. The certificate must also fix the ratio of apprentices to journeymen that will be used in the performance of the contract. The ratio of apprentices to journeymen in such cases will not be less than one to five except:

(1) When employment in the area of coverage by the joint appren- ticeship committee has exceeded an average of 15 percent in the 90 days before the request for certificate, or

(2) When the number of apprentices in training in the area exceeds a ratio of one to five, or
(3) When the trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally, or

(4) When assignment of an apprentice to any work performed under a public works contract would create a condition that would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large, or the specific task to which the apprentice is to be assigned is of a nature that training cannot be provided by a journeyman.

Pursuant to Labor Code § 1776, CONTRACTOR shall comply with all Department of Industrial Relations registration requirements.

E. CONTRACTOR is required to make contributions to funds established for the administration of apprenticeship programs if CONTRACTOR employs registered apprentices or journeymen in any apprentice able trade on such contracts and if other contractors on the public works site are making such contributions.

F. CONTRACTOR and any subcontractor must comply with Labor Code Sections 1777.5 and 1777.6 in the employment of apprentices.

G. Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations (DIR), ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
220
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 4 of 34 ends

H. CONTRACTOR and its subcontractors must keep an accurate certified payroll records showing the name, occupation, and the actual per diem wages paid to each worker employed in connection with this CONTRACT.

The record will be kept open at all reasonable hours to the inspection of the body awarding the contract and to the Division of Labor Law Enforcement.

If requested by CITY, CONTRACTOR must provide copies of the records at its cost.

5. LEGAL HOURS OF WORK: CONTRACTOR agrees to comply with the provisions of California Labor Code Section 1813 concerning penalties for workers who work excess hours. Except as provided by Labor Code Section 1815, the CONTRACTOR shall, as a penalty to the CITY, forfeit twenty five dollars ($25) for each worker employed in the execution of the Contract by the CONTRACTOR or by any Subcontractor for each calendar day during which such worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2, Part 7, Chapter 1, Article 3 (commencing at Section 1810) of the California Labor Code.

6. TRAVEL AND SUBSISTENCE PAY : CONTRACTOR agrees to pay travel and subsistence pay to each worker needed to execute the work required by this CONTRACT as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed in accordance with Labor Code Section 1773.8.

7. CONTRACTOR'S LIABILITY: The CITY and its officers, agents and employees (“Indemnitees”) shall not be answerable or accountable in any manner for any loss or damage that may happen to the work or any part thereof, or for any of the materials or other things used or employed in performing the work; or for injury or damage to any person or persons, either workers or employees of CONTRACTOR, of its subcontractors or the public, or for damage to adjoining or other property from any cause whatsoever arising out of or in connection with the performance of the work. CONTRACTOR shall be responsible for any damage or injury to any person or property resulting from defects or obstructions or from any cause whatsoever.

CONTRACTOR will indemnify Indemnities against and will hold and save Indemnitees harmless from any and all actions, claims, damages to persons or property, penalties, obligations or liabilities that may be asserted or claimed by any person, firm, entity, corporation, political subdivision, or other organization arising out of or in connection with the work, operation, or activities of CONTRACTOR, its agents, employees, subcontractors or invitees provided for herein, whether or not 221
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 5 of 34 ends

there is concurrent passive negligence on the part of CITY. In connection therewith:

a. CONTRACTOR will defend any action or actions filed in connection with any such claims, damages, penalties, obligations or liabilities and will pay all costs and expenses, including attorneys' fees, expert fees and costs incurred in connection therewith.

b. CONTRACTOR will promptly pay any judgment rendered against CONTRACTOR or Indemnitees covering such claims, damages, penalties, obligations and liabilities arising out of or in connection with such work, operations or activities of CONTRACTOR hereunder, and CONTRACTOR agrees to save and hold the Indemnitees harmless therefrom.

c. In the event Indemnitees are made a party to any action or proceeding filed or prosecuted against CONTRACTOR for damages or other claims arising out of or in connection with the work, operation or activities hereunder, CONTRACTOR agrees to pay to Indemnitees and any all costs and expenses incurred by Indemnitees in such action or proceeding together with reasonable attorneys' fees.

CONTRACTOR'S obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this CONTRACT, Contractor shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City.

So much of the money due to CONTRACTOR under and by virtue of the contract as shall be considered necessary by CITY may be retained by CITY until disposition has been made of such actions or claims for damages as aforesaid.

It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California.

This indemnity provision shall survive the termination of the CONTRACT and is in 222
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 6 of 34 ends

addition to any other rights or remedies which Indemnitees may have under the law.

This indemnity is effective without reference to the existence or applicability of any insurance coverage which may have been required under this CONTRACT or any additional insured endorsements which may extend to Indemnitees.

CONTRACTOR, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the Indemnitees, while acting within the scope of their duties, from all claims, losses and liabilities arising out of or incident to activities or operations performed by or on behalf of the CONTRACTOR regardless of any prior, concurrent, or subsequent passive negligence by the Indemnitees.

8. THIRD PARTY CLAIMS: In accordance with Public Contracts Code Section 9201, CITY will promptly inform CONTRACTOR regarding third-party claims against CONTRACTOR, but in no event later than ten (10) business days after CITY receives such claims. Such notification will be in writing and forwarded in accordance with the “Notice” section of this CONTRACT. CONTRACTOR agrees to indemnify, hold harmless and defend the City against any third-party claim.

9. POTENTIAL CLAIMS AND DISPUTE RESOLUTION: Refer to Exhibit C for potential claims and dispute resolution information.

10. WORKERS COMPENSATION: In accordance with California Labor Code Sections 1860 and 3700, CONTRACTOR and each of its subcontractors will be required to secure the payment of compensation to its employees. In accordance with the provisions of California Labor Code Section 1861, CONTRACTOR, by signing this contract, certifies as follows: “I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.”

11. INSURANCE: With respect to performance of work under this CONTRACT, CONTRACTOR shall maintain and shall require all of its subcontractors to maintain insurance as required in the Standard Specifications.

12. ASSIGNMENT: This CONTRACT is not assignable nor the performance of either party's duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations 223
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 7 of 34 ends

of either party without the prior written consent of the other shall be void and of no force and effect.

13.INDEPENDENT CONTRACTOR: CONTRACTOR is and shall at all times remain as to the CITY, a wholly independent contractor. Neither the CITY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR'S employees, except as herein set forth. CONTRACTOR shall not at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of CITY.

14.TAXES: CONTRACTOR is responsible for paying all retail sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes and operations incidental to or involved in this contract. CONTRACTOR is responsible for ascertaining and arranging to pay them. The prices established in the contract shall include compensation for any taxes CONTRACTOR is required to pay by laws and regulations in effect at the notice to proceed.

15. LICENSES: CONTRACTOR represents and warrants to CITY that it has all licenses, permits, qualifications, insurance, and approvals of whatsoever nature which are legally required of CONTRACTOR to practice its profession.

CONTRACTOR represents and warrants to CITY that CONTRACTOR shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this CONTRACT any licenses, permits, insurance, and approvals which are legally required of CONTRACTOR to practice its profession. CONTRACTOR shall maintain a City of Goleta business license, if required under CITY ordinance.

16. RECORDS: CONTRACTOR shall maintain accounts and records, including personnel, property, and financial records, adequate to identify and account for all costs pertaining to this CONTRACT and such other records as may be deemed necessary by CITY or any authorized representative, and will be retained for three years after the expiration of this CONTRACT. All such records shall be made available for inspection or audit by CITY at any time during regular business hours.

17. SEVERABILITY: If any portion of these contract documents are declared by a court of competent jurisdiction to be invalid or unenforceable, then such portion will be deemed modified to the extent necessary in the opinion of the court to render such portion enforceable and, as so modified, such portion and the balance of this CONTRACT will continue in full force and effect provided that it does not frustrate the mutual intent of the parties herein.
224
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 8 of 34 ends

18.WHOLE AGREEMENT: This CONTRACT supersedes any and all other agreements either oral or written, between the parties and contains all of the covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this contract acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statements or promise not contained in this contract shall not be valid or binding. Any modifications of this contract will be effective only if signed by the party to be charged.

19. AUTHORITY: CONTRACTOR affirms that the signatures, titles, and seals set forth hereinafter in execution of this CONTRACT represent all individuals, firm members, partners, joint ventures, and/or corporate officers having a principal interest herein. Each party warrants that the individuals who have signed this CONTRACT have the legal power, right, and authority to make this CONTRACT and to bind each respective party. This CONTRACT may be modified by written amendment. CITY’s City Manager may execute any such amendment on CITY’s behalf.

20. NOTICES: All notices permitted or required under this CONTRACT shall be in writing, and shall be deemed made when delivered to the applicable party’s representative as provided in this CONTRACT. Additionally, such notices may be given to the respective parties at the following addresses, or at such other addresses as the parties may provide in writing for this purpose.

Such notices shall be deemed made when personally delivered or when mailed forty-eight (48) hours after deposit in the U.S. mail, first-class postage prepaid, and addressed to the party at its applicable address. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.

CITY OF GOLETA
130 Cremona Drive, Suite B
Goleta, CA 93117
Attn: City Manager

CONTRACTOR
Hearn Construction Inc dba Bob’s Backhoe & Trucking
5775 Thornwood Drive
Goleta, CA 93117
225
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 9 of 34 ends

21.DISPUTES: Disputes arising from this contract will be determined in accordance with the contract documents.

22.NON-DISCRIMINATION: The CITY reaffirms its ongoing commitment to equality in the conduct of City business, and prohibits any policy, plan, program, custom or practice, including harassment, in the conduct of City business. No discrimination or discriminatory practice shall occur in either employment of persons for, or completion of, the work contemplated by this CONTRACT, when such discrimination is based on race, color, national origin, or ancestry; religion; sex; gender, gender identity, gender expression, or gender transitioning status; physical disability, mental disability, medical condition, or genetic information; marital or domestic partner status; citizenship status; age; sexual orientation; exercising a legally protected right to an employment leave of absence; status as a victim of domestic violence, sexual assault, or stalking; reproductive health decision-making, or any other classification protected under state or federal law.

Among other possible violations of law, a violation of this section exposes CONTRACTOR to the penalties provided for in Labor Code Section 1735.

23. PAPER PRODUCTS AND PRINTING REQUIREMENTS: To the extent this contract provides paper products, and printing and writing paper for the City, CONTRACTOR must meet quality standards and criteria specified in SB 1383, Sections 22150-22154 of the Public Contract Code and 16 Code of Federal Regulations (CFR) Section 260.12 by:
a. If fitness and quality are equal, provide recycled products, instead of nonrecycled products whenever recycled products are available at the same or a lesser total cost than nonrecycled items.
b. Provide paper products and printing and writing paper that meet Federal Trade Commission recyclability standard as defined in 16 CFR

c. Certify in writing, under penalty of perjury, the minimum percentage of postconsumer material in the paper products and printing and writing paper offered or sold to the City. This certification requirement may be waived if the percentage of postconsumer material in the paper products, printing and writing paper, or both can be verified by a product label, catalog, invoice, or a manufacturer or vendor internet website. d. Certify in writing, on invoices or receipts provided, that the paper products and printing and writing paper offered or sold to the City is eligible to be labeled with an unqualified recyclable label as defined in

226
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 10 of 34 ends

e. Comply with any other requirements in Goleta Municipal Code Section

8.10.900(B).

24. ORGANIC WASTE USE REQUIREMENTS: To the extent this contract provides landscaping maintenance, renovation, and construction services, CONTRACTOR must:
a. Use compost and SB 1383 eligible mulch, as practicable, produced from recovered organic waste, for all landscaping renovations, construction, or maintenance performed for the City, whenever available, and capable of meeting quality standards and criteria specified. SB 1383 eligible mulch used for land application must comply with 14 CCR Section 18993.1 - 18993.4, and must meet or exceed the physical contamination, maximum metal concentration and pathogen density standards specified in 14 CCR Sections 17852(a)(24.5)(A)(1) through (3).
b. Keep and provide records of procurement of recovered organic waste products (either through purchase or acquisition) to the City’s Designated Representative, upon completion of projects. Information to be provided must include:
i. General description of how and where the product was used and if applicable, applied;
ii. Source of product, including name, physical location, and contact information for each entity, operation, or facility from whom the recovered organic waste products were procured; iii. Type of product;
iv. Quantity of each product; and,
v. Invoice or other record demonstrating purchase or
procurement.
c. Comply with all requirements in Goleta Municipal Code Section

8.10.900(A).

25. NO THIRD PARTY BENEFICIARY: This CONTRACT and every provision herein is for the exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of the CONTRACTOR’s or the CITY’s obligations under this Contract.

26. TIME IS OF ESSENCE:Time is of the essence for each and every provision of the Contract Documents.
227
Public Works Contract
HEARN CONSTRUCTION INC DBA BOB’S

BACKHOE & TRUCKING

Page 11 of 34 ends