Agenda Item A.8

CPMS CONSENT CALENDAR
Meeting Date: September 17, 2024
____________________________________________________________ TO: Mayor and Councilmembers
SUBMITTED BY: Luz “Nina” Buelna, Interim Public Works Director PREPARED BY: Daniel Virgen Jr, Assistant Engineer
SUBJECT: Increase the Construction Contingency amount for the 2023 Pavement Rehabilitation Project
RECOMMENDATIONS:

Authorize the Public Works Director to increase the Construction Contingency for the 2023 Pavement Rehabilitation Project in the amount to $367,820 for a not -to-exceed amount of $1,418,420.

BACKGROUND:

The Public Works De partment solicited c ompetitive bids per Municipal Code Section

3.05.210 for the 2023 Pavement Rehabilitation Project (Project). The City Council authorized staff to advertise a notice inviting construction bids for the Project on January 16, 2024 . On February 29, 2024 , bid documents were published on PlanetBids.

Additionally, a notice was published in the Santa Barbara Independent on February 29, 2024, and March 7, 2024. The bids were opened virtually through PlanetBids on April 1, 2024; the City received two bids . O ne bid was received from Granite Construction (Granite) and another from Cal Portland Construction . A summary of the bids and the Engineer’s Estimate are shown in Table 1 below.

Table 1: Bid Results
Granite
Construction
CalPortland
Construction
Engineer’s
Estimate
Base bid $3,852,233.25 $3,767,417.12 $3,467,540.75
Alternate 1 Covington
Neighborhood & Hollister
Avenue
$228,448.00 $426,100.55 $205,823.48
Alternate 2 Dearborn Place $439,888.00 $672,613.20 $312,216.16 Alternate 3 Storke Road $856,570.00 $767,710.20 $698,933.75 Alternate 4 North Fairview
Avenue
$316,158.00 $493,817.50 $289,880.50
TOTAL $5,693,297.25 $6,127,658.57 $4,974,394.64
AWARD AMOUNT Base Bid
alternates 1,3, and 4 $5,253,409.25 $5,455,045.37 $4,662,178.48 1 Meeting Date: September 17, 2024

Page 2 of 3 ends

Granite was the lowest responsible bidder and was awarded the base bid, Alternates 1, 3, and 4, at the City Council meeting on May 21, 2024. The City Council authorized the City Manager to execute the construction contract for the amount of $5,253,409.25 with a contingency amount of $1,050, 600.00. Table 2 below shows details of the base bid and selected alternates.

Table 2: Awarded Base Bid and Bid Alternates for the 2023 Pavement Rehabilitation Project
Location
Base Bid Cathedral Oaks Road (Winchester Canyon Road to Paseo del Pinon) Cathedral Oaks Road (Paseo del Pinon to Evergreen Drive) Phelps Road (Pacific Oaks Road to Storke Road)
Colusa Drive (Del Norte Drive to Calle Real)
Alternate 1 Caroldale Place (Caroldale Lane to cul-de-sac) Caroldale Lane (Camino Laguna Vista to La Patera Lane)
Hollister Avenue (Cathedral Oaks Road to City Right of Way) Alternate 3 Storke Road (Hollister Avenue to US 101 On-Ramp) Alternate 4 North Fairview Avenue (US 101 On Ramp to Calle Real) On June 4, 2024, the Public Works Department presented the City Council with three options for bike lanes and parking modifications along Cathedral Oaks Road, spanning from Paseo Del Pinion to Northgate Drive . Subsequently, on July 16, 2024, the City Council decided to proceed with Alternative 3. This option featu res bike lanes next to the curb, with parallel parking shifted between the bike and travel lanes, and the implementation of back-in angled parking on the north side of Cathedral Oaks Road.

DISCUSSION:

The scope of work for this project includes pavement restoration and reconstruction, resurfacing, Americans with Disability Act (ADA) curb ramp upgrades, striping improvements, and traffic striping and marking replacement.

The City issued Granite the notice to proceed with construction on July 15, 2024, and construction on the project began July 29, 2024 , on Phelps Road. Granite has performed pavement work on every project road except for Caroldale Place. During the project's construction, unforeseen site conditions necessitated the City to direct the contractor to remove and replace additional asphalt sections and modify the pavement operations on Cathedral Oaks. These measures are being undertaken to address the increased pavement failures. Public Works staff recommends taking advantage of efficiencies of proximity and having the contractor improve areas adjacent to the current work areas, including the overlay of the bike path along Cathedral Oaks and intersection resurfacing at Storke Road and Hollister Avenue. An increase in the contingency budget would b e required to take advantage of these considerations. When the project was awarded, staff requested a contingency of 20% of the contract amount, and staff is now requesting to increase the contingency budget to 27% of the original contract amount to take on these additional tasks. Further competitive bidding to secure such work would not produce any advantage to the City, as the cost of mobilization that would need to be 2 Meeting Date: September 17, 2024

Page 3 of 3 ends

priced into such bids and which Granite is able to avoid because it has already mobilized would cause such bids to substantially exceed in price that which Granite would charge, and therefore such increases are exempt from competitive bidding under Graydon v. Pasadena Redevelopment Agency (1980) 104 Cal.App.3d 631, 636.

Public Works staff recommends that the City Council approve and authorize the Public Works Director to increase the change order in the amount of $ 367,820 for a construction contingency amount of $1,418,420.

FISCAL IMPACTS:

The total estimated costs and funding sources associated with the Project are listed in Table 3 below. The additional 7% of construction contingency will be covered by FY 24/25 General Fund Account.

Table 3 – Project Cost Estimated

Project Components Project Costs Funding Source Funding Amounts
Project Management
(Consultant)
*$75,000.00 General Fund (101) $5,339,803.25
Design (Consultant) *$650,000.00 Gas Tax (201) $1,241,417.00 Construction (Base Bid &
Alternates)
$5,253,409.25 RMRA (203) $863,017.00
Construction Contingency $1,418,420.00 Measure A (205) $354,197.00 Construction Management
(Consultant)
$739,230.00 LSTP (306) $337,625.00
Total $8,136,059.25 Total $8,136,059.25
*Previously Expended

ALTERNATIVES:

The City Council may elect to not approve the increase of construction contingency.

However, if unforeseen conditions arise , the project could be halted entirely due to budget limitations.

LEGAL REVIEW BY: Megan Garibaldi, City Attorney

APPROVED BY: Robert Nisbet, City Manager

ATTACHMENTS:

1. 2023 Pavement Rehabilitation Project Map

3 ATTACHMENT 1
2023 Pavement Rehabilitation Project Map
4 NO SCALE

PACIFIC OCEAN

CITY OF GOLETA
2023 PAVEMENT REHABILITATION PROJECT

CATHEDRAL OAKS RD

HOLLISTER AVE

CALLE REAL

PHELPS RD

LOS CARNEROS RD

CALLE REAL

COVINGTON WAY

ELLWOOD BEACH DR

DAYTONA DR

GLEN ANNIE RD

EL COLEGIO RD

CALLE REAL

STORKE RD

DEL NORTE DR

S FAIRVIEW AVE

S KELLOGG AVE

HOLLISTER AVE

N FAIRVIEW AVE

STOW CANYON RD

N LA PATERA LN

CARLO DR

DEARBORN PLACE

PADOVA DR

N PATTERSON
AVE
5

← All documents from this meeting