Attention is directed to section 7-1.02 LAWS of the State Standard Specifications.
Submit any proposed modifications to the RWQCB certification in writing to the Engineer for transmittal to the RWQCB for their approval. Modifications must not be implemented until approved in writing by the RWQCB.
Attention is directed to section 8- 1.05 TIME of these Special Provisions. Days during which your operations are restricted by the requirements of this section will be nonworking days if these restrictions cause a delay in the current controlling operation or operations. 493
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-122
You are fully bound by the provisions of this section, the RWQCB certifications, and any subsequent modifications to the RWQCB certification. Make them a part of every subcontract executed pursuant to this contract.
14-6.01C (CDFW) Relations with California Department of Fish and Wildlife A portion of this project is located within the jurisdiction of the California Department of Fish and Wildlife (CDFW). A permit has been entered into by the City of Goleta and the and CDFW. Be fully informed of the requirements of this permit as well as all rules, regulations, and conditions that may govern your operations in these areas and conduct the work accordingly.
A copy of these permits is included in the Appendix and is hereby made a part of these special provisions.
It is unlawful for any person to substantially divert or obstruct the natural flow or substantially change the bed, channel, or bank of any stream, river, or lake without first notifying CDFW, unless the project or activity is noticed and constructed in accordance with all conditions imposed under Fish and Wildlife Code Section 1602.
Attention is directed to section 7-1.02 LAWS of the State Standard Specifications.
Submit any proposed modifications to the CDFW permit in writing to the Engineer for transmittal to CDFW for their consideration. Modifications must not be implemented until approved in writing by CDFW.
Attention is directed to section 8- 1.05 TIME of these Special Provisions. Days during which your operations are restricted by the requirements of this section will be nonworking days if these restrictions cause a delay in the current controlling operation or operations.
You are fully bound by the provisions of this section, the CDFW permit, and any subsequent modifications to the CDFW permit. Make them a part of every subcontract executed pursuant to this contract.
Notify the Engineer a minimum of 5 working days in advance of planned start of dewatering work to allow time for scheduling the biologist to be onsite.
14-6.01D (CCC) California Coastal Commission
A portion of this project is located within the Coastal Zone . A permit has been entered into by the City of Goleta and the and CCC. Be fully informed of the requirements of this permit as well as all rules, regulations, and conditions that may govern your operations in these areas and conduct the work accordingly.
A copy of the permit is included in the Appendix and is hereby made a part of these special provisions.
Attention is directed to section 7-1.02 LAWS of the State Standard Specifications. 494
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-123
The permits require the Contractor to comply with all permit requirements, and mitigation measures of the California Department of Fish and Wildlife, State Water Quality Control Board, Regional Water Quality Control Board, U.S. Army Corps of Engineers, and the U.S. Fish and Wildlife Service with respect to preservation and protection of water quality and the environment. Any change in the approved project which may be required by the above stated agencies shall be submitted to the Executive Director of the CCC to determine if the proposed change shall require a permit amendment pursuant to the requirements of the Coastal Act and the California Code of Regulations.
Notify the Engineer a minimum of 5 working days in advance of planned start of dewatering work to allow time for scheduling the biologist to be onsite.
Add to the 1st paragraph of section 14-6.03A:
This project is within or near habitat for the regulated species shown in the following table:
Regulated Species
Southern California Steelhead
Tidewater Goby
California Red-Legged Frog
Coast Range Newt
Western Pond Turtle
Northern California Legless Lizard
Coast Horned Lizard
Western Snowy Plover, Pacific
Coast Population
Southwestern Willow Flycatcher
Belding’s Savanna Sparrow
Least Bell’s Vireo
Grasshopper Sparrow
Pallid Bat
Western Mastiff Bat
Western Red Bat
White-Tailed Kite
Nesting Birds
Nesting Raptors
Monarch butterfly (overwintering
population)
San Diego Desert Woodrat
Coulter’s saltbrush
Southern tarplant
Salt marsh bird’s beak
Coulter’s goldfields
495
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-124
This project includes the sensitive habitats shown in the following table:
Sensitive Habitats
Southern California Steelhead and
Tidewater Goby Critical Habitat
Coastal Pelagic Species and
Groundfish Essential Fish Habitat
Jurisdictional Waters
Jurisdictional Wetlands
Jurisdictional Riparian Habitat
California Coastal Zone
Replace item 1 in the list in the 2nd paragraph of section 14-6.03A with:
1. Stop all work within a 100-foot radius of the discovery except as shown in the following table:
Regulated
species
Protective radius
(feet)
Nesting Raptors 500
Nesting Birds 250
Roosting bats 500
Belding’s
Savanna
Sparrow
500
Least Bell’s
Vireo and
Southwestern
Willow
Flycatcher
250
San Diego
Desert Woodrat
50 Add to section 14-6.03A:
There is no suitable habitat for San Diego Desert Woodrat in the southern segment.
San Diego Desert Woodrat (northern segment):
A preconstruction survey for San Diego desert woodrat shall be conducted by a qualified biologist within two weeks prior to the start of construction-related activities. If woodrat middens are located during this survey, the qualified biologist shall establish an ESA with a 50-foot buffer around each midden and no construction activities regarding grading, mechanized equipment or vehicles, or large crews will be allowed within the 50-foot protective buffer.
If construction activities cannot avoid impacting the middens, then a qualified biologist will consult with the California Department of Fish and Wildlife prior further activity. 496
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-125
Upon CDFW consultation, a qualified biologist will dismantle the middens by hand at least seven days prior to grading or vegetation removal activities. The midden dismantling shall be conducted such that the midden material is slowly removed looking for young woodrats. The material shall be placed in a pile at the closest adjacent undisturbed habitat and more than 50 feet from construction activities.
If young are encountered during midden dismantling, the dismantling activity shall be stopped and the material replaced back on the nest and the nest shall be left alone and rechecked in 2 to 3 weeks to see if the young are out of the nest or capable of being out on their own (as determined by a qualified biologist); once the young can fend for themselves, the nest dismantling can continue.
Species protection areas within the project limits are as specified in the following table:
Species Protection Areas
Identification name Location
Species Protection Area 1 (SPA1) Coastal Zone
Species Protection Area 2 (SPA2) Jurisdictional Waters in San Jose Creek
Species Protection Area 3 (SPA3) Jurisdictional Riparian Habitat
Species Protection Area 4 (SPA4) Jurisdictional Wetlands
Comply with the following biological resource information requirements:
1. Before performing activity or work, a Worker Environmental Awareness Training Program for construction personnel will be conducted by a USFWS-approved qualified biologist. All personnel on site greater than 60 minutes are required to attend this training.
2. Notify the Engineer no later than seven days prior to start of activities or start of new field personnel to schedule the training.
3. Do not schedule more than one training session within a week.
4. As needed, training will be conducted in Spanish for Spanish language speakers.
Within Protection Area 1 (Coastal Zone), Protection Area 2 (Jurisdictional Waters in San Jose Creek), Protection Area 3 (Jurisdictional Riparian Habitat), and Protection Area 4 (Jurisdictional Wetlands) implement the following protection measures:
1. No less than 14 days prior to the start of construction activities, notify the City and City’s qualified biologist in order to schedule and conduct a pre-construction survey(s) for Regulated Species.
2. The contractor will allow access to the City’s qualified biologist to conduct pre- construction surveys prior to the start of construction activities. 497
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-126
3. If it becomes necessary to remove woody vegetation with a diameter at 4.5 feet above ground level greater than 3 inches, that is not shown for removal on the plan, the contractor must request authorization, subject to City and CDFW approval or denial.
4. Ground disturbance will not begin until written approval is received from USFWS that the biologist is qualified to conduct the work, the pre-construction surveys are complete, and the results are documented.
5. If regulated species are found, stop work and notify the Engineer and City’s qualified biologist.
6. During construction activities, all trash that may attract predators will be contained in animal-proof containers and removed from the work site and disposed of daily.
7. All vehicles, machinery, and equipment must be in a clean and soil-free condition.
8. Following construction, all trash and construction debris will be removed from work areas.
9. Visually check all sections of pipe for the presence of wildlife prior to being removed from the project site. If any sections of pipes are being stored on-site for any length of time, Permittee shall have a visual check performed to ensure wildlife is absent and then cap all ends to prevent wildlife entry.
10. Cover areas of excavation (e.g., pits, trenches, holes) overnight and during periods of inactivity, or install routes of escape (e.g., ramp constructed of dirt fill or wood planking or other suitable material that is placed at an angle no greater than 30 degrees) from excavated pits and trenches for wildlife that could potentially become entrapped.
11. No work will be completed in the San Jose Creek channel for the northern segment if water is present.
12. All refueling, maintenance, and staging of equipment and vehicles will occur at least 60 feet from riparian habitat or water bodies and in a location from where a spill would not drain directly toward aquatic habitat (e.g., on a slope that drains away from the water).
13. Do not use rodent poisons or rodenticide to control rodents.
14. Do not use herbicides as the primary method to control invasive, exotic plants.
The preferred method of invasive species removal is mechanical removal with hand tools. If herbicides are necessary, the following precautions will be taken:
a. all herbicides will be registered for aquatic use by the California Department of Pesticide Regulation
b. Herbicides will only be used as sprays via aerial or ground application when winds are less than 10 mph
c. If herbicides are used within or adjacent to streams or sensitive habitats, they will contain a dye to prevent overspray
15. All herbicides, fuels, lubricants, and equipment will be stored, poured, or refilled at least 60 feet from riparian habitat or water bodies in a location where a spill would not drain directly toward aquatic habitat, unless otherwise preapproved by the necessary agencies.
498
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-127
16. Vegetation trimming will follow the direction and specifications of a biologist; tree trimming will follow the direction and specifications of a Certified Arborist.Conduct all vegetation removal and grading activities during the non-breeding season (September 1 through January 31) per the direction of a biologist. If excavation takes place where roots will be encountered, a Certified Arborist will monitor the excavation to ensure roots are not damaged.
18. If construction, grading or other related activities are schedule during the breeding and nesting season (February 1 to August 31), preconstruction surveys for other migratory bird species shall take place no more than 3 days prior to the beginning of construction and at least twice a week while construction takes place within suitable nesting habitat during the breeding and nesting season (February 1 to August 31).
19. Thoroughly inspect all construction materials and equipment for sheltering or trapped regulated species prior to use. If regulated species are found, stop work immediately and notify the Engineer.
20. Immediately report any observations of any dead or injured wildlife to the Engineer.
Within Protection Area 2 (Jurisdictional Waters in San Jose Creek), Protection Area 3 (Jurisdictional Riparian Habitat) and Protection Area 4 (Jurisdictional Wetlands)implement the following protection measures:
1. Locate staging areas a minimum of 100 feet from aquatic areas.
2. Clean all equipment daily prior to entering stream channels and riparian habitat and wetlands. Clean equipment and refueling only within staging areas located 100 feet from aquatic and riparian areas.
3. If it becomes necessary to remove woody vegetation with a diameter at 4.5 feet above ground level greater than 3 inches, that is not shown for removal on the plan the contractor must request authorization, subject to City and CDFW approval or denial.
4. If the staging, cleaning, or refueling area is less than 100 feet and not closer than 20 feet from aquatic areas, the area must be surrounded by barriers or secondary containment (e.g., fiber rolls or equivalent) to prevent spills from entering Species Protection Areas 2, 3, and 4.
5. No concrete or any cement product may be poured within 150 feet of a stream during the rainy season, in or near a flowing stream at any time, or 7 days prior to a 25% chance or greater chance of greater than 0.25 inches or more of rain.
6. The contractor will develop and implement a toxic materials control and spill response plan prior to the start of construction. The plan will outline the practices that will be used to prevent minimize, and/or clean up potential spills during construction of the project. The Plan must detail the project elements, construction equipment types and location, access and staging and construction sequence. The Plan will be submitted to the appropriate regulatory agencies 30 days prior to the start of construction for their review and approval.
7. All equipment that will be stationary shall have catch or drip pans placed underneath them. All compressors, pumps, welders and fuel tanks shall be 499
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-128
placed inside fuel spill containment systems while operating at any time.
Stationary heavy equipment shall have suitable containment to handle a catastrophic spill/leak.
8. Locate all overnight parked vehicles within designated staging areas and no less than 10 feet from the dripline of any trees.
9. Heavy equipment shall not be operated in wetted areas (including but not limited to San Jose Creek channel, ponded, flowing, or wetland areas), except where permitted by regulatory agencies.
10. Locate all temporary soil stockpiles at least 150 feet from aquatic or riparian areas and in locations where runoff will not flow into aquatic or riparian areas.
11. The staging areas will conform to BMPs applicable to attaining zero discharge or stormwater runoff.
12. All equipment and vehicles will be checked and maintained by the contractor daily to ensure proper operation and avoid potential leaks or spills.
13. Erosion and sediment control measures must be on site prior to start of construction in Species Protection Areas 2, 3, and 4 so they are immediately available for installation ahead of rain events.
14. Areas of disturbed soils with slopes toward a stream or lake shall be stabilized to reduce erosion potential. Planting, seeding, and mulching is conditionally acceptable. Where suitable vegetation cannot reasonably be expected to become established, non-erodible materials, such as coconut fiber matting, shall be used for such stabilization. No mono-filament material shall be used within any fiber matting. Where needed, the Permittee shall use native vegetation or other treatments including native slash, jute netting, straw wattles, and geotextiles to protect and stabilize soils. Geotextiles. fiber rolls, and other erosion control treatments shall not contain plastic mesh netting.
15. No stream water may be used in construction, such as in dust control or irrigation of plants. All construction water shall be from developed sources.
16. Do not move or relocate any rock, gravel, or substrate from a stream channel or riparian area other than the minimum required to complete project activities.
17. All debris from structure removal must be removed from the creek channel and riparian areas the same day including small debris and dust.
18. No concrete or any cement product may be poured within 150 feet of a stream during the rainy season, in or near a flowing stream at any time, or 7 days prior to a 25% chance or greater chance of greater than 0.25 inches or more of rain.
19. If any concrete is poured after November 1st a quick cure ingredient shall be added.
Within Species Protection Area 2 (Jurisdictional Waters in San Jose Creek) implement the following protection measures:
1. During construction of the northern segment, instream work will only occur during dry conditions. Instream work is allowed only when conditions are dry, from June 1 and September 30 in any given year (do not work instream between October 1 and May 31). Deviations from this work window will only be made with concurrence from relevant regulatory/resource agencies. 500
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-129
2. No concrete or any cement product may be poured within 150 feet of a stream during the rainy season, in or near a flowing stream at any time, or 7 days prior to a 25% chance or greater chance of greater than 0.25 inches or more of rain.
3. Cement shall not be poured in or near a flowing stream, to reduce the potential for significant adverse impacts to the stream, water, or biota without prior approval
4. If any concrete is poured after November 1st a quick cure ingredient shall be added to the concrete mix to ensure a faster set or drying time
5. Poured concrete structure(s) shall be isolated from water and allowed to dry/cure for a minimum of 30 days. As an alternative, monitor the pH of any water that has come into contact with the poured concrete. If this water has a pH of 9.0 or greater, the water shall be pumped to a tanker truck or to a lined off-channel basin and allowed to evaporate or be transported to an appropriate facility for disposal.
6. During the pH monitoring period, all water that has come in contact with poured concrete shall be isolated and not allowed to enter the water or otherwise come in contact with fish and other aquatic resources. The water shall be retested until pH values become less than 9.0. Once this has been determined, the area no longer needs to be isolated. Results of pH monitoring shall be made available to CDFW upon request. A non-toxic substance that can buffer the pH shall be made available on-site to use if any contamination to water occurs.
7. Instream construction work related to the northern segment will only be performed in a dry work environment with no standing or flowing surface water present. Remove all equipment and stop all construction activities below the top of creek banks on any day for which the National Weather Service has predicted a 50% or more chance of at least 0.5 inches of rain within 72 hours for Goleta, CA. Construction activities may resume 24 hours after the rain has ceased, the site conditions are dry enough to continue work without discharge of sediment or other pollutants from the project site, and there is less than a 50% forecast for precipitation for the following 24-hour period.
8. No night work requiring the use of artificial lighting is permitted in areas within San Jose Creek.
The City will implement measures to avoid and minimize impacts on monarch butterfly.
Prior to conducting work and during the work associated with the northern segment, the following measures will be implemented:
1. Before any tree removal in the Elk’s Club Grove monarch overwintering habitat, a Department biologist will survey for the presence of roosting or aggregated, overwintering monarch butterflies.
2. A temporary fence will be installed along the outer boundary of the buffer zone prior to and during any grading and construction activities on the site.
3. If an active roost or aggregation is present on the project site, any construction grading, or other development within 200 feet of the active roost will be prohibited between October 1 and March 1.
501
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-130
Add to section 14-6.03B:
If tree removal is to take place between February 1 through August 31, a qualified biologist retained by the City of Goleta will conduct a “Preconstruction Nesting Bird Survey” to determine the presence of nesting special -status and non-special-status migratory birds and raptors on the project site. This will be done prior to the start of the construction, and the Contractor shall coordinate their schedule to accommodate this survey. Where presence of these species is found in the construction area, the City’s biologist will establish and determine the size of a buffer zone around nest trees, shrubs and ground.
The Contractor shall install a temporary high- visibility fence along the buffer zone perimeter of each nest tree, shrub or ground.
Signs shall be installed on, or adjacent to, the temporary fence at two equidistant locations; and shall be visible from where the construction activity area. The size of each sign shall be a minimum of 24 in. x 24 in. and shall contain the following message:
“WARNING. THIS FENCE SHALL NOT BE REMOVED OR RELOCATED
WITHOUT WRITTEN AUTHORIZATION FROM THE CITY OF GOLETA.”
Add to Section 14-6.04:
A temporary high -visibility fence shall be installed at the locations shown on the plans, and as determined by the Engineer. No construction activities shall take place beyond the boundaries of this fence without the approval of the Engineer.
Signs shall be installed on, or adjacent to, the temporary fence every 150 ft. and shall be visible from where the construction activity area.
The size of each sign shall be a minimum of 24 in. x 24 in. and shall contain the following message:
“WARNING. THIS FENCE SHALL NOT BE REMOVED OR RELOCATED WITHOUT WRITTEN AUTHORIZATION FROM THE CITY OF GOLETA.”
Replace section 14-6.05 with:
14-6.05 INVASIVE SPECIES CONTROL
Section 14-6.05 includes specifications for preventing the introduction and spread of invasive species to and from the job site.
Comply with section 13-4.03E(3).
At least 2 business days before using vehicles and equipment on the job site, submit a signed statement that the vehicles and equipment have been cleaned of soil, seeds, 502
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-131
vegetative matter, and other such debris that may introduce or spread invasive species.
The statement must include:
1. List of the vehicles and equipment with identifying numbers
2. Date of cleaning for each vehicle and piece of equipment
3. Description of the cleaning process
4. Measures to be taken to ensure the vehicles and equipment remain clean until operation at the job site
5. Verification that the equipment has not been operated in waters known to be infested by aquatic invasive species
Update the list of vehicles and equipment as needed.
Clean the following vehicles and equipment before operation at the job site:
1. Excavators
2. Loaders
3. Graders
4. Haul trucks
5. Water trucks
6. Cranes
7. Tractors
8. Trailers
9. Dump trucks
10. Waders
This project includes the sensitive areas shown in the following table:
Sensitive Habitats
Southern California Steelhead and
Tidewater Goby Critical Habitat
Coastal Pelagic Species and
Groundfish Essential Fish Habitat
Jurisdictional Waters
Jurisdictional Wetlands
Jurisdictional Riparian Habitat
California Coastal Zone
Do not clean vehicles, equipment, or tools at locations near sensitive habitat or waterways at the job site. Clean vehicles and equipment every time before it enters or leaves a sensitive habitat. Within 100 feet of aquatic areas or areas less than 100 feet from aquatic areas, but surrounded by barriers or secondary containment, implement the following protection measures:
1. Before entering or exiting, pressure wash your vehicles and equipment:
1.1. At a temperature of 140 degrees F
1.2. With a minimum nozzle pressure of 2,500 psi
503
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-132
1.3. With a minimum fan tip angle of 45 degrees
2. Thoroughly scrub personal work equipment and tools, such as boots, waders, hand tools, and any other equipment used in water at the job site, using a stiff-bristled brush to remove any organisms. Decontaminate the equipment by one of the following methods:
2.1. Immerse the equipment in water at a temperature of 140 degrees F for at least 5 minutes. If necessary, weigh down the equipment to keep it immersed in the water.
2.2. Freeze the equipment to a temperature of 32 degrees F or colder for at least 8 hours.
2.3. Thoroughly dry the equipment in a weed-free area for at least 48 hours.
3. Clean personal work equipment, and tools over drip pans or containment mats at the job site. Collect and contain the wastewater. Dispose of the wastewater at a waste management facility.
Replace Reserved in Section 14-6.06 with:
14-6.06 NON-NATIVE PLANT REMOVAL
Remove non-native vegetation from the work area and dispose of it off site. Removal must be done twice annually during the spring/summer season for the duration of the project. Arundo (Giant Cane) must be cut to a height of 6 inches or less, and the stumps painted with an herbicide approved for aquatic use within 5 minutes of cutting.
Herbicides must be applied three times during the period from May 1st to October 1st.
Invasive non-native species must be removed by hand or by hand-operated power tools rather than by chemical means. Where control of non-native vegetation is required within the bed, bank, or channel of a stream and there is a possibility that herbicides could come into contact with water, use only herbicides as approved by the Engineer, such as Rodeo/Aquamaster (Glyphosate), which are approved for aquatic use. If surfactants are approved by the Engineer for use, they shall be restricted to non-ionic chemicals, such as Agri-Dex, which are approved for aquatic use. All sprays must contain a dye to prevent overspray. Sprays must not be used when wind speed exceeds 10 mph. Sprays must not be used if rain is forecasted within 96 hours.
Replace Reserved in Section 14-6.07 with:
14-6.07 OAK ROOT PROTECTION
Do not operate equipment within the dripline of oaks not designated for removal.
Replace Reserved in section 14-6.09 with:
14-6.09: RESTORATION CONTRACTOR MITIGATION WORK
14-6.09A General
14-6.09(1) Summary
The Restoration Contractor that will be subcontracted to the General Contractor will be required to initiate the restoration phase for both onsite and offsite restoration work. Work shown in Appendix B, RESTORATION CONTRACTOR MITIGATION WORK, and on the plans designated as Mitigation Planting must be performed by a restoration or landscape 504
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-133
Contractor with the qualifications described in this section and in Appendix B. Mitigation plans include work on site within the primary jobsite as well as work off-site in other areas of the City. The Project requires on or off-site mitigation as shown in the plans, designated as:
1. Johnny D. Wallis Park is a mitigation site for the Northern Segment
2. Devereux Slough at Ellwood Mesa and Old San Jose Creek along Ekwill Street are mitigation sites for the Southern Segment
The Restoration Contractor must possess a California Contractors “C -27” Landscaping Contractor license.
14-6.09A(2) Definitions
Not Used
14-6.09A(3) Submittals
Not Used
14-6.09A(4) Quality Assurance
The project biologist will oversee the planting installation.
14-6.09B Materials
Materials will conform to the materials described in Appendix B.
14-6.09C Construction
The Contractor’s Restoration Contractor must have experience with installing and maintaining a minimum of three native habitat restoration projects each over 4 acres in southern California. The reference project experience must demonstrate experience with the native plant species listed in the mitigation plans, as well as a knowledge of non- native and invasive species common to the Goleta area. The Contractor restoration project experience must show successful planting of native species in remote (off -road) areas, including the installation of temporary above ground irrigation systems in remote locations.
The Restoration Contractor must possess and provide the following Santa Barbara County pesticide application licensing at the time of the bid submittal:
1. A pest control business (PCM) or one of its licensed branches (PCB) with a current license issued by California Environmental Protection Agency’s (EPA) Department of Pesticide Regulation (DPR);
2. A person currently licensed as a Qualified Applicator (QAL) and with a Category B (Natural Areas);
3. The PCM/PCB and the QAL must be registered with the County Commissioner in Santa Barbara County
The Restoration Contractor shall pick up the native plant stock for installation and pay the remaining balance to the Santa Barbara Natives. The Restoration Contractor will need 505
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-134
to pick up the plants at the nursery on a daily or regular basis and bring them to the site.
Only a very limited number of plants can be stored safely on- site overnight. If plants remain on-site longer than the day on which they are installed, they must be watered daily.
14-6.09D Payment
Full compensation for conforming to of the requirements of this section, including pickup, delivery, installation, and all work involved in the restoration work shall be considered as included in the contract lump sum price paid for RESTORATION CONTRACTOR MITIGATION WORK and no additional compensation will be allowed therefor.
Replace Reserved in Section 14-6.10 with:
14-6.10 ADDITIONAL MITIGATION MEASURES
The Contractor shall implement the following measures prior to work commencing on the project:
The Contractor shall use existing power sources or clean fuel generators rather than diesel generators.
The Contractor shall minimize the potential for the long- term loss of riparian vegetation by trimming vegetation rather than removing entire shrubs. Shrubs that need to be trimmed will be cut at least 1 foot above ground level to leave the root systems intact and allow for more rapid regeneration. Cutting will be limited to the minimum area necessary within the construction zone. Cutting will be allowed only for shrubs (all trees will be avoided) in areas that do not provide habitat for special -status species. Disturbance or removal of vegetation will not exceed the minimum necessary to complete operations.
Except for the vegetation specifically identified for trimming and/or removal in the notification, no native oak trees with a trunk diameter greater than 6 inches dbh will be removed or damaged without prior consultation and approval of a City of Goleta Public Works Department representative. Using hand tools (e.g., clippers, chain saw), trees may be trimmed to the extent necessary to gain access to the work sites. All cleared material/vegetation will be removed out of the riparian/stream zone.
To avoid the introduction or spread of noxious weeds into previously uninfested areas (especially within the riparian community along San Jose Creek), the Contractor shall revegetate disturbed areas immediately after construction of that area is complete. The revegetation portion of the SWPPP will contain specifications for using certified weed- free native and nonnative mixes.
Replace the 2nd paragraph of Section 14-8.02 with:
The noise level from the Contractor's operations, between the hours of 9:00 p.m. and 6:00 a.m., shall not exceed 86 dbA at a distance of 50 feet. This requirement in no way 506
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-135
relieves the Contractor from responsibility for complying with local ordinances regulating noise level.
In addition, the Contractor shall conform to the City Goleta Municipal Code.
All noise-generating project construction activities are limited to Monday through Friday, 8:00 a.m. to 5:00 p.m. Exceptions must be requested in writing and authorized by the Engineer. Prepare a Noise Mitigation Measures submittal for approval in advance of any construction activities planned to be performed after hours or on weekends/holidays.
Post a sign at least 24 X 48 inches in size stating the noise limitations at the job site.
Each internal combustion engine, used for any purpose on the job, or related to the job, shall be equipped with a muffler of a type recommended by the manufacturer. Internal combustion engines without an appropriate muffler are not allowed on the job site.
Follow the following general noise reduction strategies:
1. Use modern construction equipment
2. Plan noisiest operations for times of least intrusion
3. Use quieter alternate methods or equipment when possible
4. Locate stationary noise sources away from sensitive receiver locations
5. Operate equipment at minimum power as feasible
In addition to the requirements of Section 14-8 of the State Standard Specifications, noise level requirements shall apply to all equipment used on the project including, but not limited to, trucks, transit mixers or transient equipment that may not be owned by the Contractor. The use of loud signals shall be avoided in favor of light warnings except those required by safety laws for the protection of personnel.
Full compensation for conforming to the requirements of this section shall be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed therefore.
Add to the end of Section 14-9.02:
The US EPA has established the National Emission Standards for Hazardous Air Pollutants (NESHAP). Under the Health & Safety Code § 39658(b)(1), the Contractor’s demolition and rehabilitation activities must comply with 40 CFR 61, Subpart M (National Emission Standard for Asbestos).
The Contractor must notify the Santa Barbara County Air Pollution Control District of the
Contractor’s demolition activities even if the activities will not disturb asbestos- containing material.
The Contractor may obtain the notification form, submittal instructions, and other i
nformation from:
507
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-136
Santa Barbara County Air Pollution Control District
260 North San Antonio Road, Suite A
Santa Barbara, CA 93110-1315
https://www.ourair.org/asbestos/
Instead of the 10 working days specified at the website, submit a notification form to the Santa Barbara County Air Pollution Control District at least 15 days before starting demolition or rehabilitation activities.
Submit a copy of the notification form and the necessary attachments as informational submittals before starting demolition or rehabilitation activities.
If the Contractor discovers unanticipated asbestos-containing material during the demolition or rehabilitation activities, immediately stop work in that area and notify the Engineer. The Department will use other forces to remove and dispose of the material.
Do not resume work in the area until authorized.
Notify the Santa Barbara County Air Pollution Control District of a change to the Contractor’s demolition or rehabilitation activities, including a revised work plan or the discovery of unanticipated asbestos-containing materials, within 2 days of the change or discovery.
Replace Reserved of section 14-9.04 with:
14-9.04 CONSTRUCTION DUST CONTROL
Apply water or dust palliative to the site and wash equipment as necessary to control airborne dust. During construction, use water trucks or sprinkler systems to keep all areas of vehicle movement damp to prevent dust from leaving the site and to create a crust after each day’s activities cease. At a minimum, wet down such areas in the late morning and after work is completed for the day. Increase watering frequency whenever wind speed exceeds 15 miles per hour. Dust emissions at adjacent property lines must not exceed 20 percent opacity more than an aggregate of 3 minutes in any 60-minute period. Grading and scraping operations must be suspended when wind speeds exceed 20 mph. Minimize the amount of disturbed area and limit on-site vehicle speeds to 15 miles per hour. Install gravel pads at construction site access points. All gravel, dirt, and construction material must be cleaned from the public right-of-way at a minimum of once a day at the end of the workday.If importation, exportation, and stockpiling of fill material is needed, soil stockpiled for more than two days must be covered, kept moist, or treated with soil binders to prevent dust generation. Trucks transporting fill material to and from the site must be tarped. If an area is graded and left undeveloped for over four weeks utilize soil binders or revegetation immediately to inhibit dust generation:
No demolition or construction materials, debris, or waste shall be placed or stored where it may enter sensitive habitat, receiving waters or a storm drain, or be subject to wave, wind, rain, or tidal erosion and dispersion). No demolition or construction equipment, materials, or activity shall be placed in or occur in any location that would result in impacts to environmentally sensitive habitat areas, streams, wetlands or their buffers. Any and all debris resulting from demolition or construction activities shall be 508
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-137
removed from the project site within 24 hours of completion of the project. Demolition or construction debris and sediment shall be removed from work areas each day that demolition or construction occurs to prevent the accumulation of sediment and other debris that may be discharged into coastal waters. All trash and debris shall be disposed in the proper trash and recycling receptacles at the end of every construction day. The applicant shall provide adequate disposal facilities for solid waste, including excess concrete, produced during demolition or construction. Debris shall be disposed of at a permitted disposal site or recycled at a permitted recycling facility. If the disposal site is in the coastal zone, a coastal development permit or an amendment to this permit shall be required before disposal can take place unless the Engineer determines that no amendment or new permit is legally required.
Replace section 14-11.08 with:
14-11.08 REGULATED MATERIAL CONTAINING AERIALLY DEPOSITED LEAD 14-11.08A General
Section 14-11.08 includes specifications for management of regulated material containing ADL Management of the material includes:
1. Excavating
2. Loading and unloading containers or trucks
3. T
ransporting
4. Disposal
Manage regulated material containing ADL under the rules and regulations of the following agencies:
1. US Department of Transportation
2. US EPA
3. California Environmental Protection Agency
4. CDPH
5. DTSC
6. Cal/OSHA
7. California Department of Recycling and Recovery
8. California Air Resources Board
9. RWQCB, Region 3, Central Coast
10. Santa Barbara County Air Pollution Control District
The Department entered into agreement Docket No. ESPO-SMA 15/16-001 Soil Management Agreement for Aerially Deposited Lead-Contaminated Soils with the DTSC (ADL Agreement) regarding the management of regulated material containing ADL. As the responsible entity and the generator of waste, only the Department determines material classification. For the ADL agreement, go to the Caltrans Hazardous Waste Management website.
Regulated material containing ADL is present within the project limits and the ADL Agreement applies. Management of regulated material containing ADL exposes workers 509
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-138
to health hazards that must be addressed in your lead compliance plan under section 7-
1.02K(6)(j)(ii).
14-11.08B Definitions
average ADL concentration: Average ADL concentration calculated using the 95 percent upper confidence limit.
regulated material: ADL-contaminated material that has average ADL concentrations over 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead tested using the California Waste Extraction Test (CA-WET) or equal to or greater than 5 mg/L soluble lead tested using the Toxicity Characteristic Leaching Procedure (TCLP).
Type Z-2: Regulated material that is a Department-generated California hazardous waste that must be disposed of at an appropriately permitted California Class I disposal facility. Type Z-2 material has average ADL concentrations greater than or equal to 1,000 mg/kg total lead or 5.0 mg/L soluble lead as tested using the CA- WET.
14-11.08C Site Conditions
Concentration data and sample location maps for regulated material are included in the Information Handout.
Type Z-2 material exists from the surface to below the existing grade as shown and listed in the following table:
Location Elements of work Depth
“A1-Line” Station
31+89.44 to Station
62+85.55, Southbound
Route 217
Excavation for new
shoulders
Bike Path
0 – 1.5 feet
14-11.08D Submittals
14-11.08D(1) General
Not Used
14-11.08D(2) Perimeter Air Monitoring Requirements
Not Used
14-11.08D(3) Excavation and Transportation Plan
Within 15 days of Contract approval, submit 3 copies of an excavation and t
ransportation plan for regulated material. Allow 15 days for review. If the plan requires revisions, the Department provides comments. Submit a revised plan within 7 days of receiving comments. The Engineer may allow construction to proceed while minor revisions or amendments are being completed.
The excavation and transportation plan must comply with:
510
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-139
1. DTSC regulations
2. ADL Agreement
3. Cal/OSHA regulations
The excavation and transportation plan must include:
1. Procedures for managing the material.
2. Excavation schedule by location and date.
3. Dust control measures.
4. Transportation equipment and routes.
5. Method for preventing spills and tracked material onto public roads.
6. Truck waiting and staging areas.
7. Name and address of the California Class I disposal facility where hazardous waste will be disposed of.
14-11.08D(4) Burial Location Report
Not Used
14-11.08D(5) Bill of Lading
Not Used
14-11.08D(6) Disposal Documentation
Submit documentation from the receiving disposal facility confirming appropriate disposal within 5 business days of transporting Type Z-2 material from the job site. 14-11.08E Dust Control
Prevent visible dust migration under section 14-11.04 during management of regulated material.
14-11.08F Air Monitoring
Not Used
14-11.08G Stockpiling
Do not stockpile Type Z-2 material. Transfer Type Z-2 material directly from the excavation to containers or trucks for transportation to the disposal facility. 14-11.08H Placement
Not Used
14-11.08I Surveying Burial Site
Not Used
14-11.08J Material Transportation
Before traveling on public roads outside the controlled access construction zone, remove loose and extraneous regulated material from outside surfaces of containers and the cargo areas of trucks. Place tarpaulins or other cover over the cargo as 511
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-140
described in the authorized excavation and transportation plan. You are responsible for costs due to spillage of regulated material during transport.
Transport excavated Type Z-2 material using:
1. Hazardous waste manifest
2. Hazardous waste transporter with a current DTSC registration certificate and CA Highway Patrol (CHP) Basic Inspection of Terminals (BIT) Program documentation with a satisfactory rating.
14-11.08K Disposal
14-11.08K(1) General
Laws and regulations that govern disposal of regulated material include:
1. Health & Safety Code § 25100 et seq
2. 22 CA Code of Regs § 66250 et seq
3. 8 CA Code of Regs
The Department does not pay for additional sampling and analysis required by disposal facilities.
14-11.08K(2) Type Com Material
Not Used
Add after the 2nd paragraph of section 14-11.12A:
This project includes removal of yellow thermoplastic traffic stripe that will produce hazardous waste residue.
Add after the 1st paragraph of 14-11.12E:
After the Engineer accepts the analytical test results, dispose of yellow thermoplastic and yellow paint hazardous waste residue at a Class 1 disposal facility located in California 30 days after accumulating 220 lb of residue.
If less than 220 lb of hazardous waste residue and dust is generated in total, dispose of it within 30 days after the start of accumulation of the residue.
Replace section 14-11.14 with:
14-11.14 TREATED WOOD WASTE
14-11.14A General
Section 14-11.14 applies if treated wood waste is shown on the Bid Item List. 512
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-141
Section 14-11.14 includes specifications for handling, storing, transporting, and disposing of treated wood waste. Manage treated wood waste under Health & Safety Code §25230 et seq.
Wood removed from roadside sign post is treated wood waste. 14-11.14B Submittals
Within 5 business days of disposing of treated wood waste, submit as an informational submittal a copy of each completed shipping record and weight receipt. 14-11.14C Training
Provide training to personnel who handle or may come in contact with treated wood waste. Training must include:
1. Requirements of 8 CA Code of Regs
2. Procedures for identifying and segregating treated wood waste
3. Safe handling practices
4. Requirements of Health & Safety Code §25230 et seq
5. Proper disposal methods
Maintain training records for 3 years after contract acceptance. 14-11.14D Storage of Treated Wood Waste
Store treated wood waste at the jobsite until transport to the CA permitted disposal site.
Until disposal, store treated wood waste using the following methods:
1. Raise the waste on blocks above a foreseeable run-on elevation and protect it from precipitation for no more than 90 days.
2. Place the waste on a containment surface or pad protected from run-on and precipitation for no more than 180 days.
3. Place the waste in water-resistant containers designed for shipping or solid waste collection for no more than 1 year.
4. Place the waste in a storage building as defined in Health & Safety Code §25230 et seq.
Prevent unauthorized access to treated wood waste using a secure enclosure such as a locked chain-link-fenced area or a lockable shipping container located within the job site.
Resize and segregate treated wood waste at a location where debris including sawdust and chips can be contained. Collect and manage the debris as treated wood waste.
Identify treated wood waste and accumulation areas using water-resistant labels that comply with Health & Safety Code §25230 et seq. Labels must include:
1. The words TREATED WOOD WASTE Do not burn or scavenge
2. The words Caltrans District and the district number
3. The words Construction Contract and the contract number 513
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-142
4. District office address
5. Engineer's name, address, and telephone number
6. Contractor's contact name, address, and telephone number
7. Date placed in storage
14-11.14E Transport and Disposal of Treated Wood Waste Dispose of treated wood waste within:
1. 90 days of generation if stored on blocks
2. 180 days of generation if stored on a containment surface or pad
3. 1 year of generation if stored in a water-resistant container or within 90 days after the container is full, whichever is shorter
4. 1 year of generation if stored in a storage building as defined in Health & Safety Code §25230 et seq
Before transporting treated wood waste, obtain agreement from the receiving facility that it will accept the waste. Protect shipments of the waste from loss and exposure to precipitation. For projects generating 10,000 lb or more of treated wood waste, request a generator's EPA Identification Number from the Engineer at least 5 business days before the 1st shipment. Each shipment must be accompanied by a shipping record such as a bill of lading or invoice that includes:
1. The words Caltrans District and the district number
2. The words Construction Contract and the contract number
3. District office address
4. Engineer's name, address, and telephone number
5. Contractor's name, contact person, and telephone number
6. Receiving facility's name and address
7. Description of the waste (e.g., treated wood waste with preservative type if known or unknown/mixture)
8. Project location
9. Estimated weight or volume of the shipment
10. Date accumulation begins
11. Date of transport
12. Name of transporter
13. Date of receipt by the treated wood waste facility
14. Weight of shipment measured by the receiving facility
15. Generator's US EPA Identification Number for projects generating 10,000 lb or more of treated wood waste
The shipping record must be 8-1/2 by 11 inches and a 4-part carbon or carbonless form to provide copies for the Engineer, transporter, and treated wood waste facility.
Transport treated wood waste directly to the CA permitted disposal site after leaving the jobsite. Do not mix treated wood waste from the job site with waste from any other generator.
514
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-143
Dispose of treated wood waste at one of the following:
1. An approved California disposal site operating under a RWQCB permit that includes acceptance of treated wood waste
2. California disposal site operating under a DTSC permit that includes acceptance of treated wood waste
Replace Reserved in Section 14-12.04 with:
14-12.04 CENTRAL COAST REGIONAL WATER QUALITY CONTROL BOARD All work performed within waters of the State must be completed in a manner that minimizes impacts to beneficial uses and habitat. Implement measures to minimize land disturbances that will adversely impact the water quality of waters of the State. Do not disturb or remove vegetation more than that necessary for completing the project.
Stabilize areas of the project below top of creek banks or in other waters of the State prior to October 31 of each year, either by completing construction of those areas of the project (including installation of permanent erosion control measures), or by implementing winterization stabilization measures to prevent erosion from a 10- year 24-hour storm event. Do not work below top of creek banks or in other waters of the State between October 31 and June 1 unless approved by the Engineer. Requests to conduct construction activities below top of creek banks or in other waters of the State during the winter period shall be submitted to the Engineer at least 25 days prior to the planned winter period work date. Discharges of stormwater from the job site must comply with the permit issued by the Central Coast RWQCB Water Quality Certification Number 34223WQ33. The Central Coast RWQCB permit governs stormwater and nonstormwater discharges resulting from construction activities at the job site. The Central Coast RWQCB permit may be viewed at 895 Aerovista Place, Suite 101, San Luis Obispo, CA 93401.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
15 EXISTING FACILITIES
Delete the 7th paragraph of section 15-1.03B.
Add to the end of Section 15-1.03C:
At least 2 business days before hauling the material to the salvaged material stockpile location, notify the Engineer and inform the district recycle coordinator.
The stockpile locations are as shown in the following table:
515
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-144
Stockpile Locations
Material Location
Caltrans signal and lighting
equipment
850 Elvee Drive
Salinas, CA 93901
City of Goleta signal and
lighting equipment
City Corporation Yard at 6735
Hollister Avenue, Goleta CA
93117
Replace Reserved in Section 15-1.03D with:
15-1.03D STRUCTURE DEMOLITION
15-1.03D(1) GENERAL
Section 15-1.03D includes general specification for removing structures as shown on the plans.
15-1.03D(1)(a) RELATED SPECIFICATION SECTIONS
Related sections are specified elsewhere in these specifications and in the standard specifications.
• Permits
• Submittals
• Public safety
• Preservation of existing facilities, including utilities • Materials
• Utilities
• Temporary facilities, such as fences, barricades, bracing, signs, warning lights, and other temporary safety measures
• Noise and Dust Control
• Water pollution control and job site management
• Clearing and grubbing, including removal of trees and vegetation • Hazardous materials and handling
• Excavation, grading, and backfill
• Removal of fences and gates
• Salvage materials
• Disposal of removed materials and debris
15-1.03D(1)(b) SCOPE OF WORK
Structure demolition, removal and site preparation shall include, but is not limited to demolition and disposal for all structures including foundations and interior utilities.
Perform demolition work in accordance with applicable City, County, State codes, laws, and regulations.
Demolition and Removal includes all elements within the public right of way and as designated on the plans to the satisfaction of the Engineer. 516
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-145
• Remove building, reservoirs, storage tanks, basement, floors, roofs, foundations, slabs, walks, carports, patios, driveways, out buildings, and all appurtenances. • Remove all fixtures, equipment, appliances, plumbing, furnishings, and all materials.
• Remove concrete, and asphalt concrete driveways and pavement. • Remove all trees, shrubs, stumps, and landscaped areas, including irrigation lines.
• Remove fences.
• Clear and grub to area designated on the plans and as directed by the Engineer. • After City has coordinated disconnection of utilities at mains with SCE, Water District, Sanitary Sewer District, and other utility companies, remove all utilities overhead or underground within demolition and cleared area to include electric, water, sewer, drainage, and others.
• Grade entire cleared area to elevations matching the surrounding area, and for proper drainage.
15-1.03D(1)(c) MATERIAL OWNERSHIP AND DISPOSAL
All demolished items shall become the Contractor’s property and shall be removed, recycled, abated, or disposed from the properties in an appropriate and legal manner.
Location of disposal site and length of haul shall be the Contractor’s responsibility.
Properly dispose of all debris, trash and building materials accordance with City, County, and State requirements. Properties shall be left clean of trash and debris when completed.
Burying of trash and debris on site will not be permitted. Burning of trash and debris at the site will not be permitted.
Remove trash and debris from the site at frequent intervals so that their presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
Provide a clean and orderly site at all times.
15-1.03D(2) MATERIALS
The use of explosives is prohibited in any work to be performed under this contract.
The use of a "Headache Ball" or other battering device on any building or structure shall not be permitted when such device will swing or will be over public right of way or adjacent private property or that through its use will cause building material particles to fall onto public right of way or adjacent private property.
15-1.03D(3) EXECUTION
15-1.03D(3)(a) EXAMINATIONS
Verity that all utilities have been located and marked. 517
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-146
Examine existing conditions and correlate with requirements indicated to determine extent of demolition required.
Contract documents may not represent all surface conditions at the site and adjoining areas.
The contractor, at its own discretion, shall retain a licensed and qualified civil or structural engineer to provide analysis, including calculations, necessary to ensure the safe execution of the demolition work.
15-1.03D(3)(b) PREPARATION, PERMITS AND SUBMITTALS
Obtain all permits and licenses and provide all notices required for performance and completion of the demolition and removal work, hauling, and disposal of debris.
Submit a comprehensive demolition plan, describing the proposed sequence, methods, and equipment for demolition, removal, and disposal of structures and other materials.
Do not proceed with work until the Engineer has approved the demolition plan.
Coordinate utility disconnections with Engineer to obtain severance certificates.
Services are not to be interrupted.
Perform visual surveys as the work progresses to detect hazards resulting from demolition activities.
Conduct demolition operations and remove construction and demolition materials to ensure minimum interferences with roads, streets, walks, and other adjacent occupied and utilized facilities.
Do not close or obstruct streets, walks or other adjacent occupied or utilized facilities without prior permission from the City or State.
15-1.03D(3)(c) DEMOLISH BUILDINGS AND STRUCTURES
It is Contractor responsibility to have full knowledge of the existing site and permits prior to commencing any hazardous material abatement or structure demolition.
Demolish all existing structures and foundations of any kind. Completely remove and dispose of debris from the demolition in accordance with these specifications and all applicable laws.
Capping, removal, or abandonment of unknown features such as wells and sewer septic systems (tanks and leachfield) is to be completed in accordance with these specifications and all applicable City, County, State guidelines, regulations and laws.
Before starting demolition of any building where utility connections exist, verify with the utility company that all such utility connections have been disconnected. However, this 518
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-147
shall not relieve the Contractor from the responsibility of complying with all code regulations or general practices as required by the City, County, State, or District having jurisdiction over such utility.
Demolish all utility infrastructure within the structures, public right of way and designated clearing area and as directed by the Engineer. All utilities shall be removed, demolished, or capped, and marked and stubbed out at the City right of way in a safe manner and to the satisfaction of the Engineer.
Cap and plug water and sanitary sewer in accordance with the utility owner’s standard details and instructions. Cap and plug pipe and other conduits abandoned due to demolition, with approved type caps and plugs as required by the utility owner.
Complete work at a safe distance, horizontally and vertically, to not encroach upon any adjacent overhead powerlines or other facilities. Protect active utilities indicated on plans and when not indicated on plans. If utility is damaged, immediately notify utility owner and Engineer for corrective action.
Backfill and compact depressions caused by excavations, demolition, and removal in accordance with applicable earthwork and grading requirements.
Remove existing pavements, concrete, structures, flatwork, and site improvements within the property to the satisfaction of the Engineer.
Prevent any foreign materials from entering the sewer, septic or storm drain laterals that will remain or be abandoned by others at a later date.
Implement dust and vapor control techniques at all times during the work to prevent the formation and migration of dust and vapors during the excavation and removal of debris at the work area.
Building concrete walls, columns, beams, and other structural elements shall be demolished and disposed of.
Patio covers, carports, stairs, block walls or decks that are attached to the structure shall be demolished and disposed of.
Basement concrete walls and concrete finish floor shall be considered as foundation and shall not be removed. Basements shall be filled with clean native soil to the surrounding existing grade. Fill material shall be imported and not be obtained from any project properties.
15-1.03D(4) PAYMENT
Payment for Remove Retaining Wall at the contract lump sum price shall include all labor, materials, tools, equipment, and incidentals for structure demolition, removal, clearing, disposal, grading, and completing all work per the requirements of these 519
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-148
specifications, state standard specifications and to the satisfaction of the Engineer. No additional compensation will be considered.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ 16 TEMPORARY FACILITIES
Add to Section 16-1.01:
All temporary shoring and bracing must be designed, stamped, and signed by a civil engineer
Replace Reserved in Section 16-1.04 with:
Any shoring or bracing required for your activities is included in the payment of various items of work and no separate payment will be made for shoring or bracing.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION III EARTHWORK AND LANDSCAPE
17 GENERAL
Replace the 4th paragraph in section 17-2.03A with:
Clear and grub vegetation only within the excavation and embankment slope lines. In areas of temporary disturbance, where vegetation must be removed, native trees and shrubs with a DBH of 3 inches or less shall be cut to ground level with hand operated power tools rather than by heavy equipment.
Vegetation removed from San Jose Creek shall not be stockpiled in the stream bed or on their banks.
Add to section 17-2.03B Clearing:
Within the limits of clearing, the areas below the natural ground surface shall be grubbed to a depth necessary to remove stumps, roots, buried logs, and other objectionable material. Underground structures, debris or waste including old piping, pavement, curb, gutter shall be removed if found on the Site. Objectionable material from the clearing and grubbing process shall be removed from the Site and wasted in approved safe locations.
All material that cannot be used as backfill on the site or at the landfill shall be properly disposed of at the Contractor’s expense.
Tree stumps and roots shall be removed to at least 3 feet below finished grade. It will also include removal of existing organics, rocks, or other unsuitable materials within existing planter strips before reconstructing sidewalk.
520
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-149
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
19 EARTHWORK
Add to Section 19-1.01:
19-1.01A(1) POTHOLE UTILITIES
Prior to construction, the Contractor shall contact Underground Service Alert (U.S.A.) to field locate and mark at the surface, existing utilities and utilities structures within the project area. The Contractor shall "pothole" existing underground utilities at any location where an existing utility may be in conflict with the proposed work. The pothole information shall be submitted to the engineer 40 working days after the Notice to Proceed. Submi t information a minimum of ten working days in advance of s tarting construction. Utility agencies shall be provided 72- hours’ notice prior to potholing their facilities to schedule field personnel to be onsite to observe and advise during potholing operations. If existing potholed utility information is shown on the Plans or provided in Supplemental Pr oject Information, the City makes no guarantee that the potholed underground utility remains at the same alignment and depth away from the pothole location.
At the pre-construction meeting, the Contractor shall submit a potholing plan and schedule showing the pothole locations. A maximum of five (5) working days will be required to review and provide the Contractor with comments on the plan and schedule. The Contractor shall revise the plan per the City's comments until the plan is accepted by the Engineer. The Contractor will not be allowed to begin work until the Engineer has accepted the traffic control plan.
A representative from the City shall be onsite during the pothole operations. The Contractor shall submit pothole and survey information to the Engineer as stated in these special provisions.
The following information shall be collected for each pothole:
1. Description of location, street name, stationing, offset, and alignment (e.g. parallel or perpendicular to pipeline)
2. Street structural section
3. Size and type of utility and utility owner, and
4. depth of utility infrastructure measured from finished grade to the top of utility.
5. Where duct banks or concrete encased utilities are encountered, the top and bottom depths from finished grade shall be collected and included with the above information.
In the event realignment of the proposed improvement is necessary because of conflicts, and the realignment materially changes the character of the planned work, the work can be performed at agreed lump sum, force account, or increases or decreases in the unit cost of the work per the provisions of Section 4- 1.05 and 8 -16 of the State Standard Specifications.
521
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-150
Backfilling of potholing excavations shall be per the provisions contained in the General Requirements of these Special Provisions and the requirements of the State Standard Specifications, City of Goleta Engineering Design Standards.
Potholing shall be performed such that the trench width does not exceed two and one- half feet (2.5’). Excavation exceeding 2.5 feet in width shall not be calculated in the volume computed for payment. Unless otherwise approved by the Engineer, the maximum trench length shall be six feet (6’).
PAYMENT
Full compensation for conforming to the requirements of this section shall be considered as included in the lump sum price paid for potholing for each Project Segment of Project Connect. This includes full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for performing all work necessary to complete this item in place including pavement cutting and removal, excavation, backfilling, and repaving or other surface restoration as specified in the Plans, these Special Provisions, the City of Goleta Engineering Design Standards, and as directed by the Engineer.
19-1.01A (2) UNMARKED UTILITIES
All utilities, abandoned or live, not shown on the Plans that cross the excavation but do not physically conflict with the installation of the subgrade items of the Bid Proposal shall be paid for under this item. A crossing shall be defined as any pipe, cable, conduit including signal and lighting, or duct structure that in the opinion of the Engineer crosses the excavation within 60 degrees of a line perpendicular to the excavation. If more than one utility crosses within a 15-inch-long section of the trench, then all the utilities in that cross section will be paid as one. Crossings that are more than 60 degrees from perpendicular, run parallel in the excavation, or physically conflict with the installation shall be paid for on a time and material basis in accordance with Section 9 of the State Standard.
The quantity shown in the Proposal for this item shall be considered approximate. No guarantee is made or implied that the quantity will not be reduced, increased, or deleted as may be required by the Engineer. This item has been included in anticipation of encountering unmarked utility crossings during construction. If no unmarked utility crossings are encountered, then this item will be deleted.
Full compensation for conforming to the requirements of this section shall be considered as included in the per each unmarked utility for each Project Segment of Project Connect. Payment shall be at the unit price bid per each unmarked utility crossing and shall include full compensation for furnishing all labor, materials, tools and equipment, and incidentals for performing all work necessary to excavate around and support existing utilities in place, pavement cutting and removal, excavation, backfilling and repaving or other surface restoration as specified Plans, these Special Provisions, the City of Goleta Engineering Design Standards, and as directed by the Engineer.
522
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-151
Add to the end of Section 19-1.03B:
19-1.03B UNSUITABLE MATERIAL
Should unsuitable material be encountered which, in the opinion of the Engineer, cannot be stabilized, the Contractor shall remove the unsuitable material to the dimensions and limits directed by the Engineer. The Contractor shall use extra care in excavating unsuitable materials so as not to aggravate the conditions. If, i n the opinion of the Engineer, the Contractor’s methods and equipment are increasing the amount of unsuitable materials to be excavated, the Engineer will require the Contractor to take necessary steps to correct the situation. Should the problem continue, the Contractor shall pay all costs beginning from the time correction steps were last implemented.
When unsuitable material is removed and disposed of, the resulting space shall be filled with material suitable for the planned use. The pay quantity for backfill shall be the same as that computed for unsuitable material excavation as specified herein. Unsuitable materials shall be removed from the job site and not incorporated into embankments.
Trench backfill shall consist of Class 2 Aggregate Base (AB) or job excavated, native soil meeting the requirements of Section 26-5 of the Standard Specifications. The use of the job excavated, native soil shall be at the Contractors risk. No additional compensation will be paid to the Contractor for hauling, stockpiling, drying, wetting or any processing of the native soil or AB required in order to achieve the minimum stability and relative compaction criteria.
The estimated quantity for Unsuitable Material is for bidding purposes only and an estimated 500 cubic yards has been included for each Project Section. The quantity can be extended, reduced, or deleted at the discretion of the Engineer, with no change in the unit bid price. If unsuitable material is discovered, the Contractor will notify the Engineer for approval of excavation and backfill. If the Engineer does not approve that the material is unsuitable prior to excavation and backfill, the Contractor will be responsible for the cost of excavation and backfill.
19-1.03B.1 PAYMENT
The contract unit price paid per cubic yard for Unsuitable Material shall include full compensation for furnishing all labor, materials, tools, equipment, excavation, backfill, aggregate base, compaction, removal and incidentals, and for doing all work inv olved in constructing Unsuitable Material, complete in place, as shown on the plans, as specified in the State Standard Specifications and these Special Provisions, and as directed by the Engineer and no additional compensation will be allowed therefor
Add to the end of section 19-3.01A:
Structure backfill includes constructing the geocomposite drain system. The systems must comply with section 68-7.
523
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-152
Replace section 19-3.03A with:
19-3.03A General
Where shown, remove material below the bottom of northern segment Retaining Wall No 1, No 3, and No.4 footings. Replace the material with Class 2 AB and compact it as specified for structure backfill in section 19-3.03E. The relative compaction must be at least 95 percent.
A relative compaction of at least 95 percent must be attained to at least 0.5 foot below the bottom of excavated unstable material at the locations shown in the following table:
Bridge name and
number
Abutment
number
Bent number
Northern
Segment
Retaining Wall
No. 1
N/A N/A
Northern
Segment
Retaining Wall
No. 3
N/A N/A
Northern
Segment
Retaining Wall
No. 4
N/A N/A
Add to the beginning of section 19-3.03B(1):
For footings at locations with structure excavation (Type D), ground or surface water is expected to be encountered but seal course concrete is not needed.
Add to section 19-3.04:
Structure excavation for footings at locations not shown as structure excavation (Type D) and where ground or surface water is encountered is paid for as structure excavation (bridge),or structure excavation (retaining wall).
Pervious backfill material placed within the limits of payment for bridges is paid for as structure backfill (bridge). Pervious backfill material placed within the limits of payment for retaining walls is paid for as structure backfill (retaining wall).
524
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-153
Add to the paragraph in section 19-5.03C:
At the following locations, compact earth to a relative compaction of at least 90 percent for a depth of at least 2.5 feet below the finished grade and a width of the traveled way plus 3 feet on each side:
1. Areas paved with pervious concrete pavement
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
21 EROSION CONTROL
Replace section 21-2.02K with:
21-2.02K Compost
Compost must be derived from one or a combination of the following types of materials:
1. Green material consisting of chipped, shredded, or ground vegetation or clean, processed, recycled wood products
2. Biosolids
3. Manure
4. Mixed food waste
Compost must not be derived from mixed municipal solid waste and must not contain paint, petroleum products, pesticides, or other chemical residues harmful to plant or animal life. Metal concentrations in compost must not exceed the maximum listed under 14 CA Code of Regs § 17868.2.
Process compost materials under 14 CA Code of Regs § 17868.3. 525
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-154
The particle size must comply with the requirements shown in the following table:
Compost Gradation
Quality characteristic Test methoda Requirement
Min Max
Gradation fine:(dry weight % passing)
1-inch sieve
3/8-inch sieve
TMECC
02.02-B
100
95 --
--
Gradation medium:(dry weight %
passing)
2-inch sieve
3/8-inch sieve
TMECC
02.02-B
95 40
--
55 Gradation coarse:(dry weight %
passing)
3-inch sieve
3/8-inch sieve
TMECC
02.02-B
95 25
--
35 a TMECC refers to Test Methods for the Examination of Composting and Compost, published by the United States Department of Agriculture and the United States Compost Council (USCC).
526
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-155
The quality characteristics of compost must have the values shown in the following table:
Compost
Quality characteristic Test methoda
Requirement
Fine Medium/Coars
e
pH TMECC 04.11-
A 6.5–7.5 6.5−7.5
Soluble salts (dS/m) TMECC 04.10-
A 0–10 0−10
Moisture content (% wet weight) TMECC 03.09-
A 25–60 25−60
Organic matter content (% dry
weight)
TMECC 05.07-
A 30–70 30−100
Maturity (seed emergence)
(% relative to positive control)
TMECC 05.05-
A 80 or above 80 or above
Maturity (seedling vigor)
(% relative to positive control)
TMECC 05.05-
A 80 or above 80 or above
Stability (mg CO2-C/g OM per
day)
TMECC 05.08-
B 5 or below 8 or below
Pathogen
Salmonella (most probable
number per 4 grams dry
weight basis)
TMECC 07.01-
B < 3 < 3
Pathogen
Fecal coliform (most probable
number per gram dry weight
basis)
TMECC 07.01-
B < 1,000 < 1,000
Physical contaminants (% dry
weight)
Plastic, glass, and metal
TMECC 02.02-
C
combined
total:
< 0.5
combined
total:
< 1.0
Film plastic (% dry weight) TMECC 02.02-
C
Combined
total:
< 0.1
Combined
total:
< 0.1
a TMECC refers to Test Methods for the Examination of Composting and Compost, published by the United States Department of Agriculture and the United States Compost Council (USCC).
Add to Section 21-2.02P:
Straw for fiber roll must be certified weed free under the Department of Food and Agriculture.
527
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-156
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION V SURFACINGS AND PAVEMENTS
39 ASPHALT CONCRETE
Replace section 39-2.01B(2)(b) with:
39-2.01B(2)(b) Hot Mix Asphalt Treatments
Determine the plasticity index of the aggregate blend under California Test 204. Use only the aggregate blend with plasticity index equal to or less than 10.
Treat aggregate with dry lime or lime slurry with marination.
Replace Reserved in section 39-2.02B(3) with:
The grade of asphalt binder for Type A HMA must be PG 64-10.
For Type A HMA using RAP substitution of greater than 15 percent of the aggregate blend, the virgin binder grade must comply with the PG binder grade specified above with 6 degrees C reduction in the upper and lower temperature classification.
For Type A HMA using RAP substitution of 15 percent or less of the aggregate blend, the grade of the virgin binder must comply with the PG binder grade specified above.
Add to section 39-2.03B(3)(a):
The grade of asphalt binder for RHMA-G must be PG 64-16.
Add to the table in the paragraph of section 39-2.03B(4)(a):
Coarse durability index, Dc (min)c AASHTO T 210 65
Fine durability index, Df, (min) AASHTO T 210 50
Sodium sulfate soundness (max loss @ 5
cycles, %)d AASHTO T 104 25
cThe test is required only if the aggregate source is in Lassen, Modoc, Siskiyou, or Shasta County.
dThe test is required only if the aggregate source is in Modoc, Siskiyou, or Shasta County.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
528
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-157
40 CONCRETE PAVEMENT
Replace section 40-8 with:
40-8 PERVIOUS CONCRETE PAVEMENT
40-8.01 GENERAL
40-8.01A Summary
Section 40-8 includes specifications for constructing pervious concrete pavement.
Section 40-1 does not apply.
40-8.01B Definitions
Not Used
40-8.01C Submittals
Submit test data supporting your minimum cementitious material determination. Using trial batches is recommended.
Submit documentation of certifications of pervious concrete placement crew members.
Submit cores.
40-8.01D Quality Assurance
40-8.01D(1) General
Not Used
40-8.01D(2) Test Panels
The Engineer uses authorized test panels as the standard when evaluating the texture and color of the pavement surface.
Before pervious concrete paving operation starts, construct test panels at the jobsite.
Use the materials, tools, equipment, personnel, and methods you will use in the work.
Construct at least 2 test panels. Each panel must be at least 225 sq ft. If joints are shown, construct the joints within each panel. Test panels must comply with the requirements for surface finish, void content, infiltration rate, thickness, and joints.
Take 3 core samples from each panel. The void content of each core must be within the specified range. Perform an infiltration rate test on each test panel.
If the Engineer rejects the test panels, construct new test panels.
Obtain authorization of the test panels before placing previous concrete pavement.
Remove and dispose of rejected test panels. Authorized test panels must remain in place until all pervious concrete pavement is completed. If authorized test panels are 529
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-158
not constructed within the limits shown for pervious concrete pavement, remove and dispose of the test panels.
40-8.01D(3) Prepaving Conference
Schedule a prepaving conference at a mutually agreed upon time and place to meet with the Engineer. Make the arrangements for the conference facility. Discuss methods of performing each item of the work.
Prepaving conference attendees must sign an attendance sheet provided by the Engineer. The prepaving conference must be attended by your:
1. Project superintendent
2. Pervious concrete construction foreman and your National Ready Mix Concrete Association (NRMCA) certified pervious concrete craftsman. If you do not employ a craftsman, your NRMCA certified pervious concrete installer must attend.
3. Earthwork construction foreman
4. Base construction foreman
5. Concrete quality control or technical services manager Do not start paving work until the listed personnel have attended the prepaving conference.
40-8.01D(4) Personnel Qualifications
The paving crew must possess a documented and verifiable experience of at least 3 qualified projects successfully completed within the past 5 years, and must comply with one of the following criteria:
6. Crew must employ 1 or more NRMCA certified pervious concrete craftsman who must be onsite actively working with and guiding the placement crew during pervious concrete placement.
7. Crew must employ 1 or more NRMCA certified pervious concrete installer who must be onsite actively working with and guiding the placement crew during pervious concrete placement.
8. Crew must employ 1 or more NRMCA certified pervious concrete installer and 1 or more NRMCA certified pervious concrete technician who must all be onsite actively working with and guiding the placement crew during pervious concrete placement.
40-8.01D(5) Plastic Concrete Testing
For each day of paving, test pervious concrete for unit weight under ASTM C1688 at least once for each 150 cu yd placed or fraction thereof. Unit weight must be within 5 lb/cu ft of the submitted mixture design.
40-8.01D(6) Cores
530
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-159
For each day of paving, core 3 samples for each 10,000 sq ft or fraction thereof. The Engineer determines coring locations.
40-8.01D(7) Void Content
The Department tests void content under section 90-7. The void content must be 20 percent or less.
40-8.01D(8) Infiltration Rate
Test the infiltration rate under ASTM C1701. Perform 3 tests in areas up to 25,000 sq ft. Conduct 1 test for each additional 10,000 sq ft. Separate each test locations by at least 20 feet. Do not perform tests (1) if there is standing water on the pavement surface or (2) less than 24 hours after 1/4 inch or more of rain. The infiltration rate must be at least 100 inches/hour.
40-8.02 MATERIALS
Comply with the specifications for pervious concrete in section 90-7.
The maximum size aggregate for the pavement surface must not exceed 1/2 inch. If the pavement is constructed in 2 or more layers, layers below the surface layer may have a larger maximum size aggregate.
Determine the minimum cementitious material content. The cementitious material content must not exceed 590 lb/cu yd.
Joint filler for isolation joints must (1) be preformed expansion joint filler for concrete, bituminous type, and (2) comply with ASTM D994.
40-8.03 CONSTRUCTION
40-8.03A General
Not Used
40-8.03B Subgrade Preparation
Immediately before placing pavement, grade and finish the subgrade. The subgrade must:
1. Comply with the specified compaction and grading
2. Be free of loose and extraneous material
3. Be uniformly moist and free of standing or flowing water The finished subgrade surface must not project into the pavement cross-section at any point. Verify the finished subgrade surface by:
1. Means of a template supported on the side forms for fixed form method
2. Measuring from the offset guide line or survey marks for extruded or slip form methods
531
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-160
Fill areas of subgrade lower than the required grade with pervious concrete pavement.
No paymen
made for pavement used to fill these low areas.
40-8.03C Paving
Place pervious concrete pavement under section 40-1.03F(1) except the 4th paragraph does not apply.
Spread, compact, and shape pervious concrete pavement under section 40-1.03F(4) or under section 40- 1.03F(5). Do not use vibrators. You may use wood side forms.
Compact pervious concrete to the required cross section. If you construct pervious concrete pavement in 2 or more layers, compact the lower layer before placing the next layer. Do not allow cold joints between layers. Compact within 30 minutes after spreading the pervious concrete. Do not disturb placed plastic concrete. Do not allow foot traffic on the un-compacted surface.
Use hand tampers to compact the concrete along the formed edges. After compaction and repair of surface flaws no further finishing is required.
If you delay placing 2 consecutive loads of pervious concrete by 20 minutes or more, form a construction joint. The joint must comply with section 40- 1.03B(2) except you must remove the bulkhead and dampen the face with an atomized spray when placement continues.
40-8.03D Joints
Construct contraction joints by scoring concrete with a grooving tool and rounding corners with an edger tool or by saw -cutting hardened concrete to a depth of at least 1/4 of the pavement depth.
Construct an isolation joint at pre-existing structures that abut or penetrate the pervious concrete area. The isolation joint must extend the full depth of the pervious concrete. Place and secure the isolation joint material before placing concrete.
40-8.03E Finishing
The finished surface must not vary more than 0.02 foot from a 12-foot straightedge except at grade changes.
If placing pavement around or adjacent to miscellaneous structures such as manholes or pipe inlets, do not finish the miscellaneous structures to final grade until the pavement is finished beyond the miscellaneous structure.
40-8.04 PAYMENT
Pervious concrete pavement is measured based on the dimensions shown.
Payment for preparing the subgrade is not included in the payment for pervious concrete pavement.
532
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-161
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION VI STRUCTURES
49 PILING
Add to section 49-1.03:
Expect difficult pile installation due to the conditions shown in the following table:
Location Conditions
RW No. 19
Groundwater or perched water, dense
sands, and caving and raveling soils
can be expected during construction.
Goleta POC
Groundwater or perched water, dense
sands, and caving and raveling soils
can be expected during construction.
Add to section 49-3.02B(6)(c):
The synthetic slurry must be one of the materials shown in the following table:
533
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-162
Material Manufacturer
SlurryPro CDP KB INTERNATIONAL LLC
735 BOARD ST STE 209
CHATTANOOGA TN 37402
(423) 266-6964
Super Mud PDS CO INC
105 W SHARP ST
EL DORADO AR 71731
(870) 863-5707
Shore Pac GCV CETCO CONSTRUCTION DRILLING
PRODUCTS
2870 FORBS AVE
HOFFMAN ESTATES IL 60192
(800) 527-9948
Terragel or
Novagel Polymer
GEO-TECH SERVICES LLC
220 N. ZAPATA HWY STE 11A-449A
LAREDO TX 78043
(210) 259-6386
BIG FOOT MATRIX CONSTRUCTION PRODUCTS
50 S MAIN ST STE 200
NAPERVILLE IL 60540
(877) 591-3137
POLY-BORE BAROID INDUSTRIAL DRILLING
PRODUCTS
3000 N SAM HOUSTON PKWY EAST
HOUSTON TX 77032
(877) 379-7412
Use synthetic slurries in compliance with the manufacturer's instructions. Synthetic slurries shown in the above table may not be appropriate for a given job site.
Synthetic slurries must comply with the Department's requirements for synthetic slurries to be included in the above table. The requirements are available from:
Offices of Structure Design
P.O. Box 168041
MS# 9-4/11G
Sacramento, CA 95816-8041
SlurryPro CDP synthetic slurry must comply with the requirements shown in the following table:
534
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-163
SlurryPro CDP
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
≤ 67.0a
Before final cleaning and immediately
before placing concrete (pcf)
≤ 64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 50–120
Before final cleaning and immediately
before placing concrete (sec/qt)
≤ 70
pH Glass electrode pH
meter or pH paper
6.0–11.5
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
535
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-164
Super Mud synthetic slurry must comply with the requirements shown in the following table:
Super Mud
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
≤ 64.0a
Before final cleaning and immediately
before placing concrete (pcf)
≤ 64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 32–60
Before final cleaning and immediately
before placing concrete (sec/qt)
≤ 60
pH Glass electrode pH
meter or pH paper
8.0–10.0
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
536
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-165
Shore Pac GCV synthetic slurry must comply with the requirements shown in the following table:
Shore Pac GCV
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
≤ 64.0a
Before final cleaning and immediately
before placing concrete (pcf)
≤ 64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 33–74
Before final cleaning and immediately
before placing concrete (sec/qt)
≤ 57
pH Glass electrode pH
meter or pH paper
8.0–11.0
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
537
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-166
Terragel or Novagel Polymer synthetic slurry must comply with the requirements shown in the following table:
Terragel or Novagel Polymer
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
≤ 67.0a
Before final cleaning and immediately
before placing concrete (pcf)
≤ 64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 45–104
Before final cleaning and immediately
before placing concrete (sec/qt)
≤ 104
pH Glass electrode pH
meter or pH paper
6.0–11.5
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
538
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-167
BIG-FOOT synthetic slurry must comply with the requirements shown in the following table:
BIG-FOOT
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
≤ 64.0a
Before final cleaning and immediately
before placing concrete (pcf)
≤ 64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 30–125
Before final cleaning and immediately
before placing concrete (sec/qt)
55-114
pH Glass electrode pH
meter or pH paper
8.5–10.5
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
POLY-BORE synthetic slurry must comply with the requirements shown in the following table:
539
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-168
POLY-BORE
Quality characteristic Test method Requirement
Density: Mud weight (density),
API RP 13B-1,
section 5
During drilling (pcf)
62.8-65.8a
Before final cleaning and immediately
before placing concrete (pcf)
62.8-64.0a
Viscosity: Marsh funnel and cup,
API RP 13B-1, section
7.2 During drilling (sec/qt) 50–80
Before final cleaning and immediately
before placing concrete (sec/qt)
50-80
pH Glass electrode pH
meter or pH paper
7.0–10.0
Sand content, percent by volume: Sand,
API RP 13B-1, section
10 Before final cleaning and immediately
before placing concrete (%)
≤ 1.0
NOTE: Slurry temperature must be at least 40 °F when tested. aIf authorized, you may use slurry in a salt water environment. The allowable density of slurry in a salt water environment may be increased by 2 pcf.
Add to section 49-3.02C(1):
If the piling center-to-center spacing is less than 4 pile diameters, do not drill holes or drive casing for an adjacent pile until 24 hours have elapsed after concrete placement in the preceding pile and your prequalification test results for the concrete mix design show that the concrete will attain at least 1800 psi compressive strength at the time of drilling or driving.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
51 CONCRETE STRUCTURES
Add to section 51-1.01C(1):
If the methacrylate crack treatment is applied to a bridge deck or box culvert within 100 feet of a residence, business, or public space, submit a public safety plan. Include with the submittal:
1. Copy of public notification letter with a list of delivery addresses and posting locations. The letter must describe the work to be performed and state the treatment work locations, dates, and times. Deliver copies of the letter to residences and businesses within 100 feet of the treatment work and to local fire and police officials, 540
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-169
at least 7 days before starting treatment activities. Post a copy of the letter at the job site.
2. Airborne emissions monitoring plan. Plan must include monitoring point locations. A CIH certified in comprehensive practice by the American Board of Industrial Hygiene must prepare and execute the plan.
3. Action plan for protecting the public if levels of airborne emissions exceed permissible levels.
4. Copy of the CIH's certification.
After completing methacrylate crack treatment activities, submit results from monitoring production airborne emissions as an informational submittal.
Replace the 2nd paragraph of section 51-1.01C(1) with:
Submit a deck placement plan for concrete bridge decks and box culvert top slabs.
Include in the placement plan your method and equipment for ensuring that the concrete bridge deck and box culvert top slab is kept damp by misting immediately after finishing the concrete surface.
Add to section 51-1.03G(1):
The concrete barrier type 85A (Mod) concrete surface textures must match the texture, color, and pattern of the San Jose Creek Bridge (Br. No. 51-0162).
Replace Reserved in section 51-3.02D with:
The cubic yard price paid for Structural Concrete Bridge includes the costs to provide all materials, labor, equipment, tools, and incidentals needed to furnish and install the elastomeric bearing pads complete and in place as shown on the plans. No additional compensation will be allowed therefor
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
52 REINFORCEMENT
Add to section 52-2.01A(3):
52-2.01A(3)(c) Certificates
Submit a certificate of compliance for each shipment of dual-coated bar reinforcing steel. Include the following with the submittal:
1. Certification that the reinforcement complies with ASTM A1055
2. All certifications specified in ASTM A1055
541
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-170
Add to section 52-2.01B:
You may use dual-coated bar reinforcing steel complying with ASTM A1055 as an alternative to epoxy-coated reinforcement or epoxy-coated prefabricated reinforcement.
Bar reinforcing steel to be dual-coated must be deformed, Grade 60 bars complying with ASTM A706.
Dual-coated bar reinforcement must be the same bar size and must be placed at the same spacing as described for epoxy-coated reinforcement and epoxy-coated prefabricated reinforcement.
Add to section 52-2.01C:
Do not bend bar reinforcing steel complying with ASTM A1055 after coating application if used as an alternative to epoxy coated prefabricated reinforcement.
Job site and PC plant practices for substituted bar reinforcement must comply with appendix X1 of ASTM A1055, except replace "should" with "must." Add to section 52-2.03A(1):
Epoxy coat reinforcement at the following locations:
1. Where shown
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION VIII MISCELLANEOUS CONSTRUCTION
75 MISCELLANEOUS METAL
Add to the end of the table in section 75-1.02A:
Material Requirement
Ductile iron castings (MISO drain grate) ASTM A536, Grade 65-45-12
Add to section 75-3.04:
The price paid per pound for Bridge Deck Drainage System includes the costs to provide all materials, labor, equipment, tools, and incidentals needed to furnish and install the drainage outlets as shown.
542
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-171
Add to section 75-3.04:
The price paid per pound for Bridge Deck Drainage System includes the costs to provide all materials, labor, equipment, tools, and incidentals needed to furnish and install the drainage systems on Retaining Wall No. 3 as shown.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
78 INCIDENTAL CONSTRUCTION
Add to section 78-4.04A(1):
The application of a sealer to the stained surfaces is not required.
Add to the end of section 78-4.04B(2)(a):
The stain must be a water-based stain.
Add to the beginning of section 78-4.04C(3)(a):
For the concrete barriers as shown, stain the surfaces such that they closely resemble the colors,
mottling, shades, flecking and veining of the San Jose Creek Bridge (Bridge No. 51- 0362).
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
80 FENCES
Replace section 80-5 with:
80-5 WOOD RAIL FENCE
80-5.01A General
80-5.01A Summary
Section 80-5 includes specifications for constructing wood rail fence. 80-5.02 Materials
Minor concrete must comply with section 90-2.
Wood posts, pickets, rails and boards must be:
1. T reated per section 80-2.02C(3) Treated
2. Cut from sound timber
543
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-172
3. Straight and free from loose or unsound knots, shakes over 1/3 the post thickness, splits longer than the thickness of the post, or other defects that would make it unfit structurally for the intended purpose.
Post knots must be sound, tight, well-spaced, and not over 2-inches in size on any face.
Sweep must not exceed 0.08 foot in 6 feet.
Nails must be size 10d hot-dipped galvanized aluminum or stainless steel.
Wood rail must be nailed with at least four 10d nails per connection. 80-5.03 Construction
Fence posts must be spaced at the intervals and set to the depths as shown. 80-5.04 Payment
Not Used
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION IX TRAFFIC CONTROL DEVICES
82 SIGNS AND MARKERS
Replace the 2nd paragraph of section 82-3.04 with:
The payment quantity for barrier mounted sign (Type 85A (Mod)) and barrier mounted sign (Concrete Barrier (Type 60MP)) is paid per each. Payment per each barrier mounted sign (Type 85A(Mod)) and barrier mounted sign (Concrete Barrier (Type 60MP)) includes furnishing and installing the barrier mounted signs as shown including drill and bond (chemical adhesive), pipe posts, base plates, anchorage assemblies, and other metal parts used to mount the roadside sign on the barrier or railing.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
83 RAILINGS AND BARRIERS
Replace section 83-2.01B with:
83-2.01B VEGETATION CONTROL (CRUSHED SHALE)
83-2.01B(1) General
Section 83-2.01B includes specifications for constructing vegetation control areas around existing and/or new metal beam guardrail and thrie beam barrier posts using crushed shale.
544
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-173
83-2.01B(2) Submittals
Submit the following:
1. Ten-pound sample of the crushed shale.
83-2.01B(3) MATERIALS
83-2.01B(3)(a) Soil Sterilant
Do not use soil sterilant.
83-2.01B(3)(b) Filter Fabric
Do Not use filter fabric.
83-2.01B(3)(c) Fasteners
Do not use fasteners.
83-2.01B(3)(d) Crushed Shale
Crushed shale must:
1. Consist of light beige to dark brown colors.
2. Comply with the following grading requirements:
Gradation Requirements
Sieve size Percentage
passing
2" 100
1" 75–100
3/4" 65–100
No. 4 35–60
No. 30 10–35
No. 200 4–15
83-2.01B(4) CONSTRUCTION
83-2.01B(4)(a) General
Areas to receive vegetation control must be cleared of vegetation, trash, and debris.
Dispose of removed material.
83-2.01B(4)(b) Earthwork
Excavate areas to receive vegetation control. Where vegetation control abuts the existing surfacing, the edge of the existing surfacing must be on a neat line or must be cut on a neat line to a minimum depth of 3 inches before removing the surfacing. The finished elevation of the excavated area to receive vegetation control must maintain planned flow lines, slope gradients, and contours of the job site. 545
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-174
Grade areas to receive vegetation control to a smooth, uniform surface and compact to a relative compaction of not less than 95 percent.
Dispose of surplus excavated material uniformly along the adjacent roadway except as specified in section 14-11.
83-2.01B(4)(c) Treatment of Soil
Not used
83-2.01B(4)(d) Filter Fabric
Not used.
83-2.01B(4)(e) Crushed Shale
Place crushed shale and compact by mechanical compaction. The finished crushed shale surface must be smooth and uniform, maintaining original flow lines, slope gradients, and contours of the job site.
Replace item 1 in the list in the 2nd paragraph of section 83-2.02C(1)(a) with:
1. Steel line posts.
Replace item 2 in the list in the 2nd paragraph of section 83-2.02C(1)(a) with:
2. Recycled plastic blocks.
Add to section 83-2.02C(1)(a):
The exposed bolt threads on guardrail beyond the nut that are more than 0.5 inch must be cut off.
Add to section 83-2.08A(1):
For Concrete Barrier Type 85A (Mod) tubular bicycle railing (modified) includes the upper and lower tubular bicycle railing.
Drill and bond anchors under the specifications for drilling and bonding dowel chemical adhesive in section 51-1.
Drill and bond threaded rods under the specifications for drilling and bonding dowels in section 51.
Powder coated surfaces where shown must comply with section 83-2.10.
Replace Not Used in section 83-2.08D with:
The payment quantity for tubular bicycle railing (modified) is the length measured from end to end along the face of the upper tubular bicycle railing, including intermediate posts.
546
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-175
Replace section 83-2.10 with:
83-2.10 PEDESTRIAN RAILING
83-2.10A General
83-2.10A(1) Summary
Section 83-2.10 includes specifications for constructing decorative railing.
Decorative railing work includes metal railing with a decorative motif.
Galvanize all decorative railing components. Apply final coating system to decorative railing components as specified herein.
83-2.10A(2) Definitions
Not Used
83-2.10A(3) Submittals
83-2.10A(3)(a) General
Not Used
83-2.10A(3)(b) Certificate of Compliance
Submit a certificate of compliance for each shipment of powder coated material. Include with the submittal:
1. Application instructions
2. Manufacturer’s descriptive data which include complete description, performance data, and installation instruction for the materials
83-2.10A(3)(c) Test Samples
Before fabrication, submit an 8 by 8 inch powder coated decorative panel sample with the color finish applied for authorization.
Test samples must be:
1. Steel panel with the entire powder coating system applied
2. Constructed at an authorized location
3. Constructed and finished using the personnel, materials, equipment, and methods to be used in the work
4. Authorized before starting work
83-2.10A(3)(d) Shop Drawings
Submit 7 copies of shop drawings for the decorative railing.
The shop drawings must include:
1. Details for venting holes in rails, posts, and sleeves
2. Railing layout
3. Complete details for the construction of the work including methods of construction, sequence of shop and field assembly, galvanization, powder coating, painting, and installation procedures.
547
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-176
Allow 25 days for review. Upon authorization, the Engineer returns 2 copies to you for use during construction.
83-2.10A(4) Quality Assurance
Not Used
83-2.10B Materials
83-2.10B(1) General
The tubing, plates, bars, splice sleeves, bolts, threaded rods, nuts and washers must comply with section 83-2.08B.
83-2.10B(2) Powder Coated Surfaces
Where powder coating is shown, prepare the surface of the galvanized elements under the powder coat manufacturer’s written instructions.
The minimum total dry film thickness of the primer, fluoropolymer powder coat, and the anti-graffiti coating is 2 mils.
Powder coat must be a fluoropolymer type, having the color retention and chalk resistance typical of American Architectural Manufacturers Association Publication 2605. Use a primer recommended by the manufacturer of the powder coat to obtain the following requirements:
Quality Characteristic Test Method Requirement
Adhesion to galvanized
surface, min
ASTM D 3359, test method
B
5B
Hardness, min ASTM D 3363 H
Salt fog resistance, 4000
hrs
ASTM B 117 Scribe, >7
Impact resistance, 80 in-lb ASTM D 2794 Pass
The color of powder coating must match the railing color of the San Jose Creek Bridge (bridge no. 51-0362).
Finished surfaces must be smooth and uniform without drips, runs, uneven coloration, pin holes, dust particles or bubbles, must be free from buckles, warps, dents, cockles, burrs, and other defects resulting from fabrication.
83-2.10C Construction
Decorative railing must present a smooth, uniform appearance in its final position, conforming closely to the horizontal and vertical lines shown or ordered.
Before the decorative railing parts are assembled, gently clean the bearing surfaces and surfaces to be in permanent contact without damaging the powder coating. If the railing 548
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-177
is mounted on a concrete surface, the post bases must be true and flat to provide uniform bearing.
Carefully handle the materials such that no parts are bent, broken, abraded, or otherwise damaged. Do not use manufacturing, handling, or installation methods that damage or distort the members or damage the galvanization, powder coating, paint or vinyl coating.
Erect railing carefully and true to line and grade. Posts must be normal to the profile grade. Transverse to the profile grade, railings must be plumb within a tolerance not to exceed 0.02 foot in 10 feet. Adjacent rail elements must align with each other within 1/16 inch.
After the cleaning, painting, and powder coating processes, protect all the components from exposure to grease, oils, dust, and contaminants.
Handle painted and powder coated elements to prevent damage during shipping and installation. Repair damage to:
1. Galvanizing under section 75-1.02B
2. Paint under section 59-3
3. Powder coat with a liquid recommended by the manufacturer of the powder coat in compliance with the authorized shop drawings.
If the damage to the powder coat is visible to the public and is greater than 2 percent of the total area of any individual element, then that element will be rejected, and you must reapply the powder coat. The Engineer determines the acceptability of powder coated elements.
83-2.10D Payment
Not Used
Add to section 83-3.01A:
Random cobble stone and wood grain textures must comply with section 51-1.03G.
Add to the end of the list in the 4th paragraph of section 83-3.01A:
4. Pedestal concrete for barrier mounted sign (Type 85A(Mod))
5. Bar reinforcing steel, including the length that extends from the pedestal into the Concrete Barrier (Type 85A(Mod)).
Add to section 83-3.01C:
For a tubular bicycle railing (modified) on a Type 85A (Mod) and Type 85B (Mod) concrete barrier, submit 2 copies of the threaded rod layouts before placing the barrier reinforcement.
549
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-178
Add to section 83-3.02C:
Bar reinforcing steel for concrete barriers must be epoxy coated under section 52-2.03.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION X ELECTRICAL WORK
86 GENERAL
Add to the list in the 2nd paragraph of section 86-1.02C(1):
15. CITY on pull box cover for City lighting system
Replace the 4th paragraph of section 86-1.02F(1) with:
Conductors must be copper.
Replace the 2nd paragraph of section 86-1.02F(2)(c)(ii) with:
An equipment grounding conductor must be bare.
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
87 ELECTRICAL SYSTEMS
Add to the beginning of section 87-1.03B(3)(a):
Use Type 3 conduit for underground installation.
Use Type 3, Schedule 80 conduit in a foundation; and between a foundation and the nearest pull box.
Use Type 1 conduit for structure and surface-mounted installation.
Replace the 3rd paragraph of section 87-1.03C(2)(a) with:
Install a pull box on a bed of crushed rock.
Replace the 2nd paragraph of section 87-1.03H(2) with:
Use Method B to insulate a splice.
550
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-179
Add to the end section 87-1.03T:
A manufacturer's representative must program the accessible pedestrian signals with messages at:
1. South Kellogg Avenue
A manufacturer's representative must program the accessible pedestrian signals for a mid-block crosswalk with the message <South Kellogg Avenue> Cross with Caution.
Add to Section 87-9
87-9 RECTANGULAR RAPID FLASHING BECAONS SYSTEM
87-9.01 GENERAL
87-9.01A Summary
Section 87-9 include specifications for constructing rectangular rapid flashing beacons (RRFB) system.
A rectangular rapid flashing beacons system include:
1. Foundations
2. Standards
3. Conductors and cables
4. Light indicators
5. Signs
6. Solar engines
7. Accessible pedestrian signals
Rectangular rapid flashing beacons (RRFB) system must conform to the latest applicable provisions of the California MUTCD, and the latest State Standard Specifications and Plans, and the project plans and these Special Provisions.
RRFB system must be Carmanah R920F series or approved equal. 87-9.01B Submittal
Submit 2 copies of:
1. 5- year limited warranty document.
2. Shop drawings or installation manual.
87-9.02 MATERIAL
87-9.02A Light Indications
Each indication must be a minimum size of approximately 7” wide x 3” high.
The light intensity of the indications must meet the minimum specifications of the Society of Automotive Engineers (SAE) standard J595 (Directional Flashing Optical 551
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-180
Warning Devices for Authorized Emergency, Maintenance, and Service Vehicles) dated January 2005. Contractor must furnish a Certificate of Compliance for this standard.
Specifically, the certificate should state that the indications: “Meet photometry of jurisdictional compliance standard(s) identical to: 2 J595 Class 2 Nov08 Yellow Peak Cd and 2 J595 Class 1 Nov08 Yellow Cds/Min.
All exposed hardware must be anti-vandal.
87-9.02B Sign
All sign panels must be supplied and installed as part of this bid item. 87-9.02C Solar Engine
Solar engine must include:
1. On-broad user interface
2. Solar panel
3. Wireless radio
4. Batteries.
5. Enclosure
87-9.02C(1) On-Broad User Interface:
On-Board User Interface must:
1. Be adjustable system settings with auto-scrolling LED display on our latest EMS
2. Have system test, status, and fault detection: battery, solar, button beacon, radio, day/night
3. Flash patterns: RFB1 (WW+S), RFB2 (WSDOT), 0.5 sec alternating (MUTCD), 0.5 sec unison (MUTCD), 0.1 sec. unison, 0.25 sec. unison, 0.1 sec x3 quick flashes unison, 0.1 sec, x3 quick flashes alternating
4. Have input: momentary for push button activation, normally open switch, normally closed switch
5. Have flash duration: 5 sec. to 1 hr.
6. Have intensity setting: 20 to 1400 mA for multiple RRFBs, circular beacons, or LED enhanced signs
7. Have nighttime dimming: 10 to 100% of daytime intensity
8. Have ambient auto adjust: increases intensity during bright daytime
9. Have automatic Light Control: reduces intensity if the battery is extremely low
10. Be temperature correction: yellow or red beacons
11. Have internal time clock function
12. Have radio settings: enable/disable, selectable channel from 1 to 14
13. Have output: enabled when beacons flashing daytime and nighttime, or nighttime only
14. Be activation counts and data reporting via OBUI or optional USB connection
552
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-181
87-9.02C(2) Solar panel
The solar panel must be size according to the weather and field conditions to maximize performance.
All fasteners used must be anti-vandal.
All solar panel connectors must be dust proof, and protected from temporary immersion in water.
87-9.02C(4) Wireless Radio
Radio must integrate with communication of RRFB system control circuit to activate light indications from pushbutton input.
The radio must synchronize all of the remote light indications so they will turn on within 120msec of each other and remain synchronized through-out the duration of the flashing cycle.
Radio systems must operate from 3.6vdc to 15vdc.
87-9.02C(5) Battery
Battery unit must be rated for operation in northern climates and capable of between 200-500 daily actuations.
All batteries must be sealed in a plastic film to provide moisture corrosion resistance.
All batteries must operate between the temperatures of -20°C to +60°C.
All battery connectors must be dust proof, and protected from temporary immersion in water.
87-9.02C(6) Enclosure
Solar engine enclosure must be:
1. NEMA 3R weather proof enclosure.
2. Lockable with hinged lid for access to on-broad user interface and batteries.
3. Corrosion -resistant aluminum with stainless steel hardware.
4. Prewired to minimize installation time.
5. High efficiency optics and EMS.
6. 39 lbs or less including on-broad user interface and batteries.
87-9.02D Accessible Pedestrian Signal
The accessible pedestrian signal (APS) must conform to the latest applicable provisions of the California MUTCD, and these special provisions. The APS must be supplied by the same manufacturer of RRFB and must be furnish and installed as one package.
The accessible pedestrian signal (APS) shall be an 6-wire pushbutton type system and conform to the latest applicable provisions of the California MUTCD, and these special 553
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-182
provisions. The APS shall be from the same manufacturer of RRFB and shall be furnish and installed as one package.
A. The housing for the unit shall be 5”x14” and made of 356 aluminum heat-treated to meet Spec. T-6. The chassis is made from plastic. It shall be of a telescoping, vandal-proof design. The color shall be yellow. Adaptors may be required to install the pushbutton housing and the sign plate. The PPB shall be installed right side up.
B. The Push Button Stations (PBS) shall provide information and cues via both a vibrating arrow button and audible message saying “CROSS STREET WITH CAUTION, VEHICLES MAY NOT STOP” multiple times during 20 second interval when the RRFB is flashing. All sounds shall emanate from the back of the unit. The weather-proof speaker shall be protected by a vandal resistant screen. A pushbutton LED will flash when the RRFB indications are active. PBS shall include frame, sign, ADA compliant push button and mounting hardware.
C. By interfacing with the Control Unit that is installed in the pedestrian signal indication housing, the PBS shall provide the following standard features. • Confirmation of button push via latching LED, sound, and vibrotactile bounce. • Direction of travel (with extended button push).
• Standard voice messaging in English.
• Standard locating tone.
• All sounds automatically adjust to ambient over 60dB range. • All sounds shall be synchronized/
• Extended button push shall turn on and/or boost volumes.
D. The button should be located within five (5) feet of the crosswalk line, and mounted at a height of 42” above the finished grade.
E. The pedestrian instruction sign shall be R10-25 or otherwise noted on the plans and installed with security screws. The security screws shall be stainless steel, button head socket cap screws #8 diameter, 3/8 inch in length and 32 threads per inch. The socket shall be 3/32 inch Allen. The sign shall be integral with each pedestrian pushbutton.
The duration of a predetermined period of operation of the RRFB followings each actuation should be based on the MUTCD procedure for timing of pedestrian clearance times for pedestrian signals.
87-9.03 CONSTRUCTION
87-9.03A Light Indications
Two indications must be installed on an assembly facing each direction of approaching vehicular traffic. The two indications must be aligned horizontally, with the longer dimension of the indication horizontal, and a minimum space between the two indications of approximately 7” measured from inside edge of one indication to inside edge of second indication.
554
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-183
A single indication must be installed on an assembly facing in the direction of approaching pedestrian traffic to serve as a confirmation for the pedestrian that the system has been activated.
The outside edges of the two indications, including any housing, must not protrude beyond the outside edges of the integral signage of the assembly.
Each indication must be located between the bottom of the crossing warning sign and the top of the supplemental downward diagonal arrow plaque. 87-9.03B Solar panels
The solar engineer panel must be mounted to an aluminum plate and bracket at an angle of 45° - 60°.
87-9.04 PAYMENT
Not Used.
Add to the end of section 87-21.03C:
Modifying a lighting system includes removing, adjusting, or adding:
1. Foundations
2. Pull boxes
3. Conduit
4. Conductors
5. Standards
6. Luminaires
7. Fuse splice connectors
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
DIVISION XI MATERIALS
90 CONCRETE
Add to section 90-1.02H:
Concrete at the following locations are in a corrosive environment.
1. RW-19
2. Barriers
For concrete at:
1. RW-19
2. Barriers
555
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-184
the ratio of the quantity of free water to the quantity of cementitious material must not exceed 0.40.
Replace "Reserved" in section 90-
7 with:
90-7 PERVIOUS CONCRETE
90-7.01 GENERAL
90-7.01A Summary
Section 90-7 includes specifications for furnishing and curing pervious concrete.
Pervious concrete must comply with the specifications for minor concrete, except that section 90-2.02B does not apply.
90-7.01B Definitions
Not Used
90-7.01C Submittals
Before starting pervious concrete work, submit:
9. Test results for the void content of hardened concrete. Calculate void content under 90-7.01D(3).
10. Test results for the void content of fresh concrete under ASTM C 1688/C 1688M.
90-7.01D Quality Control and
Assurance 90-7.01D(1) General
Not Used
90-7.01D(2) Penetration
The specifications for penetration in section 90-1.02G(6) do not apply to pervious concrete.
90-7.01D(3) Void Content
The Engineer calculates void content of a core specimen using the following equation:
V= 100 - [(Ws-Wi) x 4 x F/(H x D² x Pi)] x 100
where:
V = void content, percent
Ws = saturated weight of the core under ASTM C
140, lb or g Wi = immersed weight of the core
under ASTM C 140, lb or g
F = 27.69 if measurements are in pounds and inches, 1000 if measurements are in grams and mm H = height of the core, inches or mm
556
SAN JOSE CREEK MULITPURPOSE PATH – NORTHERN AND SOUTHERN SEGEMENTS CITY PROJECT NO. 9006, FEDERAL AID PROJECT BRLS-5481(022) SP-185
D = diameter of the core,
inches or mm Pi = 3.14159
Dimensions D and H are measured with calipers to the nearest 0.02 inch or 0.5 mm.
90-7.02 MATERIALS
If you determine the minimum cementitious material content to be less than 425 lb/cu yd, replace Equation 2 in 90-1.02B(3) with:
(425 - MSCM - PC) ≥
0 Choose a combined aggregate grading such that 100 percent of the aggregate passes the maximum specified size sieve and the resulting concrete complies with the specified void content.
The mixing time in a stationary mixer must be at least 90 seconds.
Transport mixed concrete to the delivery point in a truck mixer operating at the manufacturer's designated agitating speed. Discharge pervious concrete from the truck mixer within 60 minutes of batching. If you use a hydration stabilizer, an additional 60 minutes is allowed.
90-7.03 CONSTRUCTION
Place pervious concrete when the air temperature is above 40 degrees F. After placement, do not allow the pervious concrete surface to dry. Cure pervious concrete under section 90-1.03B(4) except keep the membrane in place at least 168 hours. Do not use unconfined soil to secure the membrane. During the cure period, check the concrete daily and ensure:
4. Membrane is not displaced or damaged
5. Moisture is condensed under the membrane
Immediately repair any damaged membrane and replace any displaced membrane. If there is no condensation, place 1.5 gallons of water per square yard of concrete surface under the membrane.
90-7.04 PAYMENT
Not Used
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
557
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX A
CITY OF GOLETA
APPENDIX A
MISCELLANEOUS FORMS AND
DOCUMENTS
FOR
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
1. LAPM Exhibit 16A Weekly Statement of Working Days
2. City of Goleta Monthly Project Payment Estimate Forms
3. Post-Construction Waste Reduction & Recycling
Summary Report
4. Notice Regarding Assembly Bill 626
5. Maintenance Bond Guarantee and Warranty Security
6. Sample Door Hanger
558
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX A
Back of Cover Sheet
559
I
Local Assistance Procedures Manual Exhibit 16-A
Weekly Statement of Working Days
Exhibit 16-A:
WEEKLY STATEMENT OF WORKING DAYS
JOB STAMP
REPORT NUMBER:
CONTRACTOR: WEEK ENDING (month, day, year):
Date
(A)
Day
(B)
Weather Conditions or Other Explanation1
(C)
Working Day
(D)
Nonworking Day
(E)
Working Day No Work Done
on Controlling Activity
6 (F)
1 2
Monday
3 Tuesday
4 Wednesday
5 Thursday
6 Friday
7 8 Days this week (total lines 1D thru 7D)
9 Days previously reported (take from previous week’s report) 10 Total working days to date (lines 8D + 9D)
Change Order Time Adjustments Change Order
Days Approved Change Order Numbers2
11 12
Days this report
Days previously reported (taken from previous week’s report) 13 Total change order days to date (lines 11D + 12D)
Computation of Extended Date for Completion Number of
Days Numbered Day4 Date
14 First working day
15 Original working days specified in contract
16 COMPUTED DATE FOR COMPLETION (line 14E + line 15D minus 1) 17 Total change order days approved to date (from line 13) 18 Total Nonworking days to date 3 (from box 10E)
19 EXTENDED DATE FOR COMPLETION (line 16E + line 17D + line 18D) 20 Revised working days for contract (line 15D + line 17D) 21 Total working days to date (from box 10D)
22 WORKING DAYS REMAINING (line 20D – line 21D)
CONTROLLING ACTIVITY(IES) 5 :
REMARKS:
The contractor will be allowed fifteen (15) days in which to protest in writing the correctness of the statement; otherwise, the statement shall be deemed to have been accepted by the contractor as correct.
NOTE: Footnote Instructions to Resident Engineer are on page 2.
RESIDENT ENGINEER SIGNATURE:
DATE:
Distribution: Original -- Contractor; Copy -- Resident Engineer
August 2021
560
Local Assistance Procedures Manual Exhibit 16-A
Weekly Statement of Working Days
Exhibit 16-A: WEEKLY STATEMENT OF WORKING DAYS
FOOTNOTE INSTRUCTIONS TO RESIDENT ENGINEER
1. When determining if the day is a working day or non-working day, first determine the controlling operation (taken from the critical path of the updated approved project schedule.), second, If you determine the day is a "nonworking day", provide the contractual reason -for example, "clear-wet grade" to describe conditions when the weather is clear, but the grade is too wet. Do not list days merely as "Unworkable". When recording nonworking days due to "other", provide explanation contract lane closure restrictions, State of emergency, area-wide labor strike, etc.
2. List numbers of change orders providing for time extensions.
3. Do not include nonworking days which occur after expiration of the Extended Date of Completion. On contracts that are overtime, the total under Working Days Shall not be greater than the total of revised Working Days (line7). After approved total of working days has been reached, continue recording working and nonworking days but do not add into the totals. Make a statement under Remarks that working and nonworking days are shown for record only since the contact time has elapsed.
If an extension of time is subsequently approved, determine the new Extended Date by taking into account all nonworking days that are reachable.
4. From the calendar issued by the Division of Construction with working days numbered for convenience in computations.
5. Determine the controlling activity from the updated approved contract schedule. If the controlling activity is completed in the middle of the week and a new one begins, make this clear. For example, "Class 2 base -M, T, W; HMA -Th, Fri." This is not the place to list all the operations the contractor worked on for the week. Record that information in the Daily Report or under "remarks" if you wish.
6. Column F (lines 1-10) is informational only and tracks those days determined in column D to be working days, but the Contractor failed to work on the controlling operation.
August 2021
561
MONTHLY PROJECT PAYMENT
ESTIMATE SUMMARY
Payment Estimate No:
Department of Public Works
130 Cremona Drive, Suite B Work Performed Through:
Goleta, CA 93117
Contractor: Project:
Address: Acct.No:
Contract Summary
Original Contract Amount:
Approved Change Orders through #:
Quantity Changes (Requires Project Engineer/Inspector verification):
Total Contract Amount to Date:
Payment Summary
Original Contract Payments
Change Order Payments
Total Earnings
Less: Retention (5%)
Less: Administrative Deductions
Net Amounts
The undersigned Contractor or Contractor's Authorized Representative certifies that to the best of thier knowledge, information, and belief, the work covered in this application for payment has been completed in accordance with the contract documents and the costs shown are true and correct.
Resident Engineer: Project Engineer: Contractor:
Date: Date: Date:
Form CC 1 REV: 03/2023
AMOUNTPERIOD AMOUNT
CURRENT PAY PREVIOUS TO DATE
AMOUNT
562
Project: PROJECT PAYMENT ESTIMATE
Acct.No: Payment Estimate No:
Department of Public Works
130 Cremona Drive, Suite B Contractor:
Goleta, CA 93117
Work Performed Through:
Item Item Description Unit Estimated Unit Cost Contract No. Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Form CC 2 REV: 03/2023
Previous EstimatesThis Estimate Work Completed Work Remaining FORM CC 2 REV: 5/07
563
Project: QUANTITY ADJUSTMENT FORM
Project No: Payment Estimate No:
Department of Public Works
130 Cremona Drive, Suite B Contractor:
Goleta, CA 93117
Work Performed Through:
INSTRUCTIONS
This form is to accompany Progress Payments or the Final Payment where there are quantity changes (variations in quantities) authorized by the Department of Public Works that adjust the Total Contract Amount.
Quantity Changes in the amount of:
Progress Payment # Accompanying Progress Payment # (or Final Payment) have been reviewed and the actual quantities verified.
Item Item Description Unit Unit Cost
No. Quantity
Increase
(Decrease) Amount Quantity
Increase
(Decrease) Amount Quantity
Increase
(Decrease) Amount
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
Contractor Signature Date Resident Engineer Signature Date Form CC3 REV: 03/2023
Previous EstimatesThis Estimate
Contract Quantity Adjustments
To-Date Totals
564
CONSTRUCTION CONTRACT
FINAL RELEASE
130 Cremona Drive, Suite B
From: Date:
Contractor
Payment Request No:
Address Acct.No:
Project Name:
To: CITY OF GOLETA
Department of Public Works
CIP Division
130 Cremona Drive, Suite B
Goleta, CA 93117
Upon receipt by the undersigned of a check from the City of Goleta in the sum of payable to
Contractor Signature: Print Name:
Title: Date:
Form CC4 REV: 03/2023
This release covers the final payment to the undersigned for all labor, services, equipment or material furnished on the job, including the work of or all materials furnished for all subcontractors, suppliers, or other agents acting on behalf of the undersigned on this work. There are no disputed claims for additional work.
Goleta, CA 93117
565
CONTRACT CHANGE ORDER MEMO
Change Order No.
Department of Public Works Date Prepared:
130 Cremona Drive, Suite B
Goleta, CA 93117
Project No.:
Contractor: Project:
Address:
CONTRACT CHANGE ORDER-XX FINANCIAL IMPACT:
Total Change Order Authority Approved by Council:
Contract Amount Prior to This Change Order:
Amount to be Increased By This Change Order:
Adjusted Contract Amount Including This Change Order:
Total Remaining Change Order Authority:
Contract Period Increase Due to This Change Order: Days Final Contract Completion Date Including This Change Order: Days By:
Name: John Plummer, Resident Engineer
-$
-$
-$
DESCRIPTION OF ITEMS INCLUDED IN CONTRACT CHANGE ORDER-03:
What is the change:
Who initiated the change:
Why is the change necessary:
Modifications to the Project listed in CCO-XX have been due to the following:
Where is the change located:
How will the change be implemented:
Method of Payment:
Time Adjustment:
A time adjustment of X working days is included as part of this change order.
Original Contract Amount:
Total Change By Previous Change Orders:
566
CONTRACT CHANGE ORDER
Change Order No.
Department of Public Works Date Prepared:
130 Cremona Drive, Suite B
Goleta, CA 93117
Project No.:
Contractor: Project:
Address:
Estimated Cost: Decrease Increase
By reason of this order, the time of completion will be adjusted as follows: XXX (X) working days added.
Original Contract Amount:
Total Change by Previous Change Orders and/or Quantity Adjustment:
Contract Amount Prior to this Change Order:
$ -
Contract Amount to be Increased/Decreased by this Change Order:
Adjusted Contract Amount Including this Change Order: $ -
SIGNATURE (PRINT NAME & TITLE) DATE
SIGNATURE (PRINT NAME & TITLE) DATE
SIGNATURE (PRINT NAME & TITLE) DATE
SIGNATURE (PRINT NAME & TITLE) DATE
In accordance with Section 4-1.05 CHANGES AND EXTRA WORK of the 2023 Standard Specifications, the Contractor shall...
For this work, the Contractor is compensated $X,XXX.XX.This sum, measured in accordance with the Standard Specifications constitutes full and complete compensation, for providing all labor, materials, equipment, tools, and incidentals, including all markups for this change.
(Database Code; XXX) Total This Item:
X Working Days Added
You are directed to make the following changes from the plans and specifications or do the following described work not included in the plans and specifications for this contract.
Description of work to be done, estimate of quantities, and prices to be paid:
Andrew Fuller, Principal Engineer
CITY APPROVAL BY:
REVIEWED BY:
John Plummer, Senior Engineer
APPROVAL RECOMMENDED BY:
567
CONTRACT CHANGE ORDER
Change Order No.
Department of Public Works Date Prepared:
130 Cremona Drive, Suite B
Goleta, CA 93117
Project No.:
Contractor: Project:
SIGNATURE (PRINT NAME & TITLE) DATE
Form CC 5
Nina Buelna, Public Works Director
We, the undersigned contractor, have given careful consideration to the change proposed and agree, if this proposal is approved, that we will provide all equipment, furnish the materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment, therefore, the prices shown above. NOTE: If you, the contractor, do not sign acceptance of this order, your attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.
CONTRACTOR ACCEPTANCE BY:
568
Post-Construction Waste Reduction & Recycling Summary Report Diversion Requirement: Reduce quantity of materials disposed at landfills by 65% or more.
Column A: List estimated quantities of waste for each material type (in tons). To convert material quantities to tons, use th
e Materials Conversion Worksheet provided in your packet.
Columns B, C, D: List estimated quantities reused, recycled, or disposed.
Column E: State the name of all vendors or facilities to be used to reuse, recycle or dispose of material listed. See
example below for cases where more than one facility will be used for a particular material type.
Column Totals: Add up all quantities listed in Column A. Do the same for Columns B, C and D.
Waste Reduction & Recycling Summary REPORT (WRRS Report) Material Handling Methods - Indicate quantities (in tons only) for each material listed.
Material Type
A
Total Tons
Generated
(A=B+C+D)
B
Quantity
Salvaged or
Reused
C
Recycling
D
Estimated
Disposal
E
Anticipated Material
Destination(s)
(R): Recycled; (D): Disposal
Example:
Cardboard 2 tons 1.5 .5 (R) MarBorg
(D) Tajiguas Landfill
Asphalt & Concrete
Brick/Masonry/Tile
Building Materials (doors, windows,
fixtures, etc.)
Carpet
Carpet padding/Foam
Cardboard
Ceiling tile (acoustic)
Dirt
Drywall (used)
Drywall (new, unpainted sheets or scrap)
Landscape Debris (brush, trees, stumps,
etc.)
Scrap metal
Unpainted Wood and Pallets
Garbage/Trash
Other
Recycled mixed debris
Column Totals
7. To determine if the required 65% project waste reduction will be met, complete the following with the column totals: B + C / A = x 100 = %
8. Is the per
centage listed in #7 greater than or equal to 65%? YES NO - If “NO” please explain why:
9. Print Name: Signature: Date: __ _ _/__ __/_
__ _
569
NOTICE REGARDING ASSEMBLY BILL 626
Assembly Bill 626 (AB 626), signed into law September 29, 2016, established a new claim resolution process for public works project contracts entered into on or after January 1, 2017. AB 626 is codified in Section 9204 of the California Public Contract Code. Section 9204 remains in effect until January 1, 2020, and as of that date will be repealed unless another statute extends or deletes this sunset date.
Public Contract Code Section 9204 applies to any “claim,” as defined in Section 9204, which is presented by the Contractor to the City. Section 9204 defines a “claim” as a separate demand by the Contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following: (1) a time extension, including, without limitation, for relief from damages or penalties for delay assessed by the City;
(2) payment by the City of money or damages arising from work done by, or on behalf of, the Contractor pursuant to the Contract and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled; or (3) payment of an amount that is disputed by the City.
If Contractor presents a claim to the City in accordance with the provisions of Public Contract Code Section 9204 (hereafter referred to as a “Claim”), the process specified in Section 9204 will be followed, and the provisions of Section 4- 8 (Disputed Claims) and Section 4- 9 (Review by Claim Review Committee and Issuance of Decision by Department Director) of the City’s Standard Specifications for Public Construction will not apply to the Claim. Contractor’s Claim shall comply with the provisi ons of Section 4- 7 (Notice of Claims for Additional Compensation or Damages) of the City’s Standard Specifications or Contractor shall give a separate written notice of potential claim that complies with the requirements specified in Section 4-7, except in any case where compliance with the requirements specified in Section 4-7 would conflict with Public Contract Code Section 9204.
Subsection (e) of Public Contract Code Section 9204 requires that the text of Section 9204 or a summary be set forth in the plans or specifications for any public works project that may give rise to a claim under Section 9204.
The full text of Public Contract Code Section 9204 is as follows:
9204.
(a) The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b) Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c) For purposes of this section:
(1) “Claim” means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. 570
(2) “Contractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with apublic entity for a public works project.
(3) (A) “Public entity” means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a c harter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency.
(B) “Public entity” shall not include the following:
(i) The Department of Water Resources as to any project under the jurisdiction of that department. (ii) The Department of Transportation as to any project under the jurisdiction of that department. (iii) The Department of Parks and Recreation as to any project under the jurisdiction of that department. (iv) The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code. (v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority.
(4) “Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind. (5) “Subcontractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor.
(d) (1) (A) Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45- day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 daysafter the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2) (A) If the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute. (B) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 da ys after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the 571
disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim.
Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section. (C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parti es in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D) Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced. (E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties’ dispute. (3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entity’s failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that
(1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the 572
timeframes and procedures set forth in this section.
(g) This section applies to contracts entered into on or after January 1, 2017. (h) Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i) This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
573
MAINTENANCE BOND
GUARANTEE AND WARRANTY SECURITY
(Project: )
WHEREAS, the City of Goleta (“CITY”) and
(“PRINCIPAL”) have entered into a
(AGREEMENT”) by which PRINCIPAL agrees to install and complete certain designated public improvements and to guarantee and warrant the work for a period of One (1) year following its completion and acceptance, which agreement, dated , 20 , and identified as
(Name of Project)
is hereby referred to and made a part hereof; and
WHEREAS, said PRINCIPAL is required under the terms of said AGREEMENT to furnish a bond to guarantee and warrant the work for a period of one year following its completion and acceptance against any defective work or labor done, or defective materials furnished, to comply with the terms of said AGREEMENT; and
NOW, THEREFORE, we, the PRINCIPAL and
a , admitted and duly authorized to transact business
under the laws of the State of California, as Surety (“SURETY”), are held and firmly bound unto the CITY in the penal sum of
dollars
($ ), lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors, executors and administrators, jointly and severally, firmly by these presents.
The condition of this obligation is such that if the PRINCIPAL, his or its heirs, executors, administrators, successors or assigns, shall abide by, and in all respects perform the covenants, conditions and provisions in said AGREEMENT and any alteration thereof made as therein provided, on his or its part to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save harmless CITY, its officers, agents and employees, as therein stipulated, then this obligation shall be null and void; otherwise, this obligation shall be and remain in full force and effect.
As part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees, including reasonable attorneys' fees, incurred by CITY in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered.
Bond No.
Premium $
Warranty Bond-Page 1
574
The SURETY hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the AGREEMENT or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect SURETY’S obligations under this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the agreement or to the work or to the specifications. The SURETY waives all rights of subrogation against the CITY or any person employed by the CITY. The SURETY hereby waives the provisions of Section 2819 of the Civil Code.
IN WITNESS WHEREOF, this instrument has been duly executed by the PRINCIPAL and SURETY above-named, on the day of ,
20 .
PRINCIPAL: SURETY:
BY: BY:
PRINT NAME: PRINT NAME:
PRINT TITLE: PRINT TITLE:
AND MAILING ADDRESS:
BY:
PRINT NAME:
PRINT TITLE:
(Notarization by Surety and
copy of Power of Attorney required.)
APPROVED AS TO FORM:
BY:
Scott Shapses
Deputy City Attorney
Warranty Bond-Page 2
575
Appendix G
Sample Door Hanger
Project Name
The City of Goleta is pleased to inform you that the PROJECT NAME is about to begin. Our contractor, CONTRACTOR NAME, will be working over the next LENGTH OF PROJECT to construct this project. During that time, CONTRACTOR will be DESCRIPTION OF WORK. We apologize for any inconvenience this may cause and ask for your patience and cooperation so that we may complete this work as soon as possible.
Sign up for email/text notifications from the City on this project here:
https://public.govdelivery.com/accounts/CAGOLETA/subscriber/ new.
WORK HOURS/PARKING: The work will generally be performed between the hours of 7:30 a.m. and 4:30 p.m. However, there are work hour restrictions in some instances. Local access will be maintained during most of the work. However, parking restrictions will be necessary and will be posted a minimum of 72-hours in advance of the work. Cars will be towed if parked during the no parking dates posted on your street.
TIMELINE: Some or all of the following activities will be performed on your street:
DESCRIPTION OF ACTIVITY DATE
DESCRIPTION OF ACTIVITY DATE
DESCRIPTION OF ACTIVITY DATE
CONTACTS: If you have any questions or need information, please contact:
NAME OF CITY CONTACT PHONE NUMBER
NAME OF CONTRACT CONTACT PHONE NUMBER
576
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX B
CITY OF GOLETA
APPENDIX B
RESTORATION CONTRACTOR
MITIGATION WORK
FOR
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
577
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX B
Back of Cover Sheet
578
San Jose Creek Multi-Purpose Path
Northern and Southern Segments Project
Restoration Contractor Scope of Work for Mitigation -
On-site San Jose Creek at Northern Segment
Off-site Old San Jose Creek at Jonny D. Wallis Park
Off-site Old San Jose Creek at Ekwill Street
Off-site Devereux Creek at Ellwood Mesa
On-site San Jose Creek at Southern Segment
prepared for
City of Goleta
Public Works Department
130 Cremona Drive, Suite B
Goleta, California 93117
Contact: Teresa Lopes, PE, Project Manager
prepared by
Rincon Consultants, Inc.
319 East Carrillo Street, Suite 105
Santa Barbara, California 93101
January 2024
579
580
Table of Contents
Restoration Contractor Scope of Work for Mitigation i
Table of Contents
1 Introduction .................................................................................................................................... 1
1.1 Restoration Contractor Qualifications ................................................................................ 2
1.2 Questions and Clarification of The Scope of Work ............................................................. 4
1.3 Required Proposal Items ..................................................................................................... 4 2 Restoration Scope of Work ............................................................................................................ 5
2.1 Schedule .............................................................................................................................. 5
2.2 Coordination ....................................................................................................................... 6
2.3 Cultural Resources Monitoring ........................................................................................... 6
2.4 On-site San Jose Creek Along the Northern Segment of the Pathway ............................... 6
2.4.1 Preparation and Installation Phases ................................................................... 7
2.4.2 Maintenance Phase ..........................................................................................12
2.5 Off-site San Jose Creek at Jonny D. Wallis Park ................................................................13
2.5.1 Preparation and Installation Phases .................................................................13
2.5.2 Maintenance Phase ..........................................................................................16
2.6 Off-site Old San Jose Creek at Ekwill Street ......................................................................17
2.6.1 Preparation and Installation Phase ..................................................................17
2.6.2 Maintenance Phase ..........................................................................................21
2.7 Off-site Devereux Creek at Ellwood Mesa ........................................................................21
2.7.1 Preparation and Installation Phase ..................................................................22
2.7.2 Maintenance Phase ..........................................................................................24
2.8 On-site San Jose Creek Along the Southern Segment of the Pathway .............................24
2.8.1 Preparation and Installation Phase ..................................................................25
2.8.2 Maintenance Phase ..........................................................................................28 3 References ....................................................................................................................................29 Tables
Table 1 Task Summary by Phase and Site ........................................................................................ 3 Table 2 Restoration Schedule with Tasks ........................................................................................ 6 Table 3 Plant Palette On-site San Jose Creek Along the Northern Segment of the Pathway............................................................................................................................... 8 Table 4 Plant Palette San Jose Creek at Jonny D. Wallis Park .....................................................14 Table 5 Plant Palette Old San Jose Creek at Ekwill Street Riparian Re-establishment Areas .................................................................................................................................18 Table 6 Plant Palette Old San Jose Creek at Ekwill Street Riparian Enhancement for Monarch Area ...................................................................................................................19 Table 7 Plant Palette Devereux Creek at Ellwood Mesa .............................................................22 Table 8 Native Plant Palette San Jose Creek along Southern Segment of the Pathway ............26 581
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
ii
Figures
Figure 1 Project Location and Mitigation Areas............................................................................ F-1 Figure 2 Project Locations ............................................................................................................. F-2 Figure 3 San Jose Creek Multi-use Path Full Extent ................................................................... F-3 Figure 4 Restoration Layout On-site San Jose Creek along Northern Segment of Pathway ...... F-4 Figure 5 Restoration Layout Off-site San Jose Creek at Jonny D. Wallis Park ............................ F-5 Figure 6 Restoration Layout Off-site Old San Jose Creek at Ekwill Street ................................. F-6 Figure 7 Restoration Layout Off-site Devereux Creek at Ellwood Mesa .................................... F-7 Figure 8 Restoration Layout On-site San Jose Creek along Southern Segment of Pathway Lower Portion ............................................................................................................... F-8 Figure 9 Restoration Layout On-site San Jose Creek along Southern Segment of Pathway Upper Portion ............................................................................................................... F-9 Appendices
Appendix A Mitigation Plan (Rincon 2023)
582
Introduction
Restoration Contractor Scope of Work for Mitigation 1
1 Introduction
The purpose of this Scope of Work is to inform the Restoration Contractor that will be subcontracted to the General Contractor on what will be required to initiate the restoration phase of the City of Goleta (City) San Jose Creek Multi-Purpose Path Northern and Southern Segments Project (Project).
work described herein.
described in the Project Special Provisions and the hiring of the Restoration Contractor. Figure 1 and Figure 2 show the Project site and mitigation sites in relation to each other. Figure 3 shows the City- wide extent of the San Jose Creek Multi-Purpose Path.
The goal of the restoration phase is to fulfill the requirements of IS-MND Mitigation Measures BIO-2 and AES-2 to compensate for the loss of riparian habitat (including riparian trees), salt marsh habitat, upland trees, and jurisdictional waters associated with the Project, and to satisfy anticipated requirements of the U.S. Army Corps of Engineers (USACE), California Department of Fish and Wildlife (CDFW), Central Coast Regional Water Quality Control Board (RWQCB), and California Coastal Commission (CCC), which have jurisdiction over activities affecting San Jose Creek.
In accordance with City of Goleta policy, impacts to riparian habitat within the City of Goleta will be mitigated within the City, and impacts within the Coastal Zone will be mitigated within the Coastal Zone. The mitigation will take place on-site at the following locations (see Figure 2):
On-site San Jose Creek along the northern segment of the Pathway 0.37 acre Temporary riparian impact area up to 0.24 acres
Off-site San Jose Creek at Jonny D. Wallis Park 0.07 acre Off-site Old San Jose Creek at Ekwill Street 1.45 acres Off-site Devereux Creek at Ellwood Mesa 0.08 acre
On-site San Jose Creek along the southern segment of the Pathway 0.38 acre Restoration of these areas aims to ensure a net gain in the acreage and function of riparian woodland habitat in the San Jose Creek and Devereux Creek watersheds. The woodland corridor adjacent to San Jose Creek, Old San Jose Creek, and Devereux Creek will be expanded and enhanced through the removal of invasive species and installation of native plants. Native species diversity and abundance will be substantially increased along the otherwise non-native dominated portions of these creeks that currently exists.
This Scope of Work for restoration preparation, installation, and maintenance follows the 2023 Mitigation Plan prepared by Rincon Consultants, Inc. (Rincon) (Rincon 2023). The Mitigation Plan is included as Appendix A for reference. This Scope of Work outlines all the responsibilities that are expected of the Restoration Contractor based on the Mitigation Plan and includes a summarization of said document, i.e., restoration preparation, installation, and short-term maintenance (Sections
2.1 and portions of 2.3 of the Mitigation Plan). There are additional restoration-related aspects outlined in the Mitigation Plan that are not part of this Scope of Work and should not be included in the Restoration Contractor bid estimate that includes long-term maintenance, monitoring, and reporting (Sections 2.3, 2.4, and 2.5 of the Mitigation Plan).
Installation of the restoration, including site preparation, is phased by mitigation site and is scheduled for the summer of 2026 through the spring of 2027. Maintenance of the mitigation sites, 583
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
2 defined as the 90-day Plant Establishment Period (PEP), is phased by mitigation site and is scheduled for the winter of 2026 through the spring of 2027. The schedule is further detailed in Section 2.1 further below.
This Scope of Work is organized by mitigation site, then by Installation Phase and Maintenance Phase, then by task. A summary of anticipated tasks is outlined in Table 1 and the locations of the work areas are shown on Figure 2. The detailed Scope of Work is outlined in Section 2. The Scope of Work will be performed by the Restoration Contractor under the oversight by the City-approved Restoration Biologist.
1.1 Restoration Contractor Qualifications
The following are the qualifications that must be met by the restoration and/or native landscaping firm that will conduct the mitigation installation for the Project, herein referred to as the Restoration Contractor.
For the off-site mitigation site, the Restoration Contractor must have experience with installing and maintaining restoration sites as follows:
The Restoration Contractor shall have successfully completed the installation and long-term maintenance of a minimum of three native habitat restoration projects, each over 3 acres in southern and/or central California.
The Restoration Contractor shall be experienced with all aspects of habitat restoration and thoroughly familiar with all native plant species listed in the Mitigation Plan, as well as all non- native plant species (including invasive species) common to the Goleta area.
The Restoration Contractor shall be able to successfully install native plants in remote locations.
The Restoration Contractor shall be able to successfully install an above ground temporary irrigation system in remote locations.
The Restoration Contractor must possess and provide the following Santa Barbara County pesticide application licensing at the time of the bid submittal:
A pest control business (PCM) or one of its licensed branches (PCB) with a current license issued by California Environmental Protection Agency (EPA) Department of Pesticide Regulation (DPR) A person currently licensed as a Qualified Applicator (QAL) and with a Category B (Landscape Maintenance)
The PCM/PCB and the QAL are required to be registered with the County Commissioner in Santa Barbara County
Additionally, the Restoration Contractor shall provide the following at the time of the bid submittal:
-
Certificate of liability insurance
584
Introduction
Restoration Contractor Scope of Work for Mitigation 3
Table 1 Task Summary by Phase and Site
Task by Mitigation Site
Phase
On-site San Jose Creek along the
Northern Segment of the Pathway
Off-site San Jose Creek at
Jonny D. Wallis Park
Off-site Old San Jose Creek
at Ekwill Street
Off-site Devereux Creek at
Ellwood Mesa
On-site San Jose Creek
along the Southern
Segment of the Pathway
Preparation and Installation Phases
Task NP1: Site Preparation Task JDW1: Site
Preparation
Task ES1: Site Preparation Task EM1: Site Preparation Task SP1: Site Preparation Task NP2: Plant Installation Task JDW2: Plant
Installation
Task ES2: Plant Installation Task EM2: Plant Installation Task SP2: Plant Installation Task NP3: Plant Procurement Task JDW3: Plant
Procurement
Task ES3: Plant Procurement Task EM3: Plant Procurement Task SP3: Plant Procurement Task NP4: Irrigation Design and
Installation
Task JDW4: Irrigation
Design and Installation
Task ES4: Irrigation Design
and Installation
Task EM4: Irrigation Design
and Installation
Task SP4: Irrigation Design
and Installation
Maintenance Phase
Task NP5: Weed Removal and
General Maintenance
Task JDW5: Weed Removal
and General Maintenance
Task ES5: Weed Removal
and General Maintenance
Task EM5: Weed Removal
and General Maintenance
Task SP5: Weed Removal
and General Maintenance
Task names based on mitigation site names - NP: Northern Path, JDW: Jonny D. Wallis, ES: Ekwill Street, EM: Ellwood Mesa, SP: Southern Path
585
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
4 1.2 Questions and Clarification of The Scope of Work
Questions, requests for explanation, or clarifications in regard to this Scope of Work shall be made in written form and submitted via email to Teresa Lopes, PE, Project Manager, City of Goleta, at [email protected].
The City will advise all bidding parties of responses to the requests for explanation or clarifications via email. All bidding parties interested in responding to the Scope of Work are advised to check their email for any updates. The bidder is also responsible for ensuring that they have complete bidding documents prior to the bid due date.
A site walk may be scheduled by the City. Details will be transmitted to the confirmed bidders if a site walk is scheduled. Attendance will be limited to a maximum of three (3) persons from each bidder.
1.3 Required Proposal Items
Bidding parties must submit a proposal via email as described in the Project Special Provisions.
The following additional items shall be included in the proposal:
Technical approach and methodologies
Proposed resources: include organization chart with proposed staff at management and superintendent level
Completed bid pricing sheet
A copy of the State of California C-
References for at least three other similar projects involving native plants in a natural setting successfully completed within the last 5 years
A copy of the Santa Barbara County pesticide application license 586
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 5
2 Restoration Scope of Work
The San Jose Creek Multi-Purpose Path Northern and Southern Segments Project requires on-site restoration adjacent to the project as well as off-site restoration at the following locations (see Figure 1 and Figure 2).
On-site San Jose Creek along the northern segment of the Pathway 0.37 acre Temporary riparian impact area up to 0.24 acres
Off-site San Jose Creek at Jonny D. Wallis Park 0.07 acre Off-site Old San Jose Creek at Ekwill Street 1.45 acres Off-site Devereux Creek at Ellwood Mesa 0.08 acre
On-site San Jose Creek along the southern segment of the Pathway 0.38 acre The following summary of work by task will be performed by the Restoration Contractor under the oversight by the City-approved Restoration Biologist. All Installation and Maintenance Phases will adhere to the 2023 Mitigation Plan; specifically, the goal to reach the Performance Criteria. The Performance Criteria established for this Project includes the following (see Section 2.2 of the Mitigation Plan):
All plantings shall have a minimum of 80% survival the first year and 100% survival thereafter.
All plantings shall attain 75% cover after three years and 90% cover after five years.
The mitigation site shall be entirely without supplemental irrigation for a minimum of two years.
No single species shall constitute more than 50% of the vegetative cover.
No woody invasive species shall be present.
Herbaceous invasive species shall not exceed 5% cover.
2.1 Schedule
The restoration services outlined herein will be performed over an approximate timeframe of one and a half years, between August 2026 and spring 2027. The project Special Provisions will establish the timeframe for installation of plants, which is expected to begin in late fall 2026. The restoration work is separated into three phases: Preparation Phase, Installation Phase, and Maintenance Phase.
The Preparation Phase includes initial non-native plant removal, erosion control installation as needed, fence installation as needed, and irrigation design. The Installation Phase includes plant procurement, plant installation, and irrigation design and installation. The Maintenance Phase will begin after completing the Installation Phase and will be defined as the 90-day PEP. The Maintenance Phase includes non-native plant removal, watering, and repairing of damage to plants, erosion control devices, fencing, and/or signs as further described below. See Table 2 for a detailed draft restoration schedule. Note that although this schedule is an educated estimate, the General Contractor will provide the actual schedule to be approved by the City. However, no major alterations to the overall project schedule are expected. The Restoration Contractor must coordinate activities with the General Contractor, who is required to submit a Construction Schedule prior to the pre-construction conference.
587
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
6 Table 2 Restoration Schedule with Tasks
Timing On-site and Off-site Mitigation Sites
Preparation
Summer 2026 Task NP4, JDW4, ES4, EM4, SP4: Design irrigation system Early Fall 2026 Task NP1, JDW1, ES1, EM1, SP1: Initial non-native plant removal Task NP3, JDW3, ES3, EM3, SP3: Plant procurement
Installation
Late Summer/Early Fall 2026 Task NP4, JDW4, ES4, EM4, SP4: Install drip irrigation system Late Fall/Winter 2026 Task NP2, JDW2, ES2, EM2, SP2: Install container plants Maintenance (90-day Plant Establishment Period)
Winter 2026 to Spring 2027 Task NP5, JDW5, ES5, EM5, SP5: Conduct weeding and general maintenance Task names based on mitigation site names - NP: Northern Path, JDW: Jonny D. Wallis, ES: Ekwill Street, EM: Ellwood Mesa, SP:
Southern Path
2.2 Coordination
The Restoration Contractor will work in coordination and oversight by the City-approved Restoration Biologist. The City-approved Restoration Biologist will provide oversight for plant stock; container plant installation locations and layout; non-native plant removal; success criteria; and irrigation schedules. The City-approved Restoration Biologist will be on-site regularly to direct work as needed.
2.3 Cultural Resources Monitoring
The project area is generally sensitive for cultural resources. Therefore, a cultural resources education and monitoring program will be established to be implemented during construction per -Mitigated Negative declaration (IS-MND). The education program will describe the roles and responsibilities of the archaeologist and Native American monitor, identify what types of resources may be found in the area, procedures to follow in the event of a find, and discuss the regulatory protections for resources and identify the penalties for the destruction or unauthorized collection of cultural resources. Each team member from the Restoration Contractor crew is required to attend a cultural resources education program, which will be offered prior to the Installation Phase and at any time during the Installation Phase and/or Maintenance Phase if new crew members are employed. It is anticipated based on the requirements of other City mitigation projects in the immediate vicinity of the off-site mitigation sites that the cultural resources education program will extend to the off-site mitigation sites as well.
The preparation of the cultural resources education program will not be the responsibility of the Restoration Contractor. The summary above is included herein for informational purposes only.
2.4 On-site San Jose Creek Along the Northern
Segment of the Pathway
The mitigation site is located largely along the east side of the northern segment of the pathway and on the west side of San Jose Creek (see Figure 4). Re-establishment of 0.37 acre of riparian woodland will occur. In addition, mitigation for permanent impact to upland trees will occur along 588
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 7
Calle Real, south of the path, north of U.S. Route 101, and west of San Jose Creek. Lastly, up to 0.24 acre of temporary impacts may occur during construction along the path within the riparian habitat.
The additional riparian enhancement area, where only weeding will occur, is not included herein.
The mitigation site will be accessed by vehicle via the closest public road, then from the pathway as feasible on foot or with a small vehicle, i.e., small pickup truck or utility side-by-side. Staging areas will mainly be located near the vehicles; however, smaller temporary staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation.
The following outlines the scope of work by preparation/installation and maintenance phases, then by task. Tasks are named as NP for the northern segment of the pathway.
2.4.1 Preparation and Installation Phases
Task NP1: Site Preparation
The City-approved Restoration Biologist will work with the General Contractor and Restoration Contractor to stake the limits of restoration. Prior to installation, the site will need to be prepared for restoration activities. Site preparation includes the following:
Non-native plants will be removed from the site using hand removal methods, such as hand- held weed whips, loppers, and hoes. If hand removal is not feasible due to the characteristics of the species, such as resistance to hand removal methods, the size of the plants, or the number of plants, perennial invasive non-native species may be treated with herbicides. Herbicide application conditions are as follows:
Only individual plants will be treated; no blanket spraying efforts will be allowed.
If herbicide is applied, it will be applied during dry and low wind conditions in order to prevent conveyance of herbicide into drainages or other non-targeted areas.
Herbicide application must be performed by a licensed applicator that can identify the species to be treated and is experienced in the handling and application of herbicides.
Herbicides must be approved for use by the City of Goleta prior to application and allowed under permit and property conditions.
Only herbicides approved for use near or in water, such as AquaMaster or equivalent, will be used if necessary.
All tools, equipment, vehicles, clothing and footwear, and other gear shall be cleaned to remove soil, seeds, and other plant parts before accessing the restoration area.
Vegetation with potential to contain bird nests will not be removed during the breeding bird season (approximately February 1 through August 31) unless a City-approved biologist determines that it does not contain active bird nests. Tree removal will not occur during the monarch butterfly aggregation season (approximately October 1 through March 31) if aggregating monarchs are present.
If needed, install temporary fencing, made of green construction mesh-like fence approximately 4 feet high and t-posts (or similar). Fencing will follow the outer borders of each planting area.
If needed, install temporary signage
team and the public of restoration efforts.
589
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
8 Timing
The construction schedule will be confirmed by the General Contractor so that the on-site restoration areas are made available for restoration activities to the extent feasible, beginning in early fall 2026.
Task NP2: Plant Installation
Plant installation will require specific timing and spacing between planting as described in the 2023 Mitigation Plan. Within the 0.37-acre riparian re-establishment site, a total of 645 plants will be needed for the re-establishment and enhancement of habitat at the northern segment (see Figure 4). Table 3 provides a representative palette of native species that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed.
Table 3 Native Plant Palette On-site San Jose Creek Along the Northern Segment of the Pathway
Scientific Name Common Name Quantity1
Riparian Trees2
Juglans californica Southern California black walnut 3
Platanus racemosa Western sycamore 30
Populus trichocarpa black cottonwood 32
Quercus agrifolia coast live oak 6
Salix lasiolepis arroyo willow 37
Umbellularia californica California bay 3
Subtotal Up to 111
Shrubs
Baccharis salicifolia mulefat 39
Frangula californica California coffeeberry 38
Heteromeles arbutifolia toyon 38
Lonicera subspicata var. subspicata Santa Barbara honeysuckle 20 Phacelia ramosissima branching phacelia 38
Sambucus mexicana (S. nigra) blue elderberry 20
Subtotal 193
Grasses, Forbs, and Vines
Artemisia douglasiana mugwort 17
Bromus carinatus California brome 41
Carex barbarae Santa Barbara sedge 17
Clematis ligusticifolia creek clematis 17
Distichlis spicata saltgrass 17
Elymus condensatus giant wild rye 17
Elymus triticoides alkali ryegrass 17
Euthamia occidentalis Western goldenrod 17
Hordeum brachyantherum subsp. californicum California barley 17 Juncus patens common California rush 17
Juncus phaeocephalus brown-headed rush 17
590
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 9
Scientific Name Common Name Quantity1
Juncus textilis Basket rush 17
Juncus xiphioides iris-leaved rush 17
Rosa californica California rose 17
Rubus ursinus California blackberry 17
Salvia spathacea hummingbird sage 17
Scrophularia californica California figwort 17
Solidago velutina subsp. californica velvety goldenrod 17 Verbena lasiostachys verbena 17
Subtotal 340
Total 645
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
2 The native trees that will be installed in the temporary impact areas are included in the quantities.
In addition, mitigation for permanent impact to upland trees will occur along Calle Real, south of the path, north of U.S. Route 101, and west of San Jose Creek. Twenty coast live oak trees will be installed.
Lastly, up to 0.24 acre of temporary impacts may occur during construction along the path within the riparian habitat. Individual riparian trees will be installed in these areas as described above for the riparian re-establishment; quantities are included therein. Herbs and shrubs will also be installed to provide native cover and help reduce potential erosion issues. Quantities are not provided herein as the temporary impact areas are dependent upon the final footprint of construction, although the number of plants needed will likely be minimal and under 30.
Installation of the container plants will involve the following:
Within the 0.37-acre riparian re-establishment area, up to 111 riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. This quantity of trees includes those that will be installed within the temporary impact areas.
Within the 0.37-acre riparian re-establishment area, 533 native herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing.
Along Calle Real, 20 coast live oak trees will be installed as 15-gallon containers or 24-inch or 36- inch boxes at approximately 10 to 15-foot spacing.
Within the 0.24-acre temporary impact area within the riparian area, quantities are unknown and the number of plants need will likely be minimal and under 30.
Holes for the smaller container plants will be dug by hand using a shovel, hang auger, or similar device.
Holes for the larger trees along Calle Real will be dug with medium or light-duty equipment as needed.
The rootball, stems or branches of container plants shall not be disturbed.
Planting pits will be backfilled with native soil and wood mulch will be placed round each plant. 591
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
10 Mulch will be placed around each container plant at a depth of at least 3 inches, and at least a 2-foot radius for trees and a 1-foot radius for other species. If generated, the mulch from the removed non-native trees would be allowed some time to dry and then would be used around installed plants as feasible. Additional mulch originating from Santa Barbara may be acquired as All purchased mulch will be free of Argentine ants.
Each container plant will be immediately watered by a drip emitter system or by hand as conditions allow. Long-term irrigation will be applied and discussed in Task NP4 below.
Erosion control materials will be installed as needed and may include low silt fences, hay bales at the base of slopes, and/or straw wattle only. The quantity of erosion control materials that is expected to be needed is minimal; materials would only be used within the mitigation areas and not for the construction portion of the project.
If needed, signage and temporary construction fencing will be placed around the mitigation sites to inform people to stay out of the restoration area as described in Task NP1.
Timing
To the extent feasible, plant installation will coincide with the first major winter storm when soil conditions are moist. Installation is expected to occur in late fall/winter 2026. Adjacent construction may need to be accounted for access and safety purposes.
Task NP3: Plant Procurement
The native plant materials in Table 3 will be contracted through a qualified native nursery that propagates plants from local genetic stock in coordination with the City-approved Restoration Biologist. The approximate cost that will need to be paid by the Restoration Contractor for the five on-site and off-site mitigation sites is approximately $14,000, which should be included as a line item in
. Assume that the Restoration Contractor will
need to pick up the plants at the nursery on a daily or regular basis and bring them to the site; therefore, there will be no delivery fee. Assume that only a very limited number of plants can be stored safely on-site overnight. If plants remain on-site longer than the day on which they are installed, they must be watered daily until they are installed.
The large coast live oaks installed along the path along Calle Real as visual screening will be commercially available California natives with relatively low restrictions for the genetic requirements. The approximate cost that will need to be paid by the Restoration Contractor for 36- inch box trees is $30,000, which should be included as a line item in cost estimate. However, please note smaller trees may be used in coordination with the City and Restoration Biologist during the Preparation Phase.
Timing
A 40% deposit for the 1-gallon container plants of local genetic stock will need to be paid by the Restoration Contractor at the time the plants are ordered and the final 60% payment installment must be paid by the Restoration Contractor at the time of plant pick up. The payment for the 36- inch box trees must be paid by the Restoration Contractor at the time of plant pick up. Plant procurement will occur in fall/winter 2026.
592
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 11
Task NP4: Irrigation Design and Installation
The Restoration Contractor will design and install a temporary above ground drip irrigation system.
The irrigation system should be set up to target individual plants, i.e., drip emitters, and should avoid watering in between the plants to help prevent the growth of non-natives. Irrigation materials cannot be installed in areas where creek flows would be prohibitive.
A maximum of 0.61 acre (0.37 acre for the re-establishment areas and up to 0.24 acre for the adjacent temporary impact areas) will require a temporary irrigation system to be designed and installed by the Restoration Contractor. The design of the irrigation system is up to the Restoration Contractor based on their experience and site conditions observed during the site walk; however, primary lines should be installed before plant installation and secondary/lateral lines should be installed after plant installation. The irrigation system will be designed by a qualified irrigation specialist as an aboveground temporary drip irrigation system, which will persist for 5 years with regular maintenance, and can be easily removed at the end of 5 years. The irrigation system will be designed so that it is automated, powered by either batteries or solar operated controllers, and will be weather sensor compatible. Primary lines will be of 2-inch-diameter schedule (or larger diameter if deemed necessary by the Restoration Contractor) 40 polyvinyl chloride (PVC). Any variations from these materials specifications must be indicated in the bid estimate. The irrigation design will be schematic and does not need to include a licensed architect or engineer stamp.
Water to be used during the restoration preparation, installation, and maintenance will be supplied by the City for the Restoration Contractor and shall be of suitable quality for irrigation. For the northern section of the pathway, from its southern terminus to U.S. Highway 101, the irrigation source will be the irrigation main lateral line located at Armitos Park. For the upland trees along Calle Real, the irrigation source will be the same as what the City uses for the street median immediately to the north..
Following award of the contract, the City will supply the Restoration Contractor with site specifications needed to complete the irrigation system design (e.g., water pressure details, etc.).
The Restoration Contractor will work with the City-approved Restoration Biologist to ensure that the design meets all materials and site specifications and will submit a draft irrigation design to the City for approval by early summer 2026. The irrigation design shall be prepared in computer-aided design and drafting (CADD), or similar program that is acceptable in the landscape industry. The City will provide comments to be incorporated into the final irrigation design so that it can be installed) in late summer/early fall 2026 prior to plant installation.
Timing
The Restoration Contractor will finalize the irrigation design in summer 2026 prior to plant installation. The Restoration Contractor will install the irrigation system on-site before or after initial non-native vegetation removal, depending on a mutual agreement between the Restoration Contractor and City. The City-approved Restoration Biologist will provide oversight in the field. The irrigation system will be installed in late summer/early fall 2026, prior to plant installation in late fall/early winter 2026.
593
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project 12 2.4.2 Maintenance Phase
The Restoration Contractor will maintain the restoration site throughout the Installation Phase and 90-day PEP. Once the City and Restoration Biologist deems the restoration installation complete for each site, the 90-day PEP will begin. Maintenance will include non-native plant removal, watering, replanting if any die as a result of neglect by the Restoration Contractor, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism. The Restoration Contractor will also adhere to the following measures during the Maintenance Phase:
Large plants with potential to contain bird nests will not be removed during the breeding bird season (March 1 to September 15) unless the City-approved Restoration Biologist determines that it does not contain active bird nests.
Tree removal will not occur during the monarch butterfly aggregation season (October 1 through March 31) if aggregating monarchs are present.
Task NP5: Weed Removal and General Maintenance
Weed removal at the restoration site will include the following:
Non-native plants will be removed primarily using hand removal methods. If hand removal is not feasible due to species resistance to hand removal methods, the size of the plant, or the number of plants, perennial invasive non-native species may be treated with herbicides.
Herbicide application requirements are described in Task NP1.
All tools, equipment, vehicles, clothing and footwear, and other gear shall be cleaned to remove soil, seeds, and other plant parts before accessing the restoration area.
Frequency:
crew of an appropriate size to remove weeds throughout the mitigation site in one event.
Specifically, non-native plants will be removed from within a 3-foot radius of each mitigation tree. During the Installation Phase, weeding must be conducted so that the site and installed native plants do not become overrun or dominated by weeds, the frequency will be dependent upon site conditions. A minimum of one event per month is required. Assume a minimum of 3 events will be required during the 90-day PEP, spaced a maximum of 1 month and a minimum of 2 weeks apart over the 90-day PEP.
General maintenance at the restoration site will include the following:
The Restoration Contractor will be responsible for installing a temporary aboveground irrigation system (see Task NP4 above), maintain the system, and water the plants immediately after installation and for the duration of the 90-day PEP.
The City of Goleta-approved Restoration Biologist will establish an irrigation schedule in conjunction with the Restoration Contractor. Irrigation will be scheduled to maximize growth of native species and will account for natural rainfall, while minimizing growth of invasive non- native plants. Generally, if irrigation is needed, more irrigation will be provided during the growing season (winter and spring) to mimic seasonal weather patterns, and minimal irrigation will be provided during the summer and fall as needed to keep plants alive.
Conduct routine activities to maintain the plantings in a healthy condition.
If plants die during the 90-day PEP due to the techniques employed by the Restoration Contractor, i.e., not due to natural causes, the Restoration Contractor will be responsible for replacement planting and/or seeding.
594
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 13
Maintain fencing and signage.
Remove trash.
Control erosion of the mitigation site.
Ensure applicable performance criteria are being achieved to the extent feasible, in coordination with the Restoration Biologist.
Timing
Weed removal will occur throughout the Installation Phase, with a focus on the peak growing season in the winter 2026. Weed removal will also be conducted during the Maintenance Phase, i.e., through the 90-day PEP, approximately winter 2026 through spring 2027. General maintenance will be conducted during the Installation Phase, as well as through the 90-day PEP.
2.5 Off-site San Jose Creek at Jonny D. Wallis Park
The restoration site is located along the eastern boundary of Jonny D. Wallis Park and on the west side of San Jose Creek, see Figure 5.
Re-establishment of 0.07 acre of riparian woodland is required. Additionally, individual riparian trees will be installed along the edge of the existing riparian canopy, within the park grounds where an unmaintained or semi-natural understory occurs as further described below. The additional riparian enhancement area, where only weeding will occur, is not included herein.
The mitigation site will be accessed by vehicle via the park parking lot, then from the pathway as feasible on foot or with a small vehicle, i.e., utility side-by-side. Staging areas will mainly be located near the vehicles; however, smaller staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation.
The following outlines the scope of work by preparation/installation and maintenance phases, then by task. Tasks are named as JDW for Jonny D. Wallis Park.
2.5.1 Preparation and Installation Phases
Task JDW1: Site Preparation
The City-approved Restoration Biologist will work with the General Contractor and Restoration Contractor to stake the limits of restoration. Prior to installation, the site will need to be prepared for restoration activities. Site preparation, including non-native weed removal, herbicide application, installation of temporary fencing, and installation of temporary signage will be conducted as described in Task NP1 above. In addition, one goldenrain (Koelreuteria paniculata) tree at Jonny D. Wallis Park will need to be removed/treated prior to restoration installation.
Removal/treatment will occur before planting begins in
for safety and protecting existing infrastructure at the park or protecting native plants that may be present, the tree may be removed or girdled and left in place. For those tree(s) that can be removed, stump grinding or similar method will be used to remove most of the trunk to ground level or to 6-12 inches below ground level if possible. Holes will then be made mechanically within the root zone to allow for native plants to be installed. If the stump can be removed to 6-12 inches below ground level, soil will be placed in the hole and plants will be installed there as well. Trees may be chipped on-site, and chipped trees may be used as mulch after they have dried out. For those trees that can be girdled, girdling will occur by removing the bark around the entire 595
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
14 circumference of the trunk, thereby preventing transport of water and nutrients, and killing the tree.
Timing
Preparation is expected to occur in early fall 2026.
Task JDW2: Plant Installation
Plant installation will require specific timing and spacing between planting as described in the 2023 Mitigation Plan. Within the 0.29-acre re-establishment site, a total of 122 plants will be needed for creation of habitat at Jonny D. Wallis Park (see Figure 5). Table 4 provides a representative palette of native species that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed.
In addition, mitigation will occur along the edge of the existing riparian canopy within the park grounds. Specifically, these areas include park grounds along the existing footpaths where the understory is comprised of installed landscape or ornamental native plants and minimally maintained by weeding and/or mulching. Up to 8 riparian trees will be installed in these areas (5 black cottonwoods [Populus trichocarpa] and 3 coast live oaks [Quercus agrifolia]), which are included in Table 4. The 8 existing western sycamore x London plane hybrid trees (Platanus racemosa x P. hispanica) will be removed by the Restoration Contractor and replaced by the Restoration Contractor with native western sycamore trees that have been locally sourced by a qualified native nursery from cuttings from known pure genetic stock, e.g., the Sister Witness Tree.
Table 4 Native Plant Palette San Jose Creek at Jonny D. Wallis Park Scientific Name Common Name Quantity1
Riparian Trees2
Juglans californica Southern California black walnut 3
Platanus racemosa Western sycamore 4
Populus trichocarpa black cottonwood 11
Quercus agrifolia coast live oak 3
Salix lasiolepis arroyo willow 3
Subtotal Up to 24
Shrubs
Baccharis salicifolia mulefat 8
Frangula californica California coffeeberry 7
Heteromeles arbutifolia toyon 7
Lonicera subspicata var. subspicata Santa Barbara honeysuckle 4 Phacelia ramossisima branching phacelia 7
Sambucus mexicana (S. nigra) blue elderberry 4
Subtotal 37
Grasses, Forbs, and Vines
Artemisia douglasiana mugwort 3
Bromus carinatus California brome 6
596
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 15
Scientific Name Common Name Quantity1
Carex barbarae Santa Barbara sedge 3
Clematis ligusticifolia creek clematis 3
Distichlis spicata saltgrass 3
Elymus condensatus giant wild rye 3
Elymus triticoides alkali ryegrass 3
Euthamia occidentalis Western goldenrod 3
Hordeum brachyantherum subsp.
californicum
California barley 3
Juncus patens common California rush 3
Juncus phaeocephalus brown-headed rush 3
Juncus textilis Basket rush 3
Juncus xiphioides iris-leaved rush 3
Rosa californica California rose 3
Rubus ursinus California blackberry 3
Salvia spathacea hummingbird sage 3
Scrophularia californica California figwort 3
Solidago velutina subsp. californica velvety goldenrod 3 Verbena lasiostachys verbena 3
Subtotal 61
Total 122
1 In the re-establishment area, riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. In the park grounds, riparian trees will be installed as 15-gallon containers, 1-gallon containers, or ½-gallon tree tubes at 10-foot spacing.
Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. 2 The native trees that will be installed in the park grounds, outside of the re-establishment area, are included in the quantities.
Installation of plants in the tables above will involve the following:
Within the 0.29-acre riparian re-establishment area, up to 16 riparian trees will be installed as 1- gallon containers or ½-gallon tree tubes at 10-foot spacing.
Within the 0.29-acre riparian re-establishment area, 98 native herbs and select will be installed as 1-gallon or 4-inch containers at 5-foot spacing.
For the individual riparian trees within the park grounds, 8 riparian trees will be installed as 15- gallon containers, 1-gallon containers, or ½-gallon tree tubes at 10-foot spacing. If available, the 15-gallon size is preferred for the park grounds and will be installed.
For the replacement of native western sycamores within the park grounds, 8 trees will be installed as 1-gallon containers or ½-gallon tree tubes.
Holes for the smaller container plants will be dug by hand using a shovel, hang auger, or similar device.
Holes for the larger trees within the park grounds will be dug with medium or light-duty equipment as needed.
Installation techniques will occur as described in Task NP2. 597
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
16 Timing
To the extent feasible, plant installation will coincide with the first major winter storm when soil conditions are moist. Installation is expected to occur in late fall/winter 2026.
Task JDW3: Plant Procurement
The native plant materials in Table 4, as well as the replacement western sycamores within the park grounds, will be contracted by the City through a qualified native nursery that propagates plants from local genetic stock in coordination with the City-approved Restoration Biologist as described in Task NP3; the price to be paid by the Restoration Contractor for the plant stock is included therein.
The large black cottonwoods and coast live oaks installed within the park grounds will be commercially available California natives with relatively low restrictions for the genetic requirements. The approximate cost that will need to be paid by the Restoration Contractor for 15- gallon box trees is $1,200, which should be included as a line item in cost estimate. However, please note smaller trees may be used in coordination with the City and Restoration Biologist during the Preparation Phase.
Timing
For the local genetic stock, timing will occur as described for Task NP3. The payment for the 15- gallon box trees must be paid by the Restoration Contractor at the time of plant pick up. Plant procurement will occur in fall/winter 2026.
Task JDW4: Irrigation Design and Installation
The Restoration Contractor will design and install a temporary above ground drip irrigation system as described in Task NP4 above for the 0.07-acre re-establishment area.
Water to be used during the restoration preparation, installation, and maintenance will be furnished on-site by the City for the Restoration Contractor and will be of suitable quality for irrigation. The irrigation source will be the irrigation main lateral line located at Jonny D. Wallis Park. The Restoration Contractor will have the authority to use water as needed to fulfill the irrigation tasks
Timing
As described in Task NP4, the Restoration Contractor will finalize the irrigation design in summer 2026 prior to plant installation. The Restoration Contractor will install the irrigation system on-site before or after initial non-native vegetation removal, depending on a mutual agreement between the Restoration Contractor and City. The City-approved Restoration Biologist will provide oversight in the field. The irrigation system will be installed in late summer/early fall 2026, prior to plant installation in late fall/early winter 2026.
2.5.2 Maintenance Phase
The Restoration Contractor will maintain the restoration site throughout the Installation Phase and 90-day PEP. Once the City deems the restoration installation complete, the 90-day PEP will begin.
Maintenance will include non-native plant removal, watering, replanting, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism. 598
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 17
The Restoration Contractor will also be adhered to the following measures during the Maintenance Phase:
Large plants with potential to contain bird nests will not be removed during the breeding bird season (March 1 to September 15) unless the City-approved Restoration Biologist determines that it does not contain active bird nests.
Tree removal will not occur during the monarch butterfly aggregation season (October 1 through March 31) if aggregating monarchs are present.
Task JDW5: Weed Removal and General Maintenance
Weed removal and general maintenance will be conducted at the restoration site as described in Section 2.4.2 and Task NP5.
Timing
As described in Task NP5, weed removal will occur throughout the Installation Phase, with a focus on the peak growing season in the winter 2026. Weed removal will also be conducted during the Maintenance Phase, i.e., through the 90-day PEP, approximately winter 2026 through spring 2027.
General maintenance will be conducted during the Installation Phase, as well as through the 90-day PEP.
2.6 Off-site Old San Jose Creek at Ekwill Street
The mitigation site is located north of the soon to be constructed Ekwill Street along, east of Pine Street, along Old San Jose Creek, see Figure 6.
Re-establishment of 0.58 acre of riparian woodland and 0.87 acre of riparian enhancement for monarchs, for a total of 1.45 acres is required. The extent of the riparian woodland will be enhanced with a variety of native species that provide important food and shelter sources for a variety of wildlife species. The eucalyptus grove that comprises a portion of the mitigation site will be restored specifically for monarchs.
The mitigation site will be accessed by vehicle via the closest public road, then by foot. Staging areas will mainly be located near the vehicles; however, smaller staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation.
The following outlines the scope of work by preparation/installation and maintenance phases, then by task. Tasks are named as ES for Ekwill Street.
2.6.1 Preparation and Installation Phase
Task ES1: Site Preparation
The City-approved Restoration Biologist will work with the General Contractor and Restoration Contractor to stake the limits of restoration. Prior to installation, the site will need to be prepared for restoration activities. Site preparation, including non-native weed removal, herbicide application, installation of temporary fencing, and installation of temporary signage will be conducted as described in Task NP1 above. In addition, many black locust trees (Robinia 599
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
18 pseudoacacia) at Old San Jose Creek at Ekwill Street will need to be removed/treated prior to restoration installation. Removal/treatment will occur as described in Task JDW1 above.
Timing
Preparation is expected to occur in early fall 2026. Tree removal will not occur during the monarch butterfly aggregation season (approximately October 1 through March 31) if aggregating monarchs are present.
Task ES2: Plant Installation
Plant installation will require specific timing and spacing between planting as described in the 2023 Mitigation Plan. Within the 0.58-acre re-establishment site, up to 1,011 plants will be needed for the re-establishment of riparian woodland (see Figure 6). Table 5 provides a representative palette of native species that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed.
Table 5 Native Plant Palette Old San Jose Creek at Ekwill Street Riparian Re- establishment Areas
Scientific Name Common Name Quantity1
Riparian Trees
Juglans californica Southern California black walnut 20 Platanus racemosa western sycamore 15
Populus trichocarpa black cottonwood 50
Quercus agrifolia coast live oak 20
Salix lasiolepis arroyo willow 30
Umbellularia californica California bay 15
Subtotal Up to 150
Shrubs
Baccharis pilularis Coyote bush 48
Baccharis salicifolia mulefat 51
Frangula californica California coffeeberry 48
Heteromeles arbutifolia toyon 48
Lonicera subspicata var. subspicata Santa Barbara honeysuckle 30 Phacelia ramossisima branching phacelia 48
Sambucus mexicana (S. nigra) blue elderberry 30
Subtotal 303
Grasses, Forbs, and Vines
Artemisia douglasiana mugwort 29
Bromus carinatus California brome 44
Carex barbarae Santa Barbara sedge 29
Clematis ligusticifolia creek clematis 29
Distichlis spicata saltgrass 29
Elymus condensatus giant wild rye 20
600
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 19
Scientific Name Common Name Quantity1
Elymus triticoides alkali ryegrass 29
Euthamia occidentalis Western goldenrod 29
Hordeum brachyantherum subsp.
californicum
California barley 29
Juncus patens common California rush 29
Juncus phaeocephalus brown-headed rush 29
Juncus textilis Basket rush 29
Juncus xiphioides iris-leaved rush 29
Rosa californica California rose 29
Rubus ursinus California blackberry 29
Salvia spathacea hummingbird sage 29
Scrophularia californica California figwort 29
Solidago velutina subsp. californica velvety goldenrod 29 Verbena lasiostachys verbena 29
Subtotal 557
Total 1,011
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
Plant installation within the 0.87-acre enhancement site will occur within the eucalyptus grove that comprises this middle section of the mitigation site to be restored specifically for monarch butterflies. In coordination with a monarch biologist, the City-approved Restoration Biologist will help protect the grove and provide a wind buffer for the monarchs. Table 6 below includes the native plant palette that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed.
Table 6 Native Plant Palette Old San Jose Creek at Ekwill Street Riparian Enhancement for Monarch Area
Scientific Name Common Name Quantity1
Shrubs
Baccharis pilularis Coyote bush 5
Eriogonum fasciculatum California buckwheat 5
Isocoma menziesii coastal goldenbush 5
Mimulus aurantiacus bush monkeyflower 5
Rhus integrifolia lemonade berry 8
Subtotal 28
Grasses, Forbs, and Vines
Dichelostemma capitatum blue dicks 13
Euthamia occidentalis western goldenrod 13
601
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
20 Scientific Name Common Name Quantity1
Helianthus californicus California sunflower 13
Solidago velutina subsp. californica velvety goldenrod 13 Verbena lasiostachys var. lasiostachys verbena 14
Subtotal 66
Total 95
TBD = To be determined
1 Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
Installation of plants in the Table 5 and Table 6 above will involve the following:
Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing.
Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing.
Holes for the container plants will be dug by hand using a shovel, hang auger, or similar device.
Installation techniques will occur as described in Task NP2.
Timing
To the extent feasible, plant installation will coincide with the first major winter storm when soil conditions are moist. Installation is expected to occur in late fall/winter 2026. Adjacent construction may need to be accounted for access and safety purposes.
Task ES3: Plant Procurement
The native plant materials in Table 5 and Table 6 will be contracted through a qualified native nursery that propagates plants from local genetic stock in coordination with the City-approved Restoration Biologist as described in Task NP3; the price to be paid by the Restoration Contractor for the plant stock is included therein.
Timing
For the local genetic stock, timing will occur as described for Task NP3.
Task ES4: Irrigation Design and Installation
The Restoration Contractor will design and install a temporary above ground drip irrigation system as described in Task NP4 above for the 0.29 re-establishment area and the perimeter of the 0.87- acre riparian enhancement area for monarchs.
Water to be used during the restoration preparation, installation, and maintenance will be furnished on-site by the City for the Restoration Contractor and shall be of suitable quality for irrigation. The location of the irrigation connection point is a permanent hookup/riser for the that will be built as part of the adjacent Ekwill Street and Fowler Road Improvement Project, which will be located to the south of the eastern end of the mitigation site. The Restoration Contractor will have the authority to use water as needed to fulfill the irrigation tasks through the General
602
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 21
Timing
As described in Task NP4, the Restoration Contractor will finalize the irrigation design in summer 2026 prior to plant installation. The Restoration Contractor will install the irrigation system on-site before or after initial non-native vegetation removal, depending on a mutual agreement between the Restoration Contractor and City. The City-approved Restoration Biologist will provide oversight in the field. The irrigation system will be installed in late summer/early fall 2026, prior to plant installation in late fall/early winter 2026.
2.6.2 Maintenance Phase
The Restoration Contractor will maintain the restoration site throughout the Installation Phase and 90-day PEP. Once the City deems the restoration installation complete, the 90-day PEP will begin.
Maintenance will include non-native plant removal, watering, replanting, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism.
The Restoration Contractor will also adhere to the following measures during the Maintenance Phase:
Large plants with potential to contain bird nests will not be removed during the breeding bird season (March 1 to September 15) unless the City-approved Restoration Biologist determines that it does not contain active bird nests.
Tree removal will not occur during the monarch butterfly aggregation season (October 1 through March 31) if aggregating monarchs are present.
No eucalyptus trees within the Riparian Enhancement for Monarch Area, will be removed to preserve monarch butterfly habitat.
Task ES5: Weed Removal and General Maintenance
Weed removal and general maintenance will be conducted at the restoration site as described in Section 2.4.2 and Task NP5.
Timing
As described in Task NP5, weed removal will occur throughout the Installation Phase, with a focus on the peak growing season in the winter 2026. Weed removal will also be conducted during the Maintenance Phase, i.e., through the 90-day PEP, approximately winter 2026 through spring 2027.
General maintenance will be conducted during the Installation Phase, as well as through the 90-day PEP.
2.7 Off-site Devereux Creek at Ellwood Mesa
The mitigation site is located along Devereux Creek at the eastern edge of the Ellwood Mesa Open Space Preserve (see Figure 7). Restoration of 0.08 acre of marsh wetland enhancement is required.
The transitional salt and freshwater marsh wetland will be enhanced with a variety of native herbaceous species that provide important food and shelter sources for a variety of wildlife species.
The mitigation site will be accessed by vehicle via the closest public road, then by foot or with a small vehicle, i.e., utility side-by-side. Staging areas will mainly be located near the vehicles; however, smaller staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation. 603
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
22 The following outlines the scope of work by preparation/installation and maintenance phases, then by task. Tasks are named as EM for Ellwood Mesa.
2.7.1 Preparation and Installation Phase
Task EM1: Site Preparation
The City-approved Restoration Biologist will work with the General Contractor and Restoration Contractor to stake the limits of restoration. Prior to installation, the site will need to be prepared for restoration activities. Site preparation, including non-native weed removal, herbicide application, installation of temporary fencing, and installation of temporary signage will be conducted as described in Task NP1 above.
Timing
Preparation is expected to occur in early fall 2026.
Task EM2: Plant Installation
Plant installation will require specific timing and spacing between planting as described in the 2023 Mitigation and Monitoring Plan. Within the 0.08-acre site, a total of 125 plants will be needed for the enhancement of habitat at Ellwood Mesa (see Figure 7). Table 7 provides a representative palette of native species that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed.
Table 7 Native Plant Palette Devereux Creek at Ellwood Mesa Scientific Name Common Name Quantity1
Shrubs
Isocoma menziesii coast goldenbush 7
Atriplex lentiformis quailbush 7
Subtotal 14
Grasses and Forbs
Anemopsis californica yerba mansa 11
Ambrosia psilostachya var.
californica
Western ragweed 11
Carex barbarae Santa Barbara sedge 11
Cyperus eragrostis umbrella-sedge 11
Distichlis spicata saltgrass 11
Eleocharis macrostachya common spikerush 11
Frankenia salina alkali heath 11
Hordeum brachyantherum subsp.
californicum
California barley 11
Jaumea carnosa fleshy jaumea 11
Juncus patens common California rush 11
Juncus phaeocephalus brown-headed rush 11
Paspalum distichum knot grass 11
604
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 23
Scientific Name Common Name Quantity1
Schoenoplectus acutus hardstem bulrush 4
Subtotal 125
Total 139
TBD = To be determined
1 Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
Installation of plants in the tables above will involve the following:
Minor grading may be needed to restore better flow and function to the area chosen.
Herbs and select shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing.
Holes for the container plants will be dug by hand using a shovel, hang auger, or similar device.
Installation techniques will occur as described in Task NP2.
Timing
To the extent feasible, plant installation will coincide with the first major winter storm when soil conditions are moist. Installation is expected to occur in late fall/winter 2026. Adjacent construction may need to be accounted for access and safety purposes.
Task EM3: Plant Procurement
The native plant materials in Table 7 will be contracted through a qualified native nursery that propagates plants from local genetic stock in coordination with the City-approved Restoration Biologist as described in Task NP3; the price to be paid by the Restoration Contractor for the plant stock is included therein.
Timing
For the local genetic stock, timing will occur as described for Task NP3.
Task EM4: Irrigation Design and Installation
The Restoration Contractor will design and install a temporary above ground drip irrigation system as described in Task NP4 above for the 0.08 acre site. Note that this off-site location is remote. The storage of the water on-site and supply to the above ground temporary irrigation system will be a temporary water source such as a holding tank or water truck.
Water to be used during the restoration preparation, installation, and maintenance will be furnished on-site by the City for the Restoration Contractor and shall be of suitable quality for irrigation. The irrigation source will be the City hydrant located near 447 Ellwood Beach Drive, which is located at the terminus of that road and to the north of the mitigation site. As the hookup will be a hydrant, a crew member must physically be present each time the irrigation is used so that the water can be turned on and off at the hydrant. The Restoration Contractor will have the authority to use water as meter will be provided by the City.
605
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
24 Timing
As described in Task NP4, Restoration Contractor will finalize the irrigation design in summer 2026 prior to plant installation. The Restoration Contractor will install the irrigation system on-site before or after initial non-native vegetation removal, depending on a mutual agreement between the Restoration Contractor and City. The City-approved Restoration Biologist will provide oversight in the field. The irrigation system will be installed in late summer/early fall 2026, prior to plant installation in late fall/early winter 2026.
2.7.2 Maintenance Phase
The Restoration Contractor will maintain the restoration site throughout the Installation Phase and 90-day PEP. Once the City deems the restoration installation complete, the 90-day PEP will begin.
Maintenance will include non-native plant removal, watering, replanting, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism.
The Restoration Contractor will also adhere to the following measures during the Maintenance Phase:
Large plants with potential to contain bird nests will not be removed during the breeding bird season (March 1 to September 15) unless the City-approved Restoration Biologist determines that it does not contain active bird nests.
Tree removal will not occur during the monarch butterfly aggregation season (October 1 through March 31) if aggregating monarchs are present.
Task EM5: Weed Removal and General Maintenance
Weed removal and general maintenance will be conducted at the restoration site as described in Section 2.4.2 and Task NP5.
Timing
As described in Task NP5, weed removal will occur throughout the Installation Phase, with a focus on the peak growing season in the winter 2026. Weed removal will also be conducted during the Maintenance Phase, i.e., through the 90-day PEP, approximately winter 2026 through spring 2027.
General maintenance will be conducted during the Installation Phase, as well as through the 90-day PEP.
2.8 On-site San Jose Creek Along the Southern
Segment of the Pathway
The mitigation site is located east of the northern segment of the pathway and on the west side of San Jose Creek, see Figure 8 and Figure 9. A patchwork of creation and enhancement of 0.38 acre of riparian scrubland will occur in areas that lack or are dominated by coyote brush, respectively.
The mitigation site will be accessed by vehicle via the closest public road, then from the pathway as feasible on foot or with a small vehicle, i.e., small pickup truck or utility side-by-side. Staging areas will mainly be located near the vehicles; however, smaller staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation. Actual plant installation locations to be determined by the City-approved Restoration Biologist.
606
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 25
The following outlines the scope of work by preparation/installation and maintenance phases, then by task. Tasks are named as SP for the southern segment of the pathway.
2.8.1 Preparation and Installation Phase
Task SP1: Site Preparation
The City-approved Restoration Biologist will work with the General Contractor and Restoration Contractor to stake the limits of restoration. Prior to installation, the site will need to be prepared for restoration activities. Site preparation, including non-native weed removal, herbicide application, installation of temporary fencing, and installation of temporary signage will be conducted as described in Task NP1 above.
Timing
The construction schedule will be confirmed by the General Contractor so that the on-site restoration areas are made available for restoration activities to the extent feasible, beginning in early fall 2026.
Task SP2: Plant Installation
Plant installation will require specific timing and spacing between planting as described in the 2023 Mitigation and Monitoring Plan. Within the 0.38-acre site, a total of 166 plants will be needed for the creation/enhancement of habitat at the southern pathway segment (see Figure 8 and Figure 9).
Table 8 provides a representative palette of native species that may be used for each habitat treatment type. The City-approved Restoration Biologist will flag the exact location of each planted area and provide field oversight while the plants are installed. 607
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
26 Table 8 Native Plant Palette San Jose Creek along Southern Segment of the Pathway Scientific Name Common Name Quantity1
Riparian Trees
Juglans californica Southern California black walnut 3
Platanus racemosa western sycamore 3
Populus trichocarpa black cottonwood 3
Quercus agrifolia coast live oak 3
Umbellularia californica California bay 3
Subtotal Up to 15 2
Shrubs
Artemisia californica California sagebrush 9
Baccharis pilularis Coyote brush 9
Diplacus aurantiacus bush monkeyflower 9
Encelia californica California sunflower 9
Epilobium canum California fuchsia 9
Eriogonum parvifolium Seacliff buckwheat 9
Frangula californica California coffeeberry 9
Heteromeles arbutifolia toyon 9
Isocoma menziesii Coastal goldenbush 9
Lonicera subspicata var. subspicata Santa Barbara honeysuckle 9 Phacelia ramosissima branching phacelia 9
Salvia leucophylla purple sage 9
Salvia mellifera black sage 9
Sambucus nigra blue elderberry 9
Subtotal 99
Grasses, Forbs, and Vines
Ambrosia psilostachya var. californica Western ragweed 4 Artemisia douglasiana Mugwort 4
Bromus carinatus California brome 4
Clematis ligusticifolia creek clematis 4
Elymus condensatus giant wild rye 4
Elymus triticoides alkali ryegrass 4
Rosa californica California rose 4
Salvia spathacea hummingbird sage 4
Scrophularia californica California figwort 4
Solidago velutina subsp. californica velvety goldenrod 4 Verbena lasiostachys verbena 4
Subtotal 51
Total 166
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
2 Approximately 20 trees can be installed at the southern/downstream ed of the mitigation site.
Installation of plants in the tables above will involve the following:
608
Restoration Scope of Work
Restoration Contractor Scope of Work for Mitigation 27
The 150 herbs and select shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing.
Up to 15 riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing.
Holes for the container plants will be dug by hand using a shovel, hang auger, or similar device.
Installation techniques will occur as described in Task NP2.
Timing
To the extent feasible, plant installation will coincide with the first major winter storm when soil conditions are moist. Installation is expected to occur in late fall/winter 2026. Adjacent construction may need to be accounted for access and safety purposes.
Task SP3: Plant Procurement
The native plant materials in Table 8 will be contracted through a qualified native nursery that propagates plants from local genetic stock in coordination with the City-approved Restoration Biologist as described in Task NP3; the price to be paid by the Restoration Contractor for the plant stock is included therein.
Timing
For the local genetic stock, timing will occur as described for Task NP3.
Task SP4: Irrigation Design and Installation
The Restoration Contractor will design and install a temporary above ground drip irrigation system as described in Task NP4 above. Note that this off-site location is remote.
A maximum of 0.29 acre will require a temporary irrigation system to be designed and installed by the Restoration Contractor.
The City of Goleta will supply the water for irrigation and designate the water source. Water to be used during the restoration preparation, installation, and maintenance will be furnished on-site by the City for the Restoration Contractor and shall be of suitable quality for irrigation. The irrigation source will be the City hydrant located near 443 S Kellogg Avenue, which is located near the northern terminus of this path segment and near the proposed pedestrian bridge. As the hookup will be a hydrant, a crew member must physically be present each time the irrigation is used so that the water can be turned on and off at the hydrant. The primary line will need to be installed along the proposed pedestrian bridge. The Restoration Contractor will have the authority to use water as meter will be provided by the City.
The irrigation system will be designed so that it is automated, powered by either batteries or solar operated controllers, and will be weather sensor compatible. Primary lines will be of 2-inch- diameter schedule (or larger diameter if deemed necessary by the Restoration Contractor) 40 polyvinyl chloride (PVC).
609
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
28 Timing
As described in Task NP4, Restoration Contractor will finalize the irrigation design in summer 2026 prior to plant installation. The Restoration Contractor will install the irrigation system on-site before or after initial non-native vegetation removal, depending on a mutual agreement between the Restoration Contractor and City. The City-approved Restoration Biologist will provide oversight in the field. The irrigation system will be installed in late summer/early fall 2026, prior to plant installation in late fall/early winter 2026.
2.8.2 Maintenance Phase
The Restoration Contractor will maintain the restoration site throughout the Installation Phase and 90-day PEP. Once the City deems the restoration installation complete, the 90-day PEP will begin.
Maintenance will include non-native plant removal, watering, replanting, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism.
The Restoration Contractor will also adhere to the following measures during the Maintenance Phase:
Large plants with potential to contain bird nests will not be removed during the breeding bird season (March 1 to September 15) unless the City-approved Restoration Biologist determines that it does not contain active bird nests.
Tree removal will not occur during the monarch butterfly aggregation season (October 1 through March 31) if aggregating monarchs are present.
Task SP5: Weed Removal and General Maintenance
Weed removal and general maintenance will be conducted at the restoration site as described in Section 2.4.2 and Task NP5.
Timing
As described in Task NP5, weed removal will occur throughout the Installation Phase, with a focus on the peak growing season in the winter 2026. Weed removal will also be conducted during the Maintenance Phase, i.e., through the 90-day PEP, approximately winter 2026 through spring 2027.
General maintenance will be conducted during the Installation Phase, as well as through the 90-day PEP.
610
References
Restoration Contractor Scope of Work for Mitigation 29
3 References
For a complete list of all references used in the figures included herein, see the Mitigation Plan in Appendix A.
Dewberry. 2023. Mitigation Planting Plan engineering sheets. November 17, 2023.
Rincon Consultants, Inc. (Rincon). 2023. Mitigation Plan for the San Jose Creek Multi-Purpose Path Project. Prepared for the City of Goleta. Revised November 2023.
611
612
Figures
613
614
Figures
Restoration Contractor Scope of Work for Mitigation F-1 Figure 1 Project Location and Mitigation Areas
615
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
F-2
Figure 2 Project Locations
616
Figures
Restoration Contractor Scope of Work for Mitigation F-3 Figure 3 San Jose Creek Multi-use Path Full Extent
617
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
F-4
Figure 4 Restoration Layout On-site San Jose Creek along Northern Segment of Pathway
618
Figures
Restoration Contractor Scope of Work for Mitigation F-5 Figure 5 Restoration Layout Off-site San Jose Creek at Jonny D. Wallis Park
619
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
F-6
Figure 6 Restoration Layout Off-site Old San Jose Creek at Ekwill Street
620
Figures
Restoration Contractor Scope of Work for Mitigation F-7 Figure 7 Restoration Layout Off-site Devereux Creek at Ellwood Mesa
621
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
F-8
Figure 8 Restoration Layout On-site San Jose Creek along Southern Segment of Pathway Lower Portion
622
Figures
Restoration Contractor Scope of Work for Mitigation F-9 Figure 9 Restoration Layout On-site San Jose Creek along Southern Segment of Pathway Upper Portion
623
City of Goleta
San Jose Creek Multi-Purpose Path Northern and Southern Segments Project
F-10
This page intentionally left blank.
624
Appendix A
Mitigation Plan (Rincon 2023)
625
San Jose Creek Multi-Purpose Path –
Northern and Southern Segments
Mitigation Plan
prepared for
City of Goleta
Public Works Department
130 Cremona Drive, Suite B
Goleta, California 93117
prepared by
Rincon Consultants, Inc.
319 East Carrillo Street, Suite 105
Santa Barbara, California 93101
REVISED November 2023
626
Table of Contents
Mitigation Plan i
Table of Contents
1 Introduction ..................................................................................................................................... 1
1.1 Location ............................................................................................................................... 1
1.2 Mitigation Objectives .......................................................................................................... 5
1.3 Environmental Setting ......................................................................................................16
1.4 Site Selection .....................................................................................................................17
1.5 Responsible Party ..............................................................................................................18 2 Compensatory Mitigation Plan ......................................................................................................19
2.1 Mitigation Work Plan ........................................................................................................19
2.1.1 Restoration Approach ..........................................................................................19
2.1.2 Source of Plant Materials .....................................................................................40
2.1.3 Seed Storage and Plant Propagation ...................................................................40
2.1.4 Site Preparation ...................................................................................................41
2.1.5 Plant Installation Methods ...................................................................................42
2.1.6 Plant Protection ...................................................................................................42
2.1.7 Erosion Control ....................................................................................................42
2.1.8 Access Routes and Staging Areas .........................................................................43
2.2 Performance Criteria .........................................................................................................43
2.2.1 Reference Site ......................................................................................................43
2.3 Maintenance Plan .............................................................................................................44
2.3.1 90-Day Plant Establishment Period......................................................................44
2.3.2 Maintenance Methods and Schedule ..................................................................44
2.3.3 Irrigation Methods and Schedule ........................................................................45
2.3.4 Maintenance Restrictions ....................................................................................45
2.4 Monitoring Plan ................................................................................................................45
2.4.1 Monitoring Methods and Schedule .....................................................................46
2.5 Reporting Requirements ...................................................................................................47
2.6 Schedule ............................................................................................................................47
2.7 Site Protection Instrument................................................................................................48
2.8 Long-term Management Plan and Financial Assurances ..................................................49
2.9 Adaptive Management Plan .............................................................................................49 3 List of Preparers .............................................................................................................................50 4 References .....................................................................................................................................51 627
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments ii
Tables
Table 1 Project Impacts to Protected Habitat and Jurisdictional Waters .........................................7 Table 2 Trees to be Removed and Mitigated .................................................................................... 8 Table 3 Summary of Mitigation Requirements for Impacts to Protected Habitat/Jurisdictional Waters .................................................................................................................................. 9 Table 4 Summary of Mitigation Requirements for Impacts to Individual Trees .............................10 Table 5 Summary of Required Mitigation with Mitigation Technique and Site ..............................11 Table 6 Mitigation Site Summary ....................................................................................................18 Table 7 Summary of Habitat to be Restored within Each Mitigation Site ......................................21 Table 8 Summary of Individual Trees by Species to be Restored within the Mitigation Sites ........22 Table 9 Native Plant Palette – San Jose Creek along the Northern Segment of Pathway ..............23 Table 10 Native Plant Palette – Jonny D. Wallis Park ........................................................................27 Table 11 Existing Native Landscape Trees for Mitigation – Jonny D. Wallis Park .............................28 Table 12 Native Plant Palette – Old San Jose Creek at Ekwill Street – Riparian Re-establishment Areas ...................................................................................................................................31 Table 13 Native Plant Palette – Old San Jose Creek at Ekwill Street – Riparian Re-establishment for Monarch Area .....................................................................................................................32 Table 14 Native Plant Palette – Devereux Creek at Ellwood Mesa ...................................................34 Table 15 Native Plant Palette – San Jose Creek along Southern Segment of the Pathway ..............39 Table 16 Mitigation Schedule ............................................................................................................48 Figures
Figure 1 Project Vicinity ...................................................................................................................... 2 Figure 2 Project Location and Mitigation Sites ................................................................................... 3 Figure 3 San Jose Creek Multi-use Path – Full Extent ......................................................................... 4 Figure 4 Impacts to Protected Habitat and Jurisdicitonal Waters – Northern Segment ..................12 Figure 5 Impacts to Protected Habitat and Jurisdicitonal Waters – Lower Southern Segment .......13 Figure 6 Impacts to Protected Habitat and Jurisdicitonal Waters – Upper Southern Segment .......14 Figure 7 Impacts to Trees – Northern Segment ...............................................................................15 Figure 8 Restoration Layout – San Jose Creek along Northern Segment of Pathway ......................25 Figure 9 Restoration Layout – San Jose Creek at Jonny D. Wallis Park ............................................29 Figure 10 Restoration Layout – Old San Jose Creek at Ekwill Street ..................................................30 Figure 11 Restoration Layout – Devereux Creek at Ellwood Mesa ....................................................35 Figure 12 Restoration Layout – San Jose Creek along Southern Segment of Pathway – Lower Portion ................................................................................................................................37 Figure 13 Restoration Layout – San Jose Creek along Southern Segment of Pathway – Upper Portion ................................................................................................................................38 628
Table of Contents
Mitigation Plan iii
Appendices
Appendix A Figures – Impacts to Native and Non-native Trees (Rincon 2022) Appendix B Figures – Habitat Types and Jurisdictional Waters (Dewberry 2023a) Appendix C Mitigation Site Photographs
629
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments iv
This page intentionally left blank.
630
Introduction
Mitigation Plan 1
1 Introduction
The City of Goleta (City) proposes to implement the northern and southern segments of the San Jose Creek Multi-purpose Path Project (Project) within the City in Santa Barbara County, California (Figure 1 and Figure 2). The Project consists of building two separate segments which will tie into existing bicycle and pedestrian facilities and provide a continuous path from Calle Real to the Atascadero Creek Bikeway (Figure 3). Additionally, the Project includes implementation of habitat restoration at several mitigation sites to compensate for project-related impacts to riparian woodland and individual native trees (Figure 2).
This Mitigation Plan fulfills the requirements of Mitigation Measure BIO-2 in the City’s Initial Study and Mitigated Negative Declaration (IS-MND; City of Goleta 2022a), which states that a Mitigation Plan
1 must be prepared by the City, which will outline the mitigation requirements and approach for impacts to riparian habitat (including riparian trees), salt marsh habitat, and jurisdictional waters.
This Mitigation Plan also fulfills the requirements of IS-MND Mitigation Measure AES-2 which further specifies the requirement for riparian and upland tree replacement. This Mitigation Plan is also intended to satisfy anticipated permitting requirements of the U.S. Army Corps of Engineers (USACE), California Department of Fish and Wildlife (CDFW), Central Coast Regional Water Quality Control Board (RWQCB), and California Coastal Commission (CCC), which have jurisdiction over activities affecting San Jose Creek.
1.1 Location
The Project area and mitigation sites are located within the City of Goleta in Santa Barbara County, California (Figure 1) and within the Goleta, California U.S. Geological Survey (USGS) 7.5-minute quadrangle. The city of Goleta is located along the California coast, approximately 100 miles north of Los Angeles and 100 miles south of San Luis Obispo in Santa Barbara County, California. U.S.
Route 101 is the primary regional artery connecting the City of Goleta and City of Santa Barbara.
The northern segment of the multi-purpose path is located outside the Coastal Zone and will extend from Calle Real to Armitos Avenue, crossing under U.S. Route 101 and the Union Pacific Railroad, and following San Jose Creek. The southern segment is located both within and outside the Coastal Zone and will extend from Kellogg Avenue on the west side of State Route (SR) 217 to the existing Class I Atascadero Creek Bikeway on the east side on SR 217, passing under SR 217, and following channelized and natural portions of San Jose Creek (Figure 2).
Mitigation for Project-related impacts will occur at the Project site and at nearby locations. There are two off-site riparian mitigation sites: City-owned property along San Jose Creek at Jonny D.
Wallis Park located outside the Coastal Zone and City-owned property and right-of-way (ROW) west of Ekwill Street and east of Pine Avenue located immediately outside the Coastal Zone. There is one off-site salt marsh/wetland mitigation site, which is located within the Coastal Zone along Devereux Creek on the east end of the City-owned Ellwood Mesa Open Space Preserve (Figure 2).
1 BIO-2 requires a “Conceptual Habitat Restoration Plan”, which will include a “Tree Replacement Plan”, which is herein referred to as the “Mitigation Plan”.
631
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 2 Figure 1 Project Vicinity
632
Introduction
Mitigation Plan 3
Figure 2 Project Location and Mitigation Sites
633
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 4 Figure 3 San Jose Creek Multi-use Path – Full Extent
Source: City 2022b
634
Introduction
Mitigation Plan 5
1.2 Mitigation Objectives
The objective of this Mitigation Plan is to fulfill the requirements of IS-MND Mitigation Measures BIO-2 and AES-2 to compensate for the loss of riparian habitat (including riparian trees), salt marsh habitat, upland trees, and jurisdictional waters associated with the Project, and to satisfy anticipated requirements of the USACE, CDFW, Central Coast RWQCB, and CCC, which have jurisdiction over activities affecting San Jose Creek. In accordance with City of Goleta policy, impacts to riparian habitat within the City of Goleta will be mitigated within the City, and impacts within the Coastal Zone will be mitigated within the Coastal Zone.
The Project would permanently impact 0.93 acres and temporarily impact 0.24 acre of riparian and habitat salt marsh/wetland combined. As required by Mitigation Measure BIO-2, permanent loss of protected habitat and jurisdictional waters must be mitigated at a ratio of 3:1 by riparian habitat restoration. For purposes of RWQCB permitting authority, waters of the State are coterminous with CDFW-jurisdictional streambeds; all impacts to CDFW-jurisdictional streambeds listed herein are applicable to waters of the State. In addition, as required by the CCC during the CCC Coastal Development Permit (CDP) application process, permanent impacts to coastal wetlands must be mitigated at 4:1 and the on-site coyote brush scrub that is adjacent to the concrete channel of San Jose Creek must be mitigated at 3:1 as it CCC-designated Environmentally Sensitive Habitat Area (ESHA). Table 1 provides a summary of the permanent and temporary impacts to protected habitat and jurisdictional waters. Figure 4
2 , Figure 5, and Figure 6 display the impacts to protected habitat and jurisdictional waters within the northern and southern (lower and upper) segments, respectively. As required by Mitigation Measure AES-2, permanent removal of riparian trees must be mitigated at a ratio of 3:1 and permanent removal of upland trees must be mitigated at a ratio of 1:1. Table 2 provides a summary of riparian and upland trees to be removed. Figure 73 displays the impacts to native and non-native tree canopy combined within the Project area. See Appendix A for figures that display the impacts to native and non-native tree canopy separately. Table 3 and Table 4 provides a summary of the mitigation requirements based on these impacts to protected habitats/jurisdictional waters and individual trees, respectively. Table 5 summarizes mitigation requirements by also presenting the mitigation techniques and sites.
When completed, a total of 2.82 acres will be restored for mitigation due to permanent impacts, comprised of 2.74 acres of riparian habitat and 0.08 acres of salt marsh/wetland habitat. For permanent impacts, 1.76 acres of mitigation is required within the Coastal Zone and 1.07 acres is required outside the Coastal Zone. Although a minimum of 1.76 acres of riparian mitigation is required for impacts within the Coastal Zone, 1.83 acres of riparian mitigation will occur within and immediately adjacent to the Coastal Zone, which is collectively herein referred to as Coastal Zone mitigation. For temporary impacts, no mitigation is required within the Coastal Zone and 0.24 acre is required outside the Coastal Zone.
The Project’s mitigation effort will ensure a net gain in the acreage and function of riparian woodland habitat in the San Jose Creek watershed. The woodland corridor adjacent to San Jose Creek and Old San Jose Creek will be expanded and enhanced through the removal of invasive species and installation of native plants. Native species diversity and abundance will be substantially
2 The path alignment has been slightly modified since the creation of this figure to avoid larger mature native trees; the modified path design and reduced impact is not represented on the figure. 3 The path alignment has been slightly modified since the creation of this figure to avoid larger mature native trees; the modified path design and reduced impact is not represented on the figure. 635
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 6 increased along an otherwise non-native dominated portions of these creeks that currently exists. A total of 2.74 acre of riparian woodland habitat will be restored, including 117 riparian mitigation trees located within this acreage and immediately adjacent, in accordance with the mitigation requirements associated with the Project. In addition, 20 upland mitigation trees will be installed at the Project site, in accordance with the mitigation requirements associated with the Project. To ensure that all mitigation sites have proper woodland and riparian function, an additional 200 trees will also be installed throughout the mitigation sites. These non-mitigation trees are herein referred to “surplus” trees, which will be installed above and beyond that which is needed for mitigation.
The Project’s mitigation effort will ensure a net gain in the acreage and function of salt marsh/wetland habitat in the Devereux Creek watershed. The salt marsh habitat will be expanded and enhanced through the removal of invasive species and installation of native plants. Native species diversity and abundance will be increased along an otherwise non-native infested portion of this creek. A total of 0.08 acre of salt marsh/wetland will be restored, in accordance with the mitigation requirements associated with the Project.
The restoration efforts will be a combination of creation in upland areas where aquatic resources (i.e., native vegetation) are absent, re-establishment in areas where aquatic resources (i.e., native vegetation) will be established, and enhancement in areas where the existing aquatic resources (i.e., native vegetation) are degraded
4. Restoration will also occur at the Project site to mitigate 0.24 acre of temporary impacts to riparian habitat and jurisdictional waters due to Project-related activities.
See Table 5 for a summary of mitigation techniques by mitigation site, which is further detailed and described further below in Section 2.1.1.
4 Definitions based on the Compensatory Mitigation for Losses of Aquatic Resources (USACE and EPA 2008). 636
Introduction
Mitigation Plan 7
Table 1 Project Impacts to Protected Habitat and Jurisdictional Waters Protected Habitat/Jurisdictional Waters
Permanent Impact1
(Acres)
Temporary Impact1
(Acres)
Northern Segment
Riparian2: Intermittent Stream and Steelhead Critical Habitat (USACE Non-wetland Waters of the U.S., CDFW-jurisdictional Streambed, RWQCB Waters of the State)
0.005 0.03
Riparian2: California sycamore – Coast live oak riparian woodland (CDFW-jurisdictional Streambed, RWQCB Waters of the State)
0.35 0.21
Subtotal 0.36 0.24
Southern Segment
Wetlands2: Pickleweed Mats/Southern Coastal Salt Marsh
(USACE Wetland Non-wetland Waters of the U.S., CDFW-jurisdictional Streambed, RWQCB Waters of the State, CCC Wetland/ESHA4)
0.02 0
Riparian2: Perennial Stream, Steelhead and Tidewater Goby Critical Habitat, and Essential Fish Habitats
(USACE Waters of the U.S., CDFW-jurisdictional Streambed, RWQCB Waters of the State)
0 0
Riparian2: Arroyo Willow Thickets
(CDFW-jurisdictional Streambed, RWQCB Waters of the State, CCC ESHA4)
0.15 0
Riparian2: Coyote Brush Scrub5 (CCC ESHA4) 0.41 0
Subtotal 0.58 0
Total3 (Northern and Southern Segments) 0.93 0.24
Subtotal USACE Jurisdiction 0.03 0.03
Subtotal RWQCB and CDFW Jurisdiction 0.53 0.23
Subtotal CCC Wetlands/ESHA Jurisdiction4 0.58 0
1 The temporary and permanent impacts represented on this table indicate the total impact acreages, irrespective of agency jurisdiction.
2 “Riparian” and “wetlands” as used herein are ecological terms, irrespective of agency jurisdiction. 3 Totals are precise numbers calculated in GIS and discrepancies with tabular data presented here may occur due to rounding. 4 Impacts will occur within the Coastal Zone.
5 The on-site coyote brush scrub is located outside and adjacent to jurisdictional waters; the area is dominated by coyote brush, an upland species, and is not hydrologically dependent upon San Jose Creek due to the presence of the concrete channel that lines the creek.
637
Table 2 Trees to be Removed and Mitigated
Permanent Impact Areas1
Scientific Name Common Name
Riparian Trees to
be Removed
Upland Trees to
be Removed
Total Number of Trees to
be Removed
DBH Range
(inches)
Eucalyptus cladocalyx and E. globulus sugar gum and blue gum eucalyptus 5 18 23 4-74 Juglans californica Southern California black walnut 2 – 2 18-25 Platanus racemosa Western sycamore 8 – 8 4-42
Populus trichocarpa black cottonwood 12 – 12 5-36
Quercus agrifolia coast live oak 3 2 5 4-26
Salix lasiolepis arroyo willow 9 – 9 4-23
Umbellularia californica California bay – – – –
Total 39 20 59 –
DBH = diameter at breast height
1 Tree impacts will only occur in the Non-Coastal Zone, no impacts to trees will occur within the Coastal Zone.
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 638
Introduction
Mitigation Plan 9
Table 3 Summary of Mitigation Requirements for Impacts to Protected Habitat/Jurisdictional Waters Mitigation for Permanent Impact1 Mitigation for Temporary Impact1 Grand Total3
Mitigation
Required
(acres) Sensitive Biological Resource
Mitigation
Ratio
(acreage)
Coastal
Zone
(acres)
Non-Coastal
Zone
(acres)
Permanent
Impact Total
(acres)
Mitigation
Ratio
(acreage)
Coastal
Zone
(acres)
Non-Coastal
Zone
(acres)
Temporary
Impact Total
(acres)
Riparian2: Perennial Stream, Arroyo Willow Thickets
(USACE Waters of the U.S., CDFW-jurisdictional
Streambed, RWQCB Waters of the State, CCC ESHA)
3:1 0.45 1.07 1.52 1:1 0 0.24 0.24 1.75
Riparian2: Coyote Brush Scrub
(CCC ESHA4)
3:1 1.23 0 1.23 1:1 0 0 0 1.23
Wetland/Salt Marsh2
(USACE Waters of the U.S., CDFW-jurisdictional
Streambed, RWQCB Waters of the State, CCC
wetland/ESHA)
4:1 0.08 0 0.08 1:1 0 0 0 0.08
Total3 1.76 1.07 2.82 0 0.24 0.24 3.06
1 The temporary and permanent impacts represented on this table indicate the total impact acreages, irrespective of agency jurisdiction. 2 “Riparian” and “wetlands” as used herein are ecological terms, irrespective of agency jurisdiction. 3 Totals are precise numbers calculated in GIS and discrepancies with tabular data presented here may occur due to rounding. 4 The on-site coyote brush scrub is located outside and adjacent to jurisdictional waters; the area is dominated by coyote brush, an upland species, and is not hydrologically dependent upon San Jose Creek due to the presence of the concrete channel that lines the creek. 639
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 10 Table 4 Summary of Mitigation Requirements for Impacts to Individual Trees Removal of Riparian Trees1 Removal of Upland Trees1
Scientific Name Common Name
Trees to be
Removed
Mitigation
Ratio
Mitigation
Amount
Trees to be
Removed
Mitigation
Ratio
Mitigation
Amount
Total Mitigation
Trees Required
Eucalyptus cladocalyx
and E. globulus
sugar gum and blue gum
eucalyptus
5 3:1 15 18 1:1 18 33
2 Juglans californica Southern California black walnut 2 3:1 6 0 – – 6 Platanus racemosa Western sycamore 8 3:1 24 0 – – 24
Populus trichocarpa black cottonwood 12 3:1 36 – – 36
Quercus agrifolia coast live oak 3 3:1 9 2 1:1 2 11
Salix lasiolepis arroyo willow 9 3:1 27 0 – – 27
Umbellularia californica California bay 0 3:1 – 0 – – 0 Total 117 20 137
1 Tree impacts will only occur in the Non-Coastal Zone, no impacts to trees will occur within the Coastal Zone. 2 Eucalyptus will be replaced with native trees.
640
Introduction
Mitigation Plan 11
Table 5 Summary of Required Mitigation with Mitigation Technique and Site Mitigation Amount Required for
Permanent Impacts/Removal
Mitigation Amount Required
for Temporary Impacts
Mitigation
Technique5 Mitigation Site
Protected Habitat and Jurisdictional Waters
Riparian1
(USACE Waters of the U.S., CDFW-jurisdictional
Streambed, RWQCB Waters of the State, CCC
ESHA)
1.52 ac
(Coastal Zone4 = 0.45 ac,
Non-Coastal Zone = 1.07 ac)
Re-establishment,
Enhancement
Adjacent to Coastal Zone: Old San
Jose Creek at Ekwill Street
Non-Coastal Zone: San Jose Creek at
Northern Segment of Pathway, San
Jose Creek at Jonny D. Wallis Park
0.24 ac
(Non-Coastal Zone)
Enhancement Non-Coastal Zone: San Jose Creek at
Northern Segment of Pathway
Riparian1: Coyote Brush Scrub
(CCC ESHA)
1.23 ac
(Coastal Zone)
Creation/
Enhancement,
Re-establishment,
Enhancement
Coastal Zone: San Jose Creek at
Southern Segment of Pathway
Adjacent to Coastal Zone: Old San
Jose Creek at Ekwill Street
0 ac – –
Wetland/Salt Marsh1
(USACE Waters of the U.S., CDFW-jurisdictional
Streambed, RWQCB Waters of the State, CCC
ESHA)
0.08 ac
(Coastal Zone)
Enhancement Coastal Zone: Devereux Creek at
Ellwood Mesa
0 ac – –
Total3 2.82 ac 0.24
Individual Trees2
Riparian trees2 117 individuals – – Adjacent to Coastal Zone: Old San Jose Creek at Ekwill Street
Non-Coastal Zone: San Jose Creek at
Northern Segment of Pathway, San
Jose Creek at Jonny D. Wallis Park
Upland Trees 20 individuals – – Non-Coastal Zone: San Jose Creek at Pathway
Total 137 individuals
1 “Riparian” and “wetlands” as used herein are ecological terms, irrespective of agency jurisdiction. 2 Tree impacts will only occur in the Non-Coastal Zone, no impacts to trees will occur within the Coastal Zone. 3 Totals are precise numbers calculated in GIS and discrepancies with tabular data presented here may occur due to rounding. 4 Includes the Old San Jose Creek at Ekwill Street mitigation site which is adjacent to the Coastal Zone. 5 See Table 7 for a specific breakdown of mitigation technique by site. 641
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 12 Figure 4 Impacts to Protected Habitat and Jurisdicitonal Waters – Northern Segment Source: Dewberry 2023c
642
Introduction
Mitigation Plan 13
Figure 5 Impacts to Protected Habitat and Jurisdicitonal Waters – Lower Southern Segment Source: Dewberry 2023a
643
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 14 Figure 6 Impacts to Protected Habitat and Jurisdicitonal Waters – Upper Southern Segment Source: Dewberry 2023a
644
Introduction
Mitigation Plan 15
Figure 7 Impacts to Trees – Northern Segment
Note: The path alignment has been slightly modified since creation of this figure, to avoid larger mature native trees; the modified path design and reduced impact is not represented on the figure. 645
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 16 1.3 Environmental Setting
Land use designations surrounding the northern segment include Medium Density Residential, High Density Residential, Community Commercial, General Industrial, Planned Residential, and Open Space/Active Recreation. Land use designations surrounding the southern segment include Old Town (commercial), General Commercial, Business Park, Old Town, Service/Industrial, General Industrial, Mobile Home Park, Open Space, and Public/Quasi-Public. The Project is located adjacent to many local roads, as well as U.S. Route 101, SR 217, and the Union Pacific Railroad.
In accordance with the IS-MND, terrestrial habitat types within the Project area include urban (developed), ruderal (disturbed), barren lands; non-native vegetation communities such as ornamental, non-native grassland, iceplant mats (Carpobrotus spp. Herbaceous Semi-Natural Alliance), myoporum groves (Myoporum laetum Forest & Woodland Semi-Natural Alliance), and giant reed marshes (Arundo donax Herbaceous Semi-Natural Alliance); and native vegetation communities such as valley foothill riparian and coyote brush scrub (Baccharis pilularis Shrubland Alliance). Aquatic habitat types within the Project area include riverine (intermittent), ephemeral and perennial drainage, and riverine (tidal), and native vegetation communities such as arroyo willow riparian thicket (Salix lasiolepis Shrubland Alliance), southern coastal salt marsh/pickleweed mats (Salicornia pacifica Herbaceous Alliance), and southern coastal scrub shrub wetland. The Project area contains aquatic resources along San Jose Creek that fall under the jurisdiction of USACE, CDFW, Central Coast RWQCB, and CCC as detailed in Section 1.2. The banks of San Jose Creek range from gently sloping to relatively steep, and in some areas undercut, and are vegetated primarily with the understory species described under the valley foothill riparian habitat. San Jose Creek is a natural channel within the northern segment of the Project area. In the southern segment of the Project area, behind the chain link fence on the west side of SR 217, San Jose Creek is a concrete lined channel on the north, transitioning to a natural channel on the south. See Appendix B for figures depicting the habitat types and jurisdictional waters along the Project extent.
The Project is largely located within the San Pedro Creek watershed (Hydrologic Unit Code [HUC] 12 180600130202), which encompasses approximately 10,000 acres and stretches from the ridge of the Santa Ynez Mountains to its terminus in the Goleta Slough. Roughly 60 percent of the watershed supports native habitat (chaparral, oak woodland, and coastal sage scrub), and most of this occurs on steep mountainsides above Goleta and Santa Barbara. Roughly 18 percent of the watershed contains urban or impervious land uses, and 12 percent is occupied by irrigated agricultural uses (Stoecker 2002). The riparian mitigation sites are also located within the same watershed, along San Jose Creek and Old San Jose Creek. The salt marsh/wetland mitigation site is located within the Dos Pueblos Canyon-Frontal Santa Barbara Channel watershed (HUC12 180600130106), the watershed located immediately west of the Project area.
The Mediterranean climate of the Goleta region is mild, characterized by warm summers, and temperate, semi-moist winters. Daytime summer temperatures in the area average from the high 70s to mid-90s. Nighttime low temperatures during the summer are typically in the high 50s to low 60s. Winter daytime high temperature tends to be in the 60s, while winter low temperatures are in the 30s. Annual rainfall typically ranges from about 13 to 18 inches, with nearly all precipitation occurring between October and April (WRCC 2015). The ecology of Santa Barbara County includes vegetation communities consisting predominantly of coastal scrub, chaparral, oak woodland, marshlands, riparian woodland, and native and non-native grasslands. 646
Introduction
Mitigation Plan 17
1.4 Site Selection
The IS-MND states that the location of the mitigation sites will be prioritized to the Project site and immediate vicinity, as space allows, followed by off-site replacement in close proximity to the project site, and finally off-site but within the City of Goleta.
Mitigation was first pursued in appropriate areas within the immediate vicinity of the Project. To address mitigation required for impacts to riparian habitat, riparian trees, upland trees, and jurisdictional waters associated with the northern and southern segment of the path, one site was identified immediately adjacent to, and to the east of, the northern segment of the proposed San Jose Creek Multi-use Path. This mitigation site is 0.62 acre and includes additional areas for individual upland mitigation trees. To address mitigation required for impacts to riparian habitat, riparian trees, and jurisdictional waters, a second site was identified 0.06 miles south of the northern segment of the Project site along San Jose Creek within Jonny D. Wallis Park. This second mitigation site is 0.29 acre and includes additional areas for individual mitigation riparian trees. To address mitigation required for impacts to coyote brush scrub within the Coastal Zone, a third site was identified along the southern segment of the proposed San Jose Creek Multi-use Path, between the proposed path and concrete channel of San Jose Creek. This third mitigation site is 0.38 acre.
There is not enough suitable areas along San Jose Creek to reach the full mitigation acreage needed; therefore, a fourth site was established in the same watershed 0.29 miles southwest of the Project site along Old San Jose Creek at Ekwill Street that totals 1.45 acre. Photographs of the mitigation sites are provided in Appendix C.
To address mitigation required for impacts to salt marsh habitat and jurisdictional waters for the southern segment of the path, areas under investigation in the vicinity of the segment were too small, fragmented, not owned by the City of Goleta, or not available for purchase. Once the options for restoration within the San Jose Creek were exhausted, a site located in the watershed immediately to the west within the Devereux Creek watershed was chosen. Approximately 0.08 acre at Devereux Creek on Ellwood Mesa was selected because it is located in the Coastal Zone and the transitional salt and freshwater marsh at the eastern end of the property is highly degraded due to invasion by non-native plants, the site offers greater opportunities for public appreciation and involvement, and the site is adjacent and contiguous with the restoration efforts being carried out at the University of California Santa Barbara (UCSB) North Campus Open Space.
In summary, a total of 2.74 aces of riparian mitigation will be restored that consists of 0.62 acre of riparian habitat along the northern segment of the San Jose Creek Path (located outside the Coastal Zone within the City of Goleta), 0.29 acre along San Jose Creek at Jonny D. Wallis Park (located outside the Coastal Zone within the City of Goleta), 1.45 acres of riparian habitat along Old San Jose Creek near Ekwill Street (located immediately adjacent to the Coastal Zone within the City of Goleta), and 0.38 acre of riparian habitat along the southern segment of the San Jose Creek Path (located within the Coastal Zone within the City of Goleta). Although a minimum of 1.76 acres of riparian mitigation is required for impacts within the Coastal Zone, 1.83 acres of riparian mitigation will occur within and immediately adjacent to the Coastal Zone, which is collectively herein referred to as Coastal Zone mitigation. A total of 0.08 acre of salt marsh habitat will be restored along Devereux Creek on Ellwood Mesa (located within the Coastal Zone within the City of Goleta). The entirety of salt marsh mitigation will occur within the Coastal Zone. See for Table 6 a summary of acreage and habitat per mitigation site.
647
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 18 Table 6 Mitigation Site Summary
Mitigation Site by Habitat Type Coastal Zone1 Non-Coastal Zone Grand Total Riparian
San Jose Creek along the Northern Segment of Pathway – 0.62 ac 0.62 ac San Jose Creek at Jonny D. Wallis Park – 0.29 ac 0.29 ac Old San Jose Creek at Ekwill Street 1.45 ac – 1.45 ac
San Jose Creek along the Southern Segment of Pathway 0.38 ac – 0.38 ac Subtotal 1.83 ac 0.91 ac 2.74 ac
Salt Marsh/Wetland
Devereux Creek at Ellwood Mesa 0.08 ac – 0.08 ac
Grand Total 1.91 ac1 0.91 ac 2.82 ac
1 A minimum of 1.76 acres of mitigation is required for impacts within the Coastal Zone (See Table 3). Riparian mitigation will occur within the Coastal Zone at San Jose Creek along the Southern Segment of Pathway and immediately adjacent to the Coastal Zone at Old San Jose Creek near Ekwill Street, which is collectively herein referred to as Coastal Zone mitigation. The entirety of salt marsh mitigation will occur within the Coastal Zone.
In summary, mitigation for riparian impacts associated with the Project will largely occur at San Jose Creek, supplemented at Old San Jose Creek at Ekwill Street. Mitigation for salt marsh/wetland impacts associated with the Project will occur at Devereux Creek. The mitigation sites are depicted in Figure 2 and further described in Section 2.1.
1.5 Responsible Party
All funding for planning, implementation, maintenance, and monitoring of this restoration and monitoring program shall be the responsibility of the City of Goleta (Responsible Party). The Responsible Party also retains the legal responsibility for implementing and monitoring the restoration on-site as described in this Mitigation Plan and shall be responsible for meeting the conditions of the agency permits to obtain final approval of the restoration by the City of Goleta and applicable agencies.
Responsible Party contact information:
Teresa Lopes, PE, Senior Project Manager
City of Goleta, Public Works Department
130 Cremona Drive, Suite B
Goleta, California 93117
[email protected]
648
Compensatory Mitigation Plan
Mitigation Plan 19
2 Compensatory Mitigation Plan
This compensatory Mitigation Plan provides details on mitigation requirements identified in the IS- MND as described above and methods for implementing the mitigation as described below. This Mitigation Plan will be reviewed by the regulatory agencies and will be implemented by the City with direction and oversight provided by a City-approved Restoration Biologist. The City-approved Restoration Biologist shall be familiar with habitat restoration implementation, monitoring, and reporting. Installation and maintenance activities will be performed by a City-approved Restoration Contractor. The Restoration Contractor will be a qualified native landscape or restoration contractor with similar experience in habitat restoration and enhancement.
2.1 Mitigation Work Plan
The following section details the preparation and installation methods for restoration at the mitigation sites. Restoration preparation and implementation elements include the restoration approach, source of plant materials, seed storage, plant propagation, non-native plant removal, erosion control, plant installation methods, and plant protection. Maintenance and monitoring elements include established performance criteria, maintenance plan, monitoring plan, reporting requirements, and restoration schedule.
2.1.1 Restoration Approach
The riparian woodland corridor along San Jose and Old San Jose creeks will be expanded and enhanced through the removal of invasive, non-native plant species and installation of native plants.
Native species diversity and abundance will be increased along San Jose Creek in areas where riparian trees are removed for the Project, as well as in areas where invasive, non-native species have established. In addition, native upland tree abundance will be increased along Calle Real, which will also serve as visual screening. A total of 2.74 acre of riparian woodland habitat will be restored within the mitigation sites established along San Jose and Old San Jose creeks. In addition, individual riparian and upland trees will be installed outside this designated acreage. The salt marsh along Devereux Creek will be enhanced through the removal of invasive, non-native plant species and installation of native plants. Native species diversity and abundance will be increased where invasive, non-native species have established. A total of 0.08 acre of salt marsh wetland habitat will be restored within the mitigation site established along Devereux Creek. Restoration of approximately 0.24 acre will occur at the Project site to mitigate for temporary impacts to riparian habitat and jurisdictional waters due to project-related activities. See Table 7 for a summary of habitat to be restored within each mitigation site. Photographs of the mitigation sites are provided in Appendix C.
Based on impacts to individual trees, 137 mitigation trees are required (117 riparian trees and 20 upland trees). However, to ensure that all mitigation sites have proper woodland and riparian function, an additional 200 surplus trees will also be installed throughout the mitigation sites. These non-mitigation trees are herein referred to “surplus” trees, which will be installed above and beyond that which is needed for mitigation. Specifically, mitigation trees will be located along San Jose Creek at the mitigation sites along the northern segment of the pathway and at Jonny D. Wallis Park. Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the 649
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 20 pathway. All trees planned for Old San Jose Creek at Ekwill Street and San Jose Creek along the southern segment of the pathway will be surplus trees. All installed trees will be recorded thoroughly to document mitigation versus surplus. The distribution of trees per mitigation site is summarized in Table 7. See Table 8 for a summary of individual trees by species to be restored within the mitigation site.
This Mitigation Plan distinguishes creation, re-establishment, and enhancement 5 based on the
presence or absence of an existing native plant community. If the area is an upland and currently lacks native vegetation, restoration activities in the area are considered “creation” as the aquatic native vegetation or other resources will be established with the goal of returning natural functions and values to an upland area. If the area is aquatic and currently lacks native vegetation, restoration activities in the area are considered “re-establishment” as the aquatic resource (native vegetation) will be established with the goal of returning natural functions and values to a degraded aquatic resource. If native species are present in the area and opportunities for improvement exist, such as removing non-native species to allow native species to naturally disseminate, propagate, germinate and establish, restoration activities in the area are considered “enhancement” as the degraded aquatic resource (native vegetation) will be improved. Of the 2.74 acre of riparian woodland restoration, mitigation techniques will include the following: 1.02 acre is considered re- establishment as native vegetation is absent because the areas are dominated by invasive non- natives; 1.34 acres are considered enhancement as native vegetation is currently present, although degraded; and 0.38 acre is a mosaic of creation and enhancement, with the creation occurring in upland areas where aquatic resources are absent. The 0.08 acre of salt marsh wetland habitat at Devereux Creek is considered enhancement as native vegetation is currently present, although it is highly degraded.
The following restoration treatment types will be implemented:
Riparian woodland creation and re-establishment with planting and weeding Riparian woodland enhancement areas with weeding
Salt marsh wetland enhancement with planting and weeding The treatments will entail installing native trees, shrubs, and herbaceous species to provide a mosaic of shrub and tree canopy, as well as understory. A summary of habitat to be restored is provided below in Table 7. The following sections describe the detailed approach for each mitigation site.
5 Definitions based on the Compensatory Mitigation for Losses of Aquatic Resources (USACE and EPA 2008). 650
Compensatory Mitigation Plan
Mitigation Plan 21
Table 7 Summary of Habitat to be Restored within Each Mitigation Site Mitigation Technique
Mitigation Site
and Habitat
Riparian Re-establishment
(Acres or Number of
Individual Trees)
Riparian
Enhancement
(Acres)
Creation/
Enhancement
(Acres)
Grand
Total
(Acres)
Projected
Jurisdictional
Water Body
San Jose Creek along the Northern Segment of the Pathway Riparian
woodland
0.37 ac 0.25 ac – 0.62 ac CDFW streambed,
RWQCB Non-
wetland waters of
the State
Individual riparian
trees
Up to 111 trees1 – – – –
Individual upland
trees
20 trees – – – –
San Jose Creek at Jonny D. Wallis Park
Riparian
woodland
0.07 ac 0.22 ac – 0.29 ac CDFW streambed,
RWQCB Non-
wetland waters of
the State
Individual riparian
trees
Up to 41 trees1
(17 existing + 24 new)
– – – –
Old San Jose Creek at Ekwill Street (Adjacent to Coastal Zone) Riparian
woodland
0.58 ac 0.87 – 1.45 ac CDFW streambed,
RWQCB Non-
wetland waters of
the State
Individual riparian
trees
Up to 150 trees1
San Jose Creek along the Southern Segment of the Pathway (In Coastal Zone) Riparian
shrubland
– – 0.38 ac 0.38 ac Uplands adjacent
to jurisdictional
waters
Individual riparian
trees
15 trees
1 Riparian Subtotal 1.02 ac 1.34 ac 0.38 ac 2.74 ac
Devereux Creek at Ellwood Mesa (In Coastal Zone)
Salt marsh
wetland
– 0.08 ac – 0.08 ac CDFW streambed,
RWQCB Wetland
waters of the State,
CCC wetland
Grand Total 1.02 ac
137 mitigation trees + up
to 200 surplus trees
(337 trees total) 1
1.42 ac 0.38 ac 2.82 ac
1 Mitigation trees will be located along San Jose Creek along the northern segment of the pathway and at Jonny D. Wallis Park.
Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the pathway. All trees planned for Old San Jose Creek at Ekwill Street and San Jose Creek along the southern segment of the pathway will be surplus trees. 651
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 22 Table 8 Summary of Individual Trees by Species to be Restored within the Mitigation Sites
Scientific Name Common Name
Total Mitigation
Trees Required2
Mitigation Trees
to be Installed
Required2
Surplus Trees
to be
Installed2
Grand
Total
Eucalyptus cladocalyx
and E. globulus
sugar gum and blue
gum eucalyptus
33 1 – – –
Juglans californica Southern California
black walnut
6 12 – –
Platanus racemosa Western sycamore 24 24 – –
Populus trichocarpa black cottonwood 36 36 – –
Quercus agrifolia coast live oak 11 33 – –
Salix lasiolepis arroyo willow 27 27 – –
Umbellularia californica California bay 0 5 – –
Total
137 137 Up to 200 Up to 337
1 Eucalyptus will be replaced with native trees.
2 Mitigation trees will be located along San Jose Creek along the northern segment of the pathway and at Jonny D. Wallis Park.
Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the pathway. All trees planned for Old San Jose Creek at Ekwill Street and San Jose Creek along the southern segment of the pathway will be surplus trees.
San Jose Creek along the Northern Segment of Pathway
Mitigation for permanent impact to riparian habitat, riparian trees, and jurisdictional waters will occur within the future City ROW along San Jose Creek (excluding the active channel) immediately adjacent to, and east of, the northern segment of the pathway. The site is located outside the Coastal Zone. San Jose Creek is intermittent within this reach and is steelhead critical habitat as well as a City-designated riparian ESHA. This portion of San Jose Creek is characterized as California sycamore – coast live oak riparian woodland (Platanus racemosa – Quercus agrifolia Woodland Alliance). Native trees are abundant; however, several patches of giant reed (Arundo donax) are present and the understory is dominated by non-natives, offering ample opportunity for restoration. Re-establishment of 0.37 acre of riparian woodland and enhancement of 0.25 acre of riparian woodland, for a total of 0.62 acre, will occur as outlined further below. See Figure 8 for the restoration layout.
Mitigation for permanent impact to upland trees will occur along Calle Real, south of the path, north of U.S. Route 101, and west of San Jose Creek. Mitigation will occur within the Caltrans easement for U.S. Route 101, specifically in the upland temporary impact area. The upland habitat is not ESHA and is characterized as ornamental/landscape and ruderal. Individual upland trees will be installed as outlined below. See Figure 8 for the restoration layout.
Mitigation for temporary impacts to riparian habitat and jurisdictional waters will occur on both sides of the path. Approximately 0.24 acres will be restored. Although these areas are mutually exclusive from the re-establishment area designated for permanent impacts, the native trees that will be installed in the temporary impact areas on the east side of the path are included in the quantities therein (Figure 8). The edge of the riparian woodland will be enhanced with a variety of native tree species that provide important food and shelter sources for a variety of wildlife species.
The function of the San Jose Creek riparian corridor will also be improved as it is currently invaded by non-native plants in the understory.
652
Compensatory Mitigation Plan
Mitigation Plan 23
Riparian Re-establishment
Re-establishment of 0.37 acre of riparian woodland will occur along San Jose Creek ROW (excluding the active channel) immediately adjacent to and east of the Project site, within the areas where native and non-native trees will be removed for the Project and where large patches of giant reed will be removed (Figure 8). Up to 111 riparian trees will be installed as 1-gallon containers or ½- gallon tree tubes at 10-foot spacing. This quantity of trees includes those that will be installed within the temporary impact areas. If it is determined after Project construction and associated tree removal is complete that there is not enough space for the proposed number of trees, they will be installed at the Old San Jose Creek at Ekwill Street site instead, as described in corresponding Section below. Native herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. See Table 9 for the native plant palette. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. Plant installation methods are described in Section 2.1.5. Non-native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
Table 9 Native Plant Palette – San Jose Creek along the Northern Segment of Pathway Scientific Name Common Name Quantity1
Riparian Trees2
Juglans californica Southern California black walnut 3
Platanus racemosa Western sycamore 30
Populus trichocarpa black cottonwood 32
Quercus agrifolia coast live oak 6
Salix lasiolepis arroyo willow 37
Umbellularia californica California bay 3
Subtotal Up to 111 3
Shrubs
Baccharis salicifolia mulefat TBD
Frangula californica California coffeeberry TBD
Heteromeles arbutifolia toyon TBD
Lonicera subspicata var. subspicata Santa Barbara honeysuckle TBD Phacelia ramosissima branching phacelia TBD
Sambucus mexicana (S. nigra) blue elderberry TBD
Subtotal 193
Grasses, Forbs, and Vines
Artemisia douglasiana mugwort TBD
Bromus carinatus California brome TBD
Carex barbarae Santa Barbara sedge TBD
Clematis ligusticifolia creek clematis TBD
Distichlis spicata saltgrass TBD
Elymus condensatus giant wild rye TBD
Elymus triticoides alkali ryegrass TBD
Euthamia occidentalis Western goldenrod TBD
Hordeum brachyantherum subsp. californicum California barley TBD Juncus patens common California rush TBD
653
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 24 Scientific Name Common Name Quantity1
Juncus phaeocephalus brown-headed rush TBD
Juncus textilis Basket rush TBD
Juncus xiphioides iris-leaved rush TBD
Rosa californica California rose TBD
Rubus ursinus California blackberry TBD
Salvia spathacea hummingbird sage TBD
Scrophularia californica California figwort TBD
Solidago velutina subsp. californica velvety goldenrod TBD Verbena lasiostachys verbena TBD
Subtotal 340
Total 645
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
2 The native trees that will be installed in the temporary impact areas are included in the quantities. 3 Mitigation trees will be located along San Jose Creek at the mitigation sites along the northern segment of the pathway and at Jonny D. Wallis Park. Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the pathway.
Riparian Enhancement
Enhancement of 0.37 acre of riparian woodland enhancement will occur along San Jose Creek ROW (excluding the active channel) immediately adjacent to and east of the Project, within the areas where non-native shrubs and herbs are present within the native tree canopy (Figure 8). Generally, this area is east of the re-establishment area. Non-native plants are abundant, especially in the understory, and will be removed throughout the area as described in Section 2.3.2.
Individual Upland Trees
Mitigation for permanent impact to upland trees will occur along Calle Real, south of the path, north of U.S. Route 101, and west of San Jose Creek (Figure 8). Mitigation will occur within the Caltrans easement for U.S. Route 101, specifically in the upland temporary impact area along the south side of the path. Twenty coast live oak trees will be installed as 15-gallon containers or 24-inch or 36- inch boxes at approximately 10 to 15-foot spacing on-center. The coast live oaks will also serve as visual screening for the residential and commercial properties in the immediate vicinity. Non-native plants will be removed within a 3-foot radius from each mitigation tree as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
Temporary Impact Areas (Riparian)
Up to 0.24 acres of temporary impacts may occur during construction along the path within the riparian habitat (Figure 4 and Figure 8). Individual riparian trees will be installed in these areas as described above in the Riparian Re-establishment Section; quantities are included therein. Herbs and shrubs will also be installed to provide native cover and help reduce potential erosion issues.
The installation approach will be similar to that described above in the Riparian Re-establishment Section. Quantities are not provided herein as the temporary impact areas are dependent upon the final footprint of construction.
654
Compensatory Mitigation Plan
Mitigation Plan 25
Figure 8 Restoration Layout – San Jose Creek along Northern Segment of Pathway
Note: The path alignment has been slightly modified since creation of this figure, to avoid larger mature native trees; the modified path design and reduced impact is not represented on the figure. 655
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 26 San Jose Creek at Jonny D. Wallis Park
Mitigation for permanent impact to riparian habitat, riparian trees, and jurisdictional waters will occur within the City-owned property along San Jose Creek at Jonny D. Wallis Park. The site is located outside the Coastal Zone. San Jose Creek is intermittent within this reach and is steelhead critical habitat as well as a City-designated riparian ESHA. This portion of San Jose Creek is characterized as California sycamore – coast live oak riparian woodland. Native trees are abundant; however, several patches of herbaceous invasive non-natives are present in the understory, as well as one patch of non-native golden rain trees (Koelreuteria paniculata), offering opportunity for restoration. Re-establishment of 0.07 acre of riparian woodland and enhancement of 0.22 acre of riparian woodland, for a total of 0.29 acre, will occur as outlined further below. See Figure 9 for the restoration layout.
Mitigation for permanent impact to riparian trees will occur within the park in two ways. Firstly, individual riparian trees will be installed along the edge of the existing riparian canopy, within the park grounds where an unmaintained or semi-natural understory occurs as further described below.
Secondly, riparian trees already installed within the park grounds along the edge of the existing riparian canopy where an unmaintained or semi-natural understory occurs are included as mitigation trees for this Project as described further below. See Figure 9 for the restoration layout.
The edge of the riparian woodland will be enhanced with a variety of native tree species that provide important food and shelter sources for a variety of wildlife species. The function of the San Jose Creek riparian corridor will also be improved as there are several gaps in the native overstory and the understory has non-native plants.
Riparian Re-establishment
Re-establishment of 0.07 acre of riparian woodland will occur within the park along San Jose Creek (excluding the active channel), within the areas where non-native trees and understory will be removed (Figure 9). Up to 24 riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. See Table 10 for the native plant palette. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
Plant installation methods are described in Section 2.1.5. Non-native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
656
Compensatory Mitigation Plan
Mitigation Plan 27
Table 10 Native Plant Palette – Jonny D. Wallis Park
Scientific Name Common Name Quantity1
Riparian Trees2
Juglans californica Southern California black walnut 3
Platanus racemosa Western sycamore 4
Populus trichocarpa black cottonwood 11
Quercus agrifolia coast live oak 3
Salix lasiolepis arroyo willow 3
Subtotal Up to 24 3
Shrubs
See Table 9 for species
Subtotal 37
Grasses, Forbs, and Vines
See Table 9 for species
Subtotal 61
Total 122
1 In the re-establishment area, riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. In the park grounds, riparian trees will be installed as 15-gallon containers, 1-gallon containers, or ½-gallon tree tubes at 10-foot spacing.
Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. 2 The native trees that will be installed in the park grounds, outside of the re-establishment area, are included in the quantities. 3 Mitigation trees will be located along San Jose Creek at the mitigation sites along the northern segment of the pathway and at Jonny D. Wallis Park. Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the pathway.
Riparian Enhancement
Enhancement of 0.22 acre of riparian woodland will occur along San Jose Creek (excluding the active channel), within the areas where non-native shrubs and herbs are present within the native tree canopy (Figure 9). Generally, this area is surrounding and east of the re-establishment area. Non- native plants are abundant, especially in the understory, and will be removed throughout the area as described in Section 2.3.2.
Individual Riparian Trees
Mitigation for permanent impact to riparian trees will occur along the edge of the existing riparian canopy within the park grounds where an unmaintained or semi-natural understory occurs (Figure 9). Specifically, these areas include park grounds along the existing footpaths where the understory is comprised of installed landscape or ornamental native plants and minimally maintained by weeding and/or mulching. Up to 8 riparian trees will be installed as 15-gallon containers, 1-gallon containers, or ½-gallon tree tubes at 10-foot spacing. If available, the 15-gallon size is preferred for the park grounds and will be installed. See Table 10 for the native plant palette.
These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. Plant installation methods are described in Section 2.1.5. Non- native plants will be removed within a 3-foot radius as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3. 657
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 28 Individual Riparian Trees – Existing Native Landscape Mitigation for permanent impact to riparian trees will occur within the park grounds along the existing riparian canopy will include native trees that have already been installed; these 17 riparian trees have an un-maintained or semi-natural understory (Figure 9). See Table 11 for the existing native landscaping trees that will be included as mitigation. As part of this mitigation effort, the existing western sycamore x London plane hybrid trees will be removed and replaced with native western sycamore trees that have been locally sourced from cuttings from known pure genetic stock, e.g., the Sister Witness Tree. Non-native plants will be removed within a 3-foot radius around each mitigation tree as described in Section 2.3.2 and supplemental irrigation will be applied to the western sycamores as described in Section 2.3.3. The mitigation trees that have been planted in Jonny D. Wallis Park will not be irrigated as they are already established.
Table 11 Existing Native Landscape Trees for Mitigation – Jonny D. Wallis Park Scientific Name Common Name Quantity
Riparian Trees
Platanus racemosa x P. hispanica
(to be replaced by P. racemosa)
Western sycamore x London plane
(to be replaced by western sycamore)
8 Quercus agrifolia coast live oak 7
Umbellularia californica California bay 2
Total 17 1
1 Mitigation trees will be located along San Jose Creek at the mitigation sites along the northern segment of the pathway and at Jonny D. Wallis Park. Combined, the trees designated for these two mitigation sites will likely be more than required for mitigation; therefore, there will likely be surplus trees installed at the northern segment of the pathway.
Old San Jose Creek at Ekwill Street
Mitigation for permanent impact to riparian habitat and jurisdictional waters will occur along Old San Jose Creek near Ekwill Street within two separate areas, City-owned property to the east and City ROW to west. Old San Jose Creek is ephemeral and a City-designated riparian ESHA. The site is located immediately adjacent to the Coastal Zone. This portion of Old San Jose Creek is characterized largely by black locust groves (Robinia pseudoacacia Woodland Semi-Natural Alliance) and eucalyptus groves (Eucalyptus spp. Woodland Semi-Natural Alliance) with limited black cottonwood woodland (Populus trichocarpa Forest & Woodland Alliance) and arroyo willow thickets (Salix lasiolepis Shrubland Alliance). The existing eucalyptus grove between the two areas supports western monarchs (Danaus plexippus), a sensitive species. This site is known as Site 114 and is fully described in Monarch Butterfly Overwintering Sites, Santa Barbara County (Meade et al. 2017). The site is an autumnal site, or a transitory site, meaning monarchs temporarily roost here before moving onto more suitable overwintering habitat. The site has been surveyed regularly since 2015, with the number of monarchs ranging widely with zero in 2015, 140 in 2016, 0 in 2017, and 2 in 2018 (Xerces Society 2019). The eucalyptus grove that comprises this section of the mitigation site will be restored specifically for monarchs. Native trees, shrubs, and understory are minimal along the creek here, and the understory is dominated by non-natives, offering ample opportunity for restoration. Re-establishment of 0.58 acre of riparian woodland re-establishment and 0.87 acres of riparian enhancement for monarchs, for a total of 1.45 acres, will occur as outlined further below.
See Figure 10 for the restoration layout.
658
Compensatory Mitigation Plan
Mitigation Plan 29
Figure 9 Restoration Layout – San Jose Creek at Jonny D. Wallis Park 659
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 30 Figure 10 Restoration Layout – Old San Jose Creek at Ekwill Street
660
Compensatory Mitigation Plan
Mitigation Plan 31
The extent of the riparian woodland will be enhanced with a variety of native tree species that provide important food and shelter sources for a variety of wildlife species. Specifically, the site offers opportunities to improve habitat for the monarch butterfly by providing nectar plants and by eventually providing wind buffer of native trees. The function of the Old San Jose Creek riparian corridor will also be improved as it is invaded by non-native plants in the understory and overstory.
The site will be adjacent to the restoration efforts for the Ekwill Street and Fowler Road Improvement Project.
Riparian Re-establishment
Re-establishment of 0.58 acre of riparian woodland will occur along Old San Jose Creek in two sections, City-owned property to the east and City ROW to west (Figure 10). Up to 150 riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. In coordination with a monarch biologist, the City-approved Restoration Ecologist will take special care to install a native planting “perimeter” around the existing eucalyptus habitat to help protect the grove and provide a wind buffer for the monarchs. See Table 12 for the native plant palette. These species and quantities are general guidelines and are subject to change based on availability from the nursery, site conditions, and further coordination with monarch biologists to design the native plant perimeter around the eucalyptus grove. Plant installation methods are described in Section 2.1.5. Non-native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
Table 12 Native Plant Palette – Old San Jose Creek at Ekwill Street – Riparian Re- establishment Areas
Scientific Name Common Name Quantity1
Riparian Trees
Juglans californica Southern California black walnut TBD Platanus racemosa western sycamore TBD
Populus trichocarpa black cottonwood TBD
Quercus agrifolia coast live oak TBD
Salix lasiolepis arroyo willow TBD
Umbellularia californica California bay TBD
Subtotal Up to 150 2
Shrubs
See Table 9 for species
Baccharis pilularis Coyote bush TBD
Subtotal 303
Grasses, Forbs, and Vines
See Table 9 for species
Subtotal 557
Total 1,011
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
2 All trees planned for Old San Jose Creek at Ekwill Street and San Jose Creek along the southern segment of the pathway will be surplus trees.
661
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 32 Riparian Enhancement for Monarchs
Enhancement of 0.87 acre of riparian woodland will occur along Old San Jose Creek in one section, City-owned property to the east and City ROW to west (Figure 10). The eucalyptus grove that comprises this section of the mitigation site will be restored specifically for monarchs. Over the past three to four years the City has worked with a team of monarch butterfly scientists and certified arborists to develop strategies to support and enhance monarch butterfly habitat. Strategies include mitigating fire risk by removing dead trees and vegetation and trimming dead branches, installing plants that flower in fall and winter and provide nectaring opportunities near and around the eucalyptus grove, and planting native understory provides an opportunity for the monarch to climb off of the ground when winter storms blow them off of the trees and they have not yet warmed to the temperature at which they can fly. In coordination with a monarch biologist, the City-approved Restoration Ecologist will take special care to install a native planting “perimeter” around the existing eucalyptus habitat to help protect the grove and provide a wind buffer for the monarchs.
No trees or large shrubs will be installed within the eucalyptus grove to avoid inadvertently negatively affecting the mid-story and overstory canopy of the existing eucalyptus trees. Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. See Table 13 for the native plant palette. These species and quantities are general guidelines and are subject to change based on availability from the nursery, site conditions, and further coordination with monarch biologists to design the native plant perimeter around the eucalyptus grove. Plant installation methods are described in Section 2.1.5. Non-native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
Table 13 Native Plant Palette – Old San Jose Creek at Ekwill Street – Riparian Re- establishment for Monarch Area
Scientific Name Common Name Quantity1
Shrubs
Baccharis pilularis Coyote bush TBD
Eriogonum fasciculatum California buckwheat TBD
Isocoma menziesii coastal goldenbush TBD
Mimulus aurantiacus bush monkeyflower TBD
Rhus integrifolia lemonade berry TBD
Subtotal 28
Grasses, Forbs, and Vines
Dichelostemma capitatum blue dicks TBD
Euthamia occidentalis western goldenrod TBD
Helianthus californicus California sunflower TBD
Solidago velutina subsp. californica velvety goldenrod TBD Verbena lasiostachys var.
lasiostachys
verbena TBD
Subtotal 66
Total 95
TBD = To be determined
1 Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. 662
Compensatory Mitigation Plan
Mitigation Plan 33
Devereux Creek at Ellwood Mesa
Mitigation for permanent impact to salt marsh wetland habitat and jurisdictional waters will occur within City-owned property along Devereux Creek at the eastern edge of the Ellwood Mesa Open Space Preserve. The site is located within the Coastal Zone. The confluence of Devereux Creek and Devereux Slough is at this location, and is a City-designated marsh ESHA. This portion of Devereux Creek is characterized largely by native alkali heath marsh (Frankenia salina Herbaceous Alliance).
Native forbs are present; however, non-natives have colonized the area due to regular disturbance, offering ample opportunity for restoration. Enhancement of 0.08 acre of the transitional salt and freshwater marsh wetland will occur as further outlined below. See Figure 11 for the restoration layout.
The transitional salt and freshwater marsh wetland will be enhanced with a variety of native herbaceous species that provide important food and shelter sources for a variety of wildlife species.
The function of the Devereux Creek corridor will also be improved as it is invaded by non-native plants in the existing marsh. The site offers greater opportunities for public appreciation and involvement, and the site is adjacent and contiguous with the restoration efforts being carried out at the UCSB North Campus Open Space and will be adjacent to the prosed restoration efforts for the Ekwill Street and Fowler Road Improvement Project.
Salt Marsh Wetland Enhancement
Enhancement of 0.08 acre of marsh wetland will occur along Devereux Creek at the eastern edge of the Ellwood Mesa Open Space Preserve (Figure 11). The exact layout of this site might change slightly as the City is planning for a small pedestrian foot bridge in this general area and the exact location is unknown at this time. In addition, minor grading may be needed to restore better flow and function to the area chosen. Herbs and select shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. See Table 14 for the native plant palette.
These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. Plant installation methods are described in Section 2.1.5. Non- native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3. 663
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 34 Table 14 Native Plant Palette – Devereux Creek at Ellwood Mesa Scientific Name Common Name Quantity1
Shrubs
Isocoma menziesii coast goldenbush TBD
Atriplex lentiformis quailbush TBD
Subtotal 14
Grasses and Forbs
Anemopsis californica yerba mansa TBD
Carex barbarae Santa Barbara sedge TBD
Cyperus eragrostis umbrella-sedge TBD
Distichlis spicata saltgrass TBD
Eleocharis macrostachya common spikerush TBD
Frankenia salina alkali heath TBD
Jaumea carnosa fleshy jaumea TBD
Juncus patens common California rush TBD
Juncus phaeocephalus brown-headed rush TBD
Paspalum distichum knot grass TBD
Schoenoplectus acutus hardstem bulrush TBD
Subtotal 125
TBD = To be determined
1 Herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. 664
Compensatory Mitigation Plan
Mitigation Plan 35
Figure 11 Restoration Layout – Devereux Creek at Ellwood Mesa 665
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 36 San Jose Creek along the Southern Segment of Pathway Mitigation for permanent impact to riparian habitat and jurisdictional waters will occur within the City-owned property immediately adjacent to, and west of, the southern segment of the pathway, and west of SR 217. The site is located within the Coastal Zone. San Jose Creek is intermittent within this reach and is steelhead critical habitat as well as a City-designated unvegetated open creek channel ESHA. Additionally within this reach, San Jose Creek is completely channelized for flood protection and therefore confined between concrete walls. This portion of the creek consists of an articulated concrete revetment mat along the bottom with slotted weirs for fish passage. A layer of fine textured alluvium and sand occurs along the eastern side of the channel. Vegetation is found only on the east side of the channel and is characterized as patchy coyote brush scrub in the compacted and disturbed areas between the creek and SR 217. The coyote brush scrub, an upland species, is located outside and adjacent to jurisdictional waters. The coyote brush is not hydrologically dependent upon San Jose Creek due to the presence of the concrete channel. A patchwork of creation and enhancement of 0.38 acre of riparian scrubland will occur in areas that lack or are dominated by coyote brush, respectively, as outlined further below. See Figure 12 and Figure 13 for the restoration layout.
The edge of the uplands adjacent to the concrete channel will be enhanced with a variety of native shrub species and a few tree species that provide important food and shelter sources for a variety of wildlife species. The function of the San Jose Creek riparian corridor will also be improved as it is currently lacking native vegetation in some areas.
Riparian Creation/Enhancement
A patchwork of creation and enhancement of 0.38 acre of riparian shrubland in the form of coyote bush and coastal sage scrub will occur along San Jose Creek immediately adjacent to, and west of, the southern segment of the pathway, and west of SR 217 (Figure 12 and Figure 13). Creation will occur in upland areas adjacent to the creek where native vegetation is absent and enhancement will occur in areas where native vegetation, i.e., coyote brush scrub, is present. Up to 15 riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Trees will only be installed at the southern end of the mitigation site where there is enough space to ensure that tree roots do not inadvertently cause damage to the concrete channel. Native herbs and shrubs will be installed as 1-gallon or 4-inch containers at 5-foot spacing and will largely be installed in areas without existing coyote brush. See Table 15 for the native plant palette. These species and quantities are general guidelines and are subject to change based on availability from the nursery and site conditions. Plant installation methods are described in Section 2.1.5. Non-native plants will be removed throughout the area as described in Section 2.3.2 and supplemental irrigation will be applied as described in Section 2.3.3.
666
Compensatory Mitigation Plan
Mitigation Plan 37
Figure 12 Restoration Layout – San Jose Creek along Southern Segment of Pathway – Lower Portion
667
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 38 Figure 13 Restoration Layout – San Jose Creek along Southern Segment of Pathway – Upper Portion
668
Compensatory Mitigation Plan
Mitigation Plan 39
Table 15 Native Plant Palette – San Jose Creek along Southern Segment of the Pathway Scientific Name Common Name Quantity1
Riparian Trees
Juglans californica Southern California black walnut TBD Platanus racemosa western sycamore TBD
Populus trichocarpa black cottonwood TBD
Quercus agrifolia coast live oak TBD
Subtotal Up to 15 2
Shrubs
Artemisia californica California sagebrush TBD
Baccharis pilularis Coyote brush TBD
Diplacus aurantiacus bush monkeyflower TBD
Encelia californica California sunflower TBD
Epilobium canum California fuchsia TBD
Eriogonum parvifolium Seacliff buckwheat TBD
Frangula californica California coffeeberry TBD
Heteromeles arbutifolia toyon TBD
Isocoma menziesii Coastal goldenbush TBD
Lonicera subspicata var. subspicata Santa Barbara honeysuckle TBD Phacelia ramosissima branching phacelia TBD
Salvia leucophylla purple sage TBD
Salvia mellifera black sage TBD
Sambucus nigra blue elderberry TBD
Subtotal 99
Grasses, Forbs, and Vines
Ambrosia psilostachya var. californica Western ragweed TBD Artemisia douglasiana Mugwort TBD
Bromus carinatus California brome TBD
Carex barbarae Santa Barbara sedge TBD
Clematis ligusticifolia creek clematis TBD
Elymus condensatus giant wild rye TBD
Elymus triticoides alkali ryegrass TBD
Hordeum brachyantherum subsp. californicum California barley TBD Rosa californica California rose TBD
Salvia spathacea hummingbird sage TBD
Scrophularia californica California figwort TBD
Solidago velutina subsp. californica velvety goldenrod TBD Verbena lasiostachys verbena TBD
669
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 40 Scientific Name Common Name Quantity1
Subtotal 51
Total 166
TBD = To be determined
1 Riparian trees will be installed as 1-gallon containers or ½-gallon tree tubes at 10-foot spacing. Herbs and shrubs will be installed as 1- gallon or 4-inch containers at 5-foot spacing. These quantities are general guidelines and are subject to change based on availability from the nursery and site conditions.
2 Approximately 20 trees can be installed at the southern/downstream ed of the mitigation site. All trees planned for Old San Jose Creek at Ekwill Street and San Jose Creek along the southern segment of the pathway will be surplus trees.
2.1.2 Source of Plant Materials
The large coast live oaks installed along the path along Calle Real as visual screening will be commercially available California natives with relatively low restrictions for the genetic requirements.
For the remainder and the majority of the plant stock, a qualified native nursery in coordination with the City-approved Restoration Biologist will gather plant stock, e.g., seeds and cuttings. To preserve the integrity of local gene pools, ensure adaptation to site-specific conditions, and avoid inadvertent introduction of inappropriate species or pathogens the native plant material used for revegetation will primarily be collected from the San Jose Creek and Devereux Creek watersheds. If sufficient plant material cannot be collected from this area alone, plant material from the Santa Barbara coast south of the Santa Ynez Mountains between Carpinteria and Gaviota will be used.
Specifically, the existing western sycamore x London plane hybrid trees that will be removed and replaced with western sycamores at Jonny D. Wallis Park will be locally sourced from cuttings collected from known pure genetic stock, e.g., the Sister Witness Tree. If native material that doesn’t adhere to these sources is accidentally installed, the individuals will be removed as soon as possible and replaced with locally-native plants. More specific areas for collection of native plant materials within the areas defined above will be defined in the field, taking into account the following:
Ecological similarity to the area to the Project site
Proximity to the Project site
Land ownership
Accessibility
Abundance and availability of target species
Native plant collection shall ensure genetic diversity of source material and seed shall be collected from a diverse sample of the parent plants within the collection zone.
2.1.3 Seed Storage and Plant Propagation
A qualified native nursery contractor will store and propagate plant stock. As discussed further in Section 2.6, seed and cutting collection, and propagation of plants, will occur prior to mitigation installation and up to two years thereafter.
Seeds will be stored in a proper container in a cool, dry place. If necessary, seeds will be treated with freezing temperatures to kill insect pests by placing seeds in a freezer for 2 or 3 days. If necessary, seeds will be treated with low heat or a dehumidifier to reduce excess moisture. All containers of seeds will be labeled with the scientific name, date, and location of collection. 670
Compensatory Mitigation Plan
Mitigation Plan 41
Seeds will be sown, or cuttings will be used, to establish container plants. These container plants can either be planted in the field or used to create additional seeds or cuttings in the nursery. Salvaged plants will be either directly transplanted by a qualified native landscape contractor or taken to the nursery and prepared for later transplanting. Nursery plants must be maintained in a healthy condition until delivery, free of any disease and pests. All plants obtained from the native plant nursery will be free of Argentine ants (Linepithema humile).
2.1.4 Site Preparation
Prior to plant installation, a qualified City-approved Restoration Contractor with oversight by the City-approved Restoration Biologist will remove non-native plants at the mitigation sites. Non-native plants will be removed primarily using hand removal methods, such as hand-held weed whips, loppers, and hoes. If hand removal is not feasible due to species resistance to hand removal methods, the size of the plant, or the number of plants, perennial invasive non-native species may be treated with herbicides.
Herbicide application will be limited as much as possible while maintaining effectiveness. Only individual plants will be treated; blanket spraying efforts will not be allowed. If herbicide is applied, it will be applied during dry and low wind conditions to prevent conveyance of herbicide into San Jose, Old San Jose, or Devereux creeks or other non-targeted areas. Herbicide application must be performed by a licensed applicator that can identify the species to be treated and is experienced in the handling and application of herbicides. Herbicides must be approved for use by the City and authorized under permit and property conditions. Only herbicides approved for use near or in water, such as AquaMaster™ or equivalent, will be used if necessary. Low toxicity herbicides should be used to the greatest extent practical. Rodenticides containing any anticoagulant compounds (including, but not limited to, Warfarin, Brodifacoum, Bromadiolone, or Diphacinone) will not be used.
One goldenrain tree at Jonny D. Wallis Park and several black locusts at Old San Jose Creek at Ekwill Street will need to be removed/treated prior to restoration installation. Removal/treatment will occur before planting begins in the area. Dependent upon the City’s need for safety and protecting existing infrastructure at the park or protecting native plants that may be present at either site, the trees may be removed or girdled and left in place. For those trees that can be removed, stump grinding or similar method will be used to remove most of the trunk to ground level or to 6-12 inches below ground level if possible. Holes will then be made mechanically within the root zone to allow for native plants to be installed. If the stump can be removed to 6-12 inches below ground level, soil will be placed in the hole and plants will be installed there as well. Trees may be chipped on-site, and chipped trees may be used as mulch after they have dried out. For those trees that can be girdled, girdling will occur by removing the bark around the entire circumference of the trunk, thereby preventing transport of water and nutrients, and killing the tree. These trees will be left in place to minimize any further disturbance to native plants that would result from removal, to provide habitat for nesting birds and other wildlife as they decay, and to provide eventual structure in the creek bottom once they break down (a habitat value that is currently lacking in the creek).
Vegetation with potential to contain bird nests will not be removed during the breeding bird season (approximately February 1 through August 31) unless a City-approved biologist determines that it does not contain active bird nests. Tree removal will not occur during the monarch butterfly aggregation season (approximately October 1 through March 31) if aggregating monarchs are present.
Long term non-native plant removal will be conducted as described in Section 2.3.2. 671
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 42 2.1.5 Plant Installation Methods
A qualified Restoration Contractor with oversight by the City-approved Restoration Biologist will install plants to coincide with the first major winter storm (approximately October to December) when soil conditions are moist. The City-approved Restoration Biologist will determine precise planting locations in the field.
On average, 5-foot spacing will be used for shrubs, vines, grasses, and forbs. On average, tree species will be installed at 10-foot spacing. Table 9 through Table 15 provides the mix of plants and quantities for each riparian habitat type to be re-established.
Holes for the 1-gal container plants will be dug by hand using a shovel, hang auger, or similar device.
Holes for the larger trees along Calle Real and in the park grounds of Jonny D. Wallis Park will be dug with medium or light-duty equipment as needed. Care will be taken not to disturb the root ball, stems, or branches when installing each container plant. The soil will be backfilled so as not to leave any air spaces around the container plant soil and roots. Planting pits will be backfilled with native soil so that the soil surface of the container plant is level with the ground. If soil conditions indicate that soil amendments such as biochar, mycorrhizae inoculum, or similar is needed, they will be employed.
After installation, mulch will be placed around each plant to prevent non-native plants from establishing and to help increase soil moisture. Mulch will be placed around each container plant at a depth of 2 to 3 inches. Mulch will be placed in a 2-foot radius for trees and a 1-foot radius for other species. Mulch shall not be allowed to contact the trunks of planted trees as this can lead to fungal development and rot. If applicable, mulch originating from the non-native on-site trees as described in Section 2.1.4 will be allowed some time to dry and then will be used around installed plants as feasible. Additional bark mulch originating from Santa Barbara, such as mulch available from the County’s South Coast Recycling and Transfer Station, may be acquired as needed. Mulch should be organic, and mulch derived from Eucalyptus species shall be avoided unless it has been cured for a substantial amount of time. All purchased mulch will be free of Argentine ants.
Each container plant will be immediately watered until soil saturation is reached by a drip emitter system if feasible or by hand if water connections are not available. Long term irrigation will be applied as described in Section 2.3.3.
2.1.6 Plant Protection
Individual container plantings will not have any specific protection; however, if needed, signage and temporary construction fencing will be placed around the mitigation sites to inform people to stay out of the restoration area to minimize trampling of native plants. The temporary fencing will be made of green construction mesh-like fence approximately 4 feet high and t-posts (or similar).
Fencing will follow the outer borders of each planting area. Underground gopher cages will be used only if gophers are abundant in the area. If needed, wire cages will be placed around container plants aboveground to prevent herbivory where needed.
2.1.7 Erosion Control
If deemed necessary, the Restoration Contractor with oversight by the City-approved Restoration Biologist will install erosion control materials, although problematic erosional issues are not expected to occur as there are no issues presently on-site. Erosion control devices may include hay bales at the base of slopes, jute netting, coconut fiber mats, fiber rolls, and/or straw wattle. Erosion 672
Compensatory Mitigation Plan
Mitigation Plan 43
control materials containing plastics will not be used due to the hazards they pose to wildlife.
Erosion control materials shall be weed free. If vegetation needs to be removed to install erosion control materials, it will not be removed during the breeding bird season (approximately February 1 through August 31) unless a City-approved biologist determines that it does not contain active bird nests. Erosion control materials will be maintained during the 5-year maintenance period or until plants are well established.
2.1.8 Access Routes and Staging Areas
The mitigation site will be accessed by vehicle via the closest public road or City parking lot, then from the pathway as feasible. From the street or the pathway, the mitigation sites will be accessed by foot. Staging areas will mainly be located near the vehicles; however, smaller staging areas may be sited within the planting areas. Staging areas will be contained to the smallest footprint possible and will not disturb native vegetation.
2.2 Performance Criteria
Performance criteria will be used to determine if the Project is successful during the 5-year maintenance and monitoring period as described in Sections 2.3 and 2.4. The following performance criteria have been set within this Mitigation Plan. These criteria are typical for the region and biologically appropriate for the sites.
Installed trees shall have a minimum of 80 percent survival at the end of 5 years.
Installed non-tree species shall have a minimum of 80 percent survival at the end of 5 years.
Achieve 70 absolute percent native cover after 3 years and 85 absolute percent coverage by the end of the 5-year monitoring and maintenance period.
Non-native invasive herbaceous species, excluding annual non-native grasses, shall remain below 5 absolute percent of total vegetation cover.
No non-native invasive woody species shall be present within the mitigation site.
The mitigation site shall be entirely without supplemental irrigation for a minimum of two years at the end of the 5-year monitoring and maintenance period.
No single species may constitute more than 50 percent of the vegetative cover in the understory.
The City-approved Restoration Biologist will monitor to determine if performance criteria are being achieved as described in Section 2.4. If performance criteria are not being achieved, the City may be required to replant, as necessary, to ensure performance criteria are met.
2.2.1 Reference Site
If monitoring results indicate the success criteria are not anticipated to be achieved or if the success criteria are not met, corrective actions will be implemented as described in Section 2.9. Additionally, an assessment of conditions at a reference site with similar habitat to the mitigation site will be used to as a tool to measure the overall success of the mitigation site. A reference site will be established where ecologically intact examples of similar habitat are found, preferably in the same watershed. The reference site will be 400 square meters, per the plot size recommended for riparian woodlands in the CDFW-California Native Plant Society (CNPS) Protocol for the Combined 673
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 44 Vegetation Rapid Assessment and Relevé Field Form (CDFW-CNPS 2022 and 2023), where enough habitat is present.
2.3 Maintenance Plan
A qualified Restoration Contractor with oversight by the City-approved Restoration Biologist will conduct maintenance at the mitigation site for a period of 5 years. After initial restoration installation has been completed, the 5-year maintenance and monitoring period will commence, comprised of the 90-day Plant Establishment Period (PEP) and the following 4.75 years. Changes may be made as necessary based on annual monitoring reports, per the City’s General Plan (City of Goleta 2009, Policy CE 1.7). The City-approved biologist will oversee adjustments to maintenance activities to ensure that the performance criteria for the mitigation site are achieved. Maintenance will include non-native plant removal, watering, replanting, and repairing of damage to plants, erosion control devices, fencing, and/or signs that are a result of erosion or vandalism.
2.3.1 90-Day Plant Establishment Period
The Restoration Contractor will be responsible for successful initial plant installation as determined by the Restoration Specialist in coordination with the City. Once the City deems the restoration installation complete, the 90-day PEP will begin. During this time, the Restoration Contractor will be responsible for site maintenance, and the Restoration Biologist will conduct monitoring visits as described in Section 2.4 below.
2.3.2 Maintenance Methods and Schedule
During the 5-year maintenance period, a qualified Restoration Contractor will conduct routine activities to maintain the plantings in a healthy condition, control erosion of the mitigation site, and ensure performance criteria are being achieved. Non-native plants will be removed primarily using hand removal methods, such as hand-held weed whips, loppers, and hoes. If hand removal is not feasible due to species resistance to hand removal methods, the size of the plant, or the number of plants, perennial invasive non-native species may be treated with herbicides. Herbicides may be used as described in Section 2.1.4.
The majority of invasive non-native plant removal efforts will be conducted during the peak growing season (winter and spring) when non-native plant species are most prevalent. A regular but lower level of effort during the rest of the year is recommended to minimize the spread of non-native plant seeds. The maintenance schedule and crew size will be adjusted based on the abundance of non-native plants on-site and the effort it takes to remove them before inflorescence and/or seed set.
Non-native plant species, including invasive plant species, will be removed as part of mitigation efforts; however, implementation of the mitigation has the potential to result in the spread of invasive plant species through soil displacement and disturbance and by the inadvertent transport of propagules (e.g., seeds, pieces of invasive plants that have broken off) by vehicles and people. All efforts shall be made to avoid the spread of and otherwise eliminate invasive weeds within the mitigation site, such as ensuring tools, equipment, vehicles, clothing and footwear, and other gear shall be cleaned to remove soil, seeds, and other plant parts.
The City-approved Restoration Biologist will monitor to determine if performance criteria are being achieved as described in Section 2.2. If performance criteria are not being achieved or are projected 674
Compensatory Mitigation Plan
Mitigation Plan 45
as such, the City will take action to ensure performance criteria are met. Corrective actions may include, but are not limited to, increased frequency of non-native weed removal and replacement planting. Replacement planting in Year 1 and 2 will be necessary if survivorship does not meet the survival or percent cover percent performance criteria, and will likely occur even if performance criteria are being met to ensure the highest amount of native cover early on in the 5-year maintenance and monitoring period.
2.3.3 Irrigation Methods and Schedule
A temporary above ground irrigation system will be installed throughout the mitigation sites as feasible. The irrigation system will be set up to target individual plants via drip emitters and will avoid watering in between the plants to help prevent the growth of non-natives. The source of the water may be a permanent hookup if available, or a temporary water source such as a holding tank or water truck.
The City-approved Restoration Biologist will establish an irrigation schedule in conjunction with the qualified Restoration Contractor. Irrigation will be scheduled to maximize growth of native species and will account for natural rainfall, while minimizing growth of invasive non-native plants.
Generally, if irrigation is needed, it will be provided to a greater extent during the growing season (winter and spring) to mimic seasonal weather patterns, with minimal irrigation provided as needed during the summer and fall to keep plants alive.
Towards the end of spring of the third year, the irrigation schedule will be gradually reduced over several weeks to wean the plants to adapt to a reduced watering schedule over the summer and fall. The irrigation system will be used for up to 3 years and plants will be completely weaned from the irrigation prior to the end of the third year. If irrigation materials are installed, they will be removed once the plants are weaned. In the case of replacement of western sycamores, if irrigation is needed beyond the third year, irrigating these individuals may be done by hand as needed.
2.3.4 Maintenance Restrictions
Vegetation with potential to contain bird nests will not be removed during the breeding bird season (approximately February 1 through August 31) unless a City-approved biologist determines that it does not contain active bird nests. Tree removal will not occur during the monarch butterfly aggregation season (approximately October 1 through March 31) if aggregating monarchs are present. Herbicide use will follow the methodologies outlined in Section 2.1.4 Site Preparation.
2.4 Monitoring Plan
Monitoring will be conducted by the City-approved Restoration Biologist. The mitigation sites will be monitored for a 5-year period to ensure successful establishment. Each year of the 5-year monitoring and maintenance period is defined as a 12-month timeframe starting when restoration implementation is complete. Changes may be made as necessary based on annual monitoring reports, per the City’s General Plan.
675
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 46 2.4.1 Monitoring Methods and Schedule
Qualitative Monitoring
The mitigation sites will be qualitatively monitored by the City-approved Restoration Biologist monthly every month during Year 1 and every other month during Year 2 through Year 5.
Qualitative monitoring will be used to determine if performance criteria are being met, or likely to be met, each year and by the end of Year 5. Visual estimates of percent cover of native, non-native, and invasive non-native plants will be made at each mitigation site. Installed trees will be assessed for green foliage, seasonal new growth, vigor and health, pests, etc. Observations on wildlife use, vegetation establishment trends, non-native plant invasion, evidence and extent of erosion, and the need for corrective actions will be collected. Additionally, monitoring will document how the mitigation site compares to the surrounding lands in terms of topography, hydrology, vegetation types, sensitive species present, and use by wildlife. Recommendations for maintenance needs will be made to the qualified Restoration Contractor based on observations made during the monitoring activities.
Photographs will be taken each year during the spring and winter monitoring to qualitatively document plant establishment, hydrologic conditions, and other site conditions. Permanent photo- documentation points will be established throughout the mitigation site, primarily prior to installation. Each photo point location will be documented using global positioning system (GPS) and marked in the field with Polyvinyl chloride or vinyl (PVC) pipes anchored by rebar, or a similar mechanism, which will be removed after completion of the 5-year monitoring period. The photographs will be included in the annual monitoring report to allow comparison between monitoring years.
Quantitative Monitoring
The mitigation sites will be qualitatively monitored by the City-approved Restoration Biologist twice a year, once in spring (April/May) and one in fall (September/October). Quantitative monitoring will be used to assess the success of the mitigation site per the performance criteria are being met, or likely to be met, each year and by the end of Year 5. Fixed-line transects will be installed throughout the mitigation sites to quantify the following parameters at each mitigation site, which will also be used to determine an average across all mitigation sites combined:
Absolute percent cover for total vegetation, native species, non-native species, invasive non- native species, and bare ground
Absolute percent cover by species
Number of species present
The point-intercept method will be used to document plant species (or lack thereof) occurring along the transect and whether the species is native, non-native, or invasive non-native. Each transect will be at least 10 meters long and be sampled at 10 centimeters intervals at a minimum. Each transect location will be documented using a GPS and marked in the field with PVC pipes anchored by rebar, or similar mechanism, which will be removed after completion of the monitoring period. Transect locations will be selected systematically to sample different habitat types, with a minimum of two transects per mitigation site. Photographs will be taken at each transect during the quantitative monitoring events, separate from those photographs taken during the qualitative monitoring event. 676
Compensatory Mitigation Plan
Mitigation Plan 47
The photographs will be included in the annual monitoring report to allow comparison between monitoring years.
The number of container plants that have died will also be recorded during the spring and winter quantitative monitoring events to calculate the percent survival of trees and non-tree species. If replacement plants are installed, they will be closely monitored for a minimum of 2 years (within the 5-year monitoring period) to ensure successful establishment.
Observations on wildlife use, vegetation establishment trends, non-native plant invasion, evidence and extent of erosion, and the need for corrective actions will be collected. Recommendations for maintenance needs will be made to the qualified Restoration Contractor based on observations made during the monitoring activities.
Final Inspection
Upon completion of the 5-year monitoring period, the City, in conjunction with the City-approved Restoration Biologist, will conduct a final inspection. Any outstanding items will need to be completed before the regulatory agencies give final approval and accept the restoration project as complete.
2.5 Reporting Requirements
The City-approved Restoration Biologist will prepare an as-built report within 30 days following the complete installation of the mitigation sites. The as-built report will document the plant and seed materials installed (species and quantities), genetic sourcing, and the methods and outcome of installation for each restoration treatment type and mitigation area. The annual reports will provide photographs taken at photo documentation points, photographs taken at transects, and relevant geographic information systems (GIS)-based figures.
The City-approved Restoration Biologist will prepare annual monitoring reports that will be transmitted to the appropriate permitting agencies, i.e., USACE, CDFW, RWQCB, and CCC. As described above, the restored mitigation sites will be monitored and maintained for a 5-year period with changes made as necessary based on monitoring events and annual monitoring reports, per the City’s General Plan. Annual monitoring reports will be prepared within one month of the end of each year (a 12-month period) of the 5-year monitoring and maintenance period. The 5-year maintenance and monitoring period will begin when restoration implementation is complete.
Annual reports will document the “As Built” condition of the mitigations sites, maintenance efforts, and monitoring methods and results. Annual reports will contain a quantitative analysis of performance criteria achievement and progress toward meeting final performance criteria. The annual reports will provide photographs taken at photo documentation points, photographs taken at transects, and relevant GIS-based figures. The 5
th and final annual report will be noted as such
and will serve as the Notification of Completion for the appropriate permitting agencies.
2.6 Schedule
The schedule for restoration preparation, implementation, maintenance, monitoring, and reporting is presented in Table 16. This schedule assumes that construction of the path will begin fall 2024 and will take approximately 18 months, and that initial mitigation installation will begin in fall/winter of 2026 after construction is complete. The schedule is subject to change dependent 677
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 48 upon the construction schedule, receiving appropriate Project permits and approvals, and plant availability.
Table 16 Mitigation Schedule
Timing Task
Preparation
Through spring 2028 Collect native seeds and cuttings, and propagate plants for initial and replacement planting (Sections 2.1.1, 0, and 2.1.3).
August to October 2026 Non-native plant removal immediately before plant installation (Section 2.1.4).
Install erosion control as applicable (Section 2.1.7).
Maintenance restrictions apply as described in Sections 2.1.4 and 2.3.4.
Prior to fall 2026 Set up photopoints for baseline photo monitoring.
Installation
Fall/winter 2026 Install container plants (Section 2.1.1 and 2.1.5).
Install irrigation system (Section 2.3.3).
Fall/winter 2027 and 2028 Replacement planting as necessary.
Maintenance (Year 1 through Year 5)
January 2027 to December 2032 Conduct site maintenance (Section 2.3).
Maintenance restrictions apply as described in Sections 2.1.4 and 2.3.4.
Monitoring and Reporting (Year 1 through Year 5)
January 2027 to December 2032 Monthly qualitative monitoring (Section 2.4.1).
Each spring and winter, 2027 through 2032 Photograph monitoring (Section 2.4.1).
Each spring and winter, 2027 through 2032 Quantitative transect monitoring (Section 2.4.1).
Each January 2028 through 2033 Prepare annual monitoring reports (Section 2.5).
2.7 Site Protection Instrument
The mitigation sites are located within various parcels that are or will be protected in perpetuity as follows:
San Jose Creek along the northern segment of the Pathway – For the riparian mitigation, the City is obtaining the ROW, which will be finalized prior to construction. The upland mitigation will occur within the Caltrans easement for U.S. Route 101.
San Jose Creek at Jonny D. Wallis Park – City-owned property designated as a park Old San Jose Creek at Ekwill Street - City-owned property for the eastern section, City ROW for the western section
Devereux Creek at Ellwood Mesa - City-owned property designated as open space and managed via the Ellwood Devereux Coast Open Space and Habitat Management Plan (URS et al. 2004) San Jose Creek along the southern segment of the Pathway – City-owned property 678
Compensatory Mitigation Plan
Mitigation Plan 49
2.8 Long-term Management Plan and Financial
Assurances
The City will be responsible for long-term management of the mitigation sites through the five-year maintenance and monitoring period and will ensure that the performance criteria are attained.
Financial assurances through which the mitigation sites will be successfully completed are in development and will be finalized prior to construction.
2.9 Adaptive Management Plan
As described in Section 2.4.1, the City-approved Restoration Biologist will monitor the restoration sites to determine if performance criteria are being achieved as described in Section 2.2. Changes may be made as necessary based on results and recommendations of the monitoring efforts and annual monitoring reports. If performance criteria are not being achieved or are projected as such, the City may be required to take corrective actions. Corrective actions may include, but are not limited to, increased frequency of non-native weed removal and replacement planting has described in Section 2.3.2. If replanting occurs, restoration elements that may be changed include the plant species and quantities used and the location of the installed container plants, dependent on species. Additionally, maintenance measures such as non-native plant removal, irrigation, erosion control, vandalism repair, and/or plant protection may need to be modified to help ensure the success of the mitigation site.
If the Mitigation Plan cannot be implemented as approved, and is significantly modified as a result, the City will obtain approval from the USACE, CDFW, RWQCB, and CCC.
If monitoring or other information indicates that the Plan is not progressing towards meeting its performance criteria (See Section 2.2), the City will notify the USACE, CDFW, RWQCB, and CCC as soon as possible. The City will work with these agencies to address deficiencies in the Mitigation Plan and apply appropriate measures to ensure performance criteria are met. 679
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 50 3 List of Preparers
Rincon Consultants, Inc.
Primary Author
Julie Love, MESM, Project Manager/Senior Restoration Biologist Secondary Author
Yuling Huo, ISA Certified Arborist #WE-11975A, Biologist Technical Review
Greg Ainsworth, ISA Certified Arborist #WE-7473A, Director Field Surveys
Julie Love, MESM, Project Manager/Senior Restoration Biologist Yuling Huo, ISA Certified Arborist #WE-11975A, Biologist Kaitlyn Weaver, ISA Certified Arborist #WE-14623A, Biologist Graphics
Isabelle Radis, GIS Analyst
Emily Gaston, GIS Analyst
Publishing
Luis Apolinar, Publishing Specialist
Alvin Flores, Publishing Specialist
Yaritza Ramirez, Publishing Specialist
680
References
Mitigation Plan 51
4 References
Bing Maps. 2023. Aerial basemap imagery.
California Department of Fish and Wildlife (CDFW) and California Native Plant Society (CNPS). 2023.
CDFW-CNPS Protocol for the Combined Vegetation Rapid Assessment and Relevé Field Form. March 7, 2023.
______. 2023. CDFW-CNPS Protocol for the Combined Vegetation Rapid Assessment and Relevé Field Form Datasheet. August 23, 2022.
City of Goleta. 2022a. Final Initial Study and Mitigated Negative Declaration (IS-MND) for the San Jose Creek Multipurpose Path Project. State Clearinghouse Number 2022070006. Prepared with assistance from Dewberry. October 2022.
______. 2022b. San Jose Creek Multipurpose Path – Northern and Southern Segments (Project No. 9006) website. July 2022. Accessed online at https://www.cityofgoleta.org/your-city/public- works/capital-improvement-program-division/project-no-9006-san-jose-creek-bike-path- northern-and-southern-segments. Accessed through June 2023. ______. 2009. Goleta General Plan/Coastal Land Use Plan. Prepared by the City of Goleta Planning and Environmental Services Department. Adopted October 2006, amended and republished November 2009.
Dewberry. 2023a. Impact figures for the San Jose Creek Multipurpose Path, Northern and Southern Segment. Prepared for the City of Goleta Department of Public Works. ______. 2023b. GIS shapefiles for the San Jose Creek Multipurpose Path, Northern and Southern Segment. Prepared for the City of Goleta Department of Public Works. March 2023. ______. 2023c. Revised impact figures for the San Jose Creek Multipurpose Path, Northern and Southern Segment. Prepared for the City of Goleta Department of Public Works. November 2023.
ESRI. 2023. Basemap Imagery.
Meade, D.E., Griffiths, J., van der Heide, C. 2017. Monarch Butterfly Overwintering Sites, Santa Barbara County, California. Althouse and Meade Inc., Paso Robles, California.
Padre Associates. 2003. Draft San Jose Creek Watershed Plan. Prepared for County of Santa Barbara Water Resources Agency. January.
Rincon Consultants, Inc. (Rincon). 2022. Tree Survey and Impact Analysis for Goleta’s San Jose Creek Bike Path. Prepared for the City of Goleta. September 28, 2022.
Stoecker, M.W. 2002. Steelhead Assessment and Recovery Opportunities in Southern Santa Barbara County, California. Prepared for the Conception Coast Project.
United States Army Corps of Engineers (USACE) and Environmental Protection Agency (EPA). 2008.
Federal Register. USACE 33CR Parts 325 and 332. EPA 40 CFR Part 230. Compensatory Mitigation for Losses of Aquatic Resources. Volume 73, No. 70.
United States Fish and Wildlife Service (USFWS). 2020. National Wetlands Inventory. Wetlands Mapper (online). Accessed May 2020.
681
City of Goleta
San Jose Creek Multi-Purpose Path – Northern and Southern Segments 52 United States Geological Survey (USGS). 2023. Goleta, CA 7.5-minute topographic map. Imagery.
URS Corporation, Baikal Consulting, Bioregional Planning Associates, Wallace Roberts & Todd, LLC (URS et al.). 2004. Ellwood-Devereux Coast Open Space and Habitat Management Plan.
Prepared for the City of Goleta, County of Santa Barbara, and University of California, Santa Barbara. March 2004.
Western Regional Climate Center (WRCC). 2015. Cooperative Climatological Data Summaries: Santa Barbara FAA ARPT and Santa Barbara TV Peak Station, California. Accessed online.
Xerces Society. 2019. Western Monarch Thanksgiving Count database. https://www.westernmonarchcount.org/wp-content/uploads/2019/01/WMTC-Data-1997- 2018_1.4.2019_final.pdf. Accessed April 2, 2019.
682
Appendix A
Figures – Impacts to Native and Non-native Trees (Rincon 2022)
Note: The path alignment has been slightly modified since the creation of these figures to avoid larger mature native trees; the modified path design and reduced impact is not represented on the figure. 683
Project Footprint
Tree Canopy (5.44 acres)
Native Tree Canopy
Proposed for Removal
(0.84 acre/15% of total canopy)
±
0 18090
Feet
Imagery provided by Microsoft Bing and its licensors © 2022. Fig X Native Tree Canopy Remo val Native Tree Canopy Impact Map
684
Project Footprint
Tree Canopy (5.44 acres)
Non-Native Tree Canopy
Proposed for Removal
(0.53 acre/10% of total canopy)
±
0 18090
Feet
Imagery provided by Microsoft Bing and its licensors © 2022. Fig X Non-Native Tree Canopy Remo val Non-Native Tree Canopy Impact Map
685
Appendix B
Figures – Habitat Types and Jurisdictional Waters (Dewberry 2023a) 686
687
Figure
D-2
Habitat Types within the
Southern Segment -
Southern End
Source ESRI Online Basemap, Aerial Imagery;
Coordinate System NAD 83 State Plane
California V FIPS 0405 Feet; DHA, 2019
Notes This map was created for informational
and display purposes only;
boundary of riverine habitat is marked by the OHWM
San Jose Creek Multipurpose
Path Project
City of Goleta, Santa Barbara County, CA0 250 500125 Feet Goleta City Boundary
Habitat Type
Arroyo Willow Riparian Thicket
Barren
Coyote Brush Scrub
Iceplant Mats
Myoporum Groves
Non-Native Grassland
Riverine (Intermittent) - San Jose Creek
Riverine (Tidal) - San Jose Creek
Southern Coastal Salt Marsh (Pickleweed Mats)
Southern Coastal Scrub Shrub Wetland
Urban (Developed)
Biological Study Area
688
Figure
D-3
Habitat Types within the
Southern Segment -
Northern End
Source: ESRI Online Basemap, Aerial Imagery;
Coordinate SystemNAD 83 State Plane
California V FIPS 0405 Feet; DHA, 2019
Notes: This map was created for informational
and display purposes only;
boundary of riverine habitat is marked by the OHWM
San Jose Creek Multipurpose
Path Project
City of Goleta, Santa Barbara County, CA0 250 500125 Feet Legend
Biological Study Area
Coastal Zone Boundary
Habitat Type
Coyote Brush Scrub
Non-Native Grassland
Riverine (Intermittent) - San Jose Creek
Urban (Developed)
689
Figure
D-4
Potentially Jurisdictional
Aquatic Resources
within the Northern Segment
San Jose Creek Multipurpose
Path Project
City of Goleta, CA
Source: ESRI Online Basemap World Street Map and Aerial Imagery; Coordinate System NAD 83 State Plane California III FIPS 0403 Feet Notes: This map was created for informational and display purposes only !
0 100 20050 Feet
Legend
Biological Study Area
Potentially Jurisdictional Aquatic Resources (Corps)
Riverine (Intermittent) - San Jose Creek (0.90 acres)
Perennial Drainage Ditch (0.01 acres)
Potentially Jurisdictional Aquatic Resources (CDFW and RWQCB) California Sycamore - Coast Live Oak Riparian Woodland (3.09 acres) Common and Giant Reed Thicket (0.23 acres)
Perennial Drainage Ditch (0.01 acres)
Riverine (Intermittent) - San Jose Creek (0.90 acres)
690
691
Figure
D-6
Potentially Jurisdictional Aquatic Resources
within the Southern Segment -
Northern End
Source ESRI Online Basemap, Aerial Imagery; Coordinate System NAD 83 State Plane California V FIPS 0405 Feet;
DHA, 2019
Notes This map was created for informational and
display purposes only
San Jose Creek Multipurpose Path Project
City of Goleta, Santa Barbara County, CA0 250 500125 Feet Legend
Biological Study Area
Coastal Zone Boundary
Potentially Jurisdictional Aquatic Resources (Corps, CDFW, and RWQCB) Riverine (Intermittent) - San Jose Creek (2.93 acres)
692
Appendix C
Mitigation Site Photographs
693
Mitigation Site Photographs
Mitigation Plan C-1
Photograph 1. Northern segment of San Jose Creek Multi-use Path, approximate Project area and mitigation site. Riparian mitigation would occur to the left/east, adjacent to the creek. View facing southeast. 5/12/23.
Photograph 2. San Jose Creek Multi-use Path, approximate Project area and mitigation site. Riparian mitigation would occur to the right/east, adjacent to the creek. View facing northwest. 5/12/23. 694
City of Goleta
San Jose Creek Multi-purpose Path – Northern and Southern Segments C-2
Photograph 3. San Jose Creek Multi-use Path, Project area and mitigation site. Mitigation for individual upland trees would occur to the right/south. View facing east. 5/12/23.
Photograph 4. Jonny D. Wallis Park mitigation site. Northern riparian mitigation area; removal of goldenrain trees. View facing north. 5/12/23.
695
Mitigation Site Photographs
Mitigation Plan C-3
Photograph 5. Jonny D. Wallis Park mitigation site. Southern riparian mitigation area. View facing south. 6/23/23.
Photograph 6. Jonny D. Wallis Park mitigation site. Park grounds where individual riparian trees will be installed. View facing north. 5/12/23
696
City of Goleta
San Jose Creek Multi-purpose Path – Northern and Southern Segments C-4
Photograph 7. Jonny D. Wallis Park mitigation site. Park grounds where existing native landscape trees will become mitigation trees. View facing south. 5/12/23.
Photograph 8. Old San Jose Creek at Ekwill Street. Eastern end of riparian mitigation site; removal of non-native black locust trees. View facing north. 5/12/23. 697
Mitigation Site Photographs
Mitigation Plan C-5
Photograph 9. Old San Jose Creek at Ekwill Street. Eastern end of riparian mitigation site; removal of non-native black locust trees and cape ivy. View facing south. 5/12/23.
Photograph 10. Old San Jose Creek at Ekwill Street. Middle portion of riparian mitigation site; existing eucalyptus to remain in place, monarch-specific restoration to occur under eucalyptus. View facing northwest. 5/12/23.
698
City of Goleta
San Jose Creek Multi-purpose Path – Northern and Southern Segments C-6
Photograph 11. Old San Jose Creek at Ekwill Street. Western end of western mitigation site; removal of black locust trees. View facing north. 5/12/23.
Photograph 12. Old San Jose Creek at Ekwill Street. Western end of riparian mitigation site; channel.
Facing east. 5/12/23.
699
Mitigation Site Photographs
Mitigation Plan C-7
Photograph 13. Devereux Creek at Ellwood Mesa. Wetland mitigation site. View to north. 5/30/23.
Photograph 14. Southern segment of San Jose Creek Multi-use Path, approximate Project area and mitigation site, along South Kellogg Avenue north of Kellogg Way. Coyote brush/coastal sage scrub mitigation would occur to the left/east, between the concrete channel and the future path. View facing southwest. 5/29/19.
700
City of Goleta
San Jose Creek Multi-purpose Path – Northern and Southern Segments C-8
Photograph 15. Southern segment of San Jose Creek Multi-use Path, approximate Project area and mitigation site, along South Kellogg Avenue north of Kellogg Way. Coyote brush/coastal sage scrub mitigation would occur to the right/east, between the concrete channel and the future path. View facing northeast. 5/29/19.
701
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX C
CITY OF GOLETA
APPENDIX C
PERMITS, LICENSES, AGREEMENTS,
AND CERTIFICATIONS
FOR
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
702
SAN JOSE CREEK MULTIPURPOSE PATH PROJECT
CITY PROJECT NO. 9006
APPENDIX C
Back of Cover Sheet
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
APPENDIX E Short Form S hort Form Short Form Short Form -- -- Storm Water Data ReportStorm Water Data ReportStorm Water Data ReportStorm Water Data Report Caltrans Storm Water Quality HandbooksCaltrans Storm Water Quality HandbooksCaltrans Storm Water Quality HandbooksCaltrans Storm Water Quality Handbooks Project Planning and Design GuideProject Planning and Design GuideProject Planning and Design GuideProject Planning and Design Guide 8/1/20178/1/2017 8/1/20178/1/2017
Dist-County-Route: 05-SB -217
Post Mile Limits: 1.0/2.2
Project Type: San Jose Creek Multipurpose Path
Project ID (EA): 05-1800-0229 -1 (05-1K630 1)
Program Identification: Local Oversight
Phase: PID PA/ED PS&E
Regional Water Quality Control Board(s): Central Coast, Region 3_________
1. Does the project disturb 5 or more acres of soil? Y es No
2. Does the project disturb more than 1 acre of soil and not qualify for the R
ainfall Erosivity Waiver? As per the DNCAs per the DNCAs per the DNCAs per the DNC,, ,, a short form SWDR is a short form SWDR is a short form SWDR is a short form SWDR is appropriate for this project.appropriate for this project.appropriate for this project.appropriate for this project.
Yes No
3. Is the project required to implement Treatment BMPs (STGA, TMDL, AC)? Yes No
4. Does the project impact existing stormwater BMPs? Y es No
If the answer to any of the preceding questions is “Yes”, prepare a Long Form If the answer to any of the preceding questions is “Yes”, prepare a Long Form If the answer to any of the preceding questions is “Yes”, prepare a Long Form If the answer to any of the preceding questions is “Yes”, prepare a Long Form –– –– Storm Water Data Storm Water Data Storm Water Data Storm Water Data Report.Report. Report.Report.
Total Disturbed Soil Area: 2.34 acres New Impervious Surface: N/A Bike/Ped Project Estimated Construction Start Date: 4/15/2024 Est Const. Completion Date: 4/23/2025 Risk Level: RL 1 RL 2 RL 3 WPCP NA
Is MWELO applicable? Yes No
This Short Form This Short Form This Short Form This Short Form –– –– Storm Water Data Report has been prepared under the direction of the following Storm Water Data Report has been prepared under the direction of the following Storm Water Data Report has been prepared under the direction of the following Storm Water Data Report has been prepared under the direction of the following Licensed Person. The Licensed Person. The Licensed Person. The Licensed Person. The Licensed Person attests to the technical information contained herein and the Licensed Person attests to the technical information contained herein and the Licensed Person attests to the technical information contained herein and the Licensed Person attests to the technical information contained herein and the data upon which recommendations, conclusions, and decisions are based. Professional Engineer or data upon which recommendations, conclusions, and decisions are based. Professional Engineer or data upon which recommendations, conclusions, and decisions are based. Professional Engineer or data upon which recommendations, conclusions, and decisions are based. Professional Engineer or Landscape Architect stamp required at PS&E.Landscape Architect stamp required at PS&E.Landscape Architect stamp required at PS&E.Landscape Architect stamp required at PS&E.
4/18/2023
Miguel Ramirez, Registered Project Engineer Date
I have reviewed the stormwater quality design issues and find this I have reviewed the stormwater quality design issues and find this I have reviewed the stormwater quality design issues and find this I have reviewed the stormwater quality design issues and find this report to be complete, current and accurate:report to be complete, current and accurate:report to be complete, current and accurate:report to be complete, current and accurate:
[Stamp Required for PS&E only) Karl Mikel, SW Coordinator or Designee Date 12/18/2023
for
792
APPENDIX E Short Form Short Form Short Form Short Form -- -- Storm Water Data ReportStorm Water Data ReportStorm Water Data ReportStorm Water Data Report Caltrans Storm Water Quality HandbooksCaltrans Storm Water Quality HandbooksCaltrans Storm Water Quality HandbooksCaltrans Storm Water Quality Handbooks Project Planning and Design GuideProject Planning and Design GuideProject Planning and Design GuideProject Planning and Design Guide 8/1/20178/1/2017 8/1/20178/1/2017
1.1. 1.1. Project DescriptionProject DescriptionProject DescriptionProject Description • The San Jose Creek Multipurpose Path Project (project ) is located in Santa Barbara County in the City of Goleta on Route 217 from post mile 1.0 to post mile 2.2 and on a portion of Route 101 near post mile 21.6 along Calle Real. The project would construct a Class I bikeway (path) to close the 2.5-mile gap between the County (Cathedral Oaks Road) and Goleta Crosstown Route in the north and the County’s Obern Trail/Coast Route in the south. The path would connect the Calle Real commercial and residential on the north side of US 101 to commercial and residential areas within the Goleta Old Town redevelopment area to the University of California, Santa Barbara (UCSB) and the Coast Route.
The Northern Segment begins on Calle Real near the south end of North Kellogg Avenue. Heading east to the northern limit of the US 101 Bridge Replacement project.
Continuing south from the southern limit of the US 101 Bridge Replacement project, the path goes under the railroad bridge over San Jose Creek along the west bank. The Northern Segment is nearly a half mile. Bicyclists and pedestrians can then travel west on Armitos Avenue approximately 500’, turn south onto the existing South Kellogg Avenue for approximately 2200’ to connect to the beginning of the Southern Segment just north of Kellogg Way.
The Southern Segment is approximately 1 mile long. The proposed project would extend from the existing Class III facilities on South Kellogg Avenue, continue between the southern/eastern bank of San Jose Creek, outside the top of bank and the active channel of San Jose Creek, and the SR 217 Southbound shoulder, and ultimately connect to the existing Class I Atascadero Creek Bikeway. The proposed project would cross over San Jose Creek on the north end (northern terminus) and would cross under SR 217 on the south end (southern terminus).
The path is typically 8 to 14 feet wide, with 2-foot wide shoulders, and typical design speed of 20 mph. The Southern Segment includes a concrete barrier 2 feet in width to separate the path from SR 217 traffic. At the Northern Segment near Calle Real, the improvements also include the reconstruction of a section of the existing sidewalk on the south side of Calle Real to allow for the construction of the project, including retaining walls and concrete barrier. Between the Calle Real and the Caltrans right-of- way, it is anticipated that the existing guard rail, attached to the existing Calle Real Bridge, would need to be extended west within the project limits. The existing Class II bike lane will remain with access to the path near the existing bus stop pullout area.
Continuing along the Northern Segment, a protective steel mesh cover would be placed above the path as it crosses under the UPRR tracks to avoid items dropping onto the path. At the Southern Segment, a pedestrian bridge would be constructed to provide access over San Jose Creek. A 14-foot wide by 8-foot high by 144-foot box culvert with solar lighting would likely be utilized to provide access under SR 217.
There are several sections of retaining walls throughout the length of the project site.
The retaining wall foundation types would vary from spread footings ranging between 6 to 8 feet in depth to pile foundations up to 40 feet in depth. The maximum excavation 793
depth for the proposed project would be approximately 12 feet from existing ground at the culvert location.
The majority of the improvements would take place on the west side of San Jose Creek. It is anticipated that approximately 600 feet of the proposed trail will be constructed within the existing San Jose Creek bank, this will occur where the proposed trail crosses under the UPRR and Calle Real bridges. Downstream of UPRR, there are three minor areas of fill where the bank has eroded to the extent that these areas of fill encroach into the stream and below the ordinary high-water mark. The proposed project would perpetuate existing drainage patterns and may include placement of rock slope protection in the location of culvert outfalls throughout the stretch of the proposed project improvements. Embankments will create a detention basin.
• Disturbed Soil Area (DSA) associated with the improv ements within Caltrans ROW is
estimated to be 2.34 acres.
Table ETable E Table ETable E-- --1. Summary of P1. Summary of P1. Summary of P1. Summary of Project Areasroject Areas roject Areasroject Areas LocLoc LocLoc DSA, DSA, DSA, DSA,
acresacres acresacres
Existing Existing Existing Existing
Impervious Impervious Impervious Impervious
Area, acresArea, acres Area, acresArea, acres
Post Post Post Post
Impervious Impervious Impervious Impervious
Area, acresArea, acres Area, acresArea, acres
Net New Net New Net New Net New
Impervious Impervious Impervious Impervious
Area (NNI), Area (NNI), Area (NNI), Area (NNI),
acresacres acresacres
Replaced Replaced Replaced Replaced
Impervious Impervious Impervious Impervious
Surface Surface Surface Surface
(RIS), acres(RIS), acres (RIS), acres(RIS), acres
Excluded Excluded Excluded Excluded
Impervious Impervious Impervious Impervious
Area (EIA), Area (EIA), Area (EIA), Area (EIA),
acres acres acres acres
New New New New
Impervious Impervious Impervious Impervious
Surface Surface Surface Surface
(NIS), acres(NIS), acres (NIS), acres(NIS), acres
ATA ATA ATA ATA
#1, #1, #1, #1,
acreacre acreacress ss
ATA #2, ATA #2, ATA #2, ATA #2,
acresacres acresacres PCTA, PCTA, PCTA, PCTA,
acresacres acresacres
Northern
Segment 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0 0 0
Southern
Segment 2.15 0.00 0.87 0.00 0.00 0.91 0.00 0 0 0
TOTAL: 2.34 0.00 0.87 0.00 0.00 0.91 0.00 0 0 0
2.2. 2.2. Site Data and Stormwater Quality Design IssuesSite Data and Stormwater Quality Design IssuesSite Data and Stormwater Quality Design IssuesSite Data and Stormwater Quality Design Issues • This project is covered under Caltrans NPDES Permit
(WQO 2022-0033-DWQ). Note
that bike and ped projects are exempt from post construction runoff control TBMP requirements.
• San Jose Creek and Goleta Slough are the receiving wa ter bodies for this project. The HSA is 315.31.
• San Jose Creek is listed in the 303(d) list of impair ed waters as impaired by enterococcus, escherichia coli (E.coli), fecal coliform, sodium, specific conductivity, temperature (water) and pH.
794
• Goleta Slough is listed in the 303(d) list of impair ed waters as impaired by indicator bacteria and priority organics.
• This project is not located in a moderate or high Si gnificant Trash Generating Area, STGA.
• The project is subject to the treatment threshold re quirements of the 2012 CT MS4 Permit.
• The following permits, reviews, and approvals would be required for project construction:
Agency Permit/Approval Status
Central Coast Regional
Water Quality Control Board
Section 401 Certification
f
or impacts to waters of
the United States
To be obtained before
c
onstruction
United States Army Corps of
Engineers
Section 404 Permit for
i
mpacts to wetlands and
waters of the United
States
To be obtained before
c
onstruction
California Department of
Fish and Wildlife
Section 1602 Agreement
f
or Streambed Alteration
impacts to San Jose Creek
To be obtained before
construction
SWRCB Construction General
P
ermit
To be obtained prior to
c
onstruction
• There are no drinking Water Reservoirs and/or Recharg e Facilities within the projects limits.
• The site topography is relatively flat with drainage being redirected from natural channels, particularly along San Jose Creek south of Hollister Avenue. • The area is contained within the Transverse Ranges G eomorphic Province consisting mainly of variably deformed marine and non-marine sedimentary rocks and deposits that range in age from Jurassic to present.
• The current land use is residential and light indust rial proper to which land use was agricultural with orchards and other crops. The approximate southern quarter of the proposed project appears to have historically salt marsh or wetland prior to development.
• There are no right-of-way costs for BMPs
• There are no existing Treatment BMPs within the proj ect limits. • This project proposes to create 2.34 ac of DSA withi n Caltrans ROW. Therefore, this project will require a Storm Water Pollution Prevention Plan (SWPPP) and coverage under the Construction General Permit.
• Parts of this project are located within the City of Goleta Urban MS4 Area. • San Jose Creek has the beneficial uses of COLD, SPWN, and MIGR (CCRWQCB Basin Plan)
• The Latitude/Longitude for this project is 34.42151 /- 119.8291 • 4 acres will be used in the calculation to determine Construction General Permit (CGP) Annual fees.
1 Number of FYs of construction schedule
795
2 Additional years for vegetation period or other NOT requirements 3 Total years
$704.00 Storm Water Construction Annual Fees for 4 ac
$2,112.00 Total NOI/NOT Stormwater CGP fees
• During construction, effective combinations of tempo rary and permanent erosion and sediment controls will be used. Storm water management for the site will be coordinated through the contractor with Caltrans construction personnel to effectively manage erosion from the DSA's by implementing a Storm Water Pollution Prevention Plan (SWPPP). Selected BMP's that will be included but not limited to the SWPPP for the project are defined as follows:
Temporary Soil Stabilization Temporary Soil Stabilization Temporary Soil Stabilization Temporary Soil Stabilization • Minimize active DSA's during the rainy season utiliz ing scheduling techniques. • Preserve existing vegetation to the maximum extent f easible. • Implement temporary protective cover/erosion control on all non-active DSA's and soil stockpiles.
• Control erosive forces of storm water runoff with ef fective storm flow management such as temporary concentrated flow conveyance devices, earthen dikes, drainage swales, lined ditches, outlet protection/velocity dissipation devices, and slope drains as determined feasible.
Temporary Sediment ControlsTemporary Sediment ControlsTemporary Sediment ControlsTemporary Sediment Controls • Implement linear sediment controls such as fiber rol ls, check dams, or gravel bag berms on all active and non-active DSA's during the rainy season. • To further help prevent sediment discharge stabilize d construction site entrances, temporary drainage inlet protection, and street sweeping and vacuuming will be necessary.
• Implement appropriate wind erosion controls year rou nd.
Non Storm Water ManagementNon Storm Water ManagementNon Storm Water ManagementNon Storm Water Management • The appropriate non-storm water BMP's will be implem ented year-round as follows:
• Water conservation practices are implemented on all construction sites and wherever water is used.
• The project area includes areas defined by a high gr oundwater elevation. Multiple earthwork and excavation operations will potentially encounter groundwater during construction activities. Dewatering BMP's may need to be implemented. • Paving and Grinding procedures are implemented where paving, surfacing, resurfacing, grinding, or saw cutting may pollute storm water runoff or discharge to the storm drain system or watercourses.
• Procedures and practices designed for construction c ontractors to recognize illicit
connections or illegally dumped or discharged materials on a construction site and report incidents to the Resident Engineer.
• The following activities must be performed at least
100 feet from concentrated flows
of storm water, drainage courses, and inlets if within the floodplain and at least 50 feet if outside of the floodplain; stockpiling materials, storing equipment and liquid 796
waste containers, washing vehicles or equipment, fueling and maintaining vehicles and equipment.
• Pile driving operations will be part of the construc tion activities. • Concrete curing will be used in the construction of structures such as bridges and retaining walls. Concrete curing includes the use of both chemical and water methods.
Proper procedures will minimize pollution of runoff during concrete curing. • Since the project involves structure construction ne ar and over several San Jose,
proper procedures will be implemented to minimize pollution during these activities. • The following construction site BMPs are anticipated to be bid items for this project:
• Job Site Management
• Stormwater Pollution Prevention Program
• Storm Water Sampling and Analysis Day
• Stormwater Annual Report
• Move In/Move Out (Temporary Erosion Control)
• Temporary Hydraulic Mulch (Bonded Fiber Matrix)
• Temporary Drainage Inlet Protection
• Temporary Fiber Roll
• Temporary Gravel Bag Berm
• Temporary Large Sediment Barrier
• Temporary Construction Entrance
• Street Sweeping
• Temporary Concrete Washout
• Temporary Fence (type ESA)
• Drainage Inlet Marker
Supplemental ItemsSupplemental ItemsSupplemental ItemsSupplemental Items • Water Pollution Control Maintenance Sharing
• Additional Water Pollution Control
State Furnished ItemsState Furnished ItemsState Furnished ItemsState Furnished Items • Annual Construction General Permit Fee
• Concurrence from Construction regarding the temporar y Construction Site BMP implementation strategy and associated quantities was given by Zach Coldwell, CSWC, on 12/15/2023.
• There are no existing permanent Maintenance faciliti es (stockpile/decanting) within the project limits.
• Drainage Inlet Markers (Type Metal Medallion) shall b e installed at drain inlets where pedestrians have access. Maintenance BMPs may include maintenance vehicle pullouts, access gates and roads, and maintenance worker safety features.
797
3.3. 3.3. Construction SiteConstruction SiteConstruction SiteConstruction Site BMPsBMPs BMPsBMPs • Construction is estimated to take place from04/15/202 4 to 4/23/2025. The
Contractor is responsible for securing locations for the staging and storage that are approved by the Resident Engineer (RE). The Water Pollution Control Program (WPCP) or SWPPP will be prepared by the contractor and approved by the RE. The WPCP/SWPPP will incorporate the following temporary construction site BMPs:
temporary concrete washouts, temporary fiber roll, temporary silt fence, temporary drainage inlet protection, temporary construction entrance/exits, and temporary erosion control. Additional BMPs will be deployed as lump sum bid items under Job Site Management, Prepare WPCP/SWPPP, and Additional Water Pollution Control as shown in the attached NR Temporary Construction BMP Cost Estimator • This project has been identified as being Risk Level 2, using the GIS Map Method 1,
Appendix 1 of the 2009 Construction General Permit (CGP). The watershed Erosion Estimate is 16.34 tons/acre, which is a 0.28 sediment Risk. The Receiving Water Risk is 75.78 since there are discharges to water bodies with beneficial use within the project limits. The LS Factor value is 0.77. See the attached risk level assessment for more information.
Required AttachmentsRequired AttachmentsRequired AttachmentsRequired Attachments11 11 • Vicinity Map
• Evaluation Documentation Form
• Risk Level Determination
1 Additional attachments may be required as applicable or directed by the District/Regional Design Storm Water Coordinator (e.g. BMP line item estimate, DPP, CS checklists, etc). 798
Vicinity MapVicinity MapVicinity MapVicinity Map
799
APPENDIX E Evaluation Documentation FormE valuation Documentation FormEvaluation Documentation FormEvaluation Documentation Form DATE:DATE: DATE:DATE: 44 44// //1818 1818/202/202 /202/2023 3 33 Project ID (Project ID ( Project ID (Project ID (EA): EA): EA): EA): __ __0505 0505-- --18001800 18001800-- --02290229 02290229- - --11 11 (05(05 (05(05-- --1K6301K630 1K6301K63011 11)) )) No. Criteria Yes
No
Supplemental Information for
Evaluation
1. Begin Project evaluation regarding
requirement for implementation of
Treatment BMPs
See Figure 4-1, Project Evaluation
P
rocess for Consideration of Permanent
Treatment BMPs. Continue to 2.
2. Is the scope of the Project to install
Treatment BMPs (e.g., Alternative
Compliance, TMDL, or Trash
Amendment Compliance)?
If YesY es YesYes, go to 8.
If NoN o NoNo, continue to 3.
3. Is there a direct or indirect discharge to
surface waters? If YesY es YesYes, continue to 4.
If NoNo NoNo, go to 9.
4. As defined in the WQAR, does the
Project have:
1. Areas of Special Biological
Significance (ASBS),
2. A TMDL area where Caltrans is
named stakeholder, or
3. Other Pollution Control
Requirements for surface waters
within the project limits?
If Yes to anyY es to any Yes to anyYes to any, contact the District/Regional Stormwater
Coordinator to discuss the Department’s
obligations, go to 8 or 5.
(Dist./Reg. SW Coordinator initials)
T he receiving waters are 303(d) h e receiving waters are 303(d) he receiving waters are 303(d) he receiving waters are 303(d) listed. As per the DNC, go to listed. As per the DNC, go to listed. As per the DNC, go to listed. As per the DNC, go to question #5.question #5.question #5.question #5.
I
f NoNo NoNo, continue to 5.
5. Are any existing Treatment BMPs
partially or completely removed?
(ATA condition #1, See PPDG Section
4.4.1)
If YesY es YesYes, go to 8 ANDAND ANDAND continue to 6.
If NoN o NoNo, continue to 6.
6. Is this a Routine Maintenance Project? If YesY es YesYes, continue to 9.
If NoNo NoNo, go to 7.
7. Does the project result in one acre or
more of new impervious surface (NIS)?
If YesY es YesYes, go to 8.
____00 00_ac NIS_ac NIS _ac NIS_ac NIS (NIS=NNI+ RIS)
If NoNo NoNo, continue to 9.
8. Project is required to implement
Treatment BMPs. Complete Checklist T-1, Part 1.
9. Project is not required to implement
Treatment BMPs.
______ (Dist. /Reg. SW Coord. Initials)
______(Project Engineer Initials)
_
_____________ (Date)
D
ocument for Project Files by completing this form and
attaching it to the SWDR.
PSR
PSR
MR
12/18/2023
800
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments
K=[(0.24)+(0.32)]/2=(0.28)K=[(0.24)+(0.32)]/2=(0.28)K=[(0.24)+(0.32)]/2=(0.28)K=[(0.24)+(0.32)]/2=(0.28)
LS=[(0.97)+(0.57)]/2=(0.77)LS=[(0.97)+(0.57)]/2=(0.77)LS=[(0.97)+(0.57)]/2=(0.77)LS=[(0.97)+(0.57)]/2=(0.77)
801
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments
RISK LEVEL DETERMINATION
Project Identifier/EA : 05-1800-0229-1 (05-1K6301)
Project Description:
San Jose Creek Multipurpose
Path
Dist-County-Route: 05-SB-101 & 217
Regional Water Board: Region 3, Central Coast
MS4 Area: City of Goleta
Begin PM: 21.6 & 1.0
End PM: 2.2
DSA (Acres): 2.34
Project Engineer: Miguel Ramirez
Risk Level Components
w/GIS Map Method for
Sediment Risk (A)
w/Individual Method for
Sediment Risk (B)
R factor 75.78 0.00
K factor & soil category 0.28 0.00
LS factor 0.77 0.00
Soil loss(ton/acre) 16.34 0.00
Sediment Risk (low, med, or High Medium Low
Receiving Water San Jose Creek
303(d) listed for sediment Yes
802
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments Beneficial uses for:
Cold Yes
Spawn Yes
Migratory Yes
Receiving Water Risk
(low or high) High Low
Combined Risk Level
(1, 2, or 3) Level 2 Level 1
Prepared By: P. Riegelhuth Date: 6/27/2022
Checked By: Date:
803
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments
Project Identifier/ EA: 05-1800-0119-1
(05-1K6301)
Entry
A) R Factor
Analyses of data indicated that when factors other than rainfall are held constant, soil loss is directly proportional to a rainfall factor composed of total storm kinetic energy (E) times the maximum 30-min intensity (I30) (Wischmeier and Smith, 1958). The numerical value of R is the average annual sum of EI30 for storm events during a rainfall record of at least 22 years. "Isoerodent" maps were developed based on R values calculated for more than 1000 locations in the Western U.S. Refer to the link below to determine the R factor for the project site.
http://cfpub.epa.gov/npdes/stormwater/LEW/lewCalculator.cfm R Factor Value 75.78
B) K Factor (weighted average, by area, for all site soils) The soil-erodibility factor K represents: (1) susceptibility of soil or surface material to erosion, (2) transportability of the sediment, and (3) the amount and rate of runoff given a particular rainfall input, as measured under a standard condition. Fine-textured soils that are high in clay have low K values (about
0.05 to 0.15) because the particles are resistant to detachment. Coarse-textured soils, such as sandy soils, also have low K values (about 0.05 to 0.2) because of high infiltration resulting in low runoff even though these particles are easily detached. Medium-textured soils, such as a silt loam, have moderate K values (about 0.25 to 0.45) because they are moderately susceptible to particle detachment and they produce runoff at moderate rates. Soils having a high silt content are especially susceptible to erosion and have high K values, which can exceed 0.45 and can be as large as 0.65. Silt-size particles are easily detached and tend to crust, producing high rates and large volumes of runoff. Use Site-specific data must be submitted.
Site-specific K factor guidance
K Factor Value 0.28
C) LS Factor (weighted average, by area, for all slopes) The effect of topography on erosion is accounted for by the LS factor, which combines the effects of a hillslope-length factor, L, and a hillslope-gradient factor, S. Generally speaking, as hillslope length and/or hillslope gradient increase, soil loss increases. As hillslope length increases, total soil loss and soil loss per unit area increase due to the progressive accumulation of runoff in the downslope direction. As the hillslope gradient increases, the velocity and erosivity of runoff increases. Use the LS table located in separate tab of this spreadsheet to determine LS factors. Estimate the weighted LS for the site prior to construction.
LS Table
LS Factor Value 0.77
804
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments
Watershed Erosion Estimate (=RxKxLS) in tons/acre 16.338168 Site Sediment Risk Factor
Low Sediment Risk: < 15 tons/acre Medium
Medium Sediment Risk: >=15 and <75 tons/acre
High Sediment Risk: >= 75 tons/acre
Prepared By: P. Riegelhuth
805
APPENDIX E CGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment AttachmentsCGP Risk Assessment Attachments
806
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 807
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 1/4/2024
808
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 809
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 810
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 811
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 812
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 813
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 814
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 815
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 816
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 817
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 818
DocuSign Envelope ID: E15EEAEB-CEEE-4C35-82E6-C9EE76A6F8E4 819
Central Coast Regional Water Quality Control Board
November 8, 2023
Charles W. Ebeling VIA ELECTRONIC MAIL
City of Goleta
130 Cremona Drive, Suite B
Goleta, CA, 93117
Email: [email protected]
Dear Charles W. Ebeling:
WATER QUALITY CERTIFICATION NO. 34223WQ33 FOR THE SAN JOSE CREEK
MULTIPURPOSE PATH PROJECT, SANTA BARBARA COUNTY
Thank you for the opportunity to review your July 12, 2023 application for water quality certification of the San Jose Creek Multipurpose Path Project (Project). The application was completed on July 18, 2023. All supplemental information requested was received on October 30, 2023. The Project, if implemented as described in your application and with the additional mitigation and other conditions required by this Clean Water Act Section 401 Water Quality Certification (Certification), appears to be protective of beneficial uses of State waters. We are issuing the enclosed Certification. Should new information come to our attention that indicates a water quality problem, we may require additional monitoring and reporting, issue waste discharge requirements, or take other action.
Your Certification application and submitted documents indicate that Project activities have the potential to affect beneficial uses and water quality. The Central Coast Regional Water Quality Control Board (Central Coast Water Board) issues this Certification to protect water quality and associated beneficial uses from Project activities. We need reports to determine compliance with this Certification. All technical and monitoring reports requested in this Certification, or any time after, are required per section 13383 of the California Water Code. Failure to submit reports required by this Certification, or failure to submit a report of technical quality acceptable to the Executive Officer, may subject you to enforcement action per section 13385 of the California Water Code.
Any person affected by this Central Coast Water Board action may petition the State Water Resources Control Board (State Water Board) to review this action in accordance with California Water Code section 13320 and Title 23, California Code of Regulations, sections 2050 and 3867-3869. The State Water Board, Office of Chief Counsel, PO Box 100, Sacramento, CA 95812, must receive the petition within 30 days of the date of this Certification. We will provide upon request copies of the law and regulations applicable to filing petitions.
In compliance with Title 40, Code of Federal Regulations (CFR) Part 121.7(d)(2), an explanation for each certification condition is provided in Attachment A.
820
City of Goleta Certification No. 34223WQ33 November 8, 2023
2 If you have questions, please contact April Woods at (805) 549 3332 or via email at [email protected] or Phil Hammer at (805) 549-3882. Please mention the above certification number in all future correspondence pertaining to this Project.
Sincerely,
for
Ryan E. Lodge
Executive Officer
Enclosure: Action on Request for CWA Section 401 Water Quality Certification
cc: With enclosures
Lindsay Tisch, Dewberry Engineers Inc: [email protected]
Crystal Huerta, U.S. Army Corps of Engineers: [email protected]
Ed Pert, CA Department of Fish and Wildlife: [email protected]
U.S. Environmental Protection Agency: [email protected]
State Water Board 401 Program: [email protected]
Hayden Reed, Central Coast Water Board: [email protected]
Jesse Woodard, Central Coast Water Board: [email protected]
April Woods, Central Coast Water Board: [email protected]
Phil Hammer, Central Coast Water Board: [email protected]
R:\RB3\Shared\401\Certifications\Santa Barbara\2023\34223WQ33 San Jose Creek Multipurpose Path Project\CERT\R3-San Jose Creek Multipurpose Path Project-34223WQ33 -CERT_final
821
City of Goleta Certification No. 34223WQ33 November 8, 2023