Agenda Item A.7
CONSENT CALENDAR
Meeting Date: March 18, 2025
TO:
TO: Mayor and Councilmembers
SUBMITTED BY: Luz “Nina” Buelna, Public Works Director
PREPARED BY: Michael Winnewisser, Project Manager
SUBJECT: Professional Services Agreement with U NICO Engineering, Inc. for Construction Management, Inspection, Materials Testing, and Public Outreach Services of the San Jose Creek Multipurpose Path Project RECOMMENDATION:
Authorize the City Manager to execute a Professional Services Agreement with U NICO Engineering, Inc. for Construction Management, Inspection, Materials Testing, and Public Outreach Services for the San Jose Creek Multipurpose Path for a total not -to-exceed amount of $2,853,654, with a termination date of December 31, 2027.
BACKGROUND:
The San Jose Creek Multipurpose Path Project (Project) (Capital Improvement Program Project No. 9006), an Active Transportation Program (ATP) project, will construct a multipurpose path adjacent to the San Jose Creek connecting areas north of U.S. Route 101 with the Class I Atascadero Creek Bikeway (Obern Trail) east of State Route 217.
Northern Segment
The Northern segment of the Project is roughly 0.5 mile s long. The new Multipurpose Path will begin on Calle Real near the intersection with N. Kellogg Ave . and will tie into the existing bicycle and pedestrian facilities on the south side of Calle Real. The Multipurpose Path then heads south adjacent to the west bank of San Jose Creek and crosses under the US 101 and Union Pacific Railroad (UPRR) structures over San Jose Creek. The Multipurpose Path continues along the west bank of San Jose Creek to conform to Armitos Avenue. At Armitos Avenue, the Northern Segment will tie into the previously constructed portion of the San Jose Creek Multipurpose Path which extends south from Armitos Avenue through Jonny D. Wallis Neighborhood Park.
Construction will consist of the following:
Retaining Walls: Six (6) sections ranging from 6 to 12 feet in height and 36 to 204 feet in length.
1 Meeting Date: March 18, 2025
Graded Slopes: Cut and fill slopes will be between 10 and 14 feet wide, with 2 - foot-wide graded shoulders on each side.
Multipurpose Path: A 10-foot-wide paved multi-use Multipurpose Path with graded shoulders.
Traffic Control & Signage: Multipurpose Path closure gates, bollards, signs, and pavement striping.
Southern Segment
The southern segment of the Project will begin at the intersection of S. Kellogg Avenue and Kellogg Way (future Ekwill Street) and extend approximately one mile. It will cross over the San Jose Creek channel and continue along Sate Route (SR) 217, crossing under SR 217 just north of the SR 217 bridge over San Jose Creek. It will then connect to the existing Atascadero Creek Bike Path on the east side of SR 217.
Construction will consist of the following:
Pedestrian Bridge: This 350 -foot-long, 12-foot-wide bridge over San Jose Creek connects bicycle/pedestrian to a bicycle/pedestrian tunnel under SR 217 at the southern end.
Multipurpose Path: Varies between 8 and 12 feet wide, including shoulders. Safety Barrier: A 2-foot-wide, 3-foot-tall concrete barrier with a bicycle/pedestrian railing to separate the Multipurpose Path from SR 217.
Retaining Wall: A single retaining wall measuring 1,067 feet in length. Environmental Mitigation: Tree removal and environmental mitigation planting. Traffic Control & Signage: Multipurpose Path closure gates, bollards, signs, and pavement striping.
Union Pacific Railroad Coordination
Additional coordination with Union Pacific Railroad involves the following construction:
10-foot-wide Multipurpose Path section crossing under railroad, Multipurpose Path shoulders ranging from 0 - 2 feet wide, Retaining wall along the creek side of the Multipurpose Path with rock slope protection on the creek bank.
A portion of this Project is supported by grant funding. On January 30, 2019, the California Transportation Commission (CTC) awarded the City of Goleta approximately $18 million in Active Transportation Program (ATP) funding . Most recently, on March 22, 2024, the CTC allocated ATP funding specifically for the project's construction phase.
With funding, the Project is moving forward with the bidding p rocess. On February 18, 2025, the Council authorized staff to advertise the Project for bids. Per Goleta Municipal 2 Meeting Date: March 18, 2025
Code (GMC) Section 3.05.170(C), Council approval is required before publishing a notice inviting bids for construction projects exceeding $200,000.
A Notice Inviting Sealed Bids will be published in a public newspaper, posted on the City’s website, and advertised on PlanetBids. The Project is expected to be out for bid by Spring 2025.
The Project is currently in its final design phase, and in preparation for construction, the Public Works Department has solicited proposals for comprehensive construction management service s. These services will encompass construction management, resident engineering, inspection, environmental oversight, cultura l and biological monitoring, public outreach, and material testing. This oversight is critical to ensuring compliance with federal construction requirements and verifying that the contractor delivers the Project in accordance with the City's and State’s Design and Construction Standards, bid documents, and specifications.
Public Outreach
The public outreach team will coordinate with the City’s Community Relations Manager and Public Works staff to develop a public outreach campaign to keep the community informed of the Project’s progress and the traffic impacts during the Project's construction phase. The public outreach portion of this Project will include community meetings with the public, residents, and businesses impacted by this Project, as well as co mmunity outreach to identify stakeholders impacted by construction activities. In partnership with the City, the public outreach team will facilitate conversations and commuter outreach.
The Project will have a dedicated website, business cards specific to the Project with a dedicated hotline, and infographics. The public outreach team will coordinate with Caltrans regarding the Caltrans projects concurrently constructing in the area to keep Goleta residents aware of any traffic impacts due to these projects.
DISCUSSION:
The Public Works Capital Improvement Program (CIP) Division is responsible for constructing and maintaining essential City infrastructure, including roads, bridges, drainage facilities, and traffic signals. To ensure projects are delivered successfully, cost- effectively, and safely, they must be managed by a Construction Management Team (CMT) led by a professional engineer. For this Project, a licensed Professional Engineer (PE) is needed to oversee all aspects of construction, including material testing, inspection, and overall project coordination, ensuring compliance with regulatory standards and adherence to project specifications.
On October 10, 2024, Public Works staff issued a Request for Proposals (RFP)for Construction Management services for the Sa n Jose Creek Multipurpose Path Project.
The RFP was published on PlanetBids and advertised in the newspaper to solicit proposals. The City received a total of three proposals from the following firms:
3 Meeting Date: March 18, 2025
1. UNICO Engineering, Inc. (UNICO)
2. MNS Engineers, Inc.
3. Filippin Engineering, Inc.
The RFP closed on November 25, 2024. The Public Works department formed a review team of four members, three from the City of Goleta and one from the City of Santa Barbara. The review team evaluated the proposals and underwent interviews using the ranking criteria outlined in the City-issued RFP. Based on ranking criteria, UNICO received the top ranking.
City staff collaborated with UNICO to negotiate staffing and service costs to ensure the Project complies with all federal guidelines and bid document requirements. According to the Caltrans Local Assistance Procedures Manual, specifically Chapter 16, Section 16.1, titled "Administer Construction Contracts," the City must ensure its project team is adequately staffed and equipped to administer the contract properly . To meet these requirements, UNICO’s CMT will provide full-time inspection and support throughout the duration of the Project.
Public Works staff recommends awarding this contract prior to construction award because there are preconstruction items that the UNICO must perform prior to the start of construction. Preconstruction tasks include public outreach, environmental compliance coordination, and Union Pacific Railroad and utility coordination.
Construction is expected to begin in Fall 2025 and be completed by early Winter 2027, and plant establishment scheduled for Fall 2027.
FISCAL IMPACTS:
There are fiscal impacts associated with the execution of this contract. The UNICO contract totals $2,853,654 and includes an annual escalation percentage between 3.5% and 5% per year , a federal requirement outlined in the Caltrans Local Assistance Procedures Manual Chapter 10 "Consultant Selection”. This Project is scheduled to have construction management needs for approximately 1.5 years, including pre- and post- construction requirements; therefore, the construction management will be approximately $1.90 million a year. Public Works staff has a fiduciary responsibility to the City and will monitor the construction management tasks, and the City will only pay for tasks performed.
The Engineer’s Estimate for the total construction cost is approximately $40,215,349. The Project is funded by the Transportation Development Act ( TDA), Development Impact Fee ( DIF), Regional Surface Transportation Program (RSTP), Santa Barbara County Association of Governments (SBCAG) Measure A, ATP, Transportation, Community and System Preservation ( TCSP), and Redevelopment Project Funds Grants. Recently the City was notified of an award of $11.16 million in Federal U.S. Department of Transportation (USDOT) funds through the FY 24 Reconnecting Communities Pilot (RCP) Program grant. Table 1 below details the Project cost estimates.
4 Meeting Date: March 18, 2025
Table 1: Agreement Costs
Vendor Project
Component
Cost Funding Source Funding
Amount
UNICO
Engineering, Inc.
Construction
Management
$2,853,654 235-90-9006-57071 $272,204
206-90-9006-57071 $53,385
205-90-9006-57071 $2,028,065
318-90-9006-57071 $500,000
Total: $2,853,654 Total: $2,853,654
Table 2: Project Cost Estimates
Project
Components
Estimated
Costs Funding Source Funding
Amounts
Conceptual Design $1,837,267* TDA (202) $262,062 Environmental $978,007* Measure A (205) $3,955,414 Final Design $4,362,726 Measure A (206) $438,378 Land Acquisition $1,119,000 DIF (Transportation 220) $4,729,665 Construction
$40,215,349 DIF (Bicycle and
Pedestrian 235)
$272,204
RSTP grant (305) $30,689
ATP Grant (318) $17,960,000
Housing and Community
Development (HCD) (319)
$729,866
TCSP – Federal (407) $76,510
Redevelopment Project
Fund (601)
$24,829
TBD Grant - USDOT RCP $11,156,330
Measure A Sales Tax
Revenue Bond Proceeds
(Pending)
$8,876,402
Total: $48,512,349 Total: $48,512,349
*Actual Costs to date
ALTERNATIVES:
City Council may choose not approve the Construction Management, Inspection, Materials Testing, and Public Outreach services agreement. Doing so could delay the Project's construction and jeopardize the ATP grant funding if it is not awarded for construction by the September 30, 2025, ATP grant deadline.
LEGAL REVIEW BY: Isaac Rosen, Acting City Attorney
5 Meeting Date: March 18, 2025
APPROVED BY: Robert Nisbet, City Manager
ATTACHMENTS:
1. Professional Services Agreement with UNICO Engineering, Inc. for Construction Management Services
6 ATTACHMENT 1
Professional Services Agreement with Unico Engineering, Inc. for Construction Management Services
7 City of Goleta
Department of Public Works and Unico Engineering, Inc.
Project Name: San Jose Creek Multipurpose Path Northern and Southern Segments Project
AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN THE CITY OF GOLETA
AND
UNICO ENGINEERING, INC.
This AGREEMENT FOR PROFESSIONAL SERVICES (herein referred to as “AGREEMENT”) is made and entered into this 18th day of March 2025, by and between the CITY OF GOLETA , a municipal corporation (herein referred to as "CITY"), and UNICO ENGINEERING, INC., a California Corporation (herein referred to as "CONSULTANT").
SECTION A. RECITALS
1. The CITY has a need for professional construction management services for the San Jose Creek Multipurpose Path Northern and Southern Segments Project; and
2. The CITY does not have the personnel able and/or available to perform the services required under this AGREEMENT, and therefore, the CITY desires to contract for professional services to accomplish this work; and
3. The CITY procured these services in compliance with Goleta Municipal Code Section 3.05.260; and
4. The City Council, on this 18
th day of March 2025, approved this
AGREEMENT and authorized the City Manager to execute the AGREEMENT.
SECTION B. TERMS
1. RETENTION AS CONSULTANT
CITY hereby retains CONSULTANT, and CONSULTANT hereby accepts such engagement, to perform the services described in Section 2.
CONSULTANT warrants it has the qualifications, experience, and facilities to properly and timely perform said services.
2. DESCRIPTION OF SERVICES
The services to be performed by CONSULTANT are as follows:
8 City of Goleta
Department of Public Works and Unico Engineering, Inc.
Professional Construction Management Services in conjunction with the San Jose Creek Multipurpose Path Northern and Southern Segments Project. Services shall generally include construction management tasks, as more particularly set forth in the Scope of Work, attached as Exhibit “A,” and incorporated herein.
3. COMPENSATION AND PAYMENT
(a) Maximum and Rate . The total compensation payable to CONSULTANT by CITY for the services under this AGREEMENT SHALL NOT EXCEED the sum of $2,853,654 (herein "not to exceed amount"), and shall be earned as the work progresses on the following basis:
Hourly at the hourly rates and with reimbursement to
CONSULTANT for those expenses set forth in CONSULTANT's Schedule of Fees marked Exhibit "B," attached and incorporated herein. The rates and expenses set forth in that exhibit shall be binding upon CONSULTANT until December 31, 2027, after which any change in said rates and expenses must be approved in writing by CITY's Project Manager as described in Section 5 (CITY is to be given 60 days notice of any rate increase request), provided the not to exceed amount is the total compensation due CONSULTANT for all work described under this AGREEMENT.
(b) Payment . CONSULTANT shall provide CITY with written verification of the actual compensation earned, which written verification shall be in a form satisfactory to CITY's Project Manager, as described in Section 5.
Invoices shall be made no more frequently than on a monthly basis, and describe the work performed (including a list of hours worked by personnel classification).
All payments shall be made within 30 days after CITY’s approval of the invoice.
4. EXTRA SERVICES
CITY shall pay CONSULTANT for those CITY authorized extra services, not reasonably included within the services described in Section 2, as mutually agreed to writing in advance of the incurrence of extra services by CONSULTANT. Unless CITY and CONSULTANT have agreed in writing before the performance of extra services, no liability and no right to claim compensation for such extra services or expenses shall exist. The applicable hourly rates for extra services shall be at the hourly rates set forth in Exhibit B, if one is included as part of this agreement. Any compensation for extra services shall be part of the total compensation and shall not increase the not to exceed amount identified in Section 3.
9 City of Goleta
Department of Public Works and Unico Engineering, Inc.
5. CITY PROJECT MANAGER AND SERVICES BY CITY
The services to be performed by CONSULTANT shall be accomplished under the general direction of, and coordinate with, CITY's "Project Manager", as that staff person is designated by CITY from time to time, and who presently is Michael Winnewisser. Project Manager shall have the authority to act on behalf of the CITY in administering this AGREEMENT but shall not be authorized to extend the term of the AGREEMENT or increase the not to exceed amount.
6. TERM, PROGRESS AND COMPLETION
The term of this AGREEMENT is from the date first written above to December 31, 2027, unless term of this AGREEMENT is extended, or the AGREEMENT is terminated as provided for herein.
CONSULTANT shall not commence work on the services to be performed until (i) CONSULTANT furnishes proof of insurance as required by Section 10 below, and (ii) CITY gives written authorization to proceed with the work provided by CITY's Project Manager.
7. OWNERSHIP OF DOCUMENTS
All drawings, designs, data, photographs, reports and other documentation (other than CONSULTANT's drafts, notes and internal memorandum), including duplication of same prepared by CONSULTANT in the performance of these services, are the property of CITY. CITY shall be entitled to immediate possession of the same upon completion of the work under this AGREEMENT, or at any earlier or later time when requested by CITY. CITY agrees to hold CONSULTANT harmless from all damages, claims, expenses, and losses arising out of any reuse of the plans and specifications for purposes other than those described in this AGREEMENT, unless written authorization of CONSULTANT is first obtained.
8. PERSONAL SERVICES/NO ASSIGNMENT/SUBCONTRACTOR
This AGREEMENT is for professional services which are personal to CITY. Craig Schellenger is deemed to be specially experienced and is a key member of CONSULTANT's firm, and shall be directly involved in the performance of this work. This key person shall communicate with, and periodically report to, CITY on the progress of the work. Should any such individual be removed from assisting in this contracted work for any reason, CITY may terminate this AGREEMENT. This AGREEMENT may not be assigned or subcontracted without the City Manager’s prior written consent. 10 City of Goleta
Department of Public Works and Unico Engineering, Inc.
9. HOLD HARMLESS AND INDEMNITY
(a) Hold Harmless for CONSULTANT's Damages. CONSULTANT
holds CITY, its elected officials, officers, agents, and employees, harmless from all of CONSULTANT's claims, demands, lawsuits, judgments, damages, losses, injuries or liability to CONSULTANT, to CONSULTANT's employees, to CONSULTANT’s contractors or subcontractors, or to the owners of CONSULTANT's firm, which damages, losses, injuries or liability occur during the work required under this AGREEMENT, or occur while CONSULTANT is on CITY property, or which are connected, directly or indirectly, with CONSULTANT's performance of any activity or work required under this AGREEMENT.
(b) Defense and Indemnity of Third-Party Claims/Liability.
CONSULTANT shall investigate, defend, and indemnify CITY, its elected officials, officers, agents, and employees, from any claims, lawsuits, demands, judgments, and all liability including, but not limited to, monetary or property damage, lost profit, personal injury, wrongful death, general liability, automobile, infringement of copyright/patent/trademark, or professional errors and omissions arising out of, directly or indirectly, an error, negligence, or omission of CONSULTANT or any of CONSULTANT’s officers, agents, employees, representatives, subconsultants, or subcontractors, or the willful misconduct of CONSULTANT or any of CONSULTANT’s officers, agents, employees, representatives, subconsultants, or subcontractors, in performing the services described in, or normally associated with, this type of contracted work. The duty to defend shall include any suits or actions concerning any activity, product or work required under this AGREEMENT, and also include the payment of all court costs, attorney fees, expert witness costs, investigation costs, claims adjusting costs and any other costs required for and related thereto. (c) No Waiver. CITY does not waive, nor shall be deemed to have waived, any indemnity, defense or hold harmless rights under this section because of the acceptance by CITY, or the deposit with CITY, of any insurance certificates or policies described in Section 10.
10. INSURANCE
CONSULTANT shall, at CONSULTANT's sole cost and expense, provide insurance as described herein. All insurance is to be placed with insurers authorized to do business in the State of California with an A.M. Best and Company rating of A- or better, Class VII or better, or as otherwise approved by CITY.
Insurance shall include the following (or broader) coverage:
a) Insurance Services Office Commercial Liability coverage “occurrence” form CG 00 01 or its exact equivalent with an edition date prior to 11 City of Goleta
Department of Public Works and Unico Engineering, Inc.
2004 and with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate.
b) Insurance Services Office form number CA 00 01 or equivalent covering Automobile Liability, including hired and non-owned automobile liability with a minimum limit of $1,000,000 per accident. If the Service Provider owns no vehicles, this requirement may be satisfied by a non-owned and hired auto endorsement to Service Provider’s commercial general liability policy.
c) Workers’ Compensation insurance complying with California worker’s compensation laws, including statutory limits for workers’ compensation and an Employer’s Liability limit of $1,000,000 per accident or disease.
d) Professional liability insurance that covers the services to be performed in connection with this agreement, in the minimum amount of $1,000,000 per claim.
Liability insurance policies required to be provided by CONSULTANT hereunder shall contain or be endorsed to contain the following provisions:
a) Except for professional liability insurance, CITY, its employees, officials, agents and member agencies shall be covered as additional insureds. Coverage shall apply to any and all liability arising out of the work performed or related to the contract. Additional insured status under the general liability requirement shall be provided on Insurance Services Office Form CG 20 10, with an edition date prior to 2004, or its equivalent. Additional insured status for completed operations shall be provided either in the additional insured form or through another endorsement such as CG 20 37, or its equivalent.
b) General and automobile liability insurance shall apply separately to each insured against whom a claim is made or suit is brought, except with respect to the limits of the insurer’s liability. Coverage will not be limited to CITY’s vicarious liability.
c) Professional liability insurance policies inception date, continuity date, or retroactive date must be before the effective date of this agreement. CONSULTANT agrees to maintain continuous coverage through a period no less than three years after completion of the services required by this agreement.
d) Except for professional liability insurance, liability coverage shall be primary and non-contributing with any insurance maintained by CITY.
12 City of Goleta
Department of Public Works and Unico Engineering, Inc.
e) Evidence of coverage (including the workers’ compensation and employer’s liability policies) shall provide that coverage shall not be suspended, voided, canceled or reduced in coverage or in limits except after 30 days’ prior written notice has been given to CITY.
Such provision shall not include any limitation of liability of the insurer for failure to provide such notice.
f) No liability insurance coverage provided to comply with this AGREEMENT shall prohibit CONSULTANT, or CONSULTANT’s
employees, or agents, from waiving the right of recovery prior to a loss. CONSULTANT waives its right of recovery against CITY.
g) CONSULTANT agrees to deposit with CITY within fifteen days of Notice to Proceed of the Contract certificates of insurance and required endorsements.
h) There shall be no recourse against CITY for payment of premiums or other amounts with respect to the insurance required to be provided by CONSULTANT hereunder. Any failure, actual or alleged, on the part of CITY to monitor compliance with these requirements will not be deemed as a waiver of any rights on the part of CITY. CITY has no additional obligations by virtue of requiring the insurance set forth herein. In the event any policy of insurance required under this AGREEMENT does not comply with these requirements or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONSULTANT or CITY will withhold amounts sufficient to pay premium from CONSULTANT payments.
i) CONSULTANT agrees to provide immediate notice to CITY of any claim or loss against CONSULTANT arising out of the work performed under this AGREEMENT. CITY assumes no obligation or liability by such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve CITY.
11. RELATIONSHIP OF CONSULTANT TO CITY
The relationship of the CONSULTANT to CITY shall be that of an independent contractor and that in no event shall CONSULTANT be considered an officer, agent, servant or employee of CITY. CONSULTANT shall be solely responsible for any workers compensation insurance, withholding taxes, unemployment insurance, and any other employer obligations associated with the described work.
13 City of Goleta
Department of Public Works and Unico Engineering, Inc.
12. CORRECTIONS
In addition to the above indemnification obligations, CONSULTANT shall correct, at its expense, all errors in the work that may be disclosed during CITY's review of CONSULTANT's report or plans. Should CONSULTANT fail to make such correction in a reasonably timely manner, such correction shall be made by CITY, and the cost thereof shall be charged to CONSULTANT or withheld from any funds due to CONSULTANT hereunder.
13. TERMINATION BY CITY
CITY, by notifying CONSULTANT in writing, may upon 10 calendar days notice, terminate without cause any portion or all of the services agreed to be performed under this AGREEMENT. If termination is for cause, no notice period need be given. In the event of termination, CONSULTANT shall have the right and obligation to immediately assemble work in progress for the purpose of closing out the job. All compensation for actual work performed and charges outstanding at the time of termination shall be payable by CITY to CONSULTANT within 30 days following submission of a final statement by CONSULTANT unless termination is for cause. In such event, CONSULTANT shall be compensated only to the extent required by law.
14. ACCEPTANCE OF FINAL PAYMENT CONSTITUTES RELEASE
The acceptance by CONSULTANT of the final payment made under this AGREEMENT shall operate as and be a release of CITY from all claims and liabilities for compensation to CONSULTANT for anything done, furnished, or relating to CONSULTANT'S work or services. Acceptance of payment shall be any negotiation of CITY's check or the failure to make a written extra compensation claim within 10 calendar days of the receipt of that check.
However, approval or payment by CITY shall not constitute, nor be deemed, a release of the responsibility and liability of CONSULTANT, its employees, subcontractors, agents and CONSULTANTs for the accuracy and competency of the information provided and/or work performed; nor shall such approval or payment be deemed to be an assumption of such responsibility or liability by CITY for any defect or error in the work prepared by CONSULTANT, its employees, subcontractors, agents and consultants.
15. AUDIT OF RECORDS
At any time during normal business hours and as often as it may deem necessary, CONSULTANT shall make available to a representative of CITY for examination of all its records with respect to all matters covered by this AGREEMENT and will permit CITY to audit, examine and/or reproduce such records. CONSULTANT will retain such financial records, time sheets, work progress reports, invoices, bills and project records for at least two years after termination or final payment under this AGREEMENT.
14 City of Goleta
Department of Public Works and Unico Engineering, Inc.
16. WAIVER; REMEDIES CUMULATIVE
Failure by a party to insist upon the strict performance of any of the provisions of this AGREEMENT by the other party, irrespective of the length of time for which such failure continues, shall not constitute a waiver of such party's right to demand strict compliance by such other party in the future. No waiver by a party of a default or breach of the other party shall be effective or binding upon such party unless made in writing by such party, and no such waiver shall be implied from any omissions by a party to take any action with respect to such default or breach. No express written waiver of a specified default or breach shall affect any other default or breach, or cover any other period of time, other than any default or breach and/or period of time specified. All of the remedies permitted or available to a party under this AGREEMENT, or at law or in equity, shall be cumulative and alternative, and invocation of any such right or remedy shall not constitute a waiver or election of remedies with respect to any other permitted or available right of remedy.
17. CONFLICT OF INTEREST
CONSULTANT is unaware of any CITY employee or official that has a financial interest in CONSULTANT'S business. During the term of this AGREEMENT and/or as a result of being awarded this AGREEMENT, CONSULTANT shall not offer, encourage or accept any financial interest in CONSULTANT'S business by any CITY employee or official.
18. CONSTRUCTION OF LANGUAGE OF AGREEMENT
The provisions of this AGREEMENT shall be construed as a whole according to its common meaning of purpose of providing a public benefit and not strictly for or against any party. It shall be construed consistent with the provisions hereof, in order to achieve the objectives and purposes of the parties.
Wherever required by the context, the singular shall include the plural and vice versa, and the masculine gender shall include the feminine or neutral genders or vice versa.
19. MITIGATION OF DAMAGES
In all situations arising out of this AGREEMENT, the parties shall attempt to avoid and minimize the damages resulting from the conduct of the other party.
20. GOVERNING LAW
This AGREEMENT, and the rights and obligations of the parties, shall be governed and interpreted in accordance with the laws of the State of California.
Should litigation occur, venue shall be in Superior Court of Santa Barbara County.
15 City of Goleta
Department of Public Works and Unico Engineering, Inc.
21. NONDISCRIMINATION
The City reaffirms its ongoing commitment to equality in the conduct of City business, and prohibits any policy, plan, program, custom or practice, including harassment, in the conduct of City business. No discrimination or discriminatory practice shall occur in either employment of persons for, or completion of, the work contemplated by this Agreement, when such discrimination is based on race, color, national origin, or ancestry; religion; sex; gender, gender identity, gender expression, or gender transitioning status; physical disability, mental disability, medical condition, or genetic information; marital or domestic partner status; citizenship status; age; sexual orientation; exercising a legally protected right to an employment leave of absence; status as a victim of domestic violence, sexual assault, or stalking; reproductive health decision-making, or any other classification protected under state or federal law.
Among other possible violations of law, a violation of this section exposes CONSULTANT to the penalties provided for in Labor Code Section 1735.
22. TAXPAYER IDENTIFICATION NUMBER
CONSULTANT shall provide CITY with a complete Request for Taxpayer Identification Number and Certification, Form W-9 (Rev. October 2018), as issued by the Internal Revenue Service.
23. NON-APPROPRIATION OF FUNDS
Payments due and payable to CONSULTANT for current services are within the current budget and within an available, unexhausted and unencumbered appropriation of CITY funds. In the event CITY has not appropriated sufficient funds for payment of CONSULTANT services beyond the current fiscal year, this AGREEMENT shall cover only those costs incurred up to the conclusion of the current fiscal year.
24. MODIFICATION OF AGREEMENT
The tasks described in this AGREEMENT and all other terms of this AGREEMENT may be modified only upon mutual written consent of CITY and CONSULTANT.
25. USE OF THE TERM “CITY”
Reference to “CITY” in this AGREEMENT includes City Manager or any authorized representative acting on behalf of CITY.
26. PERMITS AND LICENSES
CONSULTANT, at its sole expense, shall obtain and maintain during the term of this AGREEMENT, all appropriate permits, licenses, and certificates that 16 City of Goleta
Department of Public Works and Unico Engineering, Inc.
may be required in connection with the performance of services under this AGREEMENT.
27. CAPTIONS
The captions or headings in this AGREEMENT are for convenience only and in no other way define, limit or describe the scope or intent of any provision or section of the AGREEMENT.
28. AUTHORIZATION
Each party has expressly authorized the execution of this AGREEMENT on its behalf and bind said party and its respective administrators, officers, directors, shareholders, divisions, subsidiaries, agents, employees, successors, assigns, principals, partners, joint venturers, insurance carriers and any others who may claim through it to this AGREEMENT.
29. ENTIRE AGREEMENT BETWEEN PARTIES
Except for CONSULTANT'S proposals and submitted representations for obtaining this AGREEMENT, this AGREEMENT supersedes any other agreements, either oral or in writing, between the parties hereto with respect to the rendering of services, and contains all of the covenants and agreements between the parties with respect to said services.
30. PARTIAL INVALIDITY
If any provision in this AGREEMENT is held by a court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions will nevertheless continue in full force without being impaired or invalidated in any way.
31. NOTICES
Any notice required to be given hereunder shall be deemed to have been given by depositing said notice in the United States mail, postage prepaid, and addressed as follows:
TO CITY: Attention: Robert Nisbet, City Manager
City of Goleta
130 Cremona Drive, Suite B
Goleta, CA 93117
TO CONSULTANT: Attn: Cesar Montes de Oca, PE, President UNICO Engineering, Inc.
110 Blue Ravine Road, Suite 101
Folsom, CA 95630
17 City of Goleta
Department of Public Works and Unico Engineering, Inc.
32. COUNTERPARTS AND ELECTRONIC/FACSIMILE SIGNATURES
This Agreement may be executed in several counterparts, which may be facsimile or electronic copies. Each counterpart is fully effective as an original, and together constitutes one and the same instrument.
33. FEDERAL REQUIREMENTS
FEMA financial assistance will be used to fund all or a portion of this contract. The Consultant shall comply with all federal requirements including, but not limited to, the following:
1. 2 C.F.R. Part 200 – Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.
2. Federal Contract Provisions attached hereto as Exhibit “C” and incorporated herein by reference.
Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, 2 C.F.R.
Part 200 and the Federal Contract Provisions.
With respect to any conflict between such federal requirements and the terms of this contract and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.
18 City of Goleta
Department of Public Works and Unico Engineering, Inc.
In concurrence and witness whereof , this AGREEMENT has been executed by the parties effective on the date and year first above written.
CITY OF GOLETA CONSULTANT
_____________________________ _____________________________ Robert Nisbet, City Manager Cesar Montes de Oca, PE, President
ATTEST
_____________________________ _____________________________ Deborah Lopez, City Clerk Cesar Montes de Oca, PE, Secretary
APPROVED AS TO FORM:
ISAAC ROSEN, ACTING CITY ATTORNEY
_____________________________
Scott Shapses, Deputy City Attorney
19 City of Goleta
Department of Public Works and Unico Engineering, Inc.
EXHIBIT A
SCOPE OF WORK
20 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 11
Quality
21 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 12
22 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 13
23 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 14
24 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 15
Safety
Lane Closures on SR 217
25 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 16
PreCast Pretensioned Concrete Girders
26 CITY OF GOLETA
San Jose Creek Multipurpose Path | Northern and Southern Segments | CM Services | 17
Cultural Resources
27 City of Goleta
Department of Public Works and Unico Engineering, Inc.
EXHIBIT B
SCHEDULE OF FEES
28 6464 Hollister Avenue, Suite 3
Goleta, CA 93117
916-900-6623
Direct Labor Rate $100.00 $90.00 $74.52 $36.06 $65.00 $65.00 $65.00 $74.80 $92.62 $85.17 $33.50 $87.46 $87.16 $76.09 $35.83 $41.60 $87.05 $59.99 $47.25 $42.04 $39.82 $31.05 $36.57 $41.67 $40.21 $52.10 $80.00 $45.00 $74.52 $62.50 $60.00 $55.00 $40.00 $30.00 $90.56 $61.01 Overhead Rate
Fee
Bill Rate $287.44 $258.70 $214.20 $103.65 $186.84 $186.84 $186.84 $215.01 $266.23 $244.81 $96.29 $303.91 $302.87 $264.40 $124.50 $144.55 $302.48 $208.46 $164.19 $146.08 $138.37 $107.89 $127.07 $144.80 $139.72 $181.04 $202.40 $113.85 $308.78 $258.97 $248.61 $227.90 $165.74 $124.31 $253.68 $170.91 Task # Task Description Total
1 Services Prior to Construction 10 40 80 80 40 40 53,597.68$ 2 Construction Management Services 50 960 1920 1920 1920 960 80 40 240 240 40 300 0 125 85 0 260 100 700 1,881,548.07$ 3 Services During Construction Closeout 10 40 80 80 40 40 53,597.68$ 4 Quality Control Plan 7 52 214 321 438 280 319 40 12 19 41 269,212.99$ 5 Tribal Cultural Resource Monitoring & Treatment Plan 18 68 50 407 2000 500 550,214.23$ 2,808,170.65$
70 1040 2080 2080 2000 1040 80 40 240 240 40 7 18 68 50 407 52 214 321 438 280 319 40 12 19 41 2000 500 300 0 125 85 0 260 100 700 45,483.35$
$ 15,000.00
$ 20,000.00
$ 10,483.35
Total 2,853,654.00$
City of Goleta
San Jose Creek Multipurpose Path - Northern and Southern Segments - (CIP 9006) -Federal Number 5481(022) Cost Proposal
Twining
143.59%
15%
149.95%
15%
UNICO Engineering
Hours
Rincon
202.16%
15%
KMP StrategiesA & G Consulting
Other Direct Costs
Lab Testing
120.00%
15%
260.31%
15%
Public Outreach Needs (i.e., Graphic
design, printing, postage, digital ads,
Rincon ODCs and Escalation
11/22/2024
29 6464 Hollister Avenue, Suite 3
Concord, CA 93117
916-900-6623
Direct Labor Rate $87.46 $87.16 $76.09 $35.83 $41.60 $87.05 $59.99 $47.25 $42.04 $39.82 $31.05 $36.57 $41.67 $40.21 $52.10 Overhead Rate
Fee
Bill Rate $303.91 $302.87 $264.40 $124.50 $144.55 $302.48 $208.46 $164.19 $146.08 $138.37 $107.89 $127.07 $144.80 $139.72 $181.04 Task # Task Description Total
1 Services Prior to Construction -$
2 Construction Management Services 7 52 214 321 438 280 319 40 12 19 41 269,212.99$ 3 Services During Construction Closeout -$
4 Quality Control Plan -$
5 Tribal Cultural Resource Monitoring & Treatment Plan 18 68 50 407 88,489.23$ 357,702.22$
7 18 68 50 407 52 214 321 438 280 319 40 12 19 41
10,483.35$
$ 10,483.35
368,185.57$
City of Goleta
San Jose Creek Multipurpose Path - Northern and Southern Segments Cost Proposal
Rincon
202.16%
15%
Other Direct Costs
Rincon ODCs and Escalation
Total
11/22/2024
30 6464 Hollister Avenue, Suite 3
Concord, CA 93117
916-900-6623
Direct Labor Rate $80.00 $45.00
Overhead Rate
Fee
Bill Rate $202.40 $113.85
Task # Task Description Total
1 Services Prior to Construction -$
2 Construction Management Services -$
3 Services During Construction Closeout -$
4 Quality Control Plan -$
5 Tribal Cultural Resource Monitoring & Treatment Plan 2000 500 461,725.00$ 461,725.00$
2000 500 0 0 0 0 0
-$
461,725.00$ Total
Other Direct Costs
City of Goleta
San Jose Creek Multipurpose Path - Northern and Southern Segments Cost Proposal
A & G Consulting
120.00%
15%
11/22/2024
31 6464 Hollister Avenue, Suite 3
Concord, CA 93117
916-900-6623
Direct Labor Rate $74.52 $62.50 $60.00 $55.00 $40.00 $30.00 Overhead Rate
Fee
Bill Rate $308.78 $258.97 $248.61 $227.90 $165.74 $124.31 Task # Task Description Total
1 Services Prior to Construction -$
2 Construction Management Services 300 0 125 85 0 260 175,401.25$ 3 Services During Construction Closeout -$
4 Quality Control Plan -$
5 Tribal Cultural Resource Monitoring & Treatment Plan -$ 175,401.25$
300 0 125 85 0 260 0 0 0 0 0
20,000.00$
$ 20,000.00
195,401.25$ Total
Public Outreach Needs (i.e.,
Graphic design, printing, postage,
City of Goleta
San Jose Creek Multipurpose Path - Northern and Southern Segments Cost Proposal
KMP Strategies
260.31%
15%
Other Direct Costs
11/22/2024
32 6464 Hollister Avenue, Suite 3
Concord, CA 93117
916-900-6623
Direct Labor Rate $90.56 $61.01
Overhead Rate
Fee
Bill Rate $253.68 $170.91
Task # Task Description Total
1 Services Prior to Construction -$
2 Construction Management Services 100 700 145,002.92$
3 Services During Construction Closeout -$
4 Quality Control Plan -$
5 Tribal Cultural Resource Monitoring & Treatment Plan -$ 145,002.92$
100 700 0 0 0
15,000.00$
$ 15,000.00
160,002.92$
City of Goleta
San Jose Creek Multipurpose Path - Northern and Southern Segments Cost Proposal
Twining
143.59%
15%
Total
Other Direct Costs
Lab Testing
11/22/2024
33 34
35 36
37 38
39 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Note: Mark-Ups are Not Allowed
Consultant: A and G Consulting
Project No. Contract No. Date
Project Name
DIRECT LABOR
Classification/Title Name Hours Actual Hr Rate Total
Cultural Resource Monitoring Gabriel Frausto 2000 80.00$ 160,000.00$ Project Manager Ashlee Frausto 500 45.00$ 22,500.00$ 2,500
LABOR COSTS
a) Subtotal Direct Labor Costs 182,500.00$
b) Anticipated Salary Increases $0.00
c) TOTAL DIRECT LABOR COSTS [(a) + (b)] 182,500.00$
INDIRECT COSTS
d) Fringe Benefits (Rate: 0.00% ) c) Total Fringe Benefits [(c) x (d)] -$ f) Overhead (Rate: 120.00% ) g) Overhead [(c) x (f)] 219,000.00$ h) General and Administrative (Rate: 0.00% ) i) Gen & Admin [(c) x (h)] -$ j) TOTAL INDIRECT COSTS [(e) + (g) + (i)] 219,000.00$
FIXED FEE k) TOTAL FIXED FEE [(c) + (j)] x fixed fee 15% ] 60,225.00$ l) CONSULTANT’S OTHER DIRECT COSTS (ODC) – ITEMIZE (Add additional pages if necessary) Quantity Unit Unit Cost Total
-$
i) TOTAL OTHER DIRECT COSTS -$
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) m) TOTAL SUBCONSULTANTS' COSTS -$
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] -$ TOTAL COST [(c) + (j) + (k) + (n)] 461,725.00$
NOTES:
Direct Labor Total Hours per Avg 5 Year
Subtotal per Cost Cost Proposal Hourly Contract
Proposal Rate Duration
= $73.00 Year 1 Avg
Hourly Rate
Avg Hourly Rate Proposed Escalation
Year 1 + 5.0% = $76.65 Year 2 Avg Hourly Rate
SAMPLE COST PROPOSAL 1
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (DESIGN, ENGINEERING AND ENVIRONMENTAL STUDIES)
November 21, 2024
San Jose Creek
Range
Description of Item
1. Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
2. The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant’s annual accounting period and established by a cognizant agency or accepted by Caltrans.
3. Anticipated salary increases calculation (page 2) must accompany.
SAMPLE COST PROPOSAL 1
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (CALCULATIONS FOR ANTICIPATED SALARY INCREASES)
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) $182,500.00 2,500
1. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %) $73.00
40 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Year 2 + 5.0% = $80.48 Year 3 Avg Hourly Rate
Year 3 + 5.0% = $84.51 Year 4 Avg Hourly Rate
Year 4 + 5.0% = $88.73 Year 5 Avg Hourly Rate
Estimated % Completed Total Hours per Cost Total Hours per Each Year Proposal Year
Year 1 * 2,500 = 2500 Estimated Hours Year 1
Year 2 * 2,500 = 0 Estimated Hours Year 2
Year 3 * 2,500 = 0 Estimated Hours Year 3
Year 4 * 2,500 = 0 Estimated Hours Year 4
Year 5 * 2,500 = 0 Estimated Hours Year 5
Total Total = 2,500
Avg Hourly Rate Estimated hours
(Calculated above) (Calculated Above)
Year 1 * 2500 = Estimated Hours Year 1
Year 2 * 0 = Estimated Hours Year 2
Year 3 * 0 = Estimated Hours Year 3
Year 4 * 0 = Estimated Hours Year 4
Year 5 * 0 = Estimated Hours Year 5
Total Direct Labor Cost with Escalation =
Direct Labor Subtotal before Escalation =
Estimated total of Direct Labor Salary Increase = Transfer to Page 1 NOTES:
3. This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
4. Calculations for anticipated salary escalation must be provided.
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) Prime Consultant or Subconsultant Certifying:
Name**: Title**:
Signature: Date of Certification (mm/dd/yyyy):
$0.00
1. This is not the only way to estimate salary increases. Other methods will be accepted if they clearly indicate the % increase, the # of years of the contract, and a breakdown of the labor to be performed each year.
Ashlee Frausto
11/21/2024
2. An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not acceptable. (i.e. $250,000 x 2% x 5 yrs = $25,000 is not an acceptable methodology) SAMPLE COST PROPOSAL 1
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements:
23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement. Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
President
$76.65
$80.48
$84.51
3. Calculate estimated hours per year (Multiply estimate % each year by total hours) 100.0%
0.0%
Year
$182,500.00
Cost Per
$0.00
$182,500.00
$182,500.00
$0.00
0.0%
0.0%
0.0%
100.0%
4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours) $73.00
$76.65
$80.48 $0.00
$84.51 $0.00
$88.73
Ashlee Frausto
41 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Email**: Phone Number:
Address: 595 Ranch Road, Solvang CA 93463
List services the consultant is providing under the proposed contract:
[email protected] 805-568-8872
**An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Tribal Cultural Resource Monitoring
42 Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal
Note: Mark-Ups are Not Allowed
Consultant: KMP STRATEGIES LLC
Project No. Contract No. Date
Project Name
DIRECT LABOR
Classification/Title Name Hours Actual Hr Rate Total
Partner Sarah Modeste 300 74.52$ 22,356.00$ Partner Noah Painter 0 62.50$ -$
Senior Project Manager KMP Staff 125 60.00$ 7,500.00$ Project Manager KMP Staff 85 55.00$ 4,675.00$ Project Coordinator KMP Staff 0 40.00$ -$ Project Assistant KMP Staff 260 30.00$ 7,800.00$ 770
LABOR COSTS
a) Subtotal Direct Labor Costs 42,331.00$
b) Anticipated Salary Increases $0.00
c) TOTAL DIRECT LABOR COSTS [(a) + (b)] 42,331.00$
INDIRECT COSTS
d) Fringe Benefits (Rate: 22.19% ) c) Total Fringe Benefits [(c) x (d)] 9,393.25$ f) Overhead (Rate: 238.12% ) g) Overhead [(c) x (f)] 100,798.58$ h) General and Administrative (Rate: 0.00% ) en & Admin [(c) x (h)] -$ j) TOTAL INDIRECT COSTS [(e) + (g) + (i)] 110,191.83$
FIXED FEE k) TOTAL FIXED FEE [(c) + (j)] x fixed fee 15% ] 22,878.42$ l) CONSULTANT’S OTHER DIRECT COSTS (ODC) – ITEMIZE (Add additional pages if necessary) Unit Cost Total
Public Outreach Needs (i.e., Graphic design, printing, postage, domain, digital ads,etc.) 20,000.00$ i) TOTAL OTHER DIRECT COSTS 20,000.00$
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) m) TOTAL SUBCONSULTANTS' COSTS -$
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] 20,000.00$ TOTAL COST [(c) + (j) + (k) + (n)] 195,401.25$
NOTES:
3. Anticipated salary increases calculation (page 2) must accompany.
1. Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
2. The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant’s annual accounting period and established by a cognizant agency or accepted by Caltrans.
Description of Item
EXHIBIT 10-H1 COST PROPOSAL Page 1 of 3
ACTUAL COST-PLUS-FIXED FEE OR LUMP SUM (FIRM FIXED PRICE) CONTRACTS (DESIGN, ENGINEERING AND ENVIRONMENTAL STUDIES)
November 21, 2024
San Jose Creek Multipurpose Path - Northern and Southern Segments Prime Consultant
Subconsultant
2nd Tier Subconsultant
January 2020
43 Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal
Direct Labor Total Hours per Avg 5 Year
Subtotal per Cost Cost Proposal Hourly Contract
Proposal Rate Duration
$54.98 Year 1 Avg
Hourly Rate
Avg Hourly Rate
Year 1 + $56.62 Year 2 Avg Hourly Rate
Year 2 + $58.32 Year 3 Avg Hourly Rate
Year 3 + $60.07 Year 4 Avg Hourly Rate
Year 4 + $61.88 Year 5 Avg Hourly Rate
Estimated % Completed Total Hours per Each Year Year
Year 1 * 770 Estimated Hours Year 1
Year 2 * 0 Estimated Hours Year 2
Year 3 * 0 Estimated Hours Year 3
Year 4 * 0 Estimated Hours Year 4
Year 5 * 0 Estimated Hours Year 5
Total 770
Avg Hourly Rate
(Calculated above)
Year 1 * Estimated Hours Year 1
Year 2 * Estimated Hours Year 2
Year 3 * Estimated Hours Year 3
Year 4 * Estimated Hours Year 4
Year 5 * Estimated Hours Year 5
Transfer to Page 1
NOTES:
3. This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
4. Calculations for anticipated salary escalation must be provided. $60.07 $0.00
$61.88 $0.00
$42,331.00
$54.98 $42,331.00
$56.62 $0.00
$58.32 $0.00
$42,331.00
$0.00
1. This is not the only way to estimate salary increases. Other methods will be accepted if they clearly indicate the % increase, the # of years of the contract, and a breakdown of the labor to be performed each year.
2. An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not acceptable. (i.e. $250,000 x 2% x 5 yrs = $25,000 is not an acceptable methodology)
0.0%
100.000%
4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours) Cost Per
Year
3. Calculate estimated hours per year (Multiply estimate % each year by total hours) 100.0%
0.0%
0.0%
0.0%
1. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %) $54.98
$56.62
$58.32
$60.07
EXHIBIT 10-H1 COST PROPOSAL Page 2 of 3
ACTUAL COST-PLUS-FIXED FEE OR LUMP SUM (FIRM FIXED PRICE) CONTRACTS (CALCULATIONS FOR ANTICIPATED SALARY INCREASES)
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) $42,331.00 770
January 2020
44 Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal
January 2020
45 Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112
- Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) Prime Consultant or Subconsultant Certifying:
Name**:
Signature:
Email**:
Address: 1721 2nd Street, Ste 100, Sacramento, CA 95811 List services the consultant is providing under the proposed contract:
11/21/2024
EXHIBIT 10-H1 COST PROPOSAL Page 3 of 3
Certification of Direct Costs:
**An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
public outreach services
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements:
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement. Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Sarah Modeste
[email protected] 916-548-1982
23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service
January 2020
46 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Note: Mark-Ups are Not Allowed
Consultant: Twining, Inc.
Project No. Contract No. Date
Project Name
DIRECT LABOR
Classification/Title Name Hours Actual Hr Rate Total
Project Manager Jeff Tawakoli 100 90.56$ 9,056.00$ Inspector Inspector 700 61.01$ 42,707.00$ 800
LABOR COSTS
a) Subtotal Direct Labor Costs 51,763.00$
b) Anticipated Salary Increases $0.00
c) TOTAL DIRECT LABOR COSTS [(a) + (b)] 51,763.00$
INDIRECT COSTS
d) Fringe Benefits (Rate: 73.69% ) c) Total Fringe Benefits [(c) x (d)] 38,144.15$ f) Overhead (Rate: 69.90% ) g) Overhead [(c) x (f)] 36,182.34$ h) General and Administrative (Rate: ) i) Gen & Admin [(c) x (h)] -$ j) TOTAL INDIRECT COSTS [(e) + (g) + (i)] 74,326.49$
FIXED FEE k) TOTAL FIXED FEE [(c) + (j)] x fixed fee 15% ] 18,913.42$ l) CONSULTANT’S OTHER DIRECT COSTS (ODC) – ITEMIZE (Add additional pages if necessary) Quantity Unit Unit Cost Total
-$
i) TOTAL OTHER DIRECT COSTS 15,000.00$
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary) m) TOTAL SUBCONSULTANTS' COSTS -$
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)] 15,000.00$ TOTAL COST [(c) + (j) + (k) + (n)] 160,002.92$
NOTES:
Direct Labor Total Hours per Avg 5 Year
Subtotal per Cost Cost Proposal Hourly Contract
Proposal Rate Duration
= $64.70 Year 1 Avg
Hourly Rate
Avg Hourly Rate Proposed Escalation
Year 1 + 5.0% = $67.94 Year 2 Avg Hourly Rate
SAMPLE COST PROPOSAL 1
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (DESIGN, ENGINEERING AND ENVIRONMENTAL STUDIES)
November 21, 2024
City of Goleta - San Jose Creek Multipurpose Path Project Range
Description of Item
1. Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
2. The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant’s annual accounting period and established by a cognizant agency or accepted by Caltrans.
3. Anticipated salary increases calculation (page 2) must accompany.
SAMPLE COST PROPOSAL 1
COST-PLUS-FIXED FEE OR LUMP SUM OR FIRM FIXED PRICE CONTRACTS (CALCULATIONS FOR ANTICIPATED SALARY INCREASES)
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) $51,763.00 800
1. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %) $64.70
47 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Year 2 + 5.0% = $71.34 Year 3 Avg Hourly Rate
Year 3 + 5.0% = $74.90 Year 4 Avg Hourly Rate
Year 4 + 5.0% = $78.65 Year 5 Avg Hourly Rate
Estimated % Completed Total Hours per Cost Total Hours per Each Year Proposal Year
Year 1 * 800 = 800 Estimated Hours Year 1
Year 2 * 800 = 0 Estimated Hours Year 2
Year 3 * 800 = 0 Estimated Hours Year 3
Year 4 * 800 = 0 Estimated Hours Year 4
Year 5 * 800 = 0 Estimated Hours Year 5
Total Total = 800
Avg Hourly Rate Estimated hours
(Calculated above) (Calculated Above)
Year 1 * 800 = Estimated Hours Year 1
Year 2 * 0 = Estimated Hours Year 2
Year 3 * 0 = Estimated Hours Year 3
Year 4 * 0 = Estimated Hours Year 4
Year 5 * 0 = Estimated Hours Year 5
Total Direct Labor Cost with Escalation =
Direct Labor Subtotal before Escalation =
Estimated total of Direct Labor Salary Increase = Transfer to Page 1 NOTES:
3. This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
4. Calculations for anticipated salary escalation must be provided.
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Procedures
5. 6. 48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable) Prime Consultant or Subconsultant Certifying:
Name**: Title**:
Signature: Date of Certification (mm/dd/yyyy):
$0.00
1. This is not the only way to estimate salary increases. Other methods will be accepted if they clearly indicate the % increase, the # of years of the contract, and a breakdown of the labor to be performed each year.
Mariel Attento Rhorer
11/21/2024
2. An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not acceptable. (i.e. $250,000 x 2% x 5 yrs = $25,000 is not an acceptable methodology) SAMPLE COST PROPOSAL 1
Certification of Direct Costs:
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements:
23 Code of Federal Regulations Part 172 - Procurement, Management, and Administration of Engineering and Design Related Service
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements are not eligible for reimbursement. Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate(s).
Chief Strategy Officer
$67.94
$71.34
$74.90
3. Calculate estimated hours per year (Multiply estimate % each year by total hours) 100.0%
0.0%
Year
$51,763.00
Cost Per
$0.00
$51,763.00
$51,763.00
$0.00
0.0%
0.0%
0.0%
100.0%
4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours) $64.70
$67.94
$71.34 $0.00
$74.90 $0.00
$78.65
48 SAMPLE COST PROPOSAL Required Cost Proposal Template To Be Determined By Agency Email**: Phone Number:
Address: 1879 Portola Rd., Suite G, Ventura, CA 93003
List services the consultant is providing under the proposed contract:
[email protected] 805-630-8390
**An individual executive or financial officer of the consultant’s or subconsultant’s organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract.
Geotechnical engineering support, materials testing and special inspections
49 City of Goleta
Department of Public Works and Unico Engineering, Inc.
EXHIBIT C
FEDERAL CONTRACT PROVISIONS
During the performance of this contract, UNICO Engineering, Inc. (the “Consultant”) shall comply with all applicable federal laws and regulations including but not limited to the federal contract provisions in this Exhibit. In this Exhibit, the term “Agency” shall mean the local agency entering into this contract with the Consultant.
1. CONTRACTING WITH SMALL AND MINORITY FIRMS, WOMEN’S
BUSINESS ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2
C.F.R. § 200.321)
A. Consultant shall be subject to 2 C.F.R. § 200.321 and will take affirmative steps to assure that minority firms, women’s business enterprises, and labor surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.
B. Affirmative steps shall include:
i. Placing qualified small and minority businesses and
women's business enterprises on solicitation lists;
ii. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are
potential sources;
iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business
enterprises;
iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and
v. Using the services/assistance of the Small Business
Administration (SBA), and the Minority Business
Development Agency (MBDA) of the Department of
Commerce.
Consultant shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.
Notwithstanding the foregoing, the affirmative steps requirements detailed above do not apply in the case of a noncompetitive procurement made 50 City of Goleta
Department of Public Works and Unico Engineering, Inc.
under the emergency exception/exigency exception to competitive procurements.
2. COST PRINCIPLES (2 C.F.R. PART 200, SUBPART E)
A. If any indirect costs will be charged to the Agency under this contract, such costs must conform to the cost principles set forth under the Uniform Rules at 2 C.F.R. Part 200, subpart E (“Cost Principles”). In general, costs must (i) be necessary and reasonable; (ii) allocable to the grant award; (iii) conform to any limitations or exclusions set forth in the Cost Principles; (iv) be adequately documented; and (v) be determined in accordance with generally accepted accounting principles (“GAAP”), except, for state and local governments and Indian tribes only, as otherwise provided for in 2 C.F.R. Part 200, subpart E. 2 C.F.R. § 200.403.
Costs that are determined unallowable pursuant to a federal audit are subject to repayment by Consultant.
3. ACCESS TO RECORDS & RECORD RETENTION (2 C.F.R. 200.336) A. Consultant shall comply with 2 C.F.R. § 200.336 and provide the Federal Agency, Inspectors General, the Comptroller General of the United States, Agency, and the State of California or any of their authorized representatives access, during normal business hours, to documents, papers, books and records which are directly pertinent to this contract for the purposes of making and responding to audits, examinations, excerpts, and transcriptions. The right also includes timely and reasonable access to the Consultant personnel for the purpose of interview and discussion related to the books and records.
B. The Consultant agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.
C. The Consultant agrees to provide the Federal Agency or its authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.
4. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH
APPENDIX II TO PART 200 – CONTRACT PROVISIONS FOR NON-
FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS (2
C.F.R. § 200.326)
51 City of Goleta
Department of Public Works and Unico Engineering, Inc.
A. Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract is in excess of $10,000 and the contract does not include provisions for both termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract is for more than the simplified acquisition threshold (see 2 C.F.R. § 200.88) at the time the contract is executed and does not provide for administrative, contractual, or legal remedies in instances where Contractor violates or breaches the terms of the contract, then the following termination clauses shall apply and have precedence over the contract. Otherwise, the following termination clauses shall not be applicable to the contract. i. Termination for Convenience. The Agency may, by written notice to Consultant, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Consultant of such termination, and specifying the effective date thereof (“Notice of Termination for Convenience”). If the termination is for the convenience of the Agency, the Agency shall compensate Provider for work or materials fully and adequately provided through the effective date of
termination. No amount shall be paid for unperformed work or materials not provided, including anticipated profit.
Consultant shall provide documentation deemed adequate
by the Agency to show the work actually completed or
materials provided by Consultant prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination.
ii. Termination for Cause. If Consultant fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to Consultant specifying the default (“Notice of Default”). If Consultant does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause. If Consultant fails to cure a default as set forth above, the Agency may, by written notice to Consultant, terminate this contract for cause, in whole or in part, and specifying the effective date thereof (“Notice of Termination for Cause”). If the termination is for cause, Consultant shall be
compensated for that portion of the work or materials
52 City of Goleta
Department of Public Works and Unico Engineering, Inc.
provided which has been fully and adequately completed
and accepted by the Agency as of the date the Agency
provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems
necessary to complete the project and correct Consultant’s deficiencies and charge the cost thereof to Consultant, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.
iii. Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work rendered or materials provided and shall be entitled to withhold compensation for defective work or other damages caused by Consultant performance of the work.
iv. Additional Termination Provisions. Upon receipt of a Notice of Termination, either for cause or for convenience,
Consultant shall promptly discontinue the work unless the Notice directs to the contrary. Consultant shall deliver to the Agency and transfer title (if necessary) to all provided materials and completed work, and work in progress
including drafts, documents, plans, forms, maps, products, graphics, computer programs and reports. The rights and remedies of the parties provided in this Section are in addition to any other rights and remedies provided by law or under this contract. Consultant acknowledges the Agency’s right to terminate this contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the Agency’s
termination of this contract. The Agency shall not be liable for any costs other than the charges or portions thereof which are specified herein. Consultant shall not be entitled to payment for unperformed work or materials not provided and shall not be entitled to damages or compensation for termination of work or supply of materials. If Agency
terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a
termination for convenience. In such event, Consultant shall be entitled to receive only the amounts payable under this Section, and Consultant specifically waives any claim for any 53 City of Goleta
Department of Public Works and Unico Engineering, Inc.
other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance.
B. Appendix II to Part 200 (C) – Equal Employment Opportunity:
Except as otherwise provided under 41 C.F.R. Part 60, Consultant shall comply with the following equal opportunity clause, in accordance with Executive Order 11246 of September 24, 1965 entitled “Equal Employment Opportunity,” as amended by
Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:
i. Consultant will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. Consultant will take affirmative action to insure that applicants are employed and that employees are treated equally during employment, without regard to race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following: employment upgrading, demotion, transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training including
apprenticeship. Consultant agrees to post in conspicuous places, available to employees and applicants for
employment, notices to be provided by the Agency setting forth the provisions of this nondiscrimination clause.
ii. Consultant will, in all solicitations or advertisements for employees placed by or on behalf of Consultant, state that all qualified applicants will receive consideration for employment without regard to their race, color, religion, sex, or national origin.
iii. Consultant will not discharge or in any other manner discriminate against any employee or applicant for
employment because such employee or applicant has
inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant.
This provision shall not apply to instances in which an employee who has access to the compensation information 54 City of Goleta
Department of Public Works and Unico Engineering, Inc.
of other employees or applicants as a part of such
employee's essential job functions discloses the
compensation of such other employees or applicants to
individuals who do not otherwise have access to such
information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an
investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with Consultant‘s legal duty to furnish information.
iv. Consultant will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of
September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
v. Consultant will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
vi. Consultant will furnish all information and reports required by Executive Order No. 11246 of September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
vii. In the event of Consultant’s noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the
contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in
Executive Order No.11246 of Sept. 24, 1965, and such other sanctions may be imposed and remedies invoked as
provided in Executive Order No.11246 of September 24,
1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
55 City of Goleta
Department of Public Works and Unico Engineering, Inc.
viii. Consultant will include the provisions of paragraphs (i) through (viii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of September 24,1965, so that such provisions will be binding upon each subcontractor or Consultant. Consultant will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, that in the event Consultant becomes involved in, or is threatened with,
litigation with a subcontractor or Consultant as a result of such direction, Consultant may request the United States to enter into such litigation to protect the interests of the United States.
C. Appendix II to Part 200 (D) – Davis-Bacon Act; Copeland Act: Not applicable to this contract.
D. Appendix II to Part 200 (E) – Contract Work Hours and Safety Standards Act:
i. If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Consultant shall
comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to
compute the wages of every mechanic and laborer on the
basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and
provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.
56 City of Goleta
Department of Public Works and Unico Engineering, Inc.
ii. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives
compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
iii. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any
subcontractor responsible therefore shall be liable for the unpaid wages. In addition, such contractor and
subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section. iv. The Agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Consultant or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other
federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be
necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.
v. The Consultant or subcontractor shall insert in any
subcontracts the clauses set forth in paragraph (ii) through (v) of this Section and also a clause requiring the
57 City of Goleta
Department of Public Works and Unico Engineering, Inc.
subcontractors to include these clauses in any lower tier subcontracts. The Contractor shall be responsible for
compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.
E. Appendix II to Part 200 (F) – Rights to Inventions Made Under a Contract or Agreement:
i. If the Federal award meets the definition of “funding agreement” under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental,
developmental, or research work under that “funding
agreement,” the non-Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative
Agreements), and any implementing regulations issued by the Agency.
ii. The regulation at 37 C.F.R. § 401.2(a) currently defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or
research work funded in whole or in part by the Federal government. This term also includes any assignment,
substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.
iii. This requirement does not apply to the Public Assistance, Hazard Mitigation Grant Program, Fire Management
Assistance Grant Program, Crisis Counseling Assistance
and Training Grant Program, Disaster Case Management
Grant Program, and Federal Assistance to Individuals and Households – Other Needs Assistance Grant Program, as
FEMA awards under these programs do not meet the
definition of “funding agreement.”
58 City of Goleta
Department of Public Works and Unico Engineering, Inc.
F. Appendix II to Part 200 (G) – Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Consultant shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401- 7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387).
i. Pursuant to the Clean Air Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the
appropriate Environmental Protection Agency Regional
Office, and (3) Consultant agrees to include these
requirements in each subcontract exceeding $150,000.
ii. Pursuant to the Federal Water Pollution Control Act, (1) Consultant agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Consultant agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Consultant
agrees to include these requirements in each subcontract exceeding $150,000.
G. Appendix II to Part 200 (H) – Debarment and Suspension: A contract award (see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 C.F.R. part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.
i. This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Consultant is 59 City of Goleta
Department of Public Works and Unico Engineering, Inc.
required to verify that none of the Consultant, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. §
180.940) or disqualified (defined at 2 C.F.R. § 180.935). ii. Consultant must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into.
iii. This certification is a material representation of fact relied upon by Agency. If it is later determined that Consultant did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available
remedies, including but not limited to suspension and/or debarment.
iv. Consultant warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs. Consultant also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from
participation in accordance with the requirements above.
Consultant further agrees to notify the Agency in writing immediately if Consultant or its subcontractors are not in compliance during the term of this contract.
H. Appendix II to Part 200 (I) – Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Consultant shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Consultant shall file with the Agency the Federal Standard Form LLL titled “Disclosure Form to Report Lobbying.” Consultants that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non- 60 City of Goleta
Department of Public Works and Unico Engineering, Inc.
Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.
I. Appendix II to Part 200 (J) – Procurement of Recovered Materials:
i. Consultant shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation
and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the
Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered
materials practicable, consistent with maintaining a
satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity
acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement.
ii. In the performance of this contract, the Consultant shall make maximum use of products containing recovered
materials that are EPA-designated items unless the product cannot be acquired: Competitively within a timeframe
providing for compliance with the contract performance
schedule; Meeting contract performance requirements; or at a reasonable price.
iii. Information about this requirement, along with the list of EPA-designate items, is available at EPA’s Comprehensive Procurement Guidelines web site,
https://www.epa.gov/smm/comprehensive-procurement-
guideline-cpg-program.
5. MISCELLANEOUS PROVISIONS
A. The Consultant shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA preapproval.
B. This is an acknowledgement that FEMA financial assistance will be used to fund the contract only. The Consultant will comply with all 61 City of Goleta
Department of Public Works and Unico Engineering, Inc.
applicable federal law, regulations, executive orders, FEMA policies, procedures, and directives.
C. Consultant acknowledges that 31 U.S.C. Chapter 38
(Administrative Remedies for False Claims and Statements) applies to the Consultant’s actions pertaining to this contract.
D. The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the Agency, Consultant, any subcontractors or any other party pertaining to any matter resulting from the contract.
E. General and Administrative Expenses And Profit For Time And Materials Contracts/Amendments.
i. General and administrative expenses shall be negotiated and must conform to the Cost Principles.
ii. Profit shall be negotiated as a separate element of the cost.
To establish a fair and reasonable profit, consideration must be given to the complexity of the work to be performed, the risk borne by the Consultant, the Consultant’s investment, the amount of subcontracting, the quality of its record of past performance, and industry profit rates in the surrounding geographical area for similar work.
iii. Any agreement, amendment or change order for work
performed on a time and materials basis shall include a ceiling price that Consultant exceeds at its own risk.