111 N. Market Street, Suite 440
San Jose, CA 95113
Ph 408.610.4202
City of Gonzales
Attention: Patrick M. Dobbins, PE
Public Works Director/City Engineer
City Hall
Gonzales, CA 93926
SUBJECT: Proposal for Slurry Seal CM and Inspection
Dear Mr. Dobbins:
Thank you for the opportunity to provide this proposal for assisting the City with Slurry Seal CM and Inspection Services
Project Understanding
The City of Gonzales is interested in services to assist the City with the construction management and inspection services during the construction of the Slurry Seal Construction Contract
Scope of Work
MNS proposes to perform the following services:
1) MNS will provide Contract Administration
2) MNS will provide Construction Inspection
3) MNS will review Contractor Submittals
4) MNS will provide Photo Documentation
5) MNS will review and recommend Progress Payments
6) MNS will provide Construction Reports
7) MNS will measure Construction Quantities
8) MNS will track Extra Work
9) MNS will coordinate with City Materials Testing Firm 10) MNS will prepare a Punch List
Conclusion
We look forward to working with the City of Gonzales. Please feel free to contact Paul Greenway with any questions you may have about our proposal at 831.400.8964 or [email protected] or me at 805.331.4848 or [email protected] Sincerely,
MNS Engineers, Inc.
Jeff Edwards
Vice President
Government Services Division
July 22, 2022
Firm Ownership Type
Corporate Office
Project
CITY OF GONZALES
SECTION 1. PROPOSER'S BACKGROUND 1
Section 1. Proposer's Background 1
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR
THE CONSTRUCTION OF SLURRY SEAL
Firm Qualifications
MNS Engineers, Inc. (MNS)
CONTACTS
111 N. Market Street, Suite 440
• Preparation of contract documents—PS&Es
• Plan check and peer review
• Coordination with project stakeholders and utilities
• Pre-bid and bid phase assistance
• Permitting with the counties, cities, Caltrans, and other Local Address
Point of Contact
Authorized
to Negotiate
Contract
San Jose, CA 95113
Doug Pike, PE, Project Manager
805.331.3553 Mobile
[email protected]
Jeff Edwards, Vice President
805.331.4848 Mobile
[email protected]
regulatory agencies
• Environmental regulations and permitting
• Requirements for funding from federal, state, and local resources
• Construction administration
• Construction cost estimates
Established in 1962, MNS is a C-Corporation that provides quality infrastructure consulting services to the transportation, water resources, and government service markets throughout California. Specializing in the core services of engineering, construction management, and land surveying, MNS'
reputation has been built on clear and direct communication and quality services. We understand the technical, environmental, and regulatory aspects required for the construction of Metz/Orchard Park. We are experienced and knowledgeable with federal funding, permitting, and multi-agency coordination.
Firm Expertise
MNS has an extensive history of successful park projects. From concept inception through project completion, we support our clients every step of the way. We focus on creating the perfect solution to best fit the City's needs.
Our engineering and technical teams stay current with material and construction method developments as well as public agency specification and code requirements. We offer in-depth project experience and a high level of engineering design skill. We cover design services for all project phases:
• Preliminary engineering studies
Construction Management and Inspection
A leader in construction management and inspection services, we offer the City a depth of experienced staff resources local to the area and with a reputation for success in meeting project quality, budget, and schedule goals. We are committed to providing a qualified construction management team that is available for the contract duration and have worked on similar pedestrian overcrossing and transportation improvement projects.
MNS focuses on providing quality construction management and inspection services for state and local agency park projects. Our expertise includes:
• Project management/coordination
• Complete construction management
• Construction inspection
• Construction management/general contractor (CM/GC) project delivery
• Scheduling and critical path method (CPM) review
• Public outreach
• Contract administration and labor compliance
• Constructability review
CITY OF GONZALES
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE
CONSTRUCTION OF SLURRY SEAL
SECTION 4. PROPOSED PERSONNEL 8
Doug Pike, PE
Project Manager
Firm
MNS Engineers, Inc.
Office Location
San Luis Obispo, CA
Areas of Expertise
Street improvement projects
Water and wastewater systems
Infrastructure site development
Project management
Years of Experience
39
Licensing
Professional Civil Engineer, CA No. 43330
Certification
California Emergency Management Agency (OES) Safety
Assessment Program
Education
MS, Construction Engineering Management/Business
Administration, Oregon State University, OR
BS, Civil Engineering, University of California, Berkeley, CA
Affiliations
American Council of Engineering Companies, San Luis
Obispo Chapter
American Public Works Association, Channel Islands
Chapter Vice President
American Society of Civil Engineers
UC Santa Barbara Economic Forecast Project, Board
President
Mr. Pike brings an impressive career experience in the
areas of public works project management, engineering
management, water resources, and transportation
engineering. Previously, Doug contracted as City
Engineer for the City of Solvang, and Assistant City
Engineer for the City of Buellton. As interim Public Works Director for Solvang, he supervised $3.5M in capital
improvement projects. Doug also spent nine years with
the City of Santa Barbara where he managed over 60
capital improvement projects for a total construction cost of over $25M. His experience includes:
Regional Open Space Park and Regional Landfill
Permit Implementation and Compliance, City of Santa
Maria, CA. Program Manager. This $1.5M engineering
project involves negotiating and obtaining permits with the Regional Water Quality Control Board and Army
Corps of Engineers for development of a large regional
park (1,700 acres) and landfill (900 acres) development for the City. The project includes groundwater protection, verification of closure or re-closure of abandoned oil
wells, BMPs and all aspects of environmental compliance for these projects.
Santa Maria River Infiltration Enhancement Project,
Santa Maria Valley Water Conservation District, CA.
Principal-in-Charge. MNS provided project management,
survey, design and permit support, and construction
management. This project reviewed the feasibility and
included a cost-benefit analysis of removal of surficial clay sediment layer, or “cap,” in the low-flow channel of the Santa Maria River from the confluence with the
Cuyama River to Bonita School Road. Surface water
flows from dam releases were modeled in HEC-RAS and
infiltration rates established based on field and laboratory measurements to establish the anticipated release water infiltration benefit for groundwater recharge.
Standard Plans Updates, City of Greenfield, CA. City
Engineer. MNS is responsible for the ongoing
development of appropriate Standard Plans for the Public Works Department. Several new, recent standards have
been developed to address changes in drainage and
water quality requirements.
City Engineer and Municipal Engineering Services,
City of Greenfield, CA. City Engineer. Doug has
designed, advertised, and directed or performed
construction management services for multiple
infrastructure projects for the City. Additional
CITY OF GONZALES
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE
CONSTRUCTION OF SLURRY SEAL
SECTION 4. PROPOSED PERSONNEL 9
responsibilities have included consulting on water and
wastewater operational and capital improvement issues.
City Engineering Services, City of Solvang, CA. City
Engineer. Responsibilities included oversight and
maintenance of Engineering Standards, improving and
adjusting them as needed.
District Engineering Services, Mission Hills
Community Services District, CA. District Engineer.
Responsibilities included providing engineering
assistance, including development of revised water and
sewer standard details and construction standards; water and sewer modeling and master planning; designing
water and wastewater capital improvements; advising the District on development impacts to the infrastructure;
regularly attending Board of Director meetings to present findings and to make recommendations for
improvements as well as other Board actions; and
directing volunteer efforts to benefit the District, including a donated design and survey for a new basketball court
for one of the District's parks.
Doug prepared the most recent Standard Plans update to
the “Mission Hills Community Services District Standards for Construction of Sewer Mains” and the “Mission Hills Community Services District Standards for Construction
of Water Mains.” These standards were updated to
incorporate new technologies and materials, but with the intent to remain similar in general format to those used by the City of Lompoc whose standards were used for
comparison. The Standards language was improved and
clarified, and inconsistencies removed. All submittal
deadlines for review were met.
Elevated Steel Water Tank Coating, City of
Greenfield, CA. Project Manager/Project Engineer. This
$320K project improved the elevated steel water tank for the City of Greenfield. Construction elements included
corrosion protection of this 150,000-gallon elevated steel water tank, remediation of lead-based paint, and
rehabilitation of elevated platforms and walkways.
Responsibilities included engineering design for the
elevated platforms and walkways as well as construction management and inspection services.
Active Transportation Project (ATP) Grant Sidewalk
Improvement and Bike Lane, City of Greenfield, CA.
Project Manager. This sidewalk and bike lane
improvement project constructed new curb, gutter, and
sidewalks; traffic calming islands; bike lane
improvements; and enhanced pedestrian crosswalks to
support safe access to two schools and a park. The
project connected the west end of the City of Greenfield Doug Pike, PE | RESUME PG 2
to the downtown area and involved significant
coordination with schools, utility companies, and the
public. Unique features included 8-foot-diameter school thermoplastic school pride medallion mascot logos
applied to intersections in front of the schools. Funding came from local and special grant sources and was
administered per Caltrans Local Assistance Procedure
Manual (LAPM).
Union Valley Parkway Extension at State Route 135,
City of Santa Maria, CA. QA/QC Engineer. This $2.5M
project designed an extension of Union Valley Parkway,
a four-lane secondary arterial. Project elements included a signalized intersection, roadway lighting, landscape
architecture, realigned frontage road, roadway median,
drainage facilities that regulated storm flows to preproject levels and promoted maintenance of existing wetlands, and pedestrian and bicycle facilities. This
project required extensive utility coordination and County and Caltrans encroachment permit applications.
Development Engineering Standards, City of Santa
Barbara, CA. Project Manager. Doug led in the effort to create the first comprehensive “City of Santa Barbara
Development Engineering Standards” document. This
effort included the review of standards from a number of different agencies in search of the best “models” to use as a template. The City finally settled on an adaptation of the City of Oceanside’s Development Engineering
Standards modified to adapt to the City’s unique needs.
In addition to their current development processes, over twenty local standards were adopted into this document
by reference or adaption and incorporation.
District Engineering Services, Santa Maria Valley
Water Conservation District, CA. District Engineer.
MNS currently provides engineering support services to
the Santa Maria Valley Water Conservation District,
which maintains Twitchell Dam and Reservoir, including
ancillary structures, roads, and facilities. Projects have included the development of planning and budgeting
documents, sedimentation studies, aerial
mapping/capacity studies for the reservoir, equipment
evaluation, maintenance recommendations, anddredging
and sedimentation management and preparation of
facility repair plans and specifications. Services entail capital project design, construction management, project management, budgeting, grant management, estimates,
studies, report preparation, and map and exhibit
preparation. Responsibilities include attending board
meetings and assist in policy and decision making.
CITY OF GONZALES
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE
CONSTRUCTION OF SLURRY SEAL
SECTION 4. PROPOSED PERSONNEL 10
Bill Smith, PE
Senior Construction Manager
Mr. Smith has over 36 years of experience in the Kitchell Engineering, Rancho Cordova, CA.
Firm
MNS Engineers
Office Location
San Jose, CA
Areas of Expertise
Construction
management and
inspection
Civil design
engineering
Project management
Transportation
projects
Vertical construction
projects
Caltrans
Years of Experience
36
Licensing
Professional Civil
Engineer, CA No.
62270
Education
BA, Mathematics,
Minor in Engineering
Technology,
Metropolitan State
College, Denver, CO
Civil Engineering
coursework,
Colorado State
University, Denver,
CO
transportation design and construction industry.
Bill has been involved in every step of the
project management process, from programming
through completion. He has worked on many
accelerated, complex, and high visibility projects
using multiple delivery methods. Additionally, he
has broad insight into the interests of all project
stakeholders within multiple levels of
government and private projects and under all
types of regulatory conditions. His experience
includes:
US Air Force at March Air Force Base,
Riverside, CA. Project Manager/Pavement
Engineer. Bill served as Project Manager,
Pavement Engineer, and Civil Engineer for the
design and construction of military base
improvement projects. His responsibilities
included providing airfield paving sustainment
and construction consultation; overseeing all
airfield and roadway pavement condition surveys
and structural surveys; developing scope of work
estimates; participating in negotiations for the
award of projects to firms for design contracts,
contractors for construction contracts, and
design-build teams; developing 5- and 10-year
Pavement Plans for airfield and non-airfield
pavements operations and maintenance (O&M)
projects; and making recommendations to
command, base Civil Engineer staff, including all
project project stakeholders and jurisdictional
regulatory authorities. In addition to numerous
renovations and upgrades of buildings, utilities,
roadways, and drainage, major projects
included:
• $15M Airfield Paving and Lighting DesignBuild
• $17M New Air Traffic Control Tower/Base
Operations Building Design-Bid-Build
• $9M New Small Arms Range Build
Florida Department of Transportation,
Deland, FL. Interstate Project Manager. Bill
managed the design of state and federal
highways projects with overlays to federal
highway widening projects, including major
interchanges and bridges. His responsibilities
included overseeing all phases of design, scope,
schedule and budget; coordinating with the
Federal Highway Administration (FHWA), local
governments, and all project stakeholders;
oversight of multiple construction projects from
design/build to completion; participating in
contract negotiations; reviewing project plans
and specifications prior to awarding contracts;
coordinating construction operations; and
ensuring contractor compliance with all aspects
of contracts and approve payments.
Project Manager. Bill managed infrastructure
portions of multiple prison expansion projects for
the California Department of Corrections and
Rehabilitation.
Works General Engineering, Yuba City, CA.
Engineering Consultant. Bill managed all phases
of projects for leveling of structures on failed
foundations of buildings, bridges, highways,
runways, and underground utilities. He
specialized in polyurethane injection techniques
and developed two patents for highway and
runway repair.
Sutter County Public Works, Yuba City, CA.
Senior Engineer/Architect. Bill was responsible
for design, construction administration, and
construction management on all building
facilities in the County; design of a new $12M
human services building; administering
contracts; managing construction of numerous
projects within the county jail; construction
management of $1M remodel of a mental health
facility; soliciting requests for proposals; and
recommending award of design services
contracts on various new and remodel projects
in buildings recently acquired by the county.
Caltrans District 3, Marysville, CA.
Transportation Engineer. Bill provided complete
design, authored the special provisions, and
reviewed the process and coordination of
correction and completion of project plans,
specifications, and estimates for state highway
projects, safety projects, road widening projects,
and over $40M in maintenance projects,
including several pilot projects with cold foam
injection.
City of Fremont, CA. Senior Construction
Inspector. Bill managed and inspected major
public works projects, housing tracts, and
encroachment permits; reviewed final plans and
specifications for construction; inspected
numerous underground utility projects; oversaw
over 30 housing tract site developments and
numerous street improvement projects, including
road widening and railroad crossings; and
reviewed design plans for various seismic retrofit
of bridges. Projects included:
• $2M Niles Community Park
• $2M Niles Main Street Redevelopment
• $1M Central Park Shoreline Restoration
• $500K Senior Center Renovation and
Addition.
CITY OF GONZALES
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE
CONSTRUCTION OF SLURRY SEAL
SECTION 4. PROPOSED PERSONNEL 11
Rob Russell, PE
Senior Construction Manager
Mr. Russell has over 35 years of civil Sample City experience:
Firm
MNS Engineers
Office Location
San Jose, CA
Areas of Expertise
Project/program
management
Capital improvement
programs
Engineering design
Transportation
improvements
Water resources
projects
Years of Experience
35
Licensing
Professional Civil
Engineer, CA No.
42871
Education
BS, Civil
Engineering,
California State
University, Chico,
CA
Affiliations
American Public
Works Association
American Society of
Civil Engineers
Awards
2012 APWA Person
of the Year Award,
Monterey Bay
Chapter
engineering experience working for a public
agency. While at the City of Salinas, Rob worked
in numerous roles; the last 16 years were spent
as Deputy City Manager, Deputy City Engineer,
Engineering/Transportation Services Director,
City Engineer, and Deputy Public Works
Director. His direct experience gives him an
intimate understanding of a public works
environment and managing a capital
improvement program (CIP). Rob’s expertise
includes program/project management,
engineering design for CIP projects, and
inspection. He is also well versed with various
funding and grant resources. His project
experience includes:
Department of Public Works, City of Salinas,
CA. Various Roles. Rob spent his civil
engineering career with the City of Salinas (City)
where he honed his skills in various roles.
Responsibilities included:
• Overseeing all engineering and
traffic/transportation operations within the
department for seven years (including
traffic/transportation, CIP design/inspection,
and private development proposal reviews
as related to engineering- and public worksrelated issues, and reviewed California Environmental Quality Act [CEQA]
documents)
• Directly supervising upper-level staff
members (three senior civil engineers)
• Approving final designs for all capital
projects placed out for public bidding (12
years)
• City Engineer duties including designation
as City Traffic Engineer, Floodplain
Administrator, ADA Coordinator, TFO
interpreter, and serving as the City’s
alternate representative on regional
transportation boards (TAMC Board,
Executive Committee, Rail Policy
Committee; and MST Board)
• Preparing plans/specifications for a variety
of capital improvement projects
• Reviewing numerous private development
proposals and conditioning those proposals
for public works/engineering-related issues
via Engineer’s reports
• Building permit and planning level permit
processes
• Field surveying (design and construction)
• Reviewing/approving final designs for all
City-related capital projects and approving
changes to plans/specifications via contract
change orders
Rico Assessment District. Project Manager.
Responsibilities included designing street
pavement section and City-standard street
improvements and sanitary sewer/storm drain
systems for 1,500 feet of new streets. Rob
prepared and reviewed specifications and
construction cost estimates; and monitored the
project schedule.
Homestead-Wilson-Villa Assessment District.
Project Manager. This project was similar to Rico
Assessment District, but involved more sidewalk,
and curb and gutter repairs; and new pedestrian
access ramps per City standards; and design of
a lime-treated street pavement section to reduce
construction/assessment costs.
Miscellaneous Drainage Improvements.
Project Manager. To successfully complete this
project, Rob met with Maintenance Supervisor to
identify greatest drainage maintenance
liabilities/biggest maintenance problems in the
City. He designed a comprehensive project to
address deficiencies requiring the greatest time
and effort each year. He coordinated
improvements with the City Storm Drain Master
Plan Priority List.
Harden Ranch Assessment District. Project
Manager. Responsibilities included reviewing the
design of the Harden Ranch Planned
Community backbone infrastructure and
reviewed technical studies related thereto
(SD/SS systems and detention pond designs);
coordinating the backbone infrastructure with
individual subdivision improvement plans to
ensure consistency and correctness; and
confirming EIR mitigation measures were
incorporated into designs as applicable.
High School No. 5 Street Improvements.
Project Manager. Responsibilities included
reviewing the design of the Rogge Road
Improvements as related to Salinas High School
#5; ensuring consistency with City standards
and the certified CEQA document; reviewing the
Low Impact Development design along the
street improvements and consistency of street
improvements with the Future Growth Area's
(FGAs) expected Specific Plan design
standards.
CITY OF GONZALES
PROFESSIONAL CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR THE
CONSTRUCTION OF SLURRY SEAL
SECTION 4. PROPOSED PERSONNEL 12
Kent Yankee, PE, QSD
Constructability Reviewer
Firm
MNS Engineers
Office Location
San Luis Obispo, CA
Areas of Expertise
Grading and drainage
Hydrology and hydraulic
Street improvement
projects
Infrastructure design
Years of Experience
20
Licensing
Professional Civil
Engineer, CA No. 74570
Certifications
Qualified SWPPP
Developer, CA No.
74570
Nuclear Gauge Safety
Residential/commercial
AdvanTex design for
septic systems
Confined Space
Awareness
Education
BS, Architectural
Engineering, California
Polytechnic State
University, San Luis
Obispo, CA
Awards
2017 APWA Monterey
Bay Chapter BEST
Award, Environmentally
Sensitive Projects
Category, Elkhorn Road
Emergency Storm
Damage Repair
2017 Transportation
Agency of Monterey
County (TAMC)
Transportation
Excellence Award,
Elkhorn Road
Emergency Storm
Damage Repair
2010 APWA Young
Professional of the Year
Award, Central Coast
Chapter
Mr. Yankee is a proficient design engineer with a
high level of skill in creating site and grading
plans, construction plan sets, project
specifications and estimates. Kent’s skills in
AutoCAD and background in structural
calculations offer a great combination of
services. He is also competent in all aspects of
field work including construction observation,
and with his background in materials testing, has
a keen eye on projects as they progress. Kent
has excelled at roles in project management by
handling the contract documentation and project
implementation of a wide variety of complex
projects and meeting time sensitive project
deadlines. His project experience includes:
River View Park, City of Buellton, CA. Project
Engineer. The project consisted of a new park
with playground facilities, restrooms, parking
areas, and a bridge over an existing creek. Kent
designed and calculated structural elements for
the pedestrian bridge crossing the existing creek
and prepared grading and drainage plans for
continuing the ADA compliant pedestrian path
through the west end of the project area. Kent
also performed compaction testing using a
nuclear density gauge for compliance as well as
asphalt placement inspection, concrete
foundation sampling and testing, and
compaction testing for base material.
Cocheo Park Restroom and Landscaping,
Vandenberg AFB, CA. Construction Inspector.
This park is the focal point for military families to
bring their children for picnic and recreational
events. The restroom was constructed with
masonry and stone veneer with exposed timber
for the interior. Plumbing, electrical, and remote
controlled irrigation systems were important
aspects of this project. With the close
coordination and management, the project was
completed 3 months early.
Sharon Place Dog Park, City of Buellton, CA.
Project Engineer. Kent was responsible for
grading and drainage plans, construction plans,
and project specifications for the City of Buellton
new Dog Park. Design incorporated features
necessary for large and small breeds, as well as
a handicap accessible route to specified site
including retaining walls as required.
Municipal Engineering Services, City of
Buellton, CA. Deputy City Engineer. Kent has
been involved in various aspects of work for the
City of Buellton including creation of traffic
control and construction plans for various street
improvements along with engineers cost
estimating for multiple projects. Using his
knowledge from field work and design he has
assisted in updating the City of Buellton
Standard Details. Kent has also been intimately
involved with mapping of City easements and
collecting and mapping data regarding the City’s
stormwater, sewer, and water systems. His
involvement in the City’s infrastructure has led
him to be involved in the preparation of the Citywide Stormwater Management Plan and updates to Federal Highway Administration (FHWA)
designated routing.
Municipal Services/Private Development, City
of Buellton, CA. Deputy City Engineer. Kent
was one of the main contacts for issuing small
permits within the City as well as issuing permits
for Private Development Projects and Capital
Improvement Projects. He would meet with
owners and contractors, review plans and
calculations, and make assess City regulations,
standards and ordinances were met or
exceeded in the process. Kent would collect fees
and perform intermediate inspections regarding
the grading and drainage, storm drain, sewer,
water and other infrastructure elements as well
as perform final inspection for permit clearance.
Munras Avenue Improvements, City of
Monterey, CA. Project Engineer. Kent worked
closely with City staff to meet their needs
improving three intersections along Munras
Avenue in need of pedestrian and ADA
complaint improvements. The project included
sidewalk, driveway, curb ramps, path of travel,
ribbon gutters and various drainage issues that
all had to be blended into the existing
topography with known drainage deficiencies.
Kent was lead designer and project manager for
creation of plans, specifications and estimates
for the project.
Quick Bid and City Standards Updates, City
of Watsonville, CA. Project Engineer. Kent
used his experience with standard
specifications, special provisions, and contract
documents to assist the City in updating their
existing standards to utilize for their Quick Bid
process. The Quick Bid process is utilized by the
City for projects under a certain value. Kent was
responsible to make sure the documents
referenced current standards as well as all
applicable contract codes, laws, and regulations.
Kent was able to utilize his knowledge to provide
recommendations to the City allowing for a more
efficient and thorough process.
22-Jul-22
Principal EngineerSupervising EngineerConstruction Inspector 1 –CM and Inspection
Construction Inspector 144.0 144.0 $21,600
Principal Engineer/Principal CM 30.0 30.0 $7,200
Hours 30.0 0 144
TOTAL Cost $7,200 $0 $21,600
Total Resource HoursTotal Resource Costs
$ 28,800
$240 $200 $150
174.0
City of Gonzales