City of Gonzales
PUBLIC WORKS / CITY ENGINEER DEPARTMENT
ACTIVITY REPORT
TO: Honorable Mayor Rios and City Council
DATE: October 17, 2022
FROM: Patrick Dobbins, Acting City Manager
THROUGH: Carmen Gil, Interim City Manager
SUBJECT: Public Works Activity Report
BUILDINGS
1. Community Center Complex Project – The “Design Criteria” documents were completed in April 2022. The Design Criteria package is comprised of 98 drawings, a Program Summary and Systems Criteria Narratives, and Technical Specifications. Measure D wasn’t approved at the 8/30/2022 special election. On 9/12/2022 we learned that the project would receive a $1.07M grant from the Building Forward Library Infrastructure Grant Program. A Tree Removal Contract was approved at the 10/03/2022 Council meeting and field work is expected to begin by late October. Staff provided a progress report at the 9/19/2022 Council meeting and will provide a follow-up progress report at the 11/21/2022 Council meeting.
2. Emergency Generator Replacements – The city received a $150,000 grant from Cal OES in 2021 to replace the emergency generators at City Hall and the Police Station. At the 2/07/2022 City Council meeting, a $175,000 contract with Alltech Services was approved. The generator at the Calif Breeze Sewer Lift Station will also be replaced under this contract and will be funded with Sewer Impact monies. The two 25KW generators (one for city hall and one for the Calif Breeze Sewer Lift Station) have ship dates of 9/13/2022 and the 80KW generator for the police station has an expected ship date of 10/10/2022. The contractor recently installed the generator at the Calif Breeze Sewer Lift Station.
The generators for the Police Station and City Hall will be installed when they’re delivered to the contractor.
WASTEWATER
Industrial Wastewater (IW) System/Reclamation Plant – Dudek is wrapping up the final design for the IW Conveyance and Treatment Facility contracts. Staff and the city surveyor are finalizing the temporary and permanent easements needed for the project. City staff continues to coordinate with AGENDA
ITEM
8 the State Water Resources Control Board regarding the city’s State Revolving Fund loan application (last virtual meeting was 10/07/2022.
WATER
1. Well 7 – In mid-July, staff began manually operating the well under our permit from the State Drinking Water Division while completing the electronic and remote controls.
2. Alpine Court Water/Sewer Service – Grant agreements with the State Water Resource Control Board (SWRCB) to fund the preliminary and final design of extending water and sewer service from Gonzales River Road to Alpine Camp were approved at the 7/06/20 City Council meeting. Staff is holding bi-weekly progress meetings with SWRCB staff. Staff prepared a draft agreement with the property owner and the City Attorney is coordinating with staff to finalize it.
3. Salinas Valley Basin Groundwater Sustainability Agency – Staff is an alternate on the SVBGSA Technical Advisory Committee (Soledad staff is the representative for South Valley cities).
ROADWAYS
1. Slurry Seal Contract – Award of contract to VSS International was made at the 6/20/2022 Council Meeting and the field work began on 8/29/2022. The contractor is completing the items on the “punch list” and acceptance of the work is expected at the November 7 Council meeting.
1. Skate Park Improvements – Phase two of improvements to the skate park will be funded by the 2018 Parks Bond Act. On 3/03/2022 staff received the executed grant agreement with the State Department of Parks and Recreation. American Ramp Company provided a revised scope and cost for the improvements due to an increase in costs over the last year. The contract with American Ramp Company was approved at the 9/19/2022 Council meeting.
2. Meyer Park – Staff has coordinated numerous maintenance items over last several months including fixing light fixtures, replacing uplifted sidewalk, pruning trees, and replacing the rubber mulch under the swings with wood fiber. We are working with MST on installing a bus shelter that the city and MST will split the cost for.
SOLID WASTE
1. Patrick Dobbins and Maury Treleven performed a “windshield survey” of solid waste containers and dumpsters at multi-family residential complexes, commercial businesses, and industrial facilities on 8/08/2022. We were primarily looking for overfilled containers and dumpsters, illegal dumping, and adequate food waste collection.
2. California Department of Resources Recycling and Recovery (“Cal Recycle”) Coordination – Our annual meeting with staff from Cal Recycle, Salinas Valley Solid Waste Agency, Tri-Cities Disposal & Recycling, and the cities of Greenfield, Soledad and Gonzales was held on 8/02/2022.
3. Quarterly Tri-Cities Franchise Agreements Meetings – Staff from the Salinas Valley Solid Waste Authority, Tri-Cities Disposal & Recycling and the cities of Gonzales, Soledad, and Greenfield meet on a quarterly basis to discuss the various waste collection programs (commercial accounts, food waste, organic waste), compliance with latest state regulations, public outreach and education, customer surveys, etc). Most recent meeting was 8/10/2022.
DEVELOPMENT PROJECTS
1. Vista Lucia Development (City’s Sphere of Influence - East of US 101) a. City staff reviewed the Admin Draft #1 and Admin Draft #2 of the SEIR and provided comments to the Community Development Director.
b. City staff is holding bi-weekly Zoom meetings with Pembrook Development and their consultants.
c. Psomas developed a capital program of improvements to convey sewage from the SOI to the City WWTP for treatment and provided the draft technical memo in Mid-November for staff’s review.
Final Technical Memorandum was submitted in April 2022. d. Staff and our on-call traffic engineer have coordinated with Caltrans District 5 staff on the process for preparation of a Project Study Report/Project Development Support (PSR-PDS).
Staff will issue a Request for Proposals to engage a consultant to prepare the PSR-PDS documents.
e. On 3/28/2022 Staff met with Monterey County PW staff and discussed the applicant’s preliminary offsite roadway design. Staff met with Monterey County staff on 10/7/2022 and discussed executing a Maintenance Agreement for the city to be responsible for maintenance of Associated Lane when it’s widened as part of the Vista Lucia Development (maintenance will be funded by an assessment district formed as part of the development).
2. Puente Del Monte Development (City’s Sphere of Influence - East of US 101) – The applicant submitted a revised Specific Plan on 4/05/2022 for city’s review. This specific plan will be revised to reflect the Rianda Property is pursuing a different development proposal.
3. Rianda Cooler Development Project (Gloria Road) – The CEQA documents are underway. Staff is coordinating with the applicant’s site civil engineer and water/wastewater consultant on the initial design and layout.
4. In June 2022, DR Horton executed an agreement with D'Arrigo Bros to look at the feasibility of developing the 130-acre parcel in the city. A kick-off meeting with DR Horton and city staff was held on 7/07/2022 and DR Horton made a presentation at the Joint Planning Commission/City Council meeting on 8/01/2022.
OTHER PROJECTS
1. GIS – City staff continues to work on a GIS mapping system by inputting field data for water, sewer and storm drainage systems. Our water and wastewater consultants are using the GIS to develop capital improvement projects to serve the proposed development projects in the SOI. We hold monthly coordination meetings with a GIS Consultant.
2. FEMA Flood Map Updates – Over the two years, FEMA and their consultants have been remapping seven watersheds in the Gabilan Mountains in the vicinity of South Salinas, Chualar, Gonzales and Soledad to update their Flood Maps. Preliminary flood insurance maps were released for public review on 10/21/2021. At the 12/06/2021 City Council Meeting, City staff made a presentation on this effort along with a letter to be sent to FEMA with our comments and questions on their mapping effort. A 90-day appeal period began on 5/12/2022 and we emailed our comment letter to FEMA staff on 7/26/2022.
3. Microgrid Project – Staff has been coordinating with Concentric Power and Sage Energy/NV5 (Program Manager) on various elements of the project. Staff participates in biweekly coordination meetings. A progress meeting with staff from Concentric Power, Sage Energy/NV5 and the Electric Authority’s legal counsel was held on 8/11/2022
4. South Salinas Valley Broadband Joint Powers Authority – Staff is supporting the efforts of this newly formed JPA. This includes preparing a Request for Proposals for Legal Counsel Services, coordinating with MBEP staff on preparing the agenda packet for the 9/29/2022 Board Meeting.
Staff attended the 9/29/2022 Board meeting and presented the agenda item for Request for Proposals for Legal Counsel Services
PUBLIC WORKS OPERATIONS AND MAINTENANCE
WASTEWATER
Staff continues to take daily reads, inspections, and tests. Staff continues to monitor the industrial users.
Staff pulled and repaired the pump in Channel B. Staff repaired the transducer in Channel A.
WATER
Staff monitors Wells 4, 5, 6 and 7 and sampling stations around town. Staff continues to read meters and investigate leaks and repairs water meters including replacing the registers when they fail.
Staff is working with Tesco and FRM to complete the SCADA programming for Well 7.
Staff has closed the pool for the season. Staff will perform some repairs at the pool over the winter. The sand in the sand filters will be replaced, the water heater needs some work.
STORM WATER
Staff had annual stormwater training with the four south county cities. Staff is completing the annual stormwater report, and cleaning storm drains before the winter rains.
PARKS - CANYON CREEK & MEYER PARKS
Staff regularly mows and edges the parks. Staff burned soccer lines at Centennial Park for the soccer season. Staff continues to weed and keeps grounds looking well.
CENTRAL PARK
Four young ladies from Girl Scout Troop 30950 painted the flagpole at Central Park on October 10. One of the scout’s lives in Gonzales and thought the flagpole needed a fresh coat of paint. Public Works staff lowered the flagpole and prepped it for the new coat of paint
GOVERNMENT BUILDING
In the next couple of months, the Fire Dept station will be fumigated for termites. Staff has replaced some exterior lighting at City Hall.
STREETS
Slurry Seal Contract went well. Staff continues to fill potholes and keep streets clear. Staff continues with traffic control at the Fifth Street Bridge during the morning commute on school days.
TRAINING
Staff recently attended storm water training with the other south county cities.