SUBJECT: Resolution No. 2022-84 Accepting the Tree Removal Contract at the Community Center Project Site as Complete, Authorize Staff to Record a Notice of Completion, and Release Retention Monies to the Contractor
RECOMMENDATION
It is recommended that the City Council Adopt Resolution No. 2022-84, A Resolution of the City Council of the City of Gonzales Accepting the Tree Removal Contract at the Community Center Project Site as Complete, Authorize Staff to Record a Notice of Completion, and Release Retention Monies to the Contractor.
BACKGROUND
At the September 6, 2022 Council meeting, a staff report was presented regarding the issuance of a bid document to remove the trees at the Community Center Complex Project site. According to the CEQA/NEPA documents prepared for the Community Center Complex Project, the trees on the site should be removed between September 15 and January 15 to minimize impacts to bats and nesting birds.
Tree removal is the first field activity for site preparation for the project. New trees and landscaping will be planted during construction of the various buildings that make up the Community Center Complex Project.
On August 25, City staff issued the bid document for the Tree Removal Contract at the Community Center Project Site. On September 21, City staff opened bids from the nine contractors and the award of contract to Topes Tree Service was approved at the October 3, 2022 Council Meeting.
REVIEW & ANALYSIS
AGENDA
ITEM
7 A preconstruction meeting was held with the contractor on October 19, 2022, field work began on November 1, 2022, and punch list items were completed on November 23, 2022.
Staff recommends that the City Council accept the contract as complete and direct staff to record a Notice of Completion with the County Recorder and Release the Retention Monies to the Contractor.
How Recommendation Supports the Vision
Gonzales will continue to be a safe, clean, family-friendly community, diverse in its heritage, and committed to working collaboratively to preserve and retain its small town charm.
Explain: Constructing a Community Center will provide residents with a facility for a wide variety of public and private functions, recreation programs and other activities which will enhance the quality of life of Gonzales residents
Explain how the Recommendation Directly Implements the Mission The City Council and Staff of the City of Gonzales will realize our Vision by providing the leadership, commitment and resources necessary to provide excellent services that enhance the quality of life of our diverse community. X Yes ____ No____ N/A
Explain: See Vision explanation above.
City services will be delivered in a cost-effective, respectful and friendly manner to insure the safety and well being of the residents and the promotion of business, recreational, housing and employment opportunities in an environmentally sustainable manner. X Yes ____No ____ N/A Explain: See Vision explanation above.
Strong fiscal policies allow us to provide appropriate infrastructure for:
• Public Safety X Yes No N/A
• Housing X Yes No N/A
• Recreation X Yes No N/A
• Environment X Yes No N/A
• Education X Yes No N/A
Explain: See Vision above.
ALTERNATIVES
There are no alternatives as the contract is complete and the last step is to accept the work.
BUDGET IMPACT
This contract was funded from Measure X monies. There were no change orders during the work so the approved contingency budget of $10,300 was not used.
CONCLUSION
It is recommended that the City Council Adopt Resolution No. 2022-84, A Resolution of the City Council of the City of Gonzales Accepting the Tree Removal Contract at the Community Center Project Site as Complete, Authorize Staff to Record a Notice of Completion, and Release Retention Monies to the Contractor.