RECOMMENDATION
It is recommended that the City Council Adopt Resolution No. 2023-43, A Resolution of the City Council of the City of Gonzales Declaring an Emergency Pursuant to Section 22050 of the Public Contract Code and Section 316.050 of the Gonzales Municipal Code and Authorizing Emergency Repair Work by Salinas Pump Company for Well 5 in an Amount Not to Exceed $75,000.
BACKGROUND
The city operates a water system serving residents, commercial businesses, and industrial facilities.
Water supply is from four active water wells and the city has three water storage tanks with a total of 7.0 million gallons of storage. Over the last four weeks, staff had an electrician and a pump company investigate why Well 5 wasn’t properly operating. Salinas Pump Company pulled the pump and determined the pump bearings needed to be replaced.
REVIEW & ANALYSIS
Salinas Pump Company provided the attached $64,585 quote to replace the bearing and other associated costs. Staff recommends adding a $10,415 contingency for unforeseen efforts for a $75,000 authorization to Salinas Pup Company to repair and reinstall the Well 5 pump.
Section 3.16.050 “Bidding Required: Exceptions” of the City’s Municipal Code allows for exceptions to public bidding if “There is a breakdown in machinery or an essential service which requires the immediate purchase of supplies or services to protect the public health, welfare or safety.” AGENDA
ITEM
16 Sections 22050 and 20168 of the Public Contract Code provide that in the case of an emergency, the City Council, by four-fifths vote, may pass a resolution declaring the public interest and necessity demand the immediate expenditure of public funds to safeguard life, health and property, and that such monies may be expended without compliance with mandatory contract bidding procedures; and The repair of the pump for Well 5 is urgent and staff recommends the City Council declare the repair an emergency and authorize Salinas Pump Company to repair the Well 5 Pump at a not-to-exceed cost of $75,000.
How Recommendation Supports the Vision
Gonzales will continue to be a safe, clean, family-friendly community, diverse in its heritage, and committed to working collaboratively to preserve and retain its small-town charm.
Explain: Maintaining the operation of the city’s water system supports our vision to provide the needed water flows for commercial and industrial facilities.
Explain how the Recommendation Directly Implements the Mission The City Council and Staff of the City of Gonzales will realize our Vision by providing the leadership, commitment and resources necessary to provide excellent services that enhance the quality of life of our diverse community. X Yes ___ No _ _ N/A
Explain: See Vision explanation above.
City services will be delivered in a cost-effective, respectful and friendly manner to insure the safety and well-being of the residents and the promotion of business, recreational, housing and employment opportunities in an environmentally sustainable manner. X Yes ____No ____ N/A Explain: See Vision explanation above.
Strong fiscal policies allow us to provide appropriate infrastructure for:
• Public Safety X Yes ____ No ___ N/A
• Housing X Yes ____ No ___ N/A
• Recreation X Yes ____ No ___ N/A
• Environment X Yes ____ No ___ N/A
• Education X Yes ____ No ___ N/A
Explain: See Vision above.
ALTERNATIVES
• Direct staff to seek additional proposals for this contract • Amend or modify staff recommendation.
BUDGET IMPACT
This contract will be funded with Water Enterprise monies.
CONCLUSIONS
It is recommended that the City Council Adopt Resolution No. 2023-43, A Resolution of the City Council of the City of Gonzales Declaring an Emergency Pursuant to Section 22050 of the Public Contract Code and Section 316.050 of the Gonzales Municipal Code and Authorizing Emergency Repair Work by Salinas Pump Company for Well 5 in an Amount Not to Exceed $75,000.
Attachments:
1. Resolution No. 2023-43
2. Salinas Pump Company June 12, 2023 Quote