PUBLIC WORKS / CITY ENGINEER DEPARTMENT
STAFF REPORT
TO: Honorable Mayor Rios and City Council
DATE: October 16, 2023
FROM: Patrick Dobbins, Public Works Director/City Engineer THROUGH: Carmen Gil, City Manager
SUBJECT: Resolution No. 2023-65 Award Fifth St. Truck Ban Contract to Chrisp Company
RECOMMENDATION
It is recommended that the City Council Adopt Resolution No. 2023-65, A Resolution of the City Council of the City of Gonzales Awarding the Fifth Street Truck Ban Signage Project to Chrisp Company, Authorizing and Directing the City Manager to Execute an Agreement with Chrisp Company in the amount of $71,523 with a contingency budget of $8,477 for unanticipated field changes; and Amend the FY 2023/24 City Budget by increasing the Industrial Business Park Benefit Assessment (Fund 316) Contractual Services - General (Object Code 6245) by $80,000.
BACKGROUND
To remove heavy vehicle traffic on Fifth Street between US101 and Alta Street the City Council adopted Ordinance 2019-113 that designated the following streets as authorized truck routes:
• All of Alta Street; and
• That portion of Gonzales River Road situated in the city limits Removing trucks from Fifth Street should make the area safer and would create less traffic. The large trucks driving to and from US101 to businesses in the Industrial Park are not familiar with local vehicular and pedestrian movements and should use North Alta or South Alta to improve safety and convenience of both the trucks and the community.
Staff had a consultant prepare the necessary plans and specifications to install the required signs. As some of the signs will be installed on US101, a Caltrans Encroachment was obtained.
AGENDA
ITEM
13 REVIEW & ANALYSIS
The bid documents (plans, technical specifications, and cost estimate) for the project were prepared by GHD Consultants. This project was issued for bids on July 17, 2023 and bid documents were provided to the Central Coast Builders Exchange in Salinas and the Santa Clara/San Benito County Builders for review by contractors. On August 17, 2023 the City received a single bid from the following contractor:
BIDDER BID AMOUNT
1 Chrisp Company, Fremont, CA $71,523.00
City staff reviewed the bid and determined that Chrisp Company provided a responsive and responsible bid. Therefore, staff is recommending the City Council award the construction contract for this project to Chrisp Company. This project will be funded by Industrial Business Park Benefit Assessment monies.
The schedule for the project is in the below table:
How Recommendation Supports the Vision
Gonzales will continue to be a safe, clean, family-friendly community, diverse in its heritage, and committed to working collaboratively to preserve and retain its small-town charm.
Explain: This change in truck routes should improve safety along Fifth Street Explain how the Recommendation Directly Implements the Mission The City Council and Staff of the City of Gonzales will realize our Vision by providing the leadership, commitment, and resources necessary to provide excellent services that enhance the quality of life of our diverse community. X Yes ____ No____ N/A
Explain: The change in truck routes should lead to a better quality of life for pedestrians along Fifth Street while minimally affecting truck traffic.
City services will be delivered in a cost-effective, respectful and friendly manner to ensure the safety and well-being of the residents and the promotion of business, recreational, housing and employment opportunities in an environmentally sustainable manner. X Yes ____No ____ N/A Explain: See Vision explanation above.
Milestone Date
Award Construction Contract at City Council Meeting 10/16/2023 Construction Contract Executed 10/27/2020
Preconstruction Meeting / Notice to Proceed 11/02/2023
Contractor Mobilization (approx.) 12/04/2023
Construction Complete 12/20/2023
Strong fiscal policies allow us to provide appropriate infrastructure for:
• Public Safety X Yes No N/A
• Housing X Yes No N/A
• Recreation X Yes No N/A
• Environment X Yes No N/A
• Education X Yes No N/A
Explain: See Vision above.
ALTERNATIVES
a. Direct staff to not construct this project.
b. Direct staff to re-bid the project.
c. Amend or modify staff recommendation.
BUDGET IMPACT
This project will be funded by Industrial Business Park Benefit Assessment reserve monies (Budget Fund 316) which has a current balance of $316,000.
CONCLUSIONS
It is recommended that the City Council Adopt Resolution No. 2023-65, A Resolution of the City Council of the City of Gonzales Awarding the Fifth Street Truck Ban Signage Project to Chrisp Company, Authorizing and Directing the City Manager to Execute an Agreement with Chrisp Company in the amount of $71,523 with a contingency budget of $8,477 for unanticipated field changes; and Amend the FY 2023/24 City Budget by increasing the Industrial Business Park Benefit Assessment (Fund 316) Contractual Services - General (Object Code 6245) by $80,000.