City of Gonzales
PUBLIC WORKS / CITY ENGINEER DEPARTMENT
STAFF REPORT
TO: Honorable Mayor Rios and City Council
DATE: February 5, 2024
FROM: Patrick Dobbins, Public Works Director/City Engineer THROUGH: Carmen Gil, City Manager
SUBJECT: Community Center Complex Project Progress Report
RECOMMENDATION
It is recommended that the City Council receive a progress report on delivery of the Community Center Complex Project and provide staff with comments and feedback.
BACKGROUND
With the passage of Measure X in the November 2020 election, the City began delivery of the Community Center Complex on City-owned property at Fifth Street/Gabilan Court. Staff issued a Request for Proposals in February 2023 to the three short-listed design/build teams. At the June 5, 2023 Council meeting, the Design/Build contract was awarded to Otto Construction/WRNS Studio. At that meeting, the Council also authorized a Notice to Proceed with Design Services for a not-to-exceed amount of $4,900,446.
The DBE Agreement with Otto Construction was executed and the Notice to Proceed with Design Services for Phases 1 and 2 was issued on June 16, 2023. Due to grant funding deadlines, construction of the project will be phased. Phase 1 is the Teen Innovation Center, County Library, meeting rooms, restrooms, courtyard including amphitheater and site improvements (new drive aisle, wet/dry utilities, parking lot and landscaping). Phase 2 is the Community Center including the Community Hall, Fitness Center, commercial kitchen, meeting rooms and restrooms.
REVIEW AND ANALYSIS
This staff report is comprised of the following sections:
• Project Design
• Funding/Financing Updates
AGENDA
ITEM
11 PROJECT DESIGN
Over the last seven months, the design/build team has advanced the project through the Design Development Phase and into the Construction Document phase.
The project is on schedule including WRNS making their 75% Construction Document submittal on January 19, 2024 (plan set has 185 sheets). Final Construction Documents are expected to be submitted for City building permit review by the end of February 2024.
As WRNS works towards issuing 100% Construction Documents, Moore Twining Associates (subcontractor to Otto Construction) for field investigations (soil borings and percolation tests). They will produce a geotechnical report to supplement the 2013 geotechnical report that will include recommendations to the design team.
Otto recently engaged with local PG&E service representatives to submit a new service application for the project. This early coordination is critical due to the long lead time for electrical gear.
WRNS staff will meet with the Gonzales Youth Council in advance of the February 5, 2024 Council meeting to present them with updates to the Teen Innovation Center. City staff is planning for a groundbreaking ceremony on April 27, 2024.
The presentation at the Council meeting will include additional details and efforts regarding the Design phase of the project.
FUNDING/FINANCING UPDATES
The Community Center Complex is estimated to cost $34,525,300 for Phases 1 and 2 consisting of the Community Center, Teen Innovation Center, County Library, and all site work. Construction of this significant civic project will be funded by a variety of sources including the following:
• Measure X (local sales tax)
• $5.0M State grant secured by State Senator Anna Caballero • Community Development Block Grant (CDBG FY 2022/23 and FY 2023/24) • $1.8M County contribution to relocate existing library from the Gonzales Shopping Center • Grants (Electric Vehicle Charging Station Grant and a Building Forward Library Grant) • Capital Campaign with a $10.0M goal with pledges and contributions currently totaling $6.7M Current funding for the project is:
1 Teen Innovation Center Grant (State Grant) $5,000,000 2 USDA Loan (paid by Measure X funds) $9,875,000
3 Community Development Block Grant (Federal monies) $827,750 4 County Library Contribution $1,800,000
5 Electric Vehicle Charging Station Grant $400,000
6 Building Forward Library Grant Program $1,067,430
7 Capital Campaign Contribution (private contributions and pledges) $6,737,100 Funding as of 1/10/2024 = $25,707,280
DBE Contract “Stipulated Sum” for Phase 1 = $23,619,838 Estimated Cost for Phase 2 = $10,905,462
Total Estimated Cost for Phases 1 and 2 = $34,525,300
Current shortfall to construct Phase 2 = $8,818,020
How Recommendation Supports the Vision
Gonzales will continue to be a safe, clean, family-friendly community, diverse in its heritage, and committed to working collaboratively to preserve and retain its small-town charm.
Explain: Constructing a Community Center will provide residents with a multi-use facility for a wide variety of public and private functions, recreation programs and other activities which will enhance the quality of life of Gonzales residents.
Explain how the Recommendation Directly Implements the Mission The City Council and Staff of the City of Gonzales will realize our Vision by providing the leadership, commitment and resources necessary to provide excellent services that enhance the quality of life of our diverse community. X Yes ____ No____ N/A
Explain: Please see explanation above for the Mission.
City services will be delivered in a cost-effective, respectful and friendly manner to insure the safety and well-being of the residents and the promotion of business, recreational, housing and employment opportunities in an environmentally sustainable manner. X Yes ____No ____ N/A Explain: See Vision explanation above.
Strong fiscal policies allow us to provide appropriate infrastructure for:
• Public Safety Yes X No N/A
• Housing Yes X No N/A
• Recreation X Yes No N/A
• Environment X Yes No N/A
• Education X Yes No N/A
ALTERNATIVES
No alternatives to consider as part of this staff report, as this is a progress report.
BUDGET IMPACT
There isn’t a budget impact related to this staff report and presentation.
CONCLUSION
It is recommended that the City Council receive a progress report on delivery of the Community Center Complex Project and provide staff with comments and feedback.