Activity ID Activity Name OD Start Finish Total Float
Gonzales Community Center Complex - Preliminary Baseline R1 Project Overview
Milestones
Phase 1
P1-ML-1000 Phase 1 Start 0 29-Apr-24 556P1-ML-1010 Phase 1 Substructure Complete 0 18-Aug-24 444P1-ML-1020 Phase 1 Topout 0 27-Sep-24 404P1-ML-1030 Phase 1 Rough MEP Complete 0 19-Nov-24 351P1-ML-1040 Phase 1 Dry In 0 06-Dec-24 334P1-ML-1050 Phase 1 Permanent Power 0 08-Apr-25 211P1-ML-1060 Phase 1 Finish 0 19-Sep-25 47 Phase 2
P2-ML-1000 Phase 2 Start 0 23-Sep-24 409P2-ML-1010 Phase 2 Substructure Complete 0 22-Dec-24 318P2-ML-1020 Phase 2 Topout 0 30-Jan-25 279P2-ML-1030 Phase 2 Rough MEP Complete 0 06-Mar-25 244P2-ML-1040 Phase 2 Dry In 0 25-Mar-25 225P2-ML-1050 Phase 2 Permanent Power 0 13-May-25 176P2-ML-1060 Phase 2 Finish 0 19-Sep-25 47 Summaries
SUM-1000 Design Duration 264 16-Jun-23 05-Mar-24 54SUM-1010 Phase 1 Duration 509 29-Apr-24 19-Sep-25 47SUM-1020 Phase 2 Duration 362 23-Sep-24 19-Sep-25 47 Design
DES-1000 NTP - Design 0 16-Jun-23* 3DES-1010 Design Development 113 10-Jul-23 30-Oct-23 3DES-1020 50% DDs 0 14-Aug-23 80DES-1030 100% DDs 0 30-Oct-23 3DES-1040 Construction Documents 113 31-Oct-23 20-Feb-24 3DES-1050 100% DD Review 14 31-Oct-23 13-Nov-23 102DES-1060 50% CDs 0 15-Dec-23 70DES-1070 100% CDs 0 20-Feb-24 3DES-1080 Permitting 65 21-Feb-24 25-Apr-24 3DES-1090 Bidding 65 21-Feb-24 25-Apr-24 3DES-1100 100% CD Review 14 21-Feb-24 05-Mar-24 54 Phase 1 Construction
Excavation & Substructure
P1-EXC-1000 NTP - Construction Phase 1 0 29-Apr-24* 0P1-EXC-1010 Mobilize & Field Office 2 29-Apr-24 30-Apr-24 0P1-EXC-1020 Install Site Fencing 2 29-Apr-24 30-Apr-24 3P1-EXC-1030 Locate Utilities 2 29-Apr-24 30-Apr-24 0P1-EXC-1040 Safe Off Utilities 3 01-May-24 03-May-24 0P1-EXC-1050 Hardscape Demo 5 06-May-24 10-May-24 0P1-EXC-1060 Clear & Grub 5 08-May-24 14-May-24 0P1-EXC-1070 Abatement 5 15-May-24 21-May-24 0P1-EXC-1080 Utility & Site Survey 2 15-May-24 16-May-24 0P1-EXC-1090 Site Grading 12 17-May-24 04-Jun-24 0 Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Phase 1 Start
Phase 1 Substructure Complete
Phase 1 Topout
Phase 1 Rough MEP Complete
Phase 1 Dry In
Phase 1 Permanent Power
Phase 1 Finish
Phase 2 Start
Phase 2 Substructure Complete
Phase 2 Topout
Phase 2 Rough MEP Complete
Phase 2 Dry In
Phase 2 Permanent Power
Phase 2 Finish
Design Duration
Phase 1 DurationPhase 2 Duration
NTP - Design
Design Development
50% DDs
100% DDs
Construction Documents
100% DD Review
50% CDs
100% CDs
PermittingBidding
100% CD Review
NTP - Construction Phase 1
Mobilize & Field OfficeInstall Site FencingLocate Utilities Safe Off Utilities
Hardscape Demo
Clear & Grub
Abatement
Utility & Site Survey
Site Grading
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23
Activity ID Activity Name OD Start Finish Total Float
P1-EXC-1100 Pad Prep 5 24-May-24 30-May-24 0P1-EXC-1110 Pad Certification 1 30-May-24 30-May-24 0P1-EXC-1120 Footing Layout 5 03-Jun-24 07-Jun-24 0P1-EXC-1130 Footing Excavation 8 10-Jun-24 19-Jun-24 0P1-EXC-1140 In Slab Plumbing 8 13-Jun-24 24-Jun-24 0P1-EXC-1150 Plumbing Test & Inspection 1 24-Jun-24 24-Jun-24 0P1-EXC-1160 Footing Reinforcing Installation 8 25-Jun-24 04-Jul-24 0P1-EXC-1170 Target Install 5 28-Jun-24 04-Jul-24 0P1-EXC-1180 Curb Reinforcing 2 05-Jul-24 08-Jul-24 0P1-EXC-1190 Holddown & AB Install 2 09-Jul-24 10-Jul-24 0P1-EXC-1200 Reinforcing Inspection 1 10-Jul-24 10-Jul-24 0P1-EXC-1210 Concrete Footings Placement (Building, Seatwall, Planter, Trash Enclosure) 1 11-Jul-24 11-Jul-24 0P1-EXC-1220 Strip & Clean Footings 2 12-Jul-24 15-Jul-24 0P1-EXC-1230 Form Slab Edge 6 16-Jul-24 23-Jul-24 0P1-EXC-1240 In Slab Electrical 7 16-Jul-24 24-Jul-24 0P1-EXC-1250 Fine Grade Slab 3 25-Jul-24 29-Jul-24 0P1-EXC-1260 Install & Compaction of Granular FIll 2 30-Jul-24 31-Jul-24 0P1-EXC-1270 Install Vapor Barrier 5 01-Aug-24 07-Aug-24 0P1-EXC-1280 Slab Reinforcing 5 05-Aug-24 09-Aug-24 0P1-EXC-1290 Sill Bolt Installation 3 07-Aug-24 09-Aug-24 0P1-EXC-1300 Slab Reinforcing Inspection 1 09-Aug-24 09-Aug-24 0P1-EXC-1310 Place & Finish Slab 2 12-Aug-24 13-Aug-24 0P1-EXC-1320 Cure & Strip Slab 5 14-Aug-24 18-Aug-24 0 Structure
P1-STR-1000 HSS Install 3 19-Aug-24 21-Aug-24 0P1-STR-1010 Exterior Wall Framing 15 19-Aug-24 06-Sep-24 0P1-STR-1020 Roof Framing 15 09-Sep-24 27-Sep-24 0P1-STR-1030 Blocking & Hardware 12 30-Sep-24 15-Oct-24 0P1-STR-1040 Interior Wall Framing 10 30-Sep-24 11-Oct-24 0P1-STR-1050 Hardlid Framing 5 07-Oct-24 11-Oct-24 2 Interior
Rough Interior
P1-RI-1000 Rough Sprinkler 18 16-Oct-24 08-Nov-24 0P1-RI-1010 Rough HVAC 18 23-Oct-24 15-Nov-24 0P1-RI-1020 Rough Electrical 18 23-Oct-24 15-Nov-24 0P1-RI-1030 Rough Plumbing 15 28-Oct-24 15-Nov-24 0P1-RI-1040 Rough Data / Fire Alarm 10 04-Nov-24 15-Nov-24 0P1-RI-1050 In Wall Inspections 2 18-Nov-24 19-Nov-24 0P1-RI-1060 OH Inspections 2 18-Nov-24 19-Nov-24 0P1-RI-1070 Install HM Frames 2 18-Nov-24 19-Nov-24 0 Finish Interior
P1-FI-1000 Base 5 20-Nov-24 26-Nov-24 0P1-FI-1010 1st Side Drywall 5 27-Nov-24 05-Dec-24 0P1-FI-1020 Insulation 10 04-Dec-24 17-Dec-24 0P1-FI-1030 2nd Side Drywall 12 11-Dec-24 08-Jan-25 0P1-FI-1040 Tape & Finish 18 23-Dec-24 28-Jan-25 0P1-FI-1050 Interior Paint 10 29-Jan-25 11-Feb-25 0 Trim Interior
Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Pad PrepPad Certification
Footing Layout
Footing Excavation
In Slab PlumbingPlumbing Test & Inspection
Footing Reinforcing InstallationTarget Install
Curb Reinforcing
Holddown & AB InstallReinforcing Inspection
Concrete Footings Placement (Building, Seatwall, Planter, Trash Enclosure) Strip & Clean Footings
Form Slab Edge
In Slab Electrical
Fine Grade Slab
Install & Compaction of Granular FIll
Install Vapor Barrier
Slab ReinforcingSill Bolt InstallationSlab Reinforcing Inspection Place & Finish Slab
Cure & Strip Slab
HSS Install
Exterior Wall Framing
Roof Framing
Blocking & Hardware
Interior Wall FramingHardlid Framing
Rough Sprinkler
Rough HVACRough ElectricalRough PlumbingRough Data / Fire Alarm In Wall InspectionsOH InspectionsInstall HM Frames
Base
1st Side Drywall
Insulation
2nd Side Drywall
Tape & Finish
Interior Paint
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23
Activity ID Activity Name OD Start Finish Total Float
P1-TI-1000 Tile Restrooms 10 12-Feb-25 25-Feb-25 0P1-TI-1010 Suspended Ceiling System 18 12-Feb-25 07-Mar-25 0P1-TI-1020 Restroom Partitions / Plumbing Finishes 10 26-Feb-25 11-Mar-25 32P1-TI-1030 Install Sprinkler Finish 5 10-Mar-25 14-Mar-25 0P1-TI-1040 Install Electrical Finish In Wall & Ceiling 12 10-Mar-25 25-Mar-25 0P1-TI-1050 Install Whiteboards & Tackpanel 5 10-Mar-25 14-Mar-25 34P1-TI-1060 Install HVAC Finish Grilles & Registers 5 10-Mar-25 14-Mar-25 112P1-TI-1070 Install Racks 5 26-Mar-25 01-Apr-25 105P1-TI-1080 Hang Lights 10 26-Mar-25 08-Apr-25 0P1-TI-1090 Place Carpet 12 09-Apr-25 24-Apr-25 0P1-TI-1100 Seal Concrete 5 25-Apr-25 01-May-25 0P1-TI-1110 Epoxy Floor 5 25-Apr-25 01-May-25 0P1-TI-1120 Casework 8 02-May-25 13-May-25 0P1-TI-1130 Trim Data 10 02-May-25 15-May-25 83P1-TI-1140 Install Interior Doors & Hardware 10 14-May-25 27-May-25 0P1-TI-1150 Data Testing 2 14-May-25 15-May-25 83P1-TI-1160 Trim Fire Alarm 5 16-May-25 22-May-25 83P1-TI-1170 Fire Alarm Testing 2 23-May-25 26-May-25 83 Exterior
P1-EXT-1000 Air & Water Barrier 10 09-Sep-24 20-Sep-24 16P1-EXT-1010 Flashings 5 23-Sep-24 27-Sep-24 16P1-EXT-1020 EIFS Installation 20 30-Sep-24 25-Oct-24 16P1-EXT-1030 Roof Drains 3 30-Sep-24 02-Oct-24 37P1-EXT-1040 Install HPL System 20 30-Sep-24 25-Oct-24 16P1-EXT-1050 Single Ply Membrane Roofing 10 03-Oct-24 16-Oct-24 37P1-EXT-1060 Metal Panel Roofing 20 17-Oct-24 13-Nov-24 138P1-EXT-1070 Curtain Wall Installation 20 28-Oct-24 22-Nov-24 16P1-EXT-1080 HM Jamb Install 5 28-Oct-24 01-Nov-24 31P1-EXT-1090 Perf Panel Installation 10 28-Oct-24 08-Nov-24 26P1-EXT-1100 Glazing 8 25-Nov-24 06-Dec-24 228P1-EXT-1110 Exterior Paint 15 25-Nov-24 17-Dec-24 16P1-EXT-1120 Exterior Overhang 8 18-Dec-24 09-Jan-25 108P1-EXT-1130 Exterior MEP Finishes 10 18-Dec-24 13-Jan-25 106P1-EXT-1140 Building Signage 8 18-Dec-24 09-Jan-25 108 Closeout
P1-CL-1000 HVAC Startup 10 28-May-25 11-Jun-25 0P1-CL-1010 Owner FF&E 5 28-May-25 04-Jun-25 10P1-CL-1020 Test & Balance 5 12-Jun-25 18-Jun-25 0P1-CL-1030 City Inspection (TCO) - Phase 1 5 12-Jun-25 18-Jun-25 0P1-CL-1040 Weather Contingency - Phase 1 67 19-Jun-25 19-Sep-25 0P1-CL-1050 Substantial Completion - Phase 1 0 19-Sep-25* 2P1-CL-1060 Closeout + Punchlist 45 20-Sep-25 03-Nov-25 2P1-CL-1070 City Inspection (CO) - Phase 1 5 28-Oct-25 03-Nov-25 2P1-CL-1080 Final Completion - Phase 1 0 03-Nov-25* 2 Phase 2 Construction
Excavation & Substructure
P2-EXC-1000 NTP - Construction Phase 2 0 23-Sep-24* 0P2-EXC-1010 Mobilize 2 23-Sep-24 24-Sep-24 0 Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Tile Restrooms
Suspended Ceiling System
Restroom Partitions / Plumbing Finishes
Install Sprinkler Finish
Install Electrical Finish In Wall & Ceiling
Install Whiteboards & TackpanelInstall HVAC Finish Grilles & Registers Install Racks
Hang Lights
Place Carpet
Seal ConcreteEpoxy Floor
Casework
Trim Data
Install Interior Doors & Hardware
Data Testing
Trim Fire Alarm
Fire Alarm Testing
Air & Water Barrier
Flashings
EIFS Installation
Roof Drains
Install HPL System
Single Ply Membrane Roofing
Metal Panel Roofing
Curtain Wall Installation
HM Jamb Install
Perf Panel Installation
Glazing
Exterior Paint
Exterior Overhang
Exterior MEP Finishes
Building Signage
HVAC Startup
Owner FF&E
Test & BalanceCity Inspection (TCO) - Phase 1
Weather Contingency - Phase 1Substantial Completion - Phase 1 Closeout + PunchlistCity Inspection (CO) - Phase 1Final Completion - Phase 1 NTP - Construction Phase 2
Mobilize
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23
Activity ID Activity Name OD Start Finish Total Float
P2-EXC-1020 Install Site Fencing 2 23-Sep-24 24-Sep-24 3P2-EXC-1030 Locate Utilities 2 23-Sep-24 24-Sep-24 0P2-EXC-1040 Safe Off Utilities 3 25-Sep-24 27-Sep-24 0P2-EXC-1050 Hardscape Demo 4 30-Sep-24 03-Oct-24 0P2-EXC-1060 Clear & Grub 4 02-Oct-24 07-Oct-24 0P2-EXC-1070 Abatement 4 08-Oct-24 11-Oct-24 0P2-EXC-1080 Utility & Site Survey 2 08-Oct-24 09-Oct-24 0P2-EXC-1090 Site Grading 8 10-Oct-24 21-Oct-24 0P2-EXC-1100 Pad Prep 4 17-Oct-24 22-Oct-24 0P2-EXC-1110 Pad Certification 1 22-Oct-24 22-Oct-24 0P2-EXC-1120 Footing Layout 4 23-Oct-24 28-Oct-24 0P2-EXC-1130 Footing Excavation 6 25-Oct-24 01-Nov-24 0P2-EXC-1140 In Slab Plumbing 6 29-Oct-24 05-Nov-24 0P2-EXC-1150 Plumbing Test & Inspection 1 05-Nov-24 05-Nov-24 0P2-EXC-1160 Footing Reinforcing Installation 5 06-Nov-24 12-Nov-24 0P2-EXC-1170 Target Install 4 07-Nov-24 12-Nov-24 0P2-EXC-1180 Curb Reinforcing 2 13-Nov-24 14-Nov-24 0P2-EXC-1190 Holddown & AB Install 2 13-Nov-24 14-Nov-24 0P2-EXC-1200 Reinforcing Inspection 1 14-Nov-24 14-Nov-24 0P2-EXC-1210 Concrete Footings Placement (Building, Seatwall, Planter, Trash Enclosure) 1 15-Nov-24 15-Nov-24 0P2-EXC-1220 Strip & Clean Footings 2 18-Nov-24 19-Nov-24 0P2-EXC-1230 Form Slab Edge 5 20-Nov-24 26-Nov-24 0P2-EXC-1240 In Slab Electrical 5 20-Nov-24 26-Nov-24 0P2-EXC-1250 Fine Grade Slab 2 27-Nov-24 02-Dec-24 0P2-EXC-1260 Install & Compaction of Granular FIll 2 03-Dec-24 04-Dec-24 0P2-EXC-1270 Install Vapor Barrier 4 05-Dec-24 10-Dec-24 0P2-EXC-1280 Slab Reinforcing 5 09-Dec-24 13-Dec-24 0P2-EXC-1290 Sill Bolt Installation 2 12-Dec-24 13-Dec-24 0P2-EXC-1300 Slab Reinforcing Inspection 1 13-Dec-24 13-Dec-24 0P2-EXC-1310 Place & Finish Slab 2 16-Dec-24 17-Dec-24 0P2-EXC-1320 Cure & Strip Slab 5 18-Dec-24 22-Dec-24 0 Structure
P2-STR-1000 HSS Install 2 23-Dec-24 06-Jan-25 0P2-STR-1010 Exterior Wall Framing 10 23-Dec-24 16-Jan-25 0P2-STR-1020 Roof Framing 10 17-Jan-25 30-Jan-25 0P2-STR-1030 Blocking & Hardware 8 31-Jan-25 11-Feb-25 0P2-STR-1040 Interior Wall Framing 8 31-Jan-25 11-Feb-25 0P2-STR-1050 Hardlid Framing 4 06-Feb-25 11-Feb-25 0 Interior
Rough Interior
P2-RI-1000 Rough Sprinkler 10 12-Feb-25 25-Feb-25 0P2-RI-1010 Rough HVAC 10 19-Feb-25 04-Mar-25 0P2-RI-1020 Rough Electrical 10 19-Feb-25 04-Mar-25 0P2-RI-1030 Rough Plumbing 10 19-Feb-25 04-Mar-25 0P2-RI-1040 Rough Data / Fire Alarm 8 21-Feb-25 04-Mar-25 0P2-RI-1050 In Wall Inspections 2 05-Mar-25 06-Mar-25 0P2-RI-1060 OH Inspections 2 05-Mar-25 06-Mar-25 0P2-RI-1070 Install HM Frames 2 05-Mar-25 06-Mar-25 0 Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Install Site FencingLocate Utilities
Safe Off Utilities
Hardscape Demo
Clear & Grub
Abatement
Utility & Site Survey
Site Grading
Pad PrepPad Certification
Footing Layout
Footing Excavation
In Slab PlumbingPlumbing Test & Inspection
Footing Reinforcing InstallationTarget Install
Curb ReinforcingHolddown & AB InstallReinforcing Inspection Concrete Footings Placement (Building, Seatwall, Planter, Trash Enclosure) Strip & Clean Footings
Form Slab EdgeIn Slab Electrical
Fine Grade Slab
Install & Compaction of Granular FIll
Install Vapor Barrier
Slab ReinforcingSill Bolt InstallationSlab Reinforcing Inspection Place & Finish Slab
Cure & Strip Slab
HSS Install
Exterior Wall Framing
Roof Framing
Blocking & HardwareInterior Wall FramingHardlid Framing Rough Sprinkler
Rough HVACRough ElectricalRough PlumbingRough Data / Fire Alarm In Wall InspectionsOH InspectionsInstall HM Frames
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23
Activity ID Activity Name OD Start Finish Total Float
Finish Interior
P2-FI-1000 Base 4 07-Mar-25 12-Mar-25 0P2-FI-1010 1st Side Drywall 4 13-Mar-25 18-Mar-25 0P2-FI-1020 Insulation 7 17-Mar-25 25-Mar-25 0P2-FI-1030 2nd Side Drywall 8 19-Mar-25 28-Mar-25 1P2-FI-1040 Tape & Finish 10 26-Mar-25 08-Apr-25 0P2-FI-1050 Interior Paint 7 09-Apr-25 17-Apr-25 0 Trim Interior
P2-TI-1000 Tile Restrooms 7 18-Apr-25 28-Apr-25 0P2-TI-1010 Suspended Ceiling System 8 18-Apr-25 29-Apr-25 0P2-TI-1020 Restroom Partitions / Plumbing Finishes 7 29-Apr-25 07-May-25 10P2-TI-1030 Install Sprinkler Finish 4 30-Apr-25 05-May-25 0P2-TI-1040 Install Whiteboards & Tackpanel 4 30-Apr-25 05-May-25 16P2-TI-1050 Install Electrical Finish In Wall & Ceiling 8 02-May-25 13-May-25 0P2-TI-1060 Install HVAC Finish Grilles & Registers 4 02-May-25 07-May-25 81P2-TI-1070 Hang Lights 5 07-May-25 13-May-25 0P2-TI-1080 Place Carpet 8 12-May-25 21-May-25 0P2-TI-1090 Install Racks 4 14-May-25 19-May-25 77P2-TI-1100 Seal Concrete 4 22-May-25 27-May-25 0P2-TI-1110 Epoxy Floor 4 22-May-25 27-May-25 0P2-TI-1120 Casework 5 28-May-25 04-Jun-25 0P2-TI-1130 Trim Data 5 28-May-25 04-Jun-25 71P2-TI-1140 Install Interior Doors & Hardware 5 03-Jun-25 09-Jun-25 0P2-TI-1150 Data Testing 2 03-Jun-25 04-Jun-25 71P2-TI-1160 Trim Fire Alarm 4 05-Jun-25 10-Jun-25 71P2-TI-1170 Fire Alarm Testing 2 11-Jun-25 12-Jun-25 71 Exterior
P2-EXT-1000 Air & Water Barrier 8 17-Jan-25 28-Jan-25 51P2-EXT-1010 Flashings 4 29-Jan-25 03-Feb-25 51P2-EXT-1020 Roof Drains 2 31-Jan-25 03-Feb-25 24P2-EXT-1030 Single Ply Membrane Roofing 8 04-Feb-25 13-Feb-25 24P2-EXT-1040 EIFS Installation 15 04-Feb-25 24-Feb-25 51P2-EXT-1050 Install HPL System 15 04-Feb-25 24-Feb-25 51P2-EXT-1060 Metal Panel Roofing 15 14-Feb-25 06-Mar-25 76P2-EXT-1070 Curtain Wall Installation 15 25-Feb-25 17-Mar-25 51P2-EXT-1080 HM Jamb Install 4 25-Feb-25 28-Feb-25 80P2-EXT-1090 Perf Panel Installation 8 25-Feb-25 06-Mar-25 76P2-EXT-1100 Glazing 6 18-Mar-25 25-Mar-25 160P2-EXT-1110 Exterior Paint 10 18-Mar-25 31-Mar-25 51P2-EXT-1120 Exterior Overhang 6 01-Apr-25 08-Apr-25 53P2-EXT-1130 Exterior MEP Finishes 8 01-Apr-25 10-Apr-25 51P2-EXT-1140 Building Signage 6 01-Apr-25 08-Apr-25 58 Closeout
P2-CL-1000 HVAC Startup 10 10-Jun-25 23-Jun-25 0P2-CL-1010 Owner FF&E 5 10-Jun-25 16-Jun-25 10P2-CL-1020 Test & Balance 5 24-Jun-25 30-Jun-25 0P2-CL-1030 City Inspection (TCO) - Phase 2 5 24-Jun-25 30-Jun-25 0P2-CL-1040 Weather Contingency - Phase 2 59 01-Jul-25 19-Sep-25 0 Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Base
1st Side Drywall
Insulation
2nd Side Drywall
Tape & Finish
Interior Paint
Tile Restrooms
Suspended Ceiling System
Restroom Partitions / Plumbing Finishes
Install Sprinkler FinishInstall Whiteboards & Tackpanel Install Electrical Finish In Wall & Ceiling
Install HVAC Finish Grilles & Registers
Hang Lights
Place Carpet
Install Racks
Seal ConcreteEpoxy Floor
CaseworkTrim Data
Install Interior Doors & Hardware
Data Testing
Trim Fire Alarm
Fire Alarm Testing
Air & Water Barrier
FlashingsRoof Drains
Single Ply Membrane Roofing
EIFS InstallationInstall HPL System
Metal Panel Roofing
Curtain Wall Installation
HM Jamb Install
Perf Panel Installation
Glazing
Exterior Paint
Exterior Overhang
Exterior MEP Finishes
Building Signage
HVAC Startup
Owner FF&E
Test & BalanceCity Inspection (TCO) - Phase 2
Weather Contingency - Phase 2
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23
Activity ID Activity Name OD Start Finish Total Float
P2-CL-1050 Substantial Completion - Phase 2 0 19-Sep-25* 2P2-CL-1060 Closeout + Punchlist 45 20-Sep-25 03-Nov-25 2P2-CL-1070 City Inspection (CO) - Phase 2 5 28-Oct-25 03-Nov-25 2P2-CL-1080 Final Completion - Phase 2 0 03-Nov-25* 2 Site Finishes
SF-1000 Sewer Tie In 8 05-Jun-24 14-Jun-24 46SF-1010 Firewater Tie In 8 05-Jun-24 14-Jun-24 46SF-1020 Domestic Water Tie In 8 05-Jun-24 14-Jun-24 46SF-1030 Joint Trench for Electrical 15 17-Jun-24 05-Jul-24 46SF-1040 D/L/B Storm Drain & Sewer 15 08-Jul-24 26-Jul-24 46SF-1050 D/L/B Firewater 20 29-Jul-24 23-Aug-24 46SF-1060 D/L/B Domestic Water 10 26-Aug-24 06-Sep-24 46SF-1070 Site Lighting & EV Conduit 15 09-Sep-24 27-Sep-24 46SF-1080 Irrigation Mains & Sleeves 20 30-Sep-24 25-Oct-24 46SF-1090 Place Base for Drive & Parking 5 30-Sep-24 04-Oct-24 94SF-1100 Stack CMU Wall 6 07-Oct-24 14-Oct-24 107SF-1110 Grout CMU Wall 1 15-Oct-24 15-Oct-24 107SF-1120 CMU Wall Cure 5 16-Oct-24 20-Oct-24 165SF-1130 Trash Enclosure Structural Steel 3 21-Oct-24 23-Oct-24 108SF-1140 Trash Enclosure Roofing 3 24-Oct-24 28-Oct-24 108SF-1150 Bioswale Piping 10 28-Oct-24 08-Nov-24 61SF-1160 Dig Form & Place Lightpole Bases 10 28-Oct-24 08-Nov-24 46SF-1170 Trash Enclosure Perforated Metal 2 29-Oct-24 30-Oct-24 108SF-1180 Trash Enclosure Gates & Doors 3 31-Oct-24 04-Nov-24 108SF-1190 Rock @ Bioswales 10 11-Nov-24 22-Nov-24 61SF-1200 Bioswale Mix 10 25-Nov-24 10-Dec-24 61SF-1210 Offsite Improvements (Replace Sidewalks & Approaches, Signage, AC Paving, Sriping) 20 11-Dec-24 20-Jan-25 61SF-1220 Site Grading 5 18-Dec-24 06-Jan-25 16SF-1230 Fine Grade Site 8 07-Jan-25 16-Jan-25 16SF-1240 F/R/P Curbs 20 17-Jan-25 13-Feb-25 16SF-1250 Resilient Tile Placement 10 17-Jan-25 30-Jan-25 33SF-1260 Reinforce Plastic Grid 5 31-Jan-25 06-Feb-25 48SF-1270 Place & Compact Base for Walks 8 04-Feb-25 13-Feb-25 19SF-1280 Soil Ammendment 15 07-Feb-25 27-Feb-25 48SF-1290 Strip & Clean Curbs 5 12-Feb-25 18-Feb-25 16SF-1300 F/R/P Concrete Walks 20 19-Feb-25 18-Mar-25 16SF-1310 Irrigation Laterals 20 25-Feb-25 24-Mar-25 16SF-1320 Sawcut 3 19-Mar-25 21-Mar-25 20SF-1330 Fine Grade Base Rock 3 24-Mar-25 26-Mar-25 20SF-1340 Set Irrigation Heads 15 25-Mar-25 14-Apr-25 16SF-1350 Set Lightpoles 5 27-Mar-25 02-Apr-25 20SF-1360 AC Pave 1 03-Apr-25 03-Apr-25 20SF-1370 Striping & Signage 3 04-Apr-25 08-Apr-25 20SF-1380 Turf Placement 5 15-Apr-25 21-Apr-25 16SF-1390 Tree Planting 10 22-Apr-25 05-May-25 16SF-1400 Planting 15 06-May-25 26-May-25 16 Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar 2023 2024 2025 2026
Substantial Completion - Phase 2
Closeout + PunchlistCity Inspection (CO) - Phase 2Final Completion - Phase 2 Sewer Tie InFirewater Tie InDomestic Water Tie In
Joint Trench for Electrical
D/L/B Storm Drain & Sewer
D/L/B Firewater
D/L/B Domestic Water
Site Lighting & EV Conduit
Irrigation Mains & Sleeves
Place Base for Drive & Parking
Stack CMU Wall
Grout CMU Wall
CMU Wall Cure
Trash Enclosure Structural Steel
Trash Enclosure Roofing
Bioswale PipingDig Form & Place Lightpole Bases
Trash Enclosure Perforated Metal
Trash Enclosure Gates & Doors
Rock @ Bioswales
Bioswale Mix
Offsite Improvements (Replace Sidewalks & Approaches, Signage Site Grading
Fine Grade Site
F/R/P Curbs
Resilient Tile Placement
Reinforce Plastic Grid
Place & Compact Base for Walks
Soil Ammendment
Strip & Clean Curbs
F/R/P Concrete Walks
Irrigation Laterals
Sawcut
Fine Grade Base Rock
Set Irrigation Heads
Set LightpolesAC Pave
Striping & Signage
Turf Placement
Tree Planting
Planting
Remaining Level of EffortActual Level of EffortActual Work Remainin...Critical R...Milestone
Gonzales Community Center Complex - Preliminary Baseline R1
All Activities
DD 16-Jun-23