ACTIVITY SUBCONTRACTOR/ NOTES 7/29 7/30 7/31 8/1 8/2 8/3 8/4 8/5 8/6 8/7 8/8 8/9 8/10 8/11 8/12 8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/21 8/22 8/23 8/24 8/25 8/26 8/27 8/28 8/29 8/30 8/31 9/1 9/2 9/3 9/4 9/5 9/6 9/7 9/8 DESCRIPTION VENDOR IMPACTS M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su SS Trenching MGH X X
SS install MGH X X
Staking MGH X
Offhaul Soils (make ready work) MGH X X X X
Excavation In Slab SS FM Booth X X
SD System Install MGH X X X X X X X X X
SS/SD Installation FM Booth X X X X X X X
Deep Underground Install Elec. Collins X X X X X X X
Deep Backfill and Compaction Elec. Collins X X X
Footing Layout Grade break X X X
Footing Dig Grade break X X X X
Backfill and Compaction FM Booth X X
Footing Reinforcement Grade break X X X X
Plates and Anchors Grade break X X X X
Sleeves footing Collins X
Verify Plates Grade break X
Footing Inspection 4 Leaf/PSI X
Footing Placement Grade break X
SOG Layout Collins X X
Form Slab Grade break X X X X X X X
Slab on Grade Collins X X X X X X X X X X
SOG Inspection Collins X
Install Drains touch up while wrap FM Booth X
Termicide Pad MGH X X
Vapor Barrier Grade break X X
Rebar Slab Grade break X X X X X X
Reinforcing Inspection 4 leaf/PSI X X
SOG Placement Grade break X X
H
O
L
I
D
A
Y
LOOK AHEAD SCHEDULE
GONZALES COMMUNITY CENTER COMPLEX
5TH STREET, GONZALES, CA
ACTIVITY SUBCONTRACTOR/ NOTES 7/29 7/30 7/31 8/1 8/2 8/3 8/4 8/5 8/6 8/7 8/8 8/9 8/10 8/11 8/12 8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/21 8/22 8/23 8/24 8/25 8/26 8/27 8/28 8/29 8/30 8/31 9/1 9/2 9/3 9/4 9/5 9/6 9/7 9/8 DESCRIPTION VENDOR IMPACTSMTW ThFS SuMTW ThFS SuMTW ThFS SuMTW ThFS SuMTW ThFS SuMTW ThFS Su