GONZALES’ STREETS AND ROADS
Conditions
Unfunded Needs
Costs
Plan
Next Steps
Recent major projects:
 Entire length of Alta Street was reconstructed in 2018. Project cost $5,200,000 and was funded through a $2.5M loan against the city’s annual allotment from TAMC’s Measure X. City still owes $900,000 (3 years away from paying off the loan). $492,000 are also owed to fund 421as a loan was pulled from there to complete the project.
 Gloria Road was reconstructed in 2020 as part of a joint project with Monterey County and SVSWA. City’s portion of project was funded with several years of SB- 1 monies. The City contribution was $600,000. The project total was $5,600,000.

Other street projects:
 A slurry seal contract was completed in 2021 for streets in various neighborhoods. This $500,000 project was funded with assessment district monies, city street funds, a Measure K allocation and TAMC RSTP monies.  In 2022 the city’s insurance carrier provided approx. $7,500 to engage a contractor to grind sections of raised sidewalks down.
 City PW staff performs as needed storm drain and pothole repairs.  The City has approximately 20 centerline miles of paved streets.  Many of them need to be resurfaced or reconstructed.
 City streets are among our most valuable assets, a full replacement would cost approx. $200 million dollars.
 The 2020 Pavement Management Program (PMP) recommended that the city budget at least $850,000 each fiscal year to maintain the condition of the roads. Additional funding is needed to improve the status of the streets.

SB 1
 $226,000 has been allocated towards resurfacing the first block of Fourth Street. City will also use $53,000 in RSTP funding for this work.

Safe Routes to Schools
 $250,000 has been awarded towards pedestrian safety improvements along Fifth St. from the US101 Bridge to the Community Center site.

Office of Traffic Safety Grant
 Partnered with Health Department to get $40,000 to support the purchase of 2 lighted stop signs, and a lighted crosswalk that will go on Fifth St. Funding will also support pedestrian safety education and trainings.

Truck Ban
 Industrial facilities will be noticed and will be asked to have their drivers use Gloria Rd. or the North Alta interchange.
 Funding source being sought out to pay for the signage that needs to go on the Freeway.

Update the Pavement Management Plan (PMP)
 Harris and Associates will be contracted to update the City’s PMP. • Send Fifth Street Truck Ban Notices to facilities in the Industrial Business Park
• Continue seeking grant funding
• Award Contract to update the Pavement Management Program • Generate a list of priority streets/areas
• Bid out the work for Fourth St.
• Work with Consultant to prepare bid documents for the work on pedestrian safety improvements for Fifth St. between Rincon Rd. and the US 101 Fifth St. Bridge.
• If Measure S were to pass, the City would receive approx. $800,000 in general fund monies
• A portion of funding could be used for road work
• An Oversight Committee would be formed to dictate how the funding gets allocated
• If it does not pass, we have to rely on what we have now, which means our streets and roads will continue to deteriorate making the work more costly in the future