Wastewater Program
1 2024 Wastewater Milestones
1. Secured IW Funding (July 2024)
2. Obtained IW Conveyance System Easements (June – October 2024)
3. Finalize Design/Bid the IW Conveyance System (May – August 2024)
4. Begin Construction of the IW Conveyance System (November 2024)
5. Finalize Design/Bid the IW Treatment Facility (October – December 2024)
6. Construction of the Emergency Infiltration Basin (November – December 2024)
7. Pursue SRF Planning Grant for MWWTP Upgrades (September 2024 – Present) 2 IW Funding Secured
3 $28.8 M SRF Loan Secured; 1.7% interest rate
$10 M Construction Loan Secured; 4.34%
IW Conveyance Easements
4 Four Temporary Construction Easements
Four Rights of Entry
Six Sewer Easements
Two Public Utility Easements
Finalize Design/Bid IW Conveyance
5 IW Conveyance Bid Opening: August 6, 2024
Five Bids Received: $7.6M - $14.3M
Award of Contract at September 3, 2024 Council Mtg
Contract Executed: September 24, 2024
Construction started: November 4, 2024
Construction of IW Conveyance
6 • 35 percent Complete
• 2,300 LF Pipeline Installed
• 5 Manholes Installed
• Completion: May 2025
Finalize Design/Bid IW Treatment Facility
7 Issued for Bid: January 15, 2025
Bid Opening: February 26, 2025
Award of Contract: March 17 Council Meeting
Anticipated Notice to Proceed: April 2025
Anticipated Completion: Spring 2027
MWWTP Emergency Infiltration Basin
8 Emergency Resolution Approved: December 11, 2024 with a budget of $950,000 Infiltration Basin Operational: December 24, 2024 with expected cost of $550,000 AWARD WINNING PROJECT!
Project of the Year - Environment
MWWTP Planning Grant
9 $300,000 SWRCB Grant Application Submitted
MWWTP Rehabilitation Planning Study
Application Review In Progress
2025 Wastewater Work Plan
1. Industrial Wastewater System
2. Municipal Wastewater System
3. Adopt Updated Sewer Ordinance with Pretreatment Program for Industrial Dischargers
10 Industrial Wastewater System
11 1. Complete IW Conveyance Project
2. Begin IW Treatment Facility Construction
3. Apply for RWQCB Discharge Permit for IWTF
Municipal Wastewater System
12 1. Clean, Video Inspect and Rehabilitate Existing 21” Sewer Trunk Main
2. Install Additional Groundwater Monitoring Wells at MWWTP
3. Begin MWWTP Rehabilitation Planning
4. Issue RFP for Wastewater Master Plan
5. Upgrade SCADA System
Adopt Updated Sewer Ordinance with
Pretreatment Program
13 Wastewater Program
14 Questions and Comments