Gonzales Community Center Complex
Monthly Progress Report: March 2025
Consultant: Harris & Associates
Overview
Harris & Associates provided Project and Construction Management (PMCM) services for the Gonzales Community Center Project between March 1 and March 31, 2025.

PMCM Services
Project and Construction management services included leading project related coordination meetings and managing correspondence with project stakeholders. Provided web-based project management services via Newforma, for project documentation distribution. Monitored construction process to verify conformity to the approved plans and specifications. Monitored expenditures and tracked various City monies and outside funding sources, including project grant reporting. Reviewed and processed project RFI’s and Submittals. Reviewed contractor look-ahead schedules. Coordinated project inspections as required by project needs. • Processed 4 Submittals (Submittal #248 – Submittal #251) • Processed 4 new RFI’s (RFI#096 – RFI#099)
• Managed 4 weekly construction project meetings
• Reviewed 4 look-ahead schedules provided by General Contractor • Harris is actively monitoring contractor labor compliance Inspections
• Daily Monitoring
o Prepared daily construction reports detailing the location and type of work performed by Contractor as well as crew size(s), reports documented equipment used and weather conditions.
▪ Provided daily construction monitoring and progress photos (18 site visits) • Special Inspections
o Processed one (1) Special inspection request (#60)
▪ Reinforcement placement verification: retaining wall footing, planter footing and seatwall footings
• Concrete placement observation and sampling, for retaining wall footing and one seatwall footing

Page 2 of 8 ends

Construction Progress Summary
During the month of March (2025), construction on the Gonzales Community Center project continued to advance steadily, maintaining alignment with the project’s baseline schedule. The project team celebrated completion of the building dry in milestone, marking a key achievement in the construction timeline.

Site Improvements
Site work continued to progress, specifically the exterior site concrete scope of work. Grade Break (concrete subcontractor) successfully installed reinforcement at the three courtyard seat walls, one of the two courtyard planter walls, and the retaining wall along the western boundary of the property. The retaining wall footing and one of the three seatwall footings were poured this month. The remaining seatwall footings and planter footing will be poured next month, along with the vertical section of the retaining wall. Additionally Grade Break focused on sawcutting weakened plane joints throughout the concrete flatwork that has been poured to date.

Collins Electric’s site work efforts this month focused on pulling wire for exterior lighting and site power.

Building Exterior
On the building exterior, Royal Glass focused on installation of glazing at the curtain wall and storefront systems; followed by pressure bar and beauty cap installation. The building is now protected from the elements, which was celebrated by the project team, by hosting a small gathering at the jobsite for project stakeholders, donors and the local community. Preparation for exterior finishes continued, with Rua & Sons continuing to install wall flashing at the exterior EIFS walls, and Brady West continuing to install the EIFS system, starting on the exterior, North elevation.

Building Interior
Interior construction activities focused on critical drywall work and electrical work. Collins installed sub panels throughout the building and continued to pull wire. Drywall has been installed on both sides of the interior walls and the screw inspections have been completed, with exception of two partial hard lid ceilings at restrooms A108 and A109, which will be completed after pending light fixtures are installed. Lastly, countertop and casework in-wall bracket supports were installed this month.

Continuous multi-discipline coordination will continue moving forward, to ensure efficiency in execution of upcoming work.

Please refer to the images provided on the following pages for visual progress of the work completed this month.

Page 3 of 8 ends

Retaining wall footing reinforcement and concrete placement (Northwest side of the property).

Seatwall footing reinforcement (South of the Library).

Page 4 of 8 ends

Saw cutting site concrete joints.

Wiring EV Transformer TEV & disconnect switch.

Page 5 of 8 ends

Glazing installation (Northwest Corner, Teen Lounge).

Building dry-in milestone ceremony.

Page 6 of 8 ends

EIFS insulation installation (Northeast corner of Building A, Library).

Interior drywall progress installation (Library).

Page 7 of 8 ends

Interior drywall and DensArmor installation at restroom A108.

Interior drywall installation at Teen Lounge.

Page 8 of 8 ends

Casework shelving supports (Teen Innovation Center, East wall).

Electrical panel, main electrical room.