Community Center Complex Progress Report

Gonzales City Council
May 19, 2025

Document
Community Center Complex Progress Report
Meeting
May 19, 2025
Body
Gonzales City Council
Original file
957 KB
Text extracted from the city's file for reading and search. Open the original on gonzalesca.iqm2.com. That file is the official record.

Dennis & Janice Caprara
Community Center Complex GONZALES COMMUNITY CENTER COMPLEX AGENDA
ITEM

1. Project Milestones

2. May 2025 Construction Progress Update

3. Schedule

4. Community Engagement

5. Q&A
Overview
Milestones Completed To Date
● Installation of Underground wet utilities
(storm, sewer, water)
● Topout
● Mechanical, Electrical, Plumbing and
Fire Sprinkler Rough Complete
● Storefront and Curtainwall installation
● TPO and Metal Roof Complete
● Building Dry-in
May 2025 Construction Update
● Site Improvements
○ Site concrete placement is underway
○ Placed concrete seat walls at courtyard
○ Placed one of the two concrete planters at the courtyard ○ PG&E elec. primary conduit extension across Fifth Street ○ Driveway and parking lot site light poles
○ EV Charger transformer installation
Planter wall placement Site concrete placement PG&E elec. trench at Fifth St.

Formwork at Amphitheater Parking lot site lights EV transformer switch May 2025 Construction Progress Update
● Building Exterior
○ Pressure bar and beauty cap installation at storefront systems ○ Exterior flashing installation complete
○ EIFS finish system installation is in progress
■ Base coat is installed
■ Finish coat is 80% complete
Glazing pressure cap Flashing at EIFS walls EIFS insulation installation EIFS base coat (North elev.) EIFS finish coat (South elev.) EIFS finish coat (South elev.) May 2025 Construction Progress Update
● Building Interior
○ Installation of electrical subpanels
○ Casework in-wall supports are installed
○ Drywall installed on both sides of interior walls
○ Drywall screw inspections have been completed
○ Drywall taping and finishing is in progress
○ Casework installation is in progress
○ Ceramic tile work at restrooms is in progress
■ Levelling and waterproofing complete
■ Wall and floor tile installed at all single occupancy Family restrooms
■ Wall and floor tile is in progress at the Men’s and Women’s restrooms, at the courtyard
Ceramic wall & floor tile Drywall taping (Teen Lounge) Taping/mudding (Library) Casework @ Library staff area Casework @ Teen Classroom Drywall finishing at Library

Schedule
● Upcoming Milestones
○ Landscape Substantial Completion: July 11, 2025
○ Permanent Power: October 27, 2025
○ Substantial Completion: November 17, 2025
● Potential Challenges and Risks
○ Main switchgear (MSB) delivery
■ ETA: 07/23/2025
○ PG&E Permanent Power
Community Engagement
● Upcoming Activities
○ Community center project tours for local
Gonzales High School Students
○ Construction career presentations for
Gonzales High and Fairview middle school
students

QUESTIONS