Task Order #3 with Dudek for Design Support Services

Gonzales City Council
June 16, 2025

Document
Task Order #3 with Dudek for Design Support Services
Meeting
June 16, 2025
Body
Gonzales City Council
Original file
1.3 MB
Text extracted from the city's file for reading and search. Open the original on gonzalesca.iqm2.com. That file is the official record.

Task Order No. 3 to Consulting Services Agreement Between City of Gonzales and Dudek Consulting for Design Support Services This is an Amendment to the Consulting Services Agreement dated June 17, 2024 between the City of Gonzales, a municipal corporation of the State of California ("City") and Dudek ("Consultant”) for Wastewater Design Services.

City and Consultant agree to the following changes to the Agreement:

Section 1 - Services
Services will now include Design Support Services during Construction of the Industrial Wastewater Treatment Facility as outlined in Dudek’s February 28, 2025 letter proposal (copy attached).

Section 2 - Compensation
City will pay Consultant an additional sum of $1,342,037 on an hourly not-to-exceed basis.

In all other respects, the terms of the Agreement shall remain in effect.

CITY CONSULTANT
City of Gonzales, a municipal corporation Dudek
_____________________________ _____________________________ Carmen Gil, City Manager Mike Metts, Principal
Date Signed: __________________ Date Signed: __________________ June 10, 2025 February 28, 2025
Patrick Dobbins, PE
City of Gonzales
[email protected]
Subject: Proposal for Engineering Support Services During Construction for Industrial Wastewater Treatment Facility Project
Dear Patrick Dobbins:

We are pleased to provide this proposal for engineering support services during construction (ESDC) for the Industrial Wastewater Treatment Facility (IWTF) project. Included in this proposal are the following sections:

1. General Information, providing general information and primary point of contact

2. Project Understanding and Approach, describing project background and objectives

3. Scope of Work, defining specific work elements

4. Fee Proposal, quantifying our anticipated level of effort Our proposal demonstrates our thorough understanding of your project goals and offers a comprehensive approach and dedicated project team for its successful completion. 1 General Information
The Dudek team presented within this proposal has the resources to perform the work required for each of the Project Tasks, as included in the Project Scope of Work. Tasks to be completed by subcontractors are also defined in the Scope of Work. Subcontractors are the same as utilized during the design phases of the project. The primary point of contact for proposal and project correspondence is Kate Palmer, P.E., Principal Engineer, available at 760.479.4160 and [email protected].
2 Project Understanding and Approach
The final design bid documents were completed by the Dudek team and advertised for bidding for the City of Gonzales (City) Industrial Wastewater Treatment Facility. Bidding of the project was completed on February 26, 2025.

TO: PATRICK DOBBINS
SUBJECT: PROPOSAL FOR ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION FOR INDUSTRIAL

WASTEWATER TREATMENT FACILITY
FEBRRUARY 2025 2
Following review of the bids and confirmation of the lowest responsive and qualified contractor, construction is expected to start in June 2025 (assumes NTP March 2025).

As Engineer of Record (EOR), Dudek understands the full scope of project construction activities for the project.

Supply chain issues may continue to impact the ability of the contractor to successfully complete construction within the anticipated contract duration. To assist in successful completion of the contract within the contract duration, Dudek will work with the City to prioritize submittal review of materials with the longest lead times, thereby allowing those to be ordered as soon as possible. These specific topics and any other critical path items may be discussed at the kick-off meeting to collaborate on potential solutions and mitigate potential delays. 3 Scope of Services
Dudek will follow the detailed scope of work tasks outlined below. In preparation, Dudek assumes that the City will employ the services of a construction management (CM) team that will provide field staff to the construction site daily, and thus we have not included scope/hours for a daily onsite presence. Use of a CM will assure constant communication between the contractor, the City and EOR, as well as assure smoother completion of construction activities. Dudek assumes that environmental monitoring services (i.e., cultural monitoring) will be provided under separate contract.

In accordance with the City’s request, Dudek proposes to provide the following services:

IWTF Engineering Services During Construction
TASK 1 PROJECT MANAGEMENT
Dudek will conduct effective project administration and management including the preparation and distribution of monthly progress reports including progress to date, potential completion issues, and anticipated next steps in progress. Progress reports will also include budget status and project schedule updates. Dudek is providing budget on this item based on a thirty (30) month project duration.

Task 1 Deliverables:
• (30) Progress Reports
TASK 2 ENGINEERING SERVICES DURING CONSTRUCTION
Task 2.1 Pre-Construction Meeting
Dudek will attend the Pre-Construction Meeting, which is assumed to occur at the City offices. The meeting is assumed to be conducted by the City’s Construction Manager. This task also includes finalization of conformed documents.

TO: PATRICK DOBBINS
SUBJECT: PROPOSAL FOR ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION FOR INDUSTRIAL

WASTEWATER TREATMENT FACILITY
FEBRRUARY 2025 3
Task 2.1 Deliverables:
• Conformed Documents (PDF)
Task 2.2 RFIs and Design Clarifications
Dudek will provide RFI and Design Clarifications for the project that include:
a. Provide responses for up to one hundred eighty-five (185) requests for information (RFIs) and/or requests for clarification (RFCs). At the City’s discretion, the Dudek team will provide responses to RFIs and RFCs in letter form or e-mail form. Dudek anticipates the following RFIs. o (100) Civil and Mechanical
o (30) Architectural
o (50) Electrical
o (20) Structural
b. Dudek assumes RFIs from the Contractor will be formally submitted to the Construction Manager.

Questions requiring responses from the design team will be forwarded to the Dudek Project Manager for distribution and response.

Task 2.2 Deliverables:
• (185) RFI Responses
Task 2.3 Shop Drawings and Submittal Reviews
Dudek will provide shop drawings and submittal review to include:
a. Review and process up to two hundred seventy-five (275) shop drawings and submittals and up to one hundred (100) resubmittals. Dudek anticipates the following submittals. o (150) Civil and Mechanical
o (50) Architectural
o (50) Electrical
o (25) Structural
b. Dudek assumes submittals and shop drawings from the Contractor will be formally submitted to the Construction Manager who will forward to the Dudek Project Manager for distribution and response Task 2,3 Deliverables:
• (275) Submittal Responses
• (100) Resubmittal Responses
Task 2.4 Site Visits / Onsite Construction Meetings
Dudek will attend onsite construction meetings and site visits at City request to observe specific conditions or situations for which design engineer input would facilitate developing an appropriate response to the Contractor.

We have assumed a total of twelve (12) onsite construction meetings and four (4) site visits by one or more TO: PATRICK DOBBINS
SUBJECT: PROPOSAL FOR ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION FOR INDUSTRIAL

WASTEWATER TREATMENT FACILITY
FEBRRUARY 2025 4
members of the design team. Structural engineer (Kelsey Structural) will attend up to two (2) on-site construction meetings. Electrical engineer (DTN) will attend up to five (5) on-site construction meetings and four (4) separate site visits. Architect (MBN) will attend one (1) site visit.

Kelsey Structural, will perform a maximum of six (6) structural observations during construction per California Building Code requirements to verify general conformance with the contract documents. A written structural observation report will be provided with comments and action items to be addressed by the Contractor.

Suggested observations would occur at the following construction milestones:
• Prior to cast-in-place concrete pours to observe dimensioning, rebar placement, waterstops, embedments, etc.
• Prior to CMU wall grouting to observe dimensioning, rebar placement, embedments, etc. • During structural steel erection to observe dimensioning, member sizing, bolting, welding, etc.

Task 2.8 Deliverables:
• (4) Field Notes
• Structural Observations Report
Task 2.5 Construction Progress Meetings
Dudek will attend weekly construction progress meetings virtually throughout the duration of the project. Dudek attendance/participation at one hundred four (104) meetings is included. Dudek attendance includes the Dudek project manager and the appropriate team member(s) based on the issue(s) being discussed. Dudek assumes weekly construction meetings will be organized and documented by the Construction Manager. Kelsey Structural will participate in a maximum of eight (8) virtual construction meetings. DTN will participate in up to twelve (12) virtual construction meetings. MBN will participate in up to nine (9) virtual construction meetings.

Task 2.6 Change Order Assistance
Dudek will assist City staff on change order reviews. We are allocating budget to be used for up to fifteen (15) change order reviews at the request and direction of the City. It is assumed that the Construction Manager will prepare, and review construction change orders, and Dudek will assist, as necessary and requested. Kelsey Structural will review and respond to a maximum of one (1) change order related to structural work. DTN will review and respond to up to fifteen (15) change orders related to electrical work. MBN will review and assist with up to one (1) change order related to architecture / HVAC / plumbing work.

Task 2.7 Design Deviation Review
Dudek will assist the City with evaluation of Contractor-proposed design deviations and substitutions to support the activities of the Construction Manager. Dudek will evaluate the proposed design changes relative to consistency with the original design intention and capability. As the extent and nature of any Contractor-proposed design deviations are currently undefined, an allowance is assumed for this contract item. Services will be provided at City direction within the available allowance.

TO: PATRICK DOBBINS
SUBJECT: PROPOSAL FOR ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION FOR INDUSTRIAL

WASTEWATER TREATMENT FACILITY
FEBRRUARY 2025 5
Task 2.8 Construction Punch List Assistance
Dudek will assist the Construction Manager with punch list resolution including the following:
a. One or more members of the Dudek Team joining the Construction Manager and/or City staff on walkthroughs to confirm that the work was constructed per the design documents, and if not, what could be done to resolve observed deficiencies.
b. As the extent and nature of the Punch List is currently undefined, an allowance is assumed for this contract item. Services will be provided at City direction within the available allowance.

Task 2.9 Deliverables:
• Construction Punch List Field Notes
Task 2.9 Record Drawing Preparation
Dudek will provide assistance to the City for preparation of record drawings:
a. Following construction, Dudek will prepare a complete set of record drawings. b. The drawings will be prepared based on field changes and redlines documented by the Construction Manager and the Contractor, and changes resulting from RFIs, clarifications and contract change orders. c. Dudek will provide electronic files (PDF and AutoCAD) of the revisions. Dudek will provide the files in electronic format only (including PDF and AutoCAD formats) and no hard copies are included.

Task 2.10 Deliverables:
• Record (as-built) Drawings (PDF and .dwg)
Assumptions

1. Change Order Support – Engineering support for change orders is limited to evaluation of design-related impacts and does not include negotiation on behalf of the owner.

2. Design Deviation Reviews – Only deviations that impact the approved design will be reviewed; minor changes that do not affect performance or compliance are assumed to be managed by the construction manager.

3. Record Drawing Preparation – Record drawings will be based on contractor-provided redlines and field verification during final site visits.

4. Final Inspection and Punch List – The punch list review will be performed once substantial completion is achieved and will not include contractor supervision for corrective work.

Exclusions

1. Construction Management – Full-time onsite construction management and inspection services are not included.

2. Quality Control/Testing – Field testing, quality control, and materials testing are excluded.

TO: PATRICK DOBBINS
SUBJECT: PROPOSAL FOR ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION FOR INDUSTRIAL

WASTEWATER TREATMENT FACILITY
FEBRRUARY 2025 6

3. Third-Party Surveys – Surveying, staking, or as-built verification by the engineer is excluded.

4. Record Drawing Verification – The engineer will not independently verify as-built conditions beyond provided contractor markups.

5. Safety Compliance – The engineer is not responsible for site safety, OSHA compliance, or contractor worksite conditions.

6. Operations & Maintenance – Development of O&M manuals, startup assistance, and training for plant operators are not included.

7. Post-Construction Support – Services beyond the final completion phase, including warranty period support or troubleshooting operational issues, are excluded unless otherwise agreed upon. 4 Fee Proposal
Dudek proposes a not-to-exceed project budget of $1,342,037 considering a 15% contingency as requested by the City for completion of the above Tasks 1 through 2 for the Industrial Wastewater Treatment Facility Project.

Full breakdowns of estimated labor hours by category for each task are attached.

We look forward to continuing our work on this project with you and the City and to providing the services described herein. Please do not hesitate to call or email me (760.479.4160 or [email protected]) with any questions you might have about our proposal.

Respectfully Submitted,
__________________________________ __________________________________ D. Michael Metts, P.E. Kate Palmer, P.E.

Chief Engineer Principal Engineer
D. Michael Metts is authorized to sign on behalf of Dudek.

City of Gonzales
Industrial Wastewater Treatment FacilityEngineering Services During Construction (ESDC) DUDEK FEE ESTIMATEFebruary 28, 2025
Project Team Role: QA/QC
Program
Manager IWTF Manager
Senior
Engineer
Project
Engineer
Electrical
Engineer CAD Designer Admin
Team Member: Metts Palmer Deibert
Tran
Diaz
Chuang
Dhanens Schneider Hunter Kinney TOTAL

DUDEK DUDEK LABOR OTHER DIRECT
Billable Rate : $320 $290 $275 $250 $230 $290 $200 $160 HOURS COSTS Hours Fee Hours Fee Hours Fee COSTS TOTAL FEE Task 1 Project Management
1 Project Management 24 180 80 80 364 $ 94,680 364 $ 94,680 Subtotal Task 1 24 180 80 80 364 $ 94,680 364 $ - $ 94,680 Task 2 Engineering Services During Construction (ESDC)

2.1 Pre-Construction Meeting / Conformed Documents 24 24 60 40 148 $ 34,400 $ - $ 60 - $ 13,690 208 $ 5,000 $ 53,090

2.2 RFIs and Design Clarifications (assume 185 RFIs) 20 200 200 120 16 556 $ 143,640 30 $ 6,509 31 $ 7,050 66 $ 17,296 683 $ 174,495

2.3 Shop Drawings and Submittal Reviews (assume 275 Submittals/100 Resubmittals) 40 225 300 300 40 905 $ 230,275 85 $ 18,285 139 $ 29,257 320 $ 86,940 1449 $ 364,757

2.4 Site Visits / Onsite Meetings 8 80 50 72 210 $ 53,620 44 $ 9,798 28 $ 7,629 80 $ 28,819 362 $ 20,000 $ 119,866

2.5 Construction Progress Meetings (Assume 104 virtual meetings) 4 24 104 104 236 $ 62,840 8 $ 1,932 9 $ 2,031 40 $ 12,972 293 $ 79,775

2.6 Change Order Assistance (assume 15 change orders) 16 60 60 60 196 $ 50,420 20 $ 4,002 2 $ 44 453 $ 12,696 262 $ 67,571

2.7 Design Deviation Review 4 32 40 40 4 80 200 $ 46,440 8 $ 1,840 9 $ 2,029 80 $ 19,826 297 $ 70,135

2.8 Construction Punch List Assistance 12 16 18 46 $ 11,440 4 $ 36 920 $ 8,632 46 $ 12,006 132 $ 2,500 $ 35,498

2.9 Record Drawing Preparation 2 8 40 40 24 220 334 $ 73,000 26 $ 4,922 31 $ 108 4,471 $ 19,729 499 $ 5,000 $ 107,123 Subtotal Task 2 94 24 745 834 710 84 340 2831 $ 706,075 225 $ 48,208 285 $ 61,551 844 $ 223,974 4185 $ 32,500 $ 1,072,308 Total Non-Optional Hours and Fee 118 204 825 834 710 84 340 80 3195 800,755 $ 225 $ 48,208 285 $ 61,551 844 223,974 $ 4549 $ 32,500 $ 1,166,988 Percent of Hours: 4% 6% 26% 26% 22% 3% 11% 3% 100% Contingency $1,342,037

TOTAL HOURS
Structural Engineering
Kelsey Structural
HVAC, Plumbing, and
Architectural
MBN
Electrical Engineering
DTN
Subconsultant Fees