GONZALES COMMUNITY CENTER COMPLEX
OZALES MAN
WRNS
• Harris & Associates STUDIO
Сок і сого • Солов OTTO
CONSTRUCTION
Overview
1. Construction Progress Update
2. Schedule Forecast + Milestones
3. Q&A
October 2025 Construction Update
• Site Improvements
Steel canopy/awning at Courtyard is complete
Site concrete is substantially complete
• Underground irrigation is 85% complete
Building monument sign footing is complete
O Trash enclosure steel and CMU is complete
Canopy installed, ready for paint.
Concrete sitework substantially complete.
October 2025 Construction Update
• Building Exterior
• High Pressure Laminate (HPL) panels are complete
Roof Fascia is substantially complete
Exterior Louvers are complete
Card readers are installed
Drinking Fountains + Water Bottle Filling stations are installed HPL Panels and Fascia
substantially complete
October 2025 Construction Update
• Building Interior
Interior lighting is substantially complete
T-bar ceiling grid and acoustical ceiling tiles are complete Acoustical ceiling baffles are complete
Interior ceramic tile installation is complete
Electrical, mechanical and plumbing finishes are 85% complete Interior paint is complete
O Low Voltage cabling installation is substantially complete O Restroom accessories are complete
Interior doors and hardware 90% complete
Interior painting/flooring Interior painting/flooring Lights/flooring (Teen center) (Teen Lounge) (Library)
Interior lights being installed Restroom accessories installed Plumbing finishes
Schedule Forecast + Milestones
• Recent Milestones
o l PG&E Permanent Power Established: August 25, 2025
• Upcoming Milestones
Landscape Substantial Completion: November 3, 2025
Temporary Certificate of Occupancy: November 4, 2025
Substantial Completion: November 4, 2025
o l Final Completion: December 19, 2025
• Potential Challenges and Risks
• Weather
QUESTIONS