Cities Index.
Community Center Progress Report

Gonzales City Council
October 6, 2025

Document
Community Center Progress Report
Meeting
October 6, 2025
Body
Gonzales City Council
Original file
1.2 MB
Text extracted from the city's file for reading and search. Open the original on gonzalesca.iqm2.com. That file is the official record.

GONZALES COMMUNITY CENTER COMPLEX

OZALES MAN
WRNS
• Harris & Associates STUDIO
Сок і сого • Солов OTTO

CONSTRUCTION
Overview

1. Construction Progress Update

2. Schedule Forecast + Milestones

3. Q&A
October 2025 Construction Update
• Site Improvements
Steel canopy/awning at Courtyard is complete
Site concrete is substantially complete
• Underground irrigation is 85% complete
Building monument sign footing is complete
O Trash enclosure steel and CMU is complete
Canopy installed, ready for paint.

Concrete sitework substantially complete.

October 2025 Construction Update
• Building Exterior
• High Pressure Laminate (HPL) panels are complete
Roof Fascia is substantially complete
Exterior Louvers are complete
Card readers are installed
Drinking Fountains + Water Bottle Filling stations are installed HPL Panels and Fascia
substantially complete
October 2025 Construction Update
• Building Interior
Interior lighting is substantially complete
T-bar ceiling grid and acoustical ceiling tiles are complete Acoustical ceiling baffles are complete
Interior ceramic tile installation is complete
Electrical, mechanical and plumbing finishes are 85% complete Interior paint is complete
O Low Voltage cabling installation is substantially complete O Restroom accessories are complete
Interior doors and hardware 90% complete
Interior painting/flooring Interior painting/flooring Lights/flooring (Teen center) (Teen Lounge) (Library)
Interior lights being installed Restroom accessories installed Plumbing finishes

Schedule Forecast + Milestones
• Recent Milestones
o l PG&E Permanent Power Established: August 25, 2025
• Upcoming Milestones
Landscape Substantial Completion: November 3, 2025
Temporary Certificate of Occupancy: November 4, 2025
Substantial Completion: November 4, 2025
o l Final Completion: December 19, 2025
• Potential Challenges and Risks
• Weather

QUESTIONS

← All documents from this meeting