Agenda Item No. 11
CITY COUNCIL STAFF REPORT
TO: Honorable Mayor and City Council DATE: September 23, 2024 FROM: Matthew Bronson, City Manager
PREPARED BY: Greg Ray, Public Works Director/City Engineer SUBJECT: West Grand Avenue Streetscape Project Change Order Approval
RECOMMENDATION
Authorize the City Manager to approve a change order for the West Grand Avenue Streetscape Project (CIP 2287) related to necessary sewer main work.
BACKGROUND
The City has placed significant emphasis on improving the West Grand Avenue corridor as part of the “Economic Development and Community Promotion” Major City Goal and the West Grand Avenue Master Plan adopted in 2011. Consistent with this Master Plan, on February 26, 2024 the Council approved a construction contract for the West Grand Avenue Streetscape Project (CIP 2287) which includes the following items:
• Storm drain installation
• Pedestrian improvements such as curb ramps, bulb outs, pedestrian beacons and sidewalk improvements at select locations
• Bike lanes including green striping at intersections
• Decorative concrete at crosswalks
• Drought-tolerant landscaped center medians and street trees • Enhanced lighting including pedestrian level streetlights • Pavement rehabilitation
During the installation of the storm drain, the project contractor discovered a significant conflict with the sewer main located in the intersection of 4th Street and West Grand Avenue. This sewer main needs to be upsized to support current and future community needs and is included in an upcoming Sewer Upgrade project (CIP 5002) which is on hold pending the outcome of Measure G-24 repealing the water and sewer rate structure. However, given the impacts of this sewer main to the West Grand Avenue Streetscape Project, staff is recommending carrying out this sewer main work now using the project contractor through a change order to eliminate the utility conflict and avoid cutting into the intersection to do this work after the street repair work was completed.
FISCAL IMPACT
The change order for the sewer main work is approximately $705,585 which is similar to the anticipated cost of doing this work through a separate project. Completing this portion of CIP 5002 now will reduce the total project cost estimated at $3.6 million and avoid duplicative efforts when the remainder of CIP 5002 is undertaken. Staff recommends using Wastewater Fund and Wastewater DIF balance to cover the estimated costs. Staff would note that this funding would Staff Report: West Grand Avenue Streetscape Project Change Order Approval Page 2 September 23, 2024
represent a significant portion of available capital improvement funding from the Wastewater Fund particularly if Measure G-24 passes and sewer rates are lowered back to 2021 levels.
ALTERNATIVES
The Council has the following alternatives to consider:
1. Authorize the City Manager to approve a change order for the West Grand Avenue Streetscape Project (CIP 2287); or
2. Provide staff with alternate direction.
PUBLIC NOTIFICATION
The agenda was posted in accordance with the Brown Act.
Attachments
1. Sewer main change order
City of Grover Beach - Department of Public Works
I CONTRACT CHANGE ORDER
CCO Number CIP Number
2 2287
CONTRACTOR:
Engineer
Change Order Re uested b : Project Name
Contractor West Grand Avenue Streetscape 4th - 8th
You are directed to do the following described work not included in the plans and specification for this contract. Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the contractor and his subcontractors and suppliers for all costs and markup directly or indirectly, including extended overhead, attributable to the change order, for all delays related thereto, and for performance of the change within the time frame stated. Contractor in addition agrees the adjustment to compensation to the base agreement as manifested by this change order represents any and all cost whatsoever related to cumulative impacts or any synergistic effects, whether known or unknown, that may arise out of the work performed under this contract or in conjunction with other work or change orders approved under this agreement. Contractor waives any right to request additional compensation for any reason other than agreed to in accordance with this change order.
NOTE: this change order is not effective until all approval signatures are received.
WORK DESCRIPTION
This change order addresses a Increase In Contract Quantities at Agreed Unit Prices - The original project as bid assumed that the Sanitary Sewer Line in 4th Street would be lowered prior to the start of the project. Since this was not achieved, the lowering 370 lf of the sanitary sewer line in 4th Street will be included as a change order to the Streetscape project. - The Bid Additive work for lowering of the Sewer line in 4th Street includes the addition of work items for Temporary Traffic Control, Survey Control & Layout, Sheeting/Shoring/Bracing & Excavation Safety Measures, Temporary Bypassing, Open Trench installation of 12" SOR 35 Sewer Pipe, Connections to existing facilities, Sewer lateral Reconnection to PVC Sewer Pipe, 6-lnch Sewer lateral Reconnection, Sewer lateral Abandonment, Subgrade repair with 6" Aggregate Base, Pavement Restoration (HMA), Traffic Striping & Markers, Vehicle Detectors, Water Pollution Control Plan, and an upgrade of the sewer pipe to C900.
Payment to the Contractor is based on actual quantities for each type of work as determined by the Field Engineer from measured area quantities. The Engineer will verify the quantities for payment based on data submitted by the Contractor and the Engineer's written determination shall be final.
Total Net Cost of this Change $ 705,585.00
Net Cost of this Change Order: I X I increase I I decrease Net Time for this Change Order: 30 Working Days I X I increase I I decrease CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT PRICE - Working Days Original Contract Price: $ 6,370,035.96 Original Contract Time: 155 Net Change from Previous Change Orders: $ (231,303.19) Net Change from Previous Change Orders: 0 Net Change from this Change Order: $ 705,585.00 Net Change from this Change Order: 30 New Contract Price: $ 6,844,317.77 New Contract Time: 185
ENGINEER APPROVAL
SIGNATURE : r
PRINT NAME & TITLEI IDATE
I DEPARTMENT HEAD APPROVAL
SIGNATURE: !'
PRINT NAME & TITLE) I
DATE
ICITY MANAGER APPROVAL
SIGNATURE : !'PRINT NAME & TITLE) IDATE
We the undersigned contractor, have given careful consideration to the change proposed and agree, if this proposal is approved, that we will provide all equipment, furnish the materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the price shown above.
CONTRACTOR ACCEPTANCE
SIGNATURE : I
DATE
9 /17/
2024
I
I
Attachment 1
MEASUREMENT AND PAYMENT 012000-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT - 24 Jul 2024
SECTION 012000 MEASUREMENT AND PAYMENT
1.01 WORK LISTED IN THE SCHEDULE OF WORK ITEMS
A. Work under this contract will be paid on a unit price or lump-sum basis as outlined on the Bid Form for the quantity of work installed.
B. The unit prices and lump-sum prices include full compensation for furnishing the labor, materials, tools, and equipment and performing all work involved to complete the work included in the contract documents.
C. The application for payment will be for a specific item based on the percentage completed or quantity installed. The percentage complete will be based on the value of the partially completed work relative to the value of the item when entirely completed and ready for service.
1.02 WORK NOT LISTED IN THE SCHEDULE OF WORK ITEMS
A. Items in the Special Provisions, general requirements, and specifications which are not listed in the schedule of work items of the Bid Form are, in general, applicable to more than one listed work item, and no separate work item is provided therefor. Include the cost of work not listed but necessary to complete the project designated in the contract documents in the various listed work items of the Bid Form.
B. The bids for the work are intended to establish a total cost for the work in its entirety. Should the Contractor feel that the cost for the work has not been established by specific items in the Bid Form, include the cost for that work in some related bid item so that the Proposal for the project reflects the total cost for completing the work in its entirety.
1.03 FURNISHING AND MAINTAINING DEWATERING AND UNWATERING
FACILITIES
Furnishing and maintaining dewatering and unwatering facilities for diversion and control of water during the contract period will not be paid as a separate item. The costs of furnishing and maintaining such facilities shall be included in the various listed work items of the Bid Form for which the dewatering and unwatering facilities are required.
1.04 BID ITEMS
BID ITEM 1--TEMPORARY TRAFFIC CONTROL
Measurement for payment for traffic control shall be made on a percent complete basis, based on the lump sum amount for this item, and shall include full compensation for furnishing the labor, materials, tools, and equipment and doing MEASUREMENT AND PAYMENT 012000-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT - 24 Jul 2024
all the work involved to implement Traffic regulation/control throughout the project duration in accordance with the Contract Documents, City standards, and Caltrans standards.
BID ITEM 2--SHEETING, SHORING, BRACING, AND EXCAVATION SAFETY
MEASURES
Measurement for payment for sheeting, shoring, bracing, and excavation safety measures shall be on a percent complete basis based on the lump sum amount and shall include full compensation for furnishing the labor, materials, tools, equipment, and performing all work involved for providing sheeting and shoring and bracing for the protection of life and limb and protection of existing utilities, and shall include, but is not limited to: complying with all applicable federal, state, and local regulations; design of shoring and/or bracing by a civil/structural engineer as required; providing jacks, trench boxes, sheets, shoring, piles, etc., as required to comply with the specifications, regulations and the drawings; and protecting in place and bracing existing utilities.
BID ITEM 3--TEMPORARY BYPASSING
Measurement for payment for temporary bypassing shall be made on a percent complete basis, based on the lump sum amount for this item, and shall include full compensation for furnishing the labor, materials, tools, and equipment and performing all work involved to implement Temporary Sewage Bypass throughout the project duration in accordance with the Contract Documents including, but not limited to: Installing, operating, and maintaining all power, primary and standby pumps; appurtenances; bypass piping; temporary piping; providing pumper trucks; clean up in the event of a spill; monitoring of bypass equipment; and all other work necessary to maintain existing sewer flows and services around work areas.
BID ITEM 4--OPEN-TRENCH INSTALLATION OF 12 SDR 35 SEWER PIPE STA 1+25.51 TO 3+56.90
Measurement for payment for open- 35 sewer pipe
shall be on a lineal foot basis and shall include full compensation for furnishing the labor, materials, tools, equipment, and performing all work involved with installing the pipeline and appurtenances from STA 1+25.51 to STA 3+56.90. This includes but is not limited to pipe, fittings, wyes, trench excavation, erosion control, pipe bedding, trench backfill and compaction, slurry backfill, disposal of trench materials including asphalt, additional utility investigation, protecting existing facilities, driveway demolition and replacement, and furnishing all labor, materials, tools, and equipment associated with the installation of the PVC (SDR 35) sewer line.
BID ITEM 5--OPEN-TRENCH INSTALLATION
STA 3+56.90 TO 7+41.96
MEASUREMENT AND PAYMENT 012000-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT - 24 Jul 2024
Measurement for payment for open- sewer pipe
shall be on a lineal foot basis and shall include full compensation for furnishing the labor, materials, tools, equipment, and performing all work involved with installing the pipeline and appurtenances from STA 3+56.90 to STA 7+41.96. This includes but is not limited to pipe, fittings, wyes, trench excavation, erosion control, pipe bedding, trench backfill and compaction, slurry backfill, disposal of trench materials including asphalt, additional utility investigation, protecting existing facilities, driveway demolition and replacement, and furnishing all labor, materials, tools, and equipment associated with the installation of the PVC (SDR 35) sewer line.
BID ITEM 6--CONNECTION AT STA 1+25.51
Measurement for payment for the connection at STA 1+25.51 shall be made on a lump sum basis, and shall include all costs for furnishing all labor, materials, and equipment to install one (1) new manhole, perform the manhole connection, and channel and shelf forming of the manhole base.
BID ITEM 7--CONNECTION AT STA 3+56.90
Measurement for payment for the connection at STA 3+56.90 shall be made on a lump sum basis, and shall include all costs for furnishing all labor, materials, and equipment to install one (1) new drop manhole, perform the manhole connection, and channel and shelf forming as shown on Detail 1 Sheet C-401 in the Drawings.
BID ITEM 8--CONNECTION AT STA 7+42
Measurement for payment for the connection at STA 7+42 shall be made on a lump sum basis, and shall include all costs for furnishing all labor, materials, and equipment to install one (1) new drop manhole, perform the manhole connection, and channel and shelf forming as shown on Detail 2 Sheet C-401 in the Drawings.
BID ITEM 9--SEWER LATERAL RECONNECTION TO PVC SEWER PIPE Measurement for payment for sewer lateral reconnections to PVC sewer pipe shall be made on a unit price per each lateral connection, which price shall include all costs for furnishing the labor, materials, tools, equipment, and performing all work involved with reconnection of existing service laterals. This includes but is not limited to pipe, fittings, wyes, trench excavation, erosion control, pipe bedding, trench backfill and compaction, slurry backfill, disposal of trench materials, removal and restoration of asphalt pavement, and protecting existing facilities.
BID ITEM 10--6-INCH SEWER LATERAL CONNECTION FOR FUTURE PVC SEWER PIPE AT STA 6+25
Measurement for payment for the 6-inch sewer lateral connection for future PVC pipe shall be made on a unit price per each wye, fittings, spool and cap for the future 6-inch lateral connection, which price shall include all costs for furnishing MEASUREMENT AND PAYMENT 012000-4
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT - 24 Jul 2024
the labor, materials, tools, equipment, and performing all work involved with installation of fittings for the future service lateral. This includes but is not limited to pipe, fittings, cap, trench excavation, erosion control, pipe bedding, trench backfill and compaction, slurry backfill, disposal of trench materials, additional utility investigation, and protecting existing facilities.
BID ITEM 11--SEWER LATERAL ABANDONMENT
Measurement for payment for sewer lateral abandonment shall be made on a lump sum basis and shall include all costs for furnishing all labor, materials, and equipment to abandon sewer laterals designated for abandonment in the Drawings as detailed on Detail 3 Sheet C-501 in the Drawings.
BID ITEM 12--PAVEMENT RESTORATION
Measurement for payment for pavement trench repair shall be made on a per ton basis assuming up to a 3-ft wide trench and 8 foot by 8 foot area for new manholes with a full pavement repair section. The minimum asphalt pave back over the trench will be the thickness of the existing asphalt plus 1-inch with a grind and overlay tee section per City Standard Detail W.8. The tee section shall extend to the edge of existing center turn lane inside the striping per Plan Sheets C-101 and C-102. The existing asphalt section is assumed to be 4-inches thick. Work shall include full compensation for furnishing the labor, materials, tools, and equipment and performing all work involved in accordance with the Contract Documents including but not limited to removal and disposal of existing pavement, secondary saw cutting, removal and disposal of existing pavement by use of grinder, placement of new pavement, surface finishing, connection to existing pavement, preparation prior to placing pavement, pavement restoration, and transition to existing pavement grade.
BID ITEM 13 TRAFFIC STRIPING AND MARKERS
Measurement and payment for traffic striping and markers shall be made on a percent complete basis, based on the lump sum amount for this item, and shall include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work involved to replace traffic striping and markers removed or damaged by construction in accordance with Caltrans Standard Plans and Specifications.
BID ITEM 14 VEHICLE DETECTORS
Measurement and payment for vehicle detectors shall be made on a percent complete basis, based on the lump sum amount for this item, and shall include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work involved to replace damaged vehicle detectors. Vehicle detectors shall conform to the provisions in Section 86-
Specifications and be in accordance with the Contract Documents and City standards.
MEASUREMENT AND PAYMENT 012000-5
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT - 24 Jul 2024
BID ITEM 15--WATER POLLUTION CONTROL PLAN
Measurement for payment for the water pollution control plan shall be on a lump sum basis. The City requires a Water Pollution Control Plan (WPCP) for all construction projects that pose a threat to water quality during construction operations. Contractor must coordinate with the City to determine which locations are in high-priority areas. Full compensation for preparation of the Water Pollution Control Plan, including all labor, materials, tools, equipment, best management practices, monitoring, inspection, reporting, correction of deficiencies, and incidentals and conforming to all application provisions of the Standard Specifications and these contract documents and the requirements of the Owner shall be considered as included in the lump sum price for this Bid Item, complete and in place and no additional compensation will be allowed therefor.
END OF SECTION
TEMPORARY SEWAGE BYPASS PUMPING 015800-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 SECTION 015800 TEMPORARY SEWAGE BYPASS PUMPING
PART 1 - GENERAL
1.01 DESCRIPTION
This specification covers the work and equipment required for temporarily diverting sewage around work areas or interrupting flow for a short duration during tie-ins of manholes. Bypass pumping includes furnishing, installing, operating, and maintaining all power, primary and standby pumps, appurtenances, bypass piping, and all the tools, labor, supervision, materials, and equipment necessary to maintain existing sewer flows and services and conforming with the Countermeasure Plan. The Contractor shall schedule work to minimize service outages.
The Contractor may perform short duration shutdowns during sewer tie-ins.
Performing Short Duration Shutdowns includes furnishing, installing, operating and maintaining all power, standby pumps, appurtenances, standby piping, and all the tools, labor, supervision, materials, and equipment necessary to conform to
Control and Countermeasure Plan. No sewer main shall be plugged for more than 10 minutes without bypass and shall occur in coordination with the City and only necessitating the shutdown is
performed. Longer time may be available for plugging of the line depending on time of work and will require coordination with City staff to determine allowable time limits. In addition to submitting the shutdown plan(s), the Contractor shall provide a minimum of 72 hours notice prior to the actual need for sewer shutdowns. The Contractor shall schedule work to minimize service outages.
1.02 SUBMITTALS
A. Bypass Pumping Plan
Submit a bypass pumping plan prepared by a licensed California Professional Engineer to the Representative for review a minimum of seven (7) days prior to any planned bypass. The permission shall be obtained prior to bypass pumping. The bypass pumping plan shall consist of the following information, at a minimum, for each bypass pumping setup:
1. Sequence of sewage flow interruption, bypass, and tie-ins.
2. Plans indicating the location of temporary sewer plugs and bypass discharge lines.
TEMPORARY SEWAGE BYPASS PUMPING 015800-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3. Drawings shall clearly indicate the proposed manhole-to-manhole pumping sequence and shall be coordinated with the C traffic
control/regulation plans.
4. Capacities of pumps, prime movers, and standby equipment. A completely redundant bypass system is required including pumps and appurtenances.
5. Design calculations proving adequacy of the system and selected equipment. Include any flow metering data collected, method used to establish design flows, and design flows used for sewer bypass system sizing.
6. Pump make, model, pump curve, design head (TDH) calculations, horsepower requirement, and noise rating.
7. Description of pump system controls and alarms.
8. Generator capacity, fuel requirements, tank size, and specifications (if generator is used). Backup fuel and fuel capacity of internal combustion engine driven pumps.
9. Sewage bypass pipe material, fitting types, and details on necessary appurtenances, including pipe plugs.
10. Method for securing plugs to prevent floating downstream.
11. Plans showing details of proposed method of temporary handling of sewage flow, routing of bypass lines, containment areas, equipment location, schematic of pump set-up and discharge, proposed sequencing, and public relations procedures.
12. Electrical, controls, and instrumentation.
13. Spill Prevention, control, and countermeasure plan.
14. Monitoring Plan and bypass checklist in accordance with Part 3.01 F.
15. Name and phone number (including emergency contact info) for person responsible for temporary service.
16. Decommissioning of bypass including cleaning of plugged lines.
B. Change-Over Plan
Submit a change-over plan to the City for review a minimum of ten (10) days prior to any planned bypassing operations. The permission shall be obtained prior to any shutdowns. The change-over plan shall consist of the following information, at a minimum:
TEMPORARY SEWAGE BYPASS PUMPING 015800-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
1. Sequence of flow interruption, short duration shutdowns, construction of tieins, construction of interference manhole, and abandonment or removal of existing piping and structures.
2. Plans indicating the location of temporary sewer plugs, standby pump(s), discharge lines and other standby equipment.
3. Capacities of pumps and standby equipment.
4. Checklist for equipment, material and manpower required to complete the change-over in a timely fashion in conformance with the plans and specifications. All equipment, material and manpower shall be on-site and ready prior to initiating the change-over. The Contractor shall also have backup equipment and material on hand and shall be prepared to pursue the completion of the change-over in an efficient diligent and timely manner.
5. Spill Prevention, control, and countermeasure plan.
C. Short Duration Shutdown Plan
Submit a short duration shutdown plan to the City for review a minimum of ten (10) days prior to any planned shutdowns. The permission shall be obtained prior to any shutdowns. The short duration shutdown plan shall consist of the following information, at a minimum, for each setup:
1. Sequence of flow interruption and construction of tie-ins, including new piping and structures.
2. Location and duration of planned short duration shutdowns.
3. Plans indicating the location of temporary sewer plugs, standby pump(s), discharge lines and other standby equipment.
4. Capacities of pumps and standby equipment.
5. Checklist for equipment, material, and manpower required to complete the tie-in in a timely fashion in conformance with the plans and specifications.
All equipment, material and manpower shall be on-site and ready prior to initiating the sewer shutdown. The Contractor shall also have backup equipment and material on hand and shall be prepared to pursue the completion of the tie-in in an efficient diligent and timely manner.
6. Spill Prevention, control, and countermeasure plan.
7. Decommissioning of bypass including cleaning of plugged lines.
TEMPORARY SEWAGE BYPASS PUMPING 015800-4
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
1.03 JOB CONDITIONS
A. Schedule the order of work to minimize bypass pumping and/or shutdown durations.
B. Protection:
1. No bypassing to the ground surface, receiving streams, storm drains, or bypassing with may result in groundwater contamination or potential health hazards shall be permitted.
C. Bypass Conditions
1. Estimated Peak Hour Flows (PHF):
a. 800 gpm from Station 0+50.00 to Station 3+57 (Rockaway Avenue) b. 200 gpm from Station 3+57 to Station 7+42 (Grand Avenue) D. Existing Gravity Sewer
The plans show locations, dimensions, and elevations of existing gravity sewer piping and manholes. These locations, dimensions, and elevations are based on available information. Contractor shall inspect existing structures prior to start of work and notify the Owner immediately of any discrepancies.
PART 2 - MATERIALS
2.01 PUMPING EQUIPMENT
Engines shall be muffled in such a manner that the maximum noise level will not exceed 65 dBA at any distance of eight feet from motors between the hours of 7:00 AM and 10:00 PM. Obtain an exception permit if equipment is to be operated between the hours of 10:00 PM and 7:00 AM. Implement sound damping measures.
Provide necessary power for standby pumps. A redundant power source is required so that there is no interruption of flow. Redundant standby pumping equipment shall be at the site continuously during bypass pumping or short duration shutdown to provide 100 percent redundant system. The standby pumps shall be connected to piping such that if the bypass duty pump fails or if interrupted sewage accumulates beyond an acceptable level, the standby pump can be online immediately.
2.02 BYPASS PIPING
Bypass piping shall be aluminum, galvanized steel, or fusion-welded solid wall HDPE.
TEMPORARY SEWAGE BYPASS PUMPING 015800-5
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 PART 3 - EXECUTION
3.01 SEWER BYPASSING
A. Sewer bypassing shall be accomplished by pumping or diverting the upstream flow around the work.
B. Provide temporary pumps, galvanized steel, aluminum, or fusion-welded solid wall HDPE bypass pipe, and other equipment to bypass the sewer flow. Furnish the necessary labor, tools, equipment, and supervision to set up, operate, and monitor the pumping and bypass system. Pumps and bypass lines shall be of adequate capacity and size to handle projected flows. All bypassed flow shall be discharged into a downstream manhole. Pumps shall have a sandbag berm to act as a temporary containment area.
C. Under no circumstances shall sewage or solids be deposited onto the ground surface, streets, or into unlined ditches, catch basins, storm drains or natural drainage ways. Sewage shall be handled in a manner so as not to create a public nuisance or health hazard. Storm drain inlets in the vicinity of the bypass shall be sandbagged prior to and during bypass pumping.
D. Maintain continuity of sanitary sewer service to the facility during the execution of the work. In the event that sewage backup occurs during Contractor bypass pumping and enters dwellings or other structures, the Contractor shall cleanup, repair, pay property damage costs, pay fines imposed by jurisdictional authorities, and handle all claims arising therefrom. All spills shall be contained and returned to the sewer system.
E. Provide a designated employee(s) whose only role in the construction effort is to be responsible for continuously monitoring (24 hours a day) the bypassing operation, and all related equipment. The designated employee(s) will not be allowed to participate in any other unrelated undertaking, while the bypassing operation is in effect.
F. Complete a bypassing checklist prior to bypassing operation. The checklist will demonstrate the step-by-step inspection of the pumps, pipes, hold-down cables, plugs, and other equipment or appurtenances that will be used in the operation and sign the checklist.
3.02 STANDBY EQUIPMENT
Maintain on site sufficient equipment and materials to ensure continuous and successful operation of the bypass and dewatering systems. Standby pumps shall be fueled and operational at all times. Maintain on site a sufficient number of valves, tees, elbows, connections, tools, sewer plugs, piping and other parts or system hardware to ensure immediate repair or modification of any part of the system as necessary.
TEMPORARY SEWAGE BYPASS PUMPING 015800-6
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.03 SPILL PREVENTION, CONTROL, AND COUNTERMEASURE PLAN Prepare, submit, and carry out a spill prevention, control, and countermeasure plan that incorporates the following:
A. Include or reference in the plan, materials provided as submittals per Part I of this Specification. Coordinate the plan to protect water quality and respond to spills of sewage, groundwater, or fuels. Describe all spill prevention measures (e.g., monitoring of upstream manholes, monitoring in the trench).
In general, good housekeeping is required so no contamination reaches surface waters or storm drains when it rains. Some specifics include, but are not limited to:
1. Prior to start of bypassing, all storm drain catch basins that are within the vicinity of the work that could possibly take in sewage, in the event of a spill, shall be isolated with sandbags or other approved means.
2. Oil pans should be under any engine that leaks oil.
3. Spill response as covered below.
B. The following spill procedures shall be incorporated into the plan in anticipation of the described failure mode, and the Contractor shall be prepared to act accordingly. If a spill is detected or a catastrophic pipe failure occurs, the immediate priority shall be to prevent any sewage from reaching surface waters and storm drains. Immediately protect all drains using rubber mats or sandbags (have sandbags on site).
1. When excavating, if moderate leaks are discovered in the existing pipe, make coupling/clamp repairs as soon as possible to minimize sewage flow into the trench. If the leak is too large to make fast coupling repair, start bypassing (see bypassing sequence below), then make repair. a. In case of catastrophic leak, immediately start the bypassing sequence:
(1) Plug upstream side of manhole upstream of a catastrophic leak.
(2) Insert bypass pump into manhole upstream of plugged manhole. The pump shall be sized to handle peak flow of existing sewer. Provide spare pump or set up standby pump availability with rental yard.
(3) Connect the hose from pump to discharge point. (NOTE: Hose shall already be in place and connected to a downstream TEMPORARY SEWAGE BYPASS PUMPING 015800-7
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 discharge point at all times when working near or with live sewers.)
(4) In the event of any spill, immediately and in parallel with above activities, notify the City and request the wastewater staff to be dispatched. Give the best indication of the approximate size of the spill (<1,000 gallons is small; 1,000 gallons to 10,000 gallons is medium; and >10,000 gallons is large) to the staff so they can dispatch the appropriate response.
staff will assist in the response and ensure that the spill is cleaned to the standards.
(5) While awaiting the wastewater staff response, pond the water in an area that can be easily and fully recovered for discharge to the . This ponding activity should not
impact any environmentally sensitive areas.
(6) When staff and any other responding staff arrive onsite, a more permanent and planned response, repair, and cleanup will ensue. Cooperate with the City to the fullest extent possible in order to minimize the impacts and volume of the spill in the most efficient manner possible.
(7) No form of disinfection is allowed. All wash water must be contained and recovered as the sewage is.
(8) Clean up may require a sweeper truck or other equipment. All City costs, time and materials, and special equipment for spill cleaning will be deducted from the progress
payment.
(9) In the event of a spill, be prepared to document the spill with a video camera and photographs. Plan on attending a debriefing immediately after the spill is contained and cleaned up.
C. Comply with the Regional Water Quality Control Board, San Luis Obispo County Public Health Department, and City Standards. Cooperate with City s staff and other regulators and environmental agencies.
3.04 DAMAGES
Without cost to the City, repair any damage that may result from the installation, operation, maintenance, and removal of the sewer bypass pumping system or short duration shutdown system. This includes, but is not limited to damages resulting TEMPORARY SEWAGE BYPASS PUMPING 015800-8
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 from inadequate or improper installation, operation and maintenance of the bypass or interruption system components, mechanical failures, or electrical failures.
If City staff are called on to assist, the Contractor shall pay for all costs incurred by the City in assisting the Contractor.
END OF SECTION
PRECAST CIRCULAR CONCRETE MANHOLES 034210-1
CIP 5002 SEWER SYSTEM UPGRADES PROJECT- 24 Jul 2024
SECTION 034210 PRECAST CIRCULAR CONCRETE MANHOLES
PART 1 - GENERAL
1.01 DESCRIPTION
This section includes design, materials, testing, and installation of precast circular concrete manholes.
1.02 RELATED WORK SPECIFIED ELSEWHERE
A. Trenching, Backfilling, and Compacting: 312316.
B. Leakage and Infiltration Testing: 330130.
C. PVC Gravity Sewer Pipe: 333112.
1.03 SUBMITTALS
A. Submit shop drawings in accordance with the Special Provisions and Section 013300.
B. Submit manufacturer's catalog data on precast concrete manholes, frames, pipe connections, joint sealing compound, and covers. Show dimensions and materials of construction by ASTM reference and grade. Show lettering on manhole covers.
PART 2 - MATERIALS
2.01 PRECAST CIRCULAR CONCRETE MANHOLES
A. Precast circular concrete manholes shall comply with ASTM C478, except that the wall thickness shall be 4 inches minimum. Minimum manhole diameter shall be 48 inches. Design manholes for the depths shown in the drawings, assuming a soil density of 130 pounds per cubic foot.
B. Minimum allowable steel shall be hoops of No. 4 wire cast into each unit.
C. Precast top sections shall be eccentric cone, except where shown otherwise in the drawings.
D. Design joints using a butyl rubber sealant per ASTM C990.
2.02 CONCRETE
A. Cement for manholes and precast bases shall conform to ASTM C150, Type II/V.
PRECAST CIRCULAR CONCRETE MANHOLES 034210-2
CIP 5002 SEWER SYSTEM UPGRADES PROJECT- 24 Jul 2024
B. Concrete used in pouring the manhole base shall be Class A as defined by the City of Grover Beach Standards and Specifications. Cast manholes without steps (ladder rungs).
2.03 MANHOLE FRAMES AND COVERS
A. Manhole frames and covers shall be made of cast iron conforming to ASTM A48, Class 30. Castings shall be smooth, clean, and free from blisters, blowholes, and shrinkage. Frames and covers shall be designed for H20-44 traffic loads. The cover shall seat firmly into the frame without rocking.
B. Grind or otherwise finish each cover so that it will fit in its frame without rocking.
Frames and covers shall be matchmarked in sets before shipping to the site.
C. Sewer manhole covers shall have the word "SEWER" and the letters as indicated in the drawings cast thereon. Do not apply any other lettering unless indicated otherwise in the drawings.
D. Before leaving the foundry, clean castings and subject them to a hammer inspection.
2.04 SEALING COMPOUND AND MORTAR
Butyl rubber sealing compound shall comply with ASTM C990. Mortar shall comply with ASTM C387, Type S, or use grout.
2.05 PIPE CONNECTIONS FOR PRECAST SEWER MANHOLES
Provide resilient watertight connectors between precast manholes and piping in accordance with ASTM C923. Connections shall consist of a chemically resistant neoprene EPDM flexible boot, locking ring, and pipe clamp(s). The locking ring shall be stainless steel and shall lock the boot into the preformed opening in the manhole. The pipe clamp shall be stainless steel. Alternatively, cast the flexible boot in the manhole and eliminate the locking ring. Pipe connections shall be KorN-Seal (Trelleborg Group), Z-Lok-XP (A-Lok Products, Inc.), or equal.
PART 3 - EXECUTION
3.01 MANHOLE BASE
A. Excavate for the manhole and compact to 90% relative density.
B. Form and pour concrete bases as one monolithic pour. Form the portion above the invert elevation of the sewer pipe to provide a smooth channel section.
Channels shall vary uniformly in size and shape from inlet to outlet.
C. Use of precast manhole bases to be approved by City prior to construction.
PRECAST CIRCULAR CONCRETE MANHOLES 034210-3
CIP 5002 SEWER SYSTEM UPGRADES PROJECT- 24 Jul 2024
3.02 INSTALLING MANHOLES
A. Set each precast concrete manhole unit plumb on a bed of sealant or mortar to make a watertight joint at least 1/2 inch thick with the concrete base or with the preceding unit. Point the inside joint and wipe off the excess sealant or mortar.
Secure the manhole frame to the grade ring with grout and cement mortar fillet.
Backfill, compact, and replace pavement.
B. Assemble units so that the cover conforms to the elevation determined by the manhole location as follows:
1. In Paved Areas: Top of cover shall be flush with the paving surface.
2. In Shoulder Areas: Top of cover shall be flush with existing surface where it is in traveled way of shoulder and 0.1 foot above existing surface where outside limits of traveled way but not in the existing roadside ditch.
3. In Roadside Ditch or Unpaved Open Areas: Top of cover shall be 18 inches above the ground surface.
3.03 SEALING AND GROUTING OF MANHOLE SECTIONS
Clean ends of precast sections of foreign materials. Place two wraps of mastic sealing compound within the groove of the lower section. Set next section in place.
Fill remaining interior and exterior joint cavity completely with mortar of the proper consistency. Trowel interior and exterior surfaces smooth on tongue-and-groove joints. Wipe off any excess grout from the interior and exterior of the joints. Prevent mortar from drying out by applying curing compound or comparable method. Chip out and replace cracked or defective mortar. Completed manhole shall be rigid and watertight.
3.04 LEAKAGE TESTING OF SEWER MANHOLES
Test manholes for leakage along with the pipe.
3.05 BACKFILL AROUND MANHOLES
Backfill and compact around the manholes using native material, per Section 312316 and the pipe specification.
END OF SECTION
TRENCHING, BACKFILLING, AND COMPACTING 312316-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
SECTION 312316 TRENCHING, BACKFILLING, AND COMPACTING
PART 1 - GENERAL
1.01 DESCRIPTION
This section includes materials, testing, and installation for pipeline trench excavation, backfilling, and compacting.
1.02 SUBMITTALS
A. Submit electronic copy of a report from a testing laboratory verifying that import material contains less than 0.25% asbestos by weight or volume.
B. Submit electronic copy of a report from a testing laboratory verifying that material conforms to the specified gradations or characteristics for granular material, imported sand, and rock refill for foundation stabilization.
C. Submit method(s) of compaction including removal sequence of shoring where used.
1.03 TESTING FOR COMPACTION
A. The Owner will test for compaction as described below.
B. Determine the density of soil in place by nuclear methods, ASTM D6938.
Compaction tests will be performed for each lift or layer.
C. Determine laboratory moisture-density relations of soils by ASTM D1557. If nuclear methods are used for in-place density determination, the compaction test results for maximum dry density and optimum water content shall be adjusted in accordance with ASTM D4718. This will be required for determination of percent relative compaction and moisture variation from optimum.
D. Determine the relative density of cohesionless soils by ASTM D4253 and D4254.
E. Sample backfill materials per ASTM D75.
F. "Relative compaction" is the ratio, expressed as a percentage, of the in-place dry density to the laboratory maximum dry density.
G. Compaction shall be deemed to comply with the specifications when no more than one test falls below the specified relative compaction. The one test shall be no more than three percentage points below the specified compaction. The Contractor shall pay the costs for any retesting or additional testing of work not conforming to the specifications.
TRENCHING, BACKFILLING, AND COMPACTING 312316-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 H. Where compaction tests indicate a failure to meet the specified compaction, the Owner will take additional tests every 25 feet in each direction until the extent of the failing area is identified. Rework the entire failed area until the specified compaction has been achieved.
1.04 PAVEMENT ZONE
The pavement zone includes the asphalt concrete and aggregate base pavement section placed over the trench backfill.
1.05 TRENCH ZONE
The trench zone includes the portion of the trench from the top of the pipe zone to the bottom of the pavement zone in paved areas or to the existing surface in unpaved areas.
1.06 PIPE ZONE
The pipe zone shall include the full width of trench from the bottom of the pipe or conduit to a horizontal level 6 inches above the top of the pipe. Where multiple pipes or conduits are placed in the same trench, the pipe zone shall extend from the bottom of the lowest pipe to a horizontal level above the top of the highest or topmost pipe.
1.07 PIPE BASE OR BEDDING
The pipe base or bedding shall be defined as a layer of material immediately below the bottom of the pipe or conduit and extending over the full trench width in which the pipe is bedded. Thickness of pipe base shall be 6 inches.
PART 2- MATERIALS
2.01 MATERIAL FOR BACKFILL TRENCH ZONE
Trench backfill shall consist of imported or onsite material that is free of organics, debris, oversized material (greater than 4 inches in size), broken pavement, and other deleterious materials. Imported trench backfill material shall have at least 85 percent of the material passing the U.S. Standard No. 4 sieve.
2.02 SAND--PIPE ZONE AND PIPE BASE
A. Native materials free of organics, debris, oversized material (greater than 3 inches in size), broken pavement, and other deleterious materials are suitable for use in the pipe zone and as pipe base.
B. Imported sand used in the pipe zone or for the pipe base shall have the following gradation:
TRENCHING, BACKFILLING, AND COMPACTING 312316-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
Sieve Size Percent Passing By Weight
1 inch 100
No. 4 80 to 100
No. 200 0 to 15
C. Imported sand shall have a minimum sand equivalent of 30 per ASTM D2419.
2.03 GRAVEL AND CRUSHED ROCK--PIPE ZONE AND PIPE BASE
A. Gravel or crushed rock material shall contain less than 0.25% asbestos by weight or volume and shall meet the following gradation:
Sieve
Sizes
Percent
Passing
1 1/2 inches 100
1 inch 86 to 100
3/4 inch 52 to 85
3/8 inch 15 to 38
No. 4 0 to 16
No. 8 0 to 6
2.04 SAND-CEMENT SLURRY BACKFILL--PIPE ZONE
Sand-cement slurry backfill shall consist of one sack (94 pounds) of Type I or II portland cement added per cubic yard of imported sand and sufficient water for workability.
2.05 FILTER FABRIC
Filter fabric shall conform to Section 96-1.02B of the California Department of Transportation Standard Specifications. Filter fabric shall be MIRAFI 140N, manufactured by Mirafi Inc.; or equal. .
PART 3 - EXECUTION
3.01 SLOPING, SHEETING, SHORING, AND BRACING OF TRENCHES Trenches shall have sloping, sheeting, shoring, and bracing conforming with 29CFR1926, Subpart P--Excavations, CAL/OSHA requirements, and the Special Provisions.
TRENCHING, BACKFILLING, AND COMPACTING 312316-4
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.02 SIDEWALK, PAVEMENT, AND CURB REMOVAL
Cut bituminous and concrete pavements regardless of the thickness and curbs and sidewalks prior to excavation of the trenches with a pavement saw or pavement cutter. Width of the pavement cut shall be at least equal to the required width of the trench at ground surface. Haul pavement and concrete materials from the site. Do not use for trench backfill.
3.03 TRENCH EXCAVATION
A. Excavate the trench to the lines and grades shown in the drawings with allowance for pipe thickness, sheeting and shoring if used, and for pipe base or special bedding. If the trench is excavated below the required grade, refill any part of the trench excavated below the grade at no additional cost to the Owner with imported sand. Place the refilling material over the full width of trench in compacted layers not exceeding 8 inches deep to the established grade with allowance for the pipe base or special bedding.
B. Trench widths in the pipe zone shall be as shown in the drawings. Comply with 29CFR Part 1926 Subpart P--Excavations. Trench width at the top of the trench will not be limited except where width of excavation would undercut adjacent structures and footings. In such case, width of trench shall be such that there is at least 2 feet between the top edge of the trench and the structure or footing.
3.04 TRENCH EXCAVATION IN BACKFILL AND EMBANKMENT AREAS A. Construct and compact the embankment to an elevation of 1-foot minimum over the top of the largest pipe or conduit to be installed.
B. Excavate trench in the compacted backfill or embankment.
3.05 LOCATION OF EXCAVATED MATERIAL
A. Contractor to identify stockpile location for excavated material. Do not obstruct any roadways or streets. Do not place trench spoil over pipe, buried utilities, manholes, or vaults. Conform to federal, state, and local codes governing the safe loading of trenches with excavated material.
B. Locate trench spoil piles at least 15 feet from the tops of the slopes of trenches.
Do not operate cranes and other equipment on the same side of the trench as the spoil piles.
3.06 LENGTH OF OPEN TRENCH
Limit the length of open trench to 100 feet in advance of pipe laying or amount of pipe installed in one working day. Complete backfilling and temporary or first layer paving not more than 50 feet in the rear of pipe laying.
TRENCHING, BACKFILLING, AND COMPACTING 312316-5
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.07 DEWATERING
Provide and maintain means and devices to remove and dispose of water entering the trench excavation during the time the trench is being prepared for the pipe laying, during the laying of the pipe, and until the backfill at the pipe zone has been completed. These provisions shall apply during both working and nonworking hours, including lunchtime, evenings, weekends, and holidays.
Dispose of the water in a manner to prevent damage to adjacent property and in accordance with regulatory agency requirements. Do not drain trench water through the pipeline under construction.
3.08 FOUNDATION STABILIZATION
A. After the required excavation has been completed, the Owner will inspect the exposed subgrade to determine the need for any additional excavation. It is the intent that additional excavation be conducted in all areas within the influence of the pipeline where unacceptable materials exist at the exposed subgrade. Over excavation shall include the removal of all such unacceptable materials that exist directly beneath the pipeline to a width 24 inches greater than the pipe outside diameter and to the depth required.
B. Place filter fabric on the bottom of the trench and up the sides a sufficient height to retain gravel material. Backfill the trench to subgrade of pipe base with gravel material for foundation stabilization. Place the foundation stabilization material over the full width of the trench and compact in layers not exceeding 8 inches deep to the required grade. Foundation stabilization work shall be executed in accordance with a change order.
C. Gravel used by the Contractor for his convenience will not be cause for any additional payment.
3.09 INSTALLING BURIED PIPING
A. Grade the bottom of the trench to the line and grade to which the pipe is to be laid, with allowance for pipe thickness. Remove hard spots that would prevent a uniform thickness of bedding. Place the specified thickness of pipe base material over the full width of trench. Grade the top of the pipe base ahead of the pipe laying to provide firm, continuous, uniform support along the full length of pipe, and compact to the relative compaction specified herein. Before laying each section of the pipe, check the grade and correct any irregularities.
B. Excavate bell holes at each joint to permit proper assembly and inspection of the entire joint. Fill the area excavated for the joints with the bedding material specified or indicated in the drawings for use in the pipe zone. If no bedding material is specified or indicated, use native or imported sand.
C. Inspect each pipe and fitting before lowering the buried pipe or fitting into the trench. Inspect the interior and exterior protective coatings. Patch damaged areas TRENCHING, BACKFILLING, AND COMPACTING 312316-6
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 in the field with material recommended by the protective coating manufacturer.
Clean ends of pipe thoroughly. Remove foreign matter and dirt from inside of pipe and keep clean during and after installation.
D. Handle pipe in such a manner as to avoid damage to the pipe. Do not drop or dump pipe into trenches under any circumstances.
E. When installing pipe, do not deviate more than 1 inch from line or 1/4 inch from grade. Measure elevation at the pipe invert.
F. After pipe has been bedded, place pipe zone material simultaneously on both sides of the pipe, in maximum 8-inch lifts, keeping the level of backfill the same on each side. If no pipe zone material is specified or indicated, use native or imported sand. Carefully place the material around the pipe so that the pipe barrel is completely supported and no voids or uncompacted areas are left beneath the pipe. Use particular care in placing material on the underside of the pipe to prevent lateral movement during subsequent backfilling.
G. Compact each lift to the relative compaction specified herein.
H. Push the backfill material carefully onto the backfill previously placed in the pipe zone. Do not permit free-fall of the material until at least 2 feet of cover is provided over the top of the pipe. Do not drop sharp, heavy pieces of material directly onto the pipe or the tamped material around the pipe. Do not operate heavy equipment or a sheepsfoot wheel mounted on a backhoe over the pipe until at least 3 feet or one-half of the internal diameter, whichever is greater, of backfill has been placed and compacted over the pipe.
I. When the pipe laying is not in progress, including the noon hours, close the open ends of pipe. Do not allow trench water, animals, or foreign material to enter the pipe.
J. Keep the trench dry until the pipe laying and jointing are completed.
3.10 BACKFILL COMPACTION
A. Unless otherwise shown in the drawings or otherwise described in the specifications for the particular type of pipe installed, relative compaction in pipe trenches shall be as follows:
1. Pipe Zone: 90% relative compaction.
2. Backfill in Trench Zone: 95% relative compaction.
3. Gravel for Foundation Stabilization: 80% relative density.
4. Refill for Overexcavation: 80% relative density.
TRENCHING, BACKFILLING, AND COMPACTING 312316-7
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
B. Compact trench backfill to the specified relative compaction. Compact by using mechanical compaction or hand tamping. Do not use high-impact hammer-type equipment except where the pipe manufacturer warrants in writing that such use will not damage the pipe.
C. Compact material placed within 12 inches of the outer surface of the pipe by hand tamping only.
D. Do not use any axle-driven or tractor-drawn compaction equipment within 5 feet of building walls, foundations, and other structures.
3.11 MATERIAL REPLACEMENT
Remove and replace any trenching and backfilling material that does not meet the specifications, at the Contractor's expense.
3.12 PLACING SAND-CEMENT SLURRY BACKFILL
Place sand-cement slurry backfill in a uniform manner that will prevent voids in or segregation of the material. Remove foreign material that falls into the excavation or trench. Do not commence backfilling over or place any material over the slurry cement backfill until at least four hours after placing the sand-cement slurry.
END OF SECTION
LEAKAGE AND INFILTRATION TESTING 330130-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
SECTION 330130 LEAKAGE AND INFILTRATION TESTING
PART 1 - GENERAL
1.01 DESCRIPTION
This section includes testing of sewers not intended to be pressurized in excess of 5 psi or 12 feet head of water. Leakage test is by internal air pressure or water.
Infiltration test is by measurement of rate of flow of water.
1.02 RELATED WORK SPECIFIED ELSEWHERE
Sanitary Sewer System Television Inspection: 330131.
PART 2 - MATERIALS
2.01 TEST PLUGS
Inflatable and expandable type, braced to contain 5 psi over the pipe cross-section area.
2.02 PRESSURE-RELIEF VALVE
Set to limit the internal pipe test pressure to 5 psi.
PART 3 - EXECUTION
3.01 SELECTION OF ALTERNATE TEST CRITERIA
A. When more than one pipe size is included in a test section, determine the test time by the criteria of ASTM F1417 for plastic pipe.
B. If the entire test section is submerged in groundwater, test for infiltration only.
3.02 PREPARATION OF THE PIPELINE
A. Prior to testing, flush and clean the pipeline to wet the pipe surface and clean out debris.
B. Plug pipe outlets, including stoppers in laterals, to resist the leakage test pressure.
3.03 LEAKAGE TEST
A. Test for leakage or for infiltration by standard hydrostatic or low pressure air test.
Test each section of pipe between manholes, along with the manholes. Use the LEAKAGE AND INFILTRATION TESTING 330130-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 air test where the difference in elevation between the invert of the upper structure and the invert of the lower structure is more than 10 feet.
B. Test each section of pipe subsequent to the last backfill compacting operation.
3.04 HYDROSTATIC TEST PROCEDURE
A. Test each section of pipe between two successive structures by closing the lower end of the pipe to be tested and the inlet pipe of the upper structure with plugs or stoppers. Fill the pipe and structure with water to a point 5 feet above the invert of the open pipe in the upper structure.
B. In the beginning of the test, the elevation of the water in the upper manhole should be measured to a point on the manhole rim. After 4 hours, the water elevation in the upper manhole shall be measured from the same point on the manhole rim to determine any loss of water during the test period.
C. The total leakage shall be the decrease in volume of water in the upper structure.
The leakage shall not exceed 0.025 gpm per inch of nominal diameter of pipe per 1,000 feet of pipe being tested.
D. Should the test result in excess leakage, the City Standards permit drawing off water to test the manholes that contained the water. This test is done by plugging all the openings in the manholes and filling it with water to the same elevation as existed during the test. The leakage from the manhole may be deducted from the total leakage of the test section to calculate the test leakage of the pipe. After testing is complete, the manhole shall be waterproofed with grouting or other approved methods by the City.
E. If the leakage is greater than allowed, overhaul the pipe and, if necessary, replace and re-lay until the joints and pipe comply with this test. Complete tests before trench is paved.
3.05 AIR TEST
A. Conduct air tests per the following standards:
Pipe Material
Specification
Section
ASTM
Specification
PVC 333112 F1417, Table 1
B. Test each section of pipe between two successive manholes by plugging pipe outlets with test plugs. Add air slowly until the internal pressure is raised to 4.0 psig. The compressor used to add air to the pipe shall have a blowoff valve set at 5 psig so that the internal pressure in the pipe never exceeds 5 psig. Maintain the internal pressure of 4 psig for at least two minutes to allow the air temperature to stabilize, then disconnect the air supply and allow the pressure to decrease to 3.5 LEAKAGE AND INFILTRATION TESTING 330130-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
psig. Measure the time in minutes that is required for the internal air pressure to drop from 3.5 psig to 2.5 psig. Compare the results with the values tabulated in the referenced ASTM specifications above.
C. If the pressure drop from 3.5 psig to 2.5 psig occurs in less time than the specified values, overhaul the pipe and, if necessary, replace and re-lay the pipe until the joints and pipe hold satisfactorily under this test.
D. Guard against the sudden expulsion of a poorly installed plug or a plug that is partially deflated.
3.06 TEST FOR INFILTRATION
A. If, in the construction of a section of the sewer between structures, excessive groundwater is encountered, close the end of the pipe at the upper structure sufficiently to prevent the entrance of water. Discontinue pumping groundwater for at least three days. Then test the section for infiltration. The infiltration shall not exceed 0.025 gpm per inch of diameter per 1,000 feet of main line pipe being tested as measured at the downstream structure. Test period shall be at least eight hours.
B. Where infiltration exceeds the maximum acceptable, immediately uncover the pipe and reduce the infiltration to within the maximum acceptable by replacing, relaying, or encasing the pipe in concrete.
3.07 CORRECTION OF OBSERVED LEAKS
Even though the infiltration is less than the maximum acceptable, stop any individual leaks that may be observed.
3.08 INSPECTION BY CONTRACTOR FOR DAMAGED OR DEFECTIVE PIPE IN PLACE
A. After backfilling and pavement replacement is complete and upon completion of the air test or infiltration test, inspect the pipe for damage and other defects by means of closed-circuit television (CCTV). Television inspection shall be in accordance with Section 330131.
B. Schedule the inspection in advance with the Owner's Representative.
C. If the CCTV inspection indicates any defects, excavate and repair or replace the faulty materials and construction and restore the work and the damage to work of others.
END OF SECTION
SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
SECTION 330131 SANITARY SEWER SYSTEM TELEVISION INSPECTION PART 1 - GENERAL
1.01 DESCRIPTION
This section includes television inspection digital audio-visual recording and reports associated with inspection of sanitary sewers.
1.02 RELATED WORK DESCRIBED ELSEWHERE
A. PVC Gravity Sewer Pipe: 333112.
1.03 DEFINITIONS
A. Television Inspection: Operation necessary to complete a true-color audio-visual inspection for verification of existing internal sewer line conditions. Furnish labor, materials, equipment, tools, and other incidental services for CCTV inspection.
B. MPEG: MPEG, which stands for Moving Pictures Expert Group, is the nickname given to a family of international standards fused for coding audio-visual information in a digital compressed format. For the purposes of this specification, digital audio-visual coding has a resolution of 352 pixels (x) by 240 pixels (y) and an interlaced frame rate of 30 frames per second. MPEG coding shall be named using the .mpg as the file extension.
C. Compact Disk-Read Only Memory (CD-ROM): For the purposes of this specification, CD-ROM shall be defined as a CDaccordance with the ISO-9660 Level 2 specifications.
PART 2 - MATERIALS
2.01 GENERAL
Furnish the television inspection studio, television camera, audio-visual digital encoding equipment/software, and other necessary equipment, materials, electricity, labor, technicians, as may be needed to perform the television inspection.
2.02 TELEVISION INSPECTION EQUIPMENT
A. The television inspection equipment shall be capable of inspecting a minimum of 1,000 feet of sewer line, when entry into the sewer can be accessed from the upstream and downstream manholes. When entry is at one end only, the inspection equipment shall be capable of inspecting 750 feet by a self-propelled SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 unit. The inspection equipment shall be capable of clearly televising the interior of a 6-inch-diameter sewer and larger sizes.
B. Transport the television equipment in a stable condition through the sewer line to be inspected. Throughout the inspection, position the camera equipment with the camera directed along the longitudinal axis of the sewer. When the television equipment is towed by winch and bond through the sewer line, the winches shall be stable with either locking or ratcheting drums. Winches shall be inherently stable under loaded conditions. The bonds shall be steel or of an equally nonelastic material to ensure the smooth and steady progress of the camera extension or traction through the sewer conduit. Prevent damage to the sewer conduit during the television inspection. In the case where the Contractor, for any reason, causes damage such as would be caused by incorrect deployment of bonds or retrieval of lodged equipment, the cost of repair or remedy shall be borne by the Contractor.
2.03 TELEVISION CAMERA
A. Use a television camera specifically designed and constructed for sewer pipeline inspection. The camera shall be waterproof and shall be operative in any conditions that may be encountered in the inspection environment. Provide a color pan and tilt camera to facilitate the inspection of service laterals and sewer line and manhole defects. The television camera shall be capable of 360-degree rotational scan indicating salient defects. The tilt arc shall not be less than 225 degrees unless otherwise approved
adjustment of focus and iris shall provide a minimum focal range of 3 inches in Provide a visual size reference visible in front of the - B. The distance along the sewer in focus from the initial point of observation shall be a minimum of twice the vertical height of the sewer.
C. The illumination shall be such as to allow an even distribution of the light shadowing.
D. The view seen by the television camera shall be transmitted to a monitor of not less than 11 inches in size. The television camera shall be capable of receiving and transmitting a picture having not less than a resolution 352(x) by 240(y). The travel speed of the television inspection camera (through the sewer) shall be Representative 6 inches per second under normal conditions.
E. Test the television inspection equipment to verify the picture quality. Use the to clearly differentiate between the following colors: white, yellow, cyan, green, magenta, red, blue, and black.
SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
F. The television inspection equipment shall be of such quality as to enable the following to be achieved:
1. Color: With the monitor adjusted for correct saturation, the six colors plus black and white shall be clearly resolved with the primary and complementary colors in order of decreasing luminance.
2. Linearity: The background grid shall show squares of equal size, without convergence/divergence over the whole of picture. The center circle shall appear round and have the correct height/width relationship (±5%).
3. Resolution: The live picture must be displayed on a digital or analog monitor capable of providing a clear, stable image free of electrical interference with minimum horizontal resolution not less than 352(x) by 240(y) lines.
4. Color Consistency: To ensure that the camera shall provide similar results when used with its own illumination source, the lighting shall be fixed in intensity prior to commencing the survey. In order to ensure color consistency, no variation illumination shall take place during the inspection.
5. picture color consistency against the color bar. Any differences will necessitate resurvey of the new length or lengths affected, at the
6. The CCTV monitor display shall incorporate an automatically updated record in feet and tenths of a foot of the distance along the line from the cable calibration point to the center point of the camera or center point of the transducer, whichever unit is being used. The relative positions of the two center points should also be noted. Use a metering device that enables the cable length to be accurately measured; this shall be accurate ±1% or 6 inches whichever is greater. Demonstrate that the tolerance is being achieved by tape measurement between manholes on the surface. This taped measurement must be included on each television log both written and digital.
7. Representative will instruct the Contractor to provide a new device to instruct the Contractor in writing, to resurvey those lengths of sewer first inspected with the original measuring device using the new measuring device.
8. Audio-visual recordings and collected data made during the television inspection shall become the property of the Owner. Submit to the Owner immediately upon completion of the television inspection.
SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-4
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
2.04 TELEVISION STUDIO
The television studio shall be large enough to accommodate three people for the purpose of viewing the television monitor while the inspection is in progress. The television studio shall be insulated against noise and extremes in temperature and shall be provided with means of controlling external and internal sources of light in a manner capable of ensuring that the monitor screen display is in accordance access to view the television screen at all times. Locate the central control panel and television camera control in the mobile television studio. Mount the television studio on a mobile vehicle (truck or trailer), which allows safe and orderly movement of the inspection equipment throughout the jobsite.
PART 3- EXECUTION
3.01 TELEVISION INSPECTION
A. Inspect sewer pipelines with pan and tilt conventional television imagery so as to record relevant features and defects of the pipeline under inspection. Inspection Representative. Perform cleaning in accordance with the requirements of the contract documents. A skilled technician or supervisor who shall be located at the control panel in the mobile television studio shall control the operation of the television equipment.
B. If television inspection of an entire section cannot be successfully performed from one manhole, perform a reverse setup to obtain a complete television inspection.
No additional payment will be made for a reverse setup.
C. Provide a complete television inspection of both the upstream and downstream manholes beginning at the top of each manhole and panning down to inspect the entire manhole.
D. Whenever prevailing conditions allow, position the camera head to reduce the risk of picture distortion. In circular sewers, position the camera lens centrally (i.e., in prime position) within the sewer. In noncircular sewers, picture orientation shall be taken at mid-height, unless otherwise agreed, and centered horizontally. Direct the camera lens along the longitudinal axis of the sewer when in prime position.
A positioning tolerance of ±10% of the vertical sewer dimension shall be allowed when the camera is in prime position.
E.
Representative will reject any television inspection that, because of high flow conditions or for any other reason, does not produce an effective survey of the sewer pipe. If the water level is greater than 25% of the pipe diameter, conventional television inspection shall not be attempted without prior approval SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-5
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
Representative in writing.
F. Do not pull a cleaning device in front of the television inspection camera during the taping of the sewer line.
3.02 DIGITAL AUDIO/VISUAL RECORDING
A. Take continuous digital video recordings of the inspection view as it appears on the television monitor. It is intended that a digital video recording will be made of the complete television inspection of the sewer lines constructed as part of this project. The recording shall also be used as a permanent record of defects. The recording shall be MPEG file format. The digital video encoding shall include both sound and video information that can be reproduced with a video image equal or very close to the quality of the original picture on the television monitor. The replay of the recorded video information, when reviewed by Windows Media PlayerTM, shall be free of electrical interference and shall produce a clear, stable image. The audio portion of the composite digital coding shall be sufficiently free of electrical interference background noise to produce an oral report that is clear and completely and easily discernible.
B. The audio portion of the inspection report shall include the location or identification of the section, the manhole-to-manhole direction of travel, and the distance traveled on the specific run encountered. The inspection camera equipment shall be on the specific run encountered. Continuously connect the inspection camera equipment to the television inspection or monitoring equipment. The recording and monitoring equipment shall have the builtRepresentative to instantly review both the audio and video quality of the recordings during the television survey. Playback speed shall be continuously adjustable from one-third normal speed for slow-motion viewing to normal playback speed.
C. Create separate MPEG files for each sewer line segment. In case of a reverse setup, store such inspection in a separate MPEG file. MPEG files shall be written to CD-ROM or DVDMultiple MPEGs may exist on each CD-ROM or DVD-ROM. Each CD-ROM or DVD-ROM shall be labeled, at a minimum, with the following information: Owner, Engineering Firm, Project Name, Date of creation, ID number, Sewer Line D. Name the MPEG files according to the following file specification: [Start Manhole Number]_[End Manhole Number]_[Month]_[Day]_[Year].mpg
E.
of poor image quality, excessive bit rates, inconsistent frame rates, or any other SANITARY SEWER SYSTEM TELEVISION INSPECTION 330131-6
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.03 TELEVISION INSPECTION REPORTS
A. Prepare a television inspection report covering the television inspection work and the information acquired. Prior to beginning work, submit a sample hardcopy B. Report sewer defects in accordance with the National Association of Sewer Service Companies (NASSCO) program known as Pipeline Assessment and refuse any inspection report that does not comply with the PACP program.
C.
is provided.
3.04 QUALITY CONTROL
A. Operate a quality control system that will effectively gauge the accuracy of inspection reports produced by the operator.
B.
present when assessments of the sewer integrity are being determined. When Representative sufficient details and information for such audit assessment. satisfactory, the Contractor, without any additional compensation, shall recode and resubmit any data or reports that the Ow
necessary.
END OF SECTION
PVC GRAVITY SEWER PIPE 333112-1
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 SECTION 333112 PVC GRAVITY SEWER PIPE
PART 1 - GENERAL
1.01 DESCRIPTION
This section includes materials, installation, and testing of PVC gravity sewer pipe conforming to ASTM D3034. 1.02 RELATED WORK SPECIFIED ELSEWHERE A. Precast Circular Concrete Manholes: 034210.
B. Trenching, Backfilling, and Compacting: 312316.
C. Leakage and Infiltration Testing: 330130.
D. Sanitary Sewer System Television Inspection: 330131.
1.03 SUBMITTALS
A. Submit reports on testing per ASTM D3034 (pipes 4 inches though 12).
PART 2 - MATERIALS
2.01 PVC MATERIAL
Additives and fillers, including stabilizers, antioxidants, lubricants, colorants, etc., shall not exceed 10 parts by weight per 100 of PVC resin in the compound.
2.02 PIPE
A. Pipe 4 through 12 inches shall conform to ASTM D3034, SDR 35.
2.03 JOINTS
Provide elastomeric gasket joints of the push-on type, conforming to ASTM D3212.
2.04 GASKETS
Gaskets for push-on joints shall conform to ASTM F477.
2.05 FITTINGS
A. Fittings for pipe 4 through 12 inches shall conform to ASTM D3034, SDR 35.
PVC GRAVITY SEWER PIPE 333112-2
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
2.06 MANDREL FOR FIELD TESTING OF PIPE DEFLECTION
The mandrel shall:
A. Be a rigid, nonadjustable, odd-numbering-leg (nine legs minimum) mandrel having an effective length not less than its nominal diameter.
B. Have a minimum diameter at any point along the full length as follows:
Pipe Material
Nominal Size
(inches)
Minimum Mandrel Diameter
(inches)
PVC-ASTM D3034
(SDR 35) 10 8.84
PVC-ASTM D3034
(SDR 35) 12 10.51
C. Be fabricated of steel; be fitted with pulling rings at each end; be stamped or engraved on some segment other than a runner indicating the pipe material specification, nominal size, and mandrel outside diameter (e.g., PVC, D 3034-8"-
7.524"); and be furnished in a carrying case labeled with the same data as stamped or engraved on the mandrel.
D. All costs incurred by the Contractor attributable to mandrel and deflection testing, including any delays, shall be borne by the Contractor at no cost to the Owner.
PART 3 - EXECUTION
3.01 INSTALLING PVC SEWER PIPE
A. Install in accordance with Section 312316, ASTM D2321, and as described below.
B. Pipe shall not deviate more than 1 inch from line or 1/4 inch from grade. Measure for grade at the pipe invert.
C. Minimum bedding thickness shall be as specified in Section 312316.
D. Lay pipe without break, upgrade from structure to structure, with the socket ends of the pipe upgrade.
E. Do not use the pipe as a drain for removing water that has infiltrated into the trench.
F. After joint assembly, bring the bedding material up to pipe spring line. Bedding material shall be imported sand per Section 312316. Place the bedding material on each side of the pipe. Tamp the bedding material into final position at pipe PVC GRAVITY SEWER PIPE 333112-3
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024 spring line and continue to the top of the pipe. Relative compaction shall be in conformance with Section 312316.
G. Then place bedding material to 6 inches above the top of the pipe and compact to the same relative compaction as in the pipe zone per Section 312316. The remainder of the trench backfill shall be native material, installed per Section 312316.
H. Do not use hydro-hammers to compact bedding or backfill.
3.02 INSTALLING LATERALS
A. Each wye branch fitting shall have its barrel diameter equal to the diameter of the sanitary sewer main and the spur (or branch) diameter. Do not place wye branches within 5 feet of any structure.
B. Install wye fittings so that the outlet branch is inclined upward at an angle of 45 degrees. Join laterals to wye branch fittings at the sanitary sewer main by eighth bends. Eighth bends and quarter bends are a part of lateral sewer line.
C. End of the lateral shall be at least 3 feet below the existing or proposed grade of the ground at existing structure to be served or as called for in the drawings.
D. Laterals shall run perpendicular to the sewer main at a minimum grade of 2%. Bed laterals the same as the sewer main into which they connect.
E. Connect to existing laterals as indicated on the drawings.
3.03 INSTALLING PIPE AT MANHOLES AND STRUCTURES
A. Place a length of pipe of the same inside diameter as the adjoining pipe at the inlet and outlet to each manhole or structure. Use one of the following methods:
1. Directly cast a manhole coupling into the manhole base. Provide rubber-ring gasket in the coupling.
2. Stretch a rubber-ring gasket around the pipe to serve as a water stop when cast into the structure wall.
B. Do not cast pipe bells into manholes or structures. Cut off the bell so that no recess or offset appears on the exposed face from the inside wall of the pipe to the outside wall of the pipe. The pipe shall have a plain end, flush with the inside wall of the manhole or structure, or as shown in the drawings.
PVC GRAVITY SEWER PIPE 333112-4
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.04 TESTING FOR DEFECTS OF INSTALLED PIPE
Following placement and compaction of backfill and prior to placing permanent pavement, ball and mandrel the pipe to measure for obstructions (excessive deflections, joint offsets, and lateral pipe intrusions).
3.05 FIELD TESTING FOR PIPE DEFLECTION
A. Test installed pipe to ensure that vertical deflections for plastic pipe do not exceed the maximum allowable deflection. Maximum allowable deflections shall be governed by the mandrel requirements stated herein and shall nominally be:
Nominal Pipe Size Percentage
10 inches 7.5
12 inches 7.5
B. The maximum average inside diameter shall be equal to the average outside diameter per applicable ASTM standard minus two minimum wall thicknesses per applicable ASTM standards. Manufacturing and other tolerances shall not be considered for determining maximum allowable deflections.
C. Perform deflection tests not sooner than 30 days after completion of placement and compaction of backfill. Clean and inspect the pipe for offsets and obstructions prior to testing.
D. Pull a mandrel through the pipe by hand to verify that maximum allowable deflections have not been exceeded. Prior to use, the mandrel shall be certified by an independent testing laboratory. Use of an uncertified mandrel or a mandrel altered or modified after certification will invalidate test. If the mandrel fails to pass, the pipe will be deemed to be over-deflected.
E. Uncover any over-deflected pipe and, if not damaged, reinstall. Remove damaged pipe from the site. Any pipe subjected to any method or process other than removal, which attempts, even successfully, to reduce or cure any over-deflection, shall be uncovered, removed from the site, and replaced with new pipe.
3.06 LEAKAGE TEST
See Section 330130.
3.07 INSTALLING UNDERGROUND DETECTABLE METALLIC PIPE WARNING
TAPE FOR NONMETALLIC PIPE
Provide permanent, bright-colored, continuous-printed tape consisting of an aluminum or steel foil sheathed in a plastic laminate, not less than 2 inches wide by 3 mils thick. Provide green tape with printing which most accurately indicates type of buried service.
PVC GRAVITY SEWER PIPE 333112-5
CHANGE ORDER FOR CIP 2287 SOUTH 4TH STREET SEWER REPLACEMENT 24 Jul 2024
3.08 TESTING FOR ALIGNMENT AND GRADE
After the pipe has been installed, tested for leakage, backfilled to existing grade, and manholes raised to grade and resurfaced, "ball" the pipe from manhole to manhole with a sewer scrubbing ball. After balling the pipe, perform the following:
A. Perform television inspection per Section 330131. If deficiencies are observed, make a digital video recording and note defects requiring correction. Upon completing the corrective work, notify the Owner; the Owner will retelevise the affected portion of the pipeline system. Costs for retelevision will be billed to the Contractor.
END OF SECTION