Central Coast Blue
Grover Beach
City Council Meeting
2 Commitment to Grover Beach
• Being a Good Neighbor
• Acknowledge the history and navigating the dynamics of the project • Compliance with Federal, State, County, and Grover Beach regulations • Listening to various stakeholders
• Communication
• Informal meeting requests
• Formal meeting with those within 300 feet of the project • Communication and Engagement Plan throughout permitting, construction, and operation
• Protection of NCMA Groundwater Basin
3 What is
Central Coast Blue?
4 Advanced Water Purification Facility
1 2 3
5 Potable Reuse in California
Image Credit: WateReuse California
6 Project
Location
Imagery Credits: Google Earth.
7 Advanced Water Purification Facility
Conceptual Layout
8 Advanced Water Purification Facility
Conceptual Layout
How is this project
different than when other
cities were partners?
10 Project Comparison
$10M
Component Phase 1 (2024) Phase 1 (Current)
Treatment Capacity 1 MGD 0.35 to 0.7 MGD
Total Yield 900 AFY 350 to 600 AFY
Pismo Beach Yield 350 AFY 350 to 600 AFY
Injection Wells 4 1
Monitoring Wells 8 2
Pipelines 17,000 LF 2,500 LF
MGD: Million Gallons per Day; AFY: Acre-Feet per Year; LF: Linear Feet 11 Project
Location
Sewer
Credits: Vexcel Imaging; Microsoft.
Why this location?
Why can’t it be in Pismo Beach?
13 Project
Location
Imagery Credits: Google Earth.
14 Timeline for Project
2026 2027 2028 2029 2030
DESIGN
CONSTRUCTION
CONSTRUCTION
PERMITTING
OA
PROCUREMENT
Startup
DESIGN-BUILDER
PROCUREMENT
OPERATIONAL PERMITTING
Fixed Price Proposals
Questions