CPF grants are subject to numerous federal requirements, necessitating coordination and involvement from both the Finance and Recreation Departments. To ensure compliance and effective grant administration, the City approved an agreement with the Michael Baker International team. Under this agreement, Michael Baker will assist with key administrative tasks related to the project and prepare the necessary environmental In addition, the design phase of the project will require architectural and engineering services. Staff recommends engaging BOA Architecture, a firm that has previously provided successful design services for the City, including work on the City Hall and Community Center expansions, as well as the Teen Center renovations.
To initiate the design process and facilitate the preparation of required submittal packages for HUD, staff recommends approval of BOA Architecture’s proposal in the amount of $98,700 for the provision of architectural and engineering design services for the C. Robert Lee Recreation Center Renovation Project.
FISCAL IMPACT
As part of the adopted FY 2025-26 Capital Improvement Program (CIP) budget, the City Council allocated $1,430,000 for the C. Robert Lee Activity Center Renovation Project.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENT(S)
A. Proposal to Provide Engineering Design Services for the C. Robert Lee Activity Center Renovation Project
1511 Cota Avenue
Long Beach, CA 90813
Telephone: 562-912-7900
Telephone: 310-832-2681
www.boaarchitecture.com
Neema Ghanbari, Public Works/Engineering Manager June 2, 2025 City of Hawaiian Gardens
Re: Fee Proposal for Architectural-Engineering Services to Remodel:
Hawaiian Gardens C Robert Lee Activity Center at Civic Center Based on our 5-28-25 site/building walk-thru with you and Ernesto, we are pleased to submit our Fee Proposal for architecture and engineering design services for PSE (plans, specs, estimate) for public bidding to general contractors. We understand that the interior of this existing 40,000 sf Activity Center building will be refreshed and remodeled. For this project we will provide professional Architectural, Electrical, and minor Plumbing and Structural engineering services. As the Architect for this project, we will have overall design and coordination responsibility for all Construction Documents in our scope. Note that we will also provide concept designs (only) to propose a 2nd floor at the boxing gym and convert the existing tennis court for additional surface parking. See that attached sketch site plan for the proposed location of the work. Please be aware that the City’s HUD funding is only $1,400,000, however your desired Scope of Work is likely to cost much more. Our itemized fee spreadsheet is attached, and our scope of work is as follows:
Scope of Work Common for Public Works Projects
1. Site visit(s) to confirm critical dimensions of impacted area, photos, site observation.
2. Attend programing meeting with Client and Users to glean room sizes, functionality, functional relationships, needs, goals, and equipment/furnishing needs.
3. Provide submittals to the Client at 30%, 60%, 90%, 100% completion. Note that we will submit to the City Building-Safety Dept. for plancheck at 90% completion.
4. Secure all relevant City plancheck and building permit approvals.
5. Provide the customary PS &E (Plans, Specs, Estimate) for Public Works bidding to contractors.
6. Provide architectural Construction Support (limited to amount of hours stated in the attached fee spreadsheet: jobsite meetings, response to RFI’s, & submittals, etc.
Scope for the Building Interior Remodel
7. Remodel existing Men-Women restrooms, for ADA Compliance and provide new plumbing fixtures, toilet partitions, toilet accessories, tile walls-flooring, lighting, paint, etc. Note that the Men-Women locker rooms will not have any work done, as they will be kept as storage rooms.
8. In the boxing gym, provide new rubber flooring, new lighting, paint walls, and provide a suspended grid above the boxing ring for lighting and speakers. Additionally, provide a feasibility study (sketch floor plan and ROM cost estimate) for a 2nd floor above the boxing gym that will be used for boxing exercisestraining and storage. Note that an elevator will not be required as the uses on the 2nd floor and the 1st floor will be very similar.
9. At the existing kitchen, provide new flooring, lighting, paint.
10. At the long entrance lobby, maintain the existing public counter, but provide new LED lights, new paint for the ceiling and walls.
11. In the basketball gym, install new fire sprinklers to increase the seating capacity from 500 occupants to 1000 occupants. Verify with the Fire Dept. that fire sprinklers for the entire building will not be needed if we sprinkle the basketball gym only. Additionally, provide new lighting, painting, and acoustic panels on the side walls. No need to replace the wood flooring as the City will do it in the future.
12. In the basketball gym stage, provide a ADA lift for ADA compliance, new flooring, and lighting.
13. In the 2 racquetball courts, replace the lighting only. Painting of the walls and ceiling is not needed.
14. In the large Multipurpose Room, provide new LVT flooring, LED lighting, and new paint on walls and ceiling.
15. Coordinate with the City’s vendor to provide location and electrical power for audio-visual system.
16. Coordinate with the City’s vendor to provide a new location for data outlets as needed.
17. Provide a feasibility study (sketch site plan and ROM cost estimate) to convert the existing tennis court to add surface parking. Also redesign the parking entry area to be more efficient and add parking stalls.
Attachment A
1511 Cota Avenue
Long Beach, CA 90813
Telephone: 562-912-7900
Telephone: 310-832-2681
www.boaarchitecture.com
Items NOT included
a. Soils-geotechnical report
b. Asbestos-hazardous materials report.
c. Coring, scanning, destructive testing
d. Topographic survey, civil engineering
e. Landscape architecture
f. Furniture, furnishings, artwork, design and selection g. ADA parking stalls, path-of-travel to the building
h. Exterior sitework
i. New HVAC equipment and ducts
j. New electrical service
k. Fire alarm system
We are excited by the chance to work with you to enhance and modernize the C. Robert Lee Activity Center. Having complete many, many architectural projects for the City of Hawaiian Gardens and remodeled over 80 municipal community centers for numerous local Cities, we think we are a “good fit” for this project. If awarded, our workload is such that we can begin design work immediately to meet your expedited schedule. If you have any questions, please do not hesitate to contact me personally at (310) 480-7730 cell.
BOA Architecture
Edward Lok Ng, Architect, LEED AP
President
FIXED FEE PROPOSAL
Hawaiian Gardens, C Robert Lee Activity Center Remodel
date: June 2, 2025 Construction Cost Estimate: TBD
prepared by: BOA, Edward Lok Ng, Architect prepared for: City of Hawaiian Gardens, N Ghanbari
HOURS HR RATE COST TOTAL
PRE-DESIGN
kick-off meeting to verify scope of work,obtain as-built dwgs. 4 hrs 150 600 project management, confirm cost/work plan & prep field work 6 hrs 150 900 programing; meeting, program assessment 4 hrs 150 600
site assessment,ADA assessment,as-built measurements,photos 10 hrs 110 1,100 CADD 30 hrs 110 3,300
6,500
ARCHITECTURAL SCHEMATIC DESIGN
preliminary design and design development 30 hrs 150 4,500 project management 10 hrs 150 1,500
CADD-3D modeling 80 hrs 110 8,800
construction cost estimate 8 hrs 150 1,200
meetings and coordination with Client 10 hrs 150 1,500
17,500
ENGINEERING and EXPENSES
structural engineering 4,000
mechanical 0
plumbing 4,000
electrical 17,000
landscape architect 0
civil engineering 0
expenses for building-safety submittal blueprints, photocopies, mailing, misc. 200 25,200
ARCHITECTURAL CONSTRUCTION DOCUMENTS
CADD-3D modeling of construction document drawings 200 hrs 110 22,000 project management,refine schematic design,coord. w engineers 20 hrs 150 3,000 design of special construction detailing 16 hrs 150 2,400 meeting and coordination with Client 20 hrs 150 3,000
specifications in CSI format 20 hrs 150 3,000
construction cost estimate 8 hrs 150 1,200
quality control 20 hrs 150 3,000
Client and City bldg-safety dept. submittal & corrections 30 hrs 110 3,300 40,900
ARCHITECTURAL CONSTRUCTION SUPPORT
pre-bid meeting hrs 150 0
pre-construction meeting 0 hrs 150 0
project management, RFI & submittal response 40 hrs 150 6,000 CADD-3D modeling of construction document drawings 10 hrs 110 1,100 construction site meeting, 1 punchlist meeting 10 hrs 150 1,500 8,600
TOTAL FEE $98,700
CITY OF HAWAIIAN GARDENS
CITY COUNCIL
STAFF REPORT
Agenda Item #B8
DATE: June 25, 2025
TO: Honorable Mayor and Members of the City Council
FROM: Ernesto Marquez, City Manager
BY: Neema Ghanbari, Public Works Manager
RECOMMENDATION:
RECOMMENDATION TO AUTHORIZE THE CITY MANAGER TO EXECUTE AGREEMENTS WITH ONSHORE MECHANICAL INC., AND MESA ENERGY SYSTEMS, INC. FOR ON-CALL HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) MAINTENANCE AND REPAIR SERVICES AT CITY FACILITIES
SUMMARY
The City of Hawaiian Gardens maintains multiple facilities that rely on Heating, Ventilating, and Air Conditioning (HVAC) systems for proper climate control to ensure the safety and comfort of employees and the public, as well as to protect equipment and infrastructure. These systems require regular maintenance and occasional emergency repair services.
To support the timely and efficient maintenance and repair of HVAC systems, the City issued a Request for Proposals (RFP) on May 7, 2025, seeking qualified contractors to provide on-call HVAC maintenance services. The goal was to establish agreements with vendor(s) to ensure responsiveness and continuity of service.
On May 28, 2025, the City received six (6) proposals from vendors. Following a thorough evaluation of qualifications, experience, responsiveness, references, and cost competitiveness, Onshore Mechanical Inc., and Mesa Energy Systems, Inc. were selected as the most qualified and responsive proposers.
Entering into agreements with both vendors will allow the City flexibility to address routine maintenance and urgent repair needs efficiently. Having two contractors ensures sufficient coverage, promotes competitive pricing, and enhances service delivery across all City facilities.
Agenda Item #B8
June 25, 2025
The agreements will cover a broad scope of services including, but not limited to:
1- Preventive maintenance of HVAC systems
2- Emergency repair and diagnostic services
3- Replacement and installation of HVAC components
4- Compliance with applicable environmental and safety regulations Work will be assigned on routine maintenance and as-needed basis under task orders issued and approved by the Public Works Department.
Staff recommends that the City Council authorize the City Manager to execute agreements with Onshore Mechanical Inc., and Mesa Energy Systems, Inc. for the provision of on-call Heating, Ventilating, and Air Conditioning (HVAC) maintenance and repair services at City facilities, each for a term of three years, with options for two oneyear extension terms.
FISCAL IMPACT
None. Sufficient funds are appropriated in the Public Works Department’s Contract Services account to cover the routine maintenance costs for HVAC maintenance and repair services.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENT(S)
A. Professional Services Agreement Between the City of Hawaiian Gardens and Mesa Energy Systems, Inc.
B. Professional Services Agreement Between the City of Hawaiian Gardens and Onshore Mechanical Inc.
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY OF HAWAIIAN GARDENS AND MESA ENERGY SYSTEMS, INC.
This AGREEMENT is entered into this 25th day of June 2025 by and between the CITY OF HAWAIIAN GARDENS, a general law city a municipal corporation (“CITY”) and Mesa Energy Systems, Inc. (“CONTRACTOR”). CITY and CONTRACTOR may be referred to individually as “Party” or collectively as “Parties.”
R E C I T A L S
A. The CITY desires to obtain preventive maintenance of HVAC systems, emergency repair and diagnostic services, replacement and installation of HVAC components, and compliance with applicable environmental and safety regulations.
B. The CITY does not have the personnel able and/or available to perform the services required under this agreement and therefore, the CITY desires to contract for services to accomplish this work.
C. The CONTRACTOR warrants to the CITY that it has the qualifications, experience and facilities to perform properly and timely the services under this Agreement.
D. The CITY desires to contract with the CONTRACTOR to perform the services as described in Exhibit A of this Agreement.
NOW, THEREFORE, based on the foregoing recitals, the CITY and the CONTRACTOR agree as follows:
CONSIDERATION AND COMPENSATION As partial consideration, CONTRACTOR agrees to perform the work listed in the SCOPE OF SERVICES, attached as EXHIBIT A.
As additional consideration, CONTRACTOR and CITY agree to abide by the terms and conditions contained in this Agreement.
As additional consideration, CITY agrees to pay CONTRACTOR An amount not to exceed $100,000 during the term of the Agreement as specified in paragraph 7 below, for CONTRACTOR’s services, unless otherwise specified by written amendment to this Agreement.
No additional compensation shall be paid for any other expenses incurred, unless first approved by the City Manager or his/her designee.
CONTRACTOR shall submit to CITY, by not later than the 10th day of each month, its invoice for services itemizing the fees and costs incurred during the previous month. CITY shall pay CONTRACTOR all uncontested amounts set forth in CONTRACTOR’s invoice within 30 days after it is received.
SCOPE OF SERVICES. CONTRACTOR will perform the services and activities set forth in the SCOPE OF SERVICE attached hereto as Exhibit A and incorporated herein by this reference.
Attachment A
Except as herein otherwise expressly specified to be furnished by CITY, CONTRACTOR will, in a professional manner, furnish all of the labor, technical, administrative, professional and other personnel, all supplies and materials, equipment, printing, vehicles, transportation, office space, and facilities necessary or proper to perform and complete the work and provide the professional services required of CONTRACTOR by this Agreement.
PAYMENTS. For CITY to pay CONTRACTOR as specified by this Agreement, CONTRACTOR must submit an invoice to CITY which lists the reimbursable costs, the specific tasks performed, and, for work that includes deliverables, the percentage of the task completed during the billing period in accordance with the schedule of compensation incorporated in “Exhibit A.” TIME OF PERFORMANCE. The services of the CONTRACTOR are to commence upon receipt of a notice to proceed from the CITY and shall continue until all authorized work is completed to the CITY’s reasonable satisfaction, in accordance with the schedule incorporated in “Exhibit A,” unless extended in writing by the CITY.
FAMILIARITY WITH WORK. By executing this Agreement, CONTRACTOR represents that CONTRACTOR has (a) thoroughly investigated and considered the scope of services to be performed; (b) carefully considered how the services should be performed; and (c) understands the facilities, difficulties, and restrictions attending performance of the services under this Agreement.
KEY PERSONNEL. CONTRACTOR’s key person assigned to perform work under this Agreement is Bryan Gilbert. CONTRACTOR shall not assign another person to be in charge of the work contemplated by this Agreement without the prior written authorization of the CITY.
TERM OF AGREEMENT. The term of this Agreement shall commence upon execution by both parties and shall expire on June 25, 2028, unless earlier termination occurs under Section 11 of this Agreement, or this Agreement is extended in writing in advance by both parties.
CHANGES. CITY may order changes in the services within the general scope of this Agreement, consisting of additions, deletions, or other revisions, and the contract sum and the contract time will be adjusted accordingly. All such changes must be authorized in writing, executed by CONTRACTOR and CITY. The cost or credit to CITY resulting from changes in the services will be determined in accordance with written agreement between the parties.
TAXPAYER IDENTIFICATION NUMBER. CONTRACTOR will provide CITY with a Taxpayer Identification Number.
PERMITS AND LICENSES. CONTRACTOR will obtain and maintain during the term of this Agreement all necessary permits, licenses, and certificates that may be required in connection with the performance of services under this Agreement.
TERMINATION. Except as otherwise provided, CITY may terminate this Agreement at any time with or without cause. Notice of termination shall be in writing.
CONTRACTOR may terminate this Agreement. Notice will be in writing at least 30 days before the effective termination date.
In the event of such termination, the CONTRACTOR shall cease services as of the date of termination, and all finished or unfinished documents, data, drawings, maps, and other materials prepared by CONTRACTOR shall, at CITY’s option, become CITY’s property, and CONTRACTOR will receive just and equitable compensation for any work satisfactorily completed up to the effective date of notice of termination.
Should the Agreement be terminated pursuant to this Section, CITY may procure services similar to those terminated without restriction by this Agreement.
INDEMNIFICATION. CONTRACTOR shall indemnify, defend with counsel approved by CITY, and hold harmless CITY, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, and cost (including without limitation reasonable attorneys fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with CONTRACTOR's performance of work hereunder or its failure to comply with any of its obligations contained in this AGREEMENT, regardless of CITY’S passive negligence, but excepting such loss or damage which is caused by the sole active negligence or willful misconduct of the CITY. Should CITY in its sole discretion find CONTRACTOR’S legal counsel unacceptable, then CONTRACTOR shall reimburse the CITY its costs of defense, including without limitation reasonable attorneys fees, expert fees and all other costs and fees of litigation. The CONTRACTOR shall promptly pay any final judgmentrendered against the CITY (and its officers, officials, employees and volunteers) covered by this indemnity obligation. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement.
The requirements as to the types and limits of insurance coverage to be maintained by CONTRACTOR as required by Section 17, and any approval of said insurance by CITY, are not intended to and will not in any manner limit or qualify the liabilities and obligations otherwise assumed by CONTRACTOR pursuant to this Agreement, including, without limitation, to the provisions concerning indemnification.
ASSIGNABILITY. This Agreement is for CONTRACTOR’s professional services. CONTRACTOR’s attempts to assign the benefits or burdens of this Agreement without CITY’s written approval are prohibited and will be null and void.
INDEPENDENT CONTRACTOR. CITY and CONTRACTOR agree that CONTRACTOR will act as an independent contractor and will have control of all work and the manner in which is it performed.
CONTRACTOR will be free to contract for similar service to be performed for other employers while under contract with CITY. CONTRACTOR is not an agent or employee of CITY and is not entitled to participate in any pension plan, insurance, bonus or similar benefits CITY provides for its employees.
Any provision in this Agreement that may appear to give CITY the right to direct CONTRACTOR as to the details of doing the work or to exercise a measure of control over the work means that CONTRACTOR will follow the direction of the CITY as to end results of the work only.
AUDIT OF RECORDS. CONTRACTOR agrees that CITY, or designee, hasthe right to review, obtain, and copy all records pertaining to the performance of this Agreement. CONTRACTOR agrees to provide CITY, or designee, with any relevant information requested and will permit CITY, or designee, access to its premises, upon reasonable notice, during normal business hours for the purpose of interviewing employees and inspecting and copying such books, records, accounts, and other material that may be relevant to a matter under investigation for the purpose of determining compliance with this Agreement. CONTRACTOR further agrees to maintain such records for a period of three (3) years following final payment under this Agreement.
CONTRACTOR will keep all books, records, accounts and documents pertaining to this Agreement separate from other activities unrelated to this Agreement.
CORRECTIVE MEASURES. CONTRACTOR will promptly implement any corrective measures required by CITY regarding the requirements and obligations of this Agreement. CONTRACTOR will be given a reasonable amount of time as determined by the CITY to implement said corrective measures.
Failure of CONTRACTOR to implement required corrective measures shall result in immediate termination of this Agreement.
INSURANCE REQUIREMENTS.
A. The CONTRACTOR, at the CONTRACTOR’s own cost and expense, shall procure and maintain, for the duration of the contract, the following insurance policies:
1. Workers Compensation Insurance as required by law. The CONTRACTOR shall require all subcontractors similarly to provide such compensation insurance for their respective employees.
Any notice of cancellation or non-renewal of all Workers’ Compensation policies must be received by the CITY at least thirty (30) days prior to such change. The insurer shall agree to waive all rights of subrogation against the CITY, its officers, agents, employees, and volunteers for losses arising from work performed by the CONTRACTOR for CITY.
2. General Liability Coverage. The CONTRACTOR shall maintain commercial general liability insurance in an amount of not less than two million dollars ($2,000,000) per occurrence for bodily injury, personal injury, and property damage. If a commercial general liability insurance form or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to the work to be performed under this Agreement or the general aggregate limit shall be at least twice the required occurrence limit.
3. Automobile Liability Coverage. The CONTRACTOR shall maintain automobile liability insurance covering bodily injury and property damage for all activities of the CONTRACTOR arising out of or in connection with the work to be performed under this Agreement, including coverage for owned, hired, and non-owned vehicles, in an amount of not less than one million dollars ($1,000,000) combined single limit for each occurrence.
4. Professional Liability Coverage. The CONTRACTOR shall maintain professional errors and omissions liability insurance for protection against claims alleging negligent acts, errors, or omissions which may arise from the CONTRACTOR’S operations under this Agreement, whether such operations be by the CONTRACTOR or by its employees, subcontractors, or subcontractors. The amount of this insurance shall not be less than one million dollars ($1,000,000) on a claims-made annual aggregate basis, or a combined single-limit-peroccurrence basis. When coverage is provided on a “claims made basis,” CONTRACTOR will continue to renew the insurance for a period of three (3) years after this Agreement expires or is terminated. Such insurance will have the same coverage and limits as the policy that was in effect during the term of this Agreement, and will cover CONTRACTOR for all claims made by CITY arising out of any errors or omissions of CONTRACTOR, or its officers, employees or agents during the time this Agreement was in effect.
B. Endorsements. Each general liability, automobile liability and professional liability insurance policy shall be issued by a financially responsible insurance company or companies admitted and authorized to do business in the State of California, or which is approved in writing by CITY, and shall be endorsed as follows. CONTRACTOR also agrees to require all contractors, and subcontractors to do likewise.
1. “The CITY, its elected or appointed officers, officials, employees, agents, and volunteers are to be covered as additional insureds with respect to liability arising out of work performed by or on behalf of the CONTRACTOR, including materials, parts, or equipment furnished in connection with such work or operations.”
2. This policy shall be considered primary insurance as respects the CITY, its elected or appointed officers, officials, employees, agents, and volunteers. Any insurance maintained by the CITY, including any self-insured retention the CITY may have, shall be considered excess insurance only and shall not contribute with this policy.
3. This insurance shall act for each insured and additional insured as though a separate policy had been written for each, except with respect to the limits of liability of the insuring company.
4. The insurer waives all rights of subrogation against the CITY, its elected or appointed officers, officials, employees, or agents.
5. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the CITY, its elected or appointed officers, officials, employees, agents, or volunteers.
6. The insurance provided by this policy shall not be suspended, voided, canceled, or reduced in coverage or in limits except after thirty (30) days written notice has been received by the CITY.
C. CONTRACTOR agreesto provide immediate notice to CITY of any claim or loss against Contractor arising out of the work performed under this agreement. CITY assumes no obligation or liability by such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve CITY.
D. Any deductibles or self-insured retentions must be declared to and approved by the CITY. At the CITY’s option, the CONTRACTOR shall demonstrate financial capability for payment of such deductibles or self-insured retentions.
E. The CONTRACTOR shall provide certificates of insurance with original endorsements to the CITY as evidence of the insurance coverage required herein. Certificates of such insurance shall be filed with the CITY on or before commencement of performance of this Agreement. Current certification of insurance shall be kept on file with the CITY at all times during the term of this Agreement.
F. Failure on the part of the CONTRACTOR to procure or maintain required insurance shall constitute a material breach of contract under which the CITY may terminate this Agreement pursuant to Section 11 above.
G. The commercial general and automobile liability policies required by this Agreement shall allow CITY, as additional insured, to satisfy the self-insured retention (“SIR”) and/or deductible of the policy in lieu of the CONTRACTOR (as the named insured) should CONTRACTOR fail to pay the SIR or deductible requirements. The amount of the SIR or deductible shall be subject to the approval of the City Attorney and the Finance Director. CONTRACTOR understands and agrees that satisfaction of this requirement is an express condition precedent to the effectiveness of this Agreement. Failure by CONTRACTOR as primary insured to pay its SIR or deductible constitutes a material breach of this Agreement. Should CITY pay the SIR or deductible on CONTRACTOR’s behalf upon the CONTRACTOR’s failure or refusal to do so in order to secure defense and indemnification as an additional insured under the policy, CITY may include such amounts as damages in any action against CONTRACTOR for breach of this Agreement in addition to any other damages incurred by CITY due to the breach.
USE OF OTHER CONTRACTORS. CONTRACTOR must obtain CITY’s prior written approval to use any sub-contractors while performing any portion of this Agreement. Such approval must include approval of the proposed CONTRACTOR and the terms of compensation.
FINAL PAYMENT ACCEPTANCE CONSTITUTES RELEASE. The acceptance by the CONTRACTOR of the final payment made under this Agreement shall operate as and be a release of the CITY from all claims and liabilities for compensation to the CONTRACTOR for anything done, furnished or relating to the CONTRACTOR’S work or services. Acceptance of payment shall be any negotiation of the CITY’S check or the failure to make a written extra compensation claim within ten (10) calendar days of the receipt of that check. However, approval or payment by the CITY shall not constitute, nor be deemed, a release of the responsibility and liability of the CONTRACTOR, its employees, sub-contractors and agents for the accuracy and competency of the information provided
and/or work performed; nor shall such approval or payment be deemed to be an assumption of such responsibility or liability by the CITY for any defect or error in the work prepared by the CONTRACTOR, its employees, sub-contractors and agents.
CORRECTIONS. In addition to the above indemnification obligations, the CONTRACTOR shall correct, at its expense, all errors in the work which may be disclosed during the CITY’s review of the CONTRACTOR’s report or plans. Should the CONTRACTOR fail to make such correction in a reasonably timely manner, such correction shall be made by the CITY, and the cost thereof shall be charged to the CONTRACTOR. In addition to all other available remedies, the CITY may deduct the cost ofsuch correction from any retention amount held by the CITY or may withhold payment otherwise owed CONTRACTOR under this Agreement up to the amount of the cost of correction.
NON-APPROPRIATION OF FUNDS. Payments to be made to CONTRACTOR by CITY for services preformed within the current fiscal year are within the current fiscal budget and within an available, unexhausted fund. In the event that CITY does not appropriate sufficient funds for payment of CONTRACTOR’S services beyond the current fiscal year, the Agreement shall cover payment for CONTRACTOR’S services only to the conclusion of the last fiscal year in which CITY appropriates sufficient funds and shall automatically terminate at the conclusion of such fiscal year.
NOTICES. All communications to either party by the other party will be deemed made when received by such party at its respective name and address as follows:
CITY CONTRACTOR
City of Hawaiian Gardens
21815 Pioneer Blvd.,
Hawaiian Gardens, CA 90716
ATTN: City Manager
Any such written communications by mail will be conclusively deemed to have been received by the addressee upon deposit thereof in the United States Mail, postage prepaid and properly addressed as noted above. In all other instances, notices will be deemed given at the time of actual delivery. Changes may be made in the names or addresses of persons to whom notices are to be given by giving notice in the manner prescribed in this paragraph. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.
SOLICITATION. CONTRACTOR maintains and warrants that it has not employed nor retained any company or person, other than CONTRACTOR’s bona fide employee, to solicit or secure this Agreement. Further, CONTRACTOR warrantsthat it has not paid nor has it agreed to pay any company or person, other than CONTRACTOR’s bona fide employee, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. Should CONTRACTOR breach or violate this warranty, CITY may rescind this Agreement without liability.
THIRD PARTY BENEFICIARIES. This Agreement and every provision herein is generally for the exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of CONTRACTOR’s or CITY’s obligations under this Agreement.
Mesa Energy Systems, Inc.
2 Cromwell
Irvine, CA 92618
ATTN: Bryan Gilbert,GM
INTERPRETATION. This Agreement was drafted in, and will be construed in accordance with the laws of the State of California, and exclusive venue for any action involving this agreement will be in Los Angeles County.
ENTIRE AGREEMENT. This Agreement, and its Attachments, sets forth the entire understanding of the parties. There are no other understandings, terms or other agreements expressed or implied, oral or written.
RULES OF CONSTRUCTION. Each Party had the opportunity to independently review this Agreement with legal counsel. Accordingly, this Agreement will be construed simply, as a whole, and in accordance with its fair meaning; it will not be interpreted strictly for or against either Party.
AUTHORITY/MODIFICATION. The Parties represent and warrant that all necessary action has been taken by the Parties to authorize the undersigned to execute this Agreement and to engage in the actions described herein. This Agreement may be modified by written amendment with signatures of all parties to this Agreement. CITY’s City Manager, or designee, may execute any such amendment on behalf of CITY.
ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES. The Parties agree that this Contract, agreements ancillary to this Contract, and related documents to be entered into in connection with this Contract will be considered signed when the signature of a party is delivered by facsimile transmission or scanned and delivered via electronic mail. Such facsimile or electronic mail copies will be treated in all respects as having the same effect as an original signature.
FORCE MAJEURE. Should performance of this Agreement be impossible due to fire, flood, explosion, war, embargo, government action, civil or military authority, the natural elements, or other similar causes beyond the Parties’ control, then the Agreement will immediately terminate without obligation of either party to the other.
TIME IS OF ESSENCE. Time is of the essence to comply with dates and schedules to be provided.
ATTORNEY’S FEES. The parties hereto acknowledge and agree that each will bear his or its own costs, expenses and attorneys' fees arising out of and/or connected with the negotiation, drafting and execution of the Agreement, and all matters arising out of or connected therewith except that, in the event any action is brought by any party hereto to enforce this Agreement, the prevailing party in such action shall be entitled to reasonable attorneys' fees and costs in addition to all other relief to which that party or those parties may be entitled.
STATEMENT OF EXPERIENCE. By executing this Agreement, CONTRACTOR represents that it has demonstrated trustworthiness and possesses the quality, fitness and capacity to perform the Agreement in a manner satisfactory to CITY. CONTRACTOR represents that its financial resources, surety and insurance experience, service experience, completion ability, personnel, current workload, experience in dealing with private CONTRACTORs, and experience in dealing with public agencies all suggest that CONTRACTOR is capable of performing the proposed contract and has a demonstrated capacity to deal fairly and effectively with and to satisfy a public agency.
OWNERSHIP OF DOCUMENTS. It is understood and agreed that the CITY shall own all documents and other work product of the CONTRACTOR, except the CONTRACTOR’s notes and workpapers, which pertain to the work performed under this Agreement. The CITY shall have the sole right to use such materials in its discretion and without further compensation to the CONTRACTOR, but any re-
use of such documents by the CITY on any other project without prior written consent of the CONTRACTOR shall be at the sole risk of the CITY.
DISCLOSURE REQUIRED. (CITY and CONTRACTOR initials required at one of the following paragraphs)
By their respective initials next to this paragraph, CITY and CONTRACTOR hereby acknowledge that CONTRACTOR is a “CONTRACTOR” for the purposes of the California Political Reform Act because CONTRACTOR’s duties would require him or her to make one or more of the governmental decisions set forth in Fair Political Practices Commission Regulation 18700.3(a) or otherwise serves in a staff capacity for which disclosure would otherwise be required were CONTRACTOR employed by the CITY.
CONTRACTOR hereby acknowledges his or her assuming-office, annual, and leaving-office financial reporting obligations under the California Political Reform Act and the CITY’s Conflict of Interest Code and agrees to comply with those obligations at his or her expense. Prior to CONTRACTOR commencing services hereunder, the City’s Manager shall prepare and deliver to CONTRACTOR a memorandum detailing the extent of CONTRACTOR’s disclosure obligations in accordance with the CITY’s Conflictof Interest Code.
36 LABOR COMPLIANCE. As used herein, “Project” is synonymous with services described in this Agreement.
36.1 Prevailing Wages. Contractor is aware of the requirements of California Labor Code Section 1720 et seq., and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq., (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. Since the Services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Contract upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at Contractor’s principal place of business and at the project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. Contractor and any subcontractor shall forfeit a penalty of up to $200 per calendar day or portion thereof for each worker paid less than the prevailing wage rates.
36.2 Apprenticeable Crafts. When Contractor employs workmen in an apprenticeable craft or trade, Contractor shall comply with the provisions of Section 1777.5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works. The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor. The Contractor or any subcontractor that is determined by the Labor Commissioner to have knowingly violated Section 1777.5 shall forfeit as a civil penalty an amount not exceeding $100 for each full calendar day of noncompliance, or such greater amount as provided by law.
36.3 Hours of Work. Contractor is advised that eight (8) hours labor constitutes a legal day’s work. Pursuant to Section 1813 of the California Labor Code, Contractor shall forfeit a penalty of $25.00 per worker for each day that each worker is permitted to work more than eight (8) hours in any one calendar day and forty (40) hours in any one calendar week, except when payment for overtime is made at not less than one and one-half (1-1/2) times the basic rate for that worker.
36.4 Payroll Records. Contractor and each subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime
hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the public work. The payroll records shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor in the manner provided in Labor Code section 1776. In the event of noncompliance with the requirements of this section, Contractor shall have 10 days in which to comply subsequent to receipt of written notice specifying in what respects such Contractor must comply with this section. Should noncompliance still be evident after such 10-day period, Contractor shall, as a penalty to City, forfeit not more than $100.00 for each calendar day or portion thereof, for each worker, until strict compliance is effectuated. The amount of the forfeiture is to be determined by the Labor Commissioner. A contractor who is found to have violated the provisions of law regarding wages on Public Works with the intent to defraud shall be ineligible to bid on Public Works contracts for a period of one to three years as determined by the Labor Commissioner. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payments then due. The responsibility for compliance with this section is on Contractor. The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4.
36.5 Contractor and Subcontractor Registration. Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. Contractor is directed to review, fill out and execute the Public Works Contractor Registration Certification attached hereto as Exhibit “E” prior to contract execution. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.
36.6 Labor Compliance; Stop Orders. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be the Contractor’s sole responsibility to evaluate and pay the cost of complying with all labor compliance requirements under this Contract and applicable law. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.
CITY Initials
CONTRACTOR Initials
OR
By their initials next to this paragraph, CITY and CONTRACTOR hereby acknowledge that CONTRACTOR is not a “CONTRACTOR” for the purpose of the California Political Reform Act because CONTRACTOR’s duties and responsibilities are not within the scope of the definition of CONTRACTOR in Fair Political Practice Commission Regulation 18700.3(a) and is otherwise not serving in staff capacity in accordance with the CITY’s Conflict of Interest Code.
CITY Initials
CONTRACTOR Initials
IN WITNESS WHEREOF the parties hereto have executed this contract the day and year first hereinabove written.
CITY OF HAWAIIAN GARDENS CONTRACTOR
Ernesto Marquez, City Manager By: Bryan Gilbert, SVP & General Manager ATTEST:
Pablo Rubio, City Clerk Taxpayer ID No.
APPROVED AS TO FORM:
Norma Tabares, City Attorney
17 City of Hawaiian Gardens On-Call HVAC Preventative Maintenance and Repair 5/28/2025
Proposal Title
18 City of Hawaiian Gardens On-Call HVAC Preventative Maintenance and Repair 5/28/2025
Proposal Title
19 City of Hawaiian Gardens On-Call HVAC Preventative Maintenance and Repair 5/28/2025
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY OF HAWAIIAN GARDENS AND ONSHORE MECHANICAL INC.
This AGREEMENT is entered into this 25th day of June 2025 by and between the CITY OF HAWAIIAN GARDENS, a general law city a municipal corporation (“CITY”) and Onshore Mechanical (“CONTRACTOR”). CITY and CONTRACTOR may be referred to individually as “Party” or collectively as “Parties.”
R E C I T A L S
A. The CITY desires to obtain preventive maintenance of HVAC systems, emergency repair and diagnostic services, replacement and installation of HVAC components, and compliance with applicable environmental and safety regulations.
B. The CITY does not have the personnel able and/or available to perform the services required under this agreement and therefore, the CITY desires to contract for services to accomplish this work.
C. The CONTRACTOR warrants to the CITY that it has the qualifications, experience and facilities to perform properly and timely the services under this Agreement.
D. The CITY desires to contract with the CONTRACTOR to perform the services as described in Exhibit A of this Agreement.
NOW, THEREFORE, based on the foregoing recitals, the CITY and the CONTRACTOR agree as follows:
CONSIDERATION AND COMPENSATION As partial consideration, CONTRACTOR agrees to perform the work listed in the SCOPE OF SERVICES, attached as EXHIBIT A.
As additional consideration, CONTRACTOR and CITY agree to abide by the terms and conditions contained in this Agreement.
As additional consideration, CITY agrees to pay CONTRACTOR An amount not to exceed $100,000 during the term of the Agreement as specified in paragraph 7 below, for CONTRACTOR’s services, unless otherwise specified by written amendment to this Agreement.
No additional compensation shall be paid for any other expenses incurred, unless first approved by the City Manager or his/her designee.
CONTRACTOR shall submit to CITY, by not later than the 10th day of each month, its invoice for services itemizing the fees and costs incurred during the previous month. CITY shall pay CONTRACTOR all uncontested amounts set forth in CONTRACTOR’s invoice within 30 days after it is received.
SCOPE OF SERVICES. CONTRACTOR will perform the services and activities set forth in the SCOPE OF SERVICE attached hereto as Exhibit A and incorporated herein by this reference.
Attachment B
Except as herein otherwise expressly specified to be furnished by CITY, CONTRACTOR will, in a professional manner, furnish all of the labor, technical, administrative, professional and other personnel, all supplies and materials, equipment, printing, vehicles, transportation, office space, and facilities necessary or proper to perform and complete the work and provide the professional services required of CONTRACTOR by this Agreement.
PAYMENTS. For CITY to pay CONTRACTOR as specified by this Agreement, CONTRACTOR must submit an invoice to CITY which lists the reimbursable costs, the specific tasks performed, and, for work that includes deliverables, the percentage of the task completed during the billing period in accordance with the schedule of compensation incorporated in “Exhibit A.” TIME OF PERFORMANCE. The services of the CONTRACTOR are to commence upon receipt of a notice to proceed from the CITY and shall continue until all authorized work is completed to the CITY’s reasonable satisfaction, in accordance with the schedule incorporated in “Exhibit A,” unless extended in writing by the CITY.
FAMILIARITY WITH WORK. By executing this Agreement, CONTRACTOR represents that CONTRACTOR has (a) thoroughly investigated and considered the scope of services to be performed; (b) carefully considered how the services should be performed; and (c) understands the facilities, difficulties, and restrictions attending performance of the services under this Agreement.
KEY PERSONNEL. CONTRACTOR’s key person assigned to perform work under this Agreement is Brock A. Dains. CONTRACTOR shall not assign another person to be in charge of the work contemplated by this Agreement without the prior written authorization of the CITY.
TERM OF AGREEMENT. The term of this Agreement shall commence upon execution by both parties and shall expire on June 25, 2028, unless earlier termination occurs under Section 11 of this Agreement, or this Agreement is extended in writing in advance by both parties.
CHANGES. CITY may order changes in the services within the general scope of this Agreement, consisting of additions, deletions, or other revisions, and the contract sum and the contract time will be adjusted accordingly. All such changes must be authorized in writing, executed by CONTRACTOR and CITY. The cost or credit to CITY resulting from changes in the services will be determined in accordance with written agreement between the parties.
TAXPAYER IDENTIFICATION NUMBER. CONTRACTOR will provide CITY with a Taxpayer Identification Number.
PERMITS AND LICENSES. CONTRACTOR will obtain and maintain during the term of this Agreement all necessary permits, licenses, and certificates that may be required in connection with the performance of services under this Agreement.
TERMINATION. Except as otherwise provided, CITY may terminate this Agreement at any time with or without cause. Notice of termination shall be in writing.
CONTRACTOR may terminate this Agreement. Notice will be in writing at least 30 days before the effective termination date.
In the event of such termination, the CONTRACTOR shall cease services as of the date of termination, and all finished or unfinished documents, data, drawings, maps, and other materials prepared by CONTRACTOR shall, at CITY’s option, become CITY’s property, and CONTRACTOR will receive just and equitable compensation for any work satisfactorily completed up to the effective date of notice of termination.
Should the Agreement be terminated pursuant to this Section, CITY may procure services similar to those terminated without restriction by this Agreement.
INDEMNIFICATION. CONTRACTOR shall indemnify, defend with counsel approved by CITY, and hold harmless CITY, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, and cost (including without limitation reasonable attorneys fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with CONTRACTOR's performance of work hereunder or its failure to comply with any of its obligations contained in this AGREEMENT, regardless of CITY’S passive negligence, but excepting such loss or damage which is caused by the sole active negligence or willful misconduct of the CITY. Should CITY in its sole discretion find CONTRACTOR’S legal counsel unacceptable, then CONTRACTOR shall reimburse the CITY its costs of defense, including without limitation reasonable attorneys fees, expert fees and all other costs and fees of litigation. The CONTRACTOR shall promptly pay any final judgmentrendered against the CITY (and its officers, officials, employees and volunteers) covered by this indemnity obligation. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement.
The requirements as to the types and limits of insurance coverage to be maintained by CONTRACTOR as required by Section 17, and any approval of said insurance by CITY, are not intended to and will not in any manner limit or qualify the liabilities and obligations otherwise assumed by CONTRACTOR pursuant to this Agreement, including, without limitation, to the provisions concerning indemnification.
ASSIGNABILITY. This Agreement is for CONTRACTOR’s professional services. CONTRACTOR’s attempts to assign the benefits or burdens of this Agreement without CITY’s written approval are prohibited and will be null and void.
INDEPENDENT CONTRACTOR. CITY and CONTRACTOR agree that CONTRACTOR will act as an independent contractor and will have control of all work and the manner in which is it performed.
CONTRACTOR will be free to contract for similar service to be performed for other employers while under contract with CITY. CONTRACTOR is not an agent or employee of CITY and is not entitled to participate in any pension plan, insurance, bonus or similar benefits CITY provides for its employees.
Any provision in this Agreement that may appear to give CITY the right to direct CONTRACTOR as to the details of doing the work or to exercise a measure of control over the work means that CONTRACTOR will follow the direction of the CITY as to end results of the work only.
AUDIT OF RECORDS. CONTRACTOR agrees that CITY, or designee, hasthe right to review, obtain, and copy all records pertaining to the performance of this Agreement. CONTRACTOR agrees to provide CITY, or designee, with any relevant information requested and will permit CITY, or designee, access to its premises, upon reasonable notice, during normal business hours for the purpose of interviewing employees and inspecting and copying such books, records, accounts, and other material that may be relevant to a matter under investigation for the purpose of determining compliance with this Agreement. CONTRACTOR further agrees to maintain such records for a period of three (3) years following final payment under this Agreement.
CONTRACTOR will keep all books, records, accounts and documents pertaining to this Agreement separate from other activities unrelated to this Agreement.
CORRECTIVE MEASURES. CONTRACTOR will promptly implement any corrective measures required by CITY regarding the requirements and obligations of this Agreement. CONTRACTOR will be given a reasonable amount of time as determined by the CITY to implement said corrective measures.
Failure of CONTRACTOR to implement required corrective measures shall result in immediate termination of this Agreement.
INSURANCE REQUIREMENTS.
A. The CONTRACTOR, at the CONTRACTOR’s own cost and expense, shall procure and maintain, for the duration of the contract, the following insurance policies:
1. Workers Compensation Insurance as required by law. The CONTRACTOR shall require all subcontractors similarly to provide such compensation insurance for their respective employees.
Any notice of cancellation or non-renewal of all Workers’ Compensation policies must be received by the CITY at least thirty (30) days prior to such change. The insurer shall agree to waive all rights of subrogation against the CITY, its officers, agents, employees, and volunteers for losses arising from work performed by the CONTRACTOR for CITY.
2. General Liability Coverage. The CONTRACTOR shall maintain commercial general liability insurance in an amount of not less than two million dollars ($2,000,000) per occurrence for bodily injury, personal injury, and property damage. If a commercial general liability insurance form or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to the work to be performed under this Agreement or the general aggregate limit shall be at least twice the required occurrence limit.
3. Automobile Liability Coverage. The CONTRACTOR shall maintain automobile liability insurance covering bodily injury and property damage for all activities of the CONTRACTOR arising out of or in connection with the work to be performed under this Agreement, including coverage for owned, hired, and non-owned vehicles, in an amount of not less than one million dollars ($1,000,000) combined single limit for each occurrence.
4. Professional Liability Coverage. The CONTRACTOR shall maintain professional errors and omissions liability insurance for protection against claims alleging negligent acts, errors, or omissions which may arise from the CONTRACTOR’S operations under this Agreement, whether such operations be by the CONTRACTOR or by its employees, subcontractors, or subcontractors. The amount of this insurance shall not be less than one million dollars ($1,000,000) on a claims-made annual aggregate basis, or a combined single-limit-peroccurrence basis. When coverage is provided on a “claims made basis,” CONTRACTOR will continue to renew the insurance for a period of three (3) years after this Agreement expires or is terminated. Such insurance will have the same coverage and limits as the policy that was in effect during the term of this Agreement, and will cover CONTRACTOR for all claims made by CITY arising out of any errors or omissions of CONTRACTOR, or its officers, employees or agents during the time this Agreement was in effect.
B. Endorsements. Each general liability, automobile liability and professional liability insurance policy shall be issued by a financially responsible insurance company or companies admitted and authorized to do business in the State of California, or which is approved in writing by CITY, and shall be endorsed as follows. CONTRACTOR also agrees to require all contractors, and subcontractors to do likewise.
1. “The CITY, its elected or appointed officers, officials, employees, agents, and volunteers are to be covered as additional insureds with respect to liability arising out of work performed by or on behalf of the CONTRACTOR, including materials, parts, or equipment furnished in connection with such work or operations.”
2. This policy shall be considered primary insurance as respects the CITY, its elected or appointed officers, officials, employees, agents, and volunteers. Any insurance maintained by the CITY, including any self-insured retention the CITY may have, shall be considered excess insurance only and shall not contribute with this policy.
3. This insurance shall act for each insured and additional insured as though a separate policy had been written for each, except with respect to the limits of liability of the insuring company.
4. The insurer waives all rights of subrogation against the CITY, its elected or appointed officers, officials, employees, or agents.
5. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the CITY, its elected or appointed officers, officials, employees, agents, or volunteers.
6. The insurance provided by this policy shall not be suspended, voided, canceled, or reduced in coverage or in limits except after thirty (30) days written notice has been received by the CITY.
C. CONTRACTOR agreesto provide immediate notice to CITY of any claim or loss against Contractor arising out of the work performed under this agreement. CITY assumes no obligation or liability by such notice, but has the right (but not the duty) to monitor the handling of any such claim or claims if they are likely to involve CITY.
D. Any deductibles or self-insured retentions must be declared to and approved by the CITY. At the CITY’s option, the CONTRACTOR shall demonstrate financial capability for payment of such deductibles or self-insured retentions.
E. The CONTRACTOR shall provide certificates of insurance with original endorsements to the CITY as evidence of the insurance coverage required herein. Certificates of such insurance shall be filed with the CITY on or before commencement of performance of this Agreement. Current certification of insurance shall be kept on file with the CITY at all times during the term of this Agreement.
F. Failure on the part of the CONTRACTOR to procure or maintain required insurance shall constitute a material breach of contract under which the CITY may terminate this Agreement pursuant to Section 11 above.
G. The commercial general and automobile liability policies required by this Agreement shall allow CITY, as additional insured, to satisfy the self-insured retention (“SIR”) and/or deductible of the policy in lieu of the CONTRACTOR (as the named insured) should CONTRACTOR fail to pay the SIR or deductible requirements. The amount of the SIR or deductible shall be subject to the approval of the City Attorney and the Finance Director. CONTRACTOR understands and agrees that satisfaction of this requirement is an express condition precedent to the effectiveness of this Agreement. Failure by CONTRACTOR as primary insured to pay its SIR or deductible constitutes a material breach of this Agreement. Should CITY pay the SIR or deductible on CONTRACTOR’s behalf upon the CONTRACTOR’s failure or refusal to do so in order to secure defense and indemnification as an additional insured under the policy, CITY may include such amounts as damages in any action against CONTRACTOR for breach of this Agreement in addition to any other damages incurred by CITY due to the breach.
USE OF OTHER CONTRACTORS. CONTRACTOR must obtain CITY’s prior written approval to use any sub-contractors while performing any portion of this Agreement. Such approval must include approval of the proposed CONTRACTOR and the terms of compensation.
FINAL PAYMENT ACCEPTANCE CONSTITUTES RELEASE. The acceptance by the CONTRACTOR of the final payment made under this Agreement shall operate as and be a release of the CITY from all claims and liabilities for compensation to the CONTRACTOR for anything done, furnished or relating to the CONTRACTOR’S work or services. Acceptance of payment shall be any negotiation of the CITY’S check or the failure to make a written extra compensation claim within ten (10) calendar days of the receipt of that check. However, approval or payment by the CITY shall not constitute, nor be deemed, a release of the responsibility and liability of the CONTRACTOR, its employees, sub-contractors and agents for the accuracy and competency of the information provided
and/or work performed; nor shall such approval or payment be deemed to be an assumption of such responsibility or liability by the CITY for any defect or error in the work prepared by the CONTRACTOR, its employees, sub-contractors and agents.
CORRECTIONS. In addition to the above indemnification obligations, the CONTRACTOR shall correct, at its expense, all errors in the work which may be disclosed during the CITY’s review of the CONTRACTOR’s report or plans. Should the CONTRACTOR fail to make such correction in a reasonably timely manner, such correction shall be made by the CITY, and the cost thereof shall be charged to the CONTRACTOR. In addition to all other available remedies, the CITY may deduct the cost ofsuch correction from any retention amount held by the CITY or may withhold payment otherwise owed CONTRACTOR under this Agreement up to the amount of the cost of correction.
NON-APPROPRIATION OF FUNDS. Payments to be made to CONTRACTOR by CITY for services preformed within the current fiscal year are within the current fiscal budget and within an available, unexhausted fund. In the event that CITY does not appropriate sufficient funds for payment of CONTRACTOR’S services beyond the current fiscal year, the Agreement shall cover payment for CONTRACTOR’S services only to the conclusion of the last fiscal year in which CITY appropriates sufficient funds and shall automatically terminate at the conclusion of such fiscal year.
NOTICES. All communications to either party by the other party will be deemed made when received by such party at its respective name and address as follows:
CITY CONTRACTOR
City of Hawaiian Gardens
21815 Pioneer Blvd.,
Hawaiian Gardens, CA 90716
ATTN: City Manager
Any such written communications by mail will be conclusively deemed to have been received by the addressee upon deposit thereof in the United States Mail, postage prepaid and properly addressed as noted above. In all other instances, notices will be deemed given at the time of actual delivery. Changes may be made in the names or addresses of persons to whom notices are to be given by giving notice in the manner prescribed in this paragraph. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.
SOLICITATION. CONTRACTOR maintains and warrants that it has not employed nor retained any company or person, other than CONTRACTOR’s bona fide employee, to solicit or secure this Agreement. Further, CONTRACTOR warrantsthat it has not paid nor has it agreed to pay any company or person, other than CONTRACTOR’s bona fide employee, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. Should CONTRACTOR breach or violate this warranty, CITY may rescind this Agreement without liability.
THIRD PARTY BENEFICIARIES. This Agreement and every provision herein is generally for the exclusive benefit of CONTRACTOR and CITY and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of CONTRACTOR’s or CITY’s obligations under this Agreement.
Onshore Mechanical Inc.
7263 Murdy Cir
Huntington Beach, CA 92647
ATTN: Brock A. Dains, CEO
INTERPRETATION. This Agreement was drafted in, and will be construed in accordance with the laws of the State of California, and exclusive venue for any action involving this agreement will be in Los Angeles County.
ENTIRE AGREEMENT. This Agreement, and its Attachments, sets forth the entire understanding of the parties. There are no other understandings, terms or other agreements expressed or implied, oral or written.
RULES OF CONSTRUCTION. Each Party had the opportunity to independently review this Agreement with legal counsel. Accordingly, this Agreement will be construed simply, as a whole, and in accordance with its fair meaning; it will not be interpreted strictly for or against either Party.
AUTHORITY/MODIFICATION. The Parties represent and warrant that all necessary action has been taken by the Parties to authorize the undersigned to execute this Agreement and to engage in the actions described herein. This Agreement may be modified by written amendment with signatures of all parties to this Agreement. CITY’s City Manager, or designee, may execute any such amendment on behalf of CITY.
ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES. The Parties agree that this Contract, agreements ancillary to this Contract, and related documents to be entered into in connection with this Contract will be considered signed when the signature of a party is delivered by facsimile transmission or scanned and delivered via electronic mail. Such facsimile or electronic mail copies will be treated in all respects as having the same effect as an original signature.
FORCE MAJEURE. Should performance of this Agreement be impossible due to fire, flood, explosion, war, embargo, government action, civil or military authority, the natural elements, or other similar causes beyond the Parties’ control, then the Agreement will immediately terminate without obligation of either party to the other.
TIME IS OF ESSENCE. Time is of the essence to comply with dates and schedules to be provided.
ATTORNEY’S FEES. The parties hereto acknowledge and agree that each will bear his or its own costs, expenses and attorneys' fees arising out of and/or connected with the negotiation, drafting and execution of the Agreement, and all matters arising out of or connected therewith except that, in the event any action is brought by any party hereto to enforce this Agreement, the prevailing party in such action shall be entitled to reasonable attorneys' fees and costs in addition to all other relief to which that party or those parties may be entitled.
STATEMENT OF EXPERIENCE. By executing this Agreement, CONTRACTOR represents that it has demonstrated trustworthiness and possesses the quality, fitness and capacity to perform the Agreement in a manner satisfactory to CITY. CONTRACTOR represents that its financial resources, surety and insurance experience, service experience, completion ability, personnel, current workload, experience in dealing with private CONTRACTORs, and experience in dealing with public agencies all suggest that CONTRACTOR is capable of performing the proposed contract and has a demonstrated capacity to deal fairly and effectively with and to satisfy a public agency.
OWNERSHIP OF DOCUMENTS. It is understood and agreed that the CITY shall own all documents and other work product of the CONTRACTOR, except the CONTRACTOR’s notes and workpapers, which pertain to the work performed under this Agreement. The CITY shall have the sole right to use such materials in its discretion and without further compensation to the CONTRACTOR, but any re-
use of such documents by the CITY on any other project without prior written consent of the CONTRACTOR shall be at the sole risk of the CITY.
DISCLOSURE REQUIRED. (CITY and CONTRACTOR initials required at one of the following paragraphs)
By their respective initials next to this paragraph, CITY and CONTRACTOR hereby acknowledge that CONTRACTOR is a “CONTRACTOR” for the purposes of the California Political Reform Act because CONTRACTOR’s duties would require him or her to make one or more of the governmental decisions set forth in Fair Political Practices Commission Regulation 18700.3(a) or otherwise serves in a staff capacity for which disclosure would otherwise be required were CONTRACTOR employed by the CITY.
CONTRACTOR hereby acknowledges his or her assuming-office, annual, and leaving-office financial reporting obligations under the California Political Reform Act and the CITY’s Conflict of Interest Code and agrees to comply with those obligations at his or her expense. Prior to CONTRACTOR commencing services hereunder, the City’s Manager shall prepare and deliver to CONTRACTOR a memorandum detailing the extent of CONTRACTOR’s disclosure obligations in accordance with the CITY’s Conflictof Interest Code.
36 LABOR COMPLIANCE. As used herein, “Project” is synonymous with services described in this Agreement.
36.1 Prevailing Wages. Contractor is aware of the requirements of California Labor Code Section 1720 et seq., and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq., (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. Since the Services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Contract upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at Contractor’s principal place of business and at the project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. Contractor and any subcontractor shall forfeit a penalty of up to $200 per calendar day or portion thereof for each worker paid less than the prevailing wage rates.
36.2 Apprenticeable Crafts. When Contractor employs workmen in an apprenticeable craft or trade, Contractor shall comply with the provisions of Section 1777.5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works. The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor. The Contractor or any subcontractor that is determined by the Labor Commissioner to have knowingly violated Section 1777.5 shall forfeit as a civil penalty an amount not exceeding $100 for each full calendar day of noncompliance, or such greater amount as provided by law.
36.3 Hours of Work. Contractor is advised that eight (8) hours labor constitutes a legal day’s work. Pursuant to Section 1813 of the California Labor Code, Contractor shall forfeit a penalty of $25.00 per worker for each day that each worker is permitted to work more than eight (8) hours in any one calendar day and forty (40) hours in any one calendar week, except when payment for overtime is made at not less than one and one-half (1-1/2) times the basic rate for that worker.
36.4 Payroll Records. Contractor and each subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime
hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the public work. The payroll records shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor in the manner provided in Labor Code section 1776. In the event of noncompliance with the requirements of this section, Contractor shall have 10 days in which to comply subsequent to receipt of written notice specifying in what respects such Contractor must comply with this section. Should noncompliance still be evident after such 10-day period, Contractor shall, as a penalty to City, forfeit not more than $100.00 for each calendar day or portion thereof, for each worker, until strict compliance is effectuated. The amount of the forfeiture is to be determined by the Labor Commissioner. A contractor who is found to have violated the provisions of law regarding wages on Public Works with the intent to defraud shall be ineligible to bid on Public Works contracts for a period of one to three years as determined by the Labor Commissioner. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payments then due. The responsibility for compliance with this section is on Contractor. The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4.
36.5 Contractor and Subcontractor Registration. Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. Contractor is directed to review, fill out and execute the Public Works Contractor Registration Certification attached hereto as Exhibit “E” prior to contract execution. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.
36.6 Labor Compliance; Stop Orders. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be the Contractor’s sole responsibility to evaluate and pay the cost of complying with all labor compliance requirements under this Contract and applicable law. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.
CITY Initials
CONTRACTOR Initials
OR
By their initials next to this paragraph, CITY and CONTRACTOR hereby acknowledge that CONTRACTOR is not a “CONTRACTOR” for the purpose of the California Political Reform Act because CONTRACTOR’s duties and responsibilities are not within the scope of the definition of CONTRACTOR in Fair Political Practice Commission Regulation 18700.3(a) and is otherwise not serving in staff capacity in accordance with the CITY’s Conflict of Interest Code.
CITY Initials
CONTRACTOR Initials
IN WITNESS WHEREOF the parties hereto have executed this contract the day and year first hereinabove written.
CITY OF HAWAIIAN GARDENS CONTRACTOR
Ernesto Marquez, City Manager By: Brock A. Dains, CEO
ATTEST:
Pablo Rubio, City Clerk Taxpayer ID No.
APPROVED AS TO FORM:
Norma Tabares, City Attorney
“Cost Proposal”
Section 1: Quarterly Preventative
Maintenance Pricing
CITY FACILITY ADDRESS
COST FOR
QUARTERLY
MAINTENANCE
TOTAL ANNUAL
MAINTENANCE COST
City Hall 21815 Pioneer Blvd $ $
C. Robert Lee Activity
Center
21815 Pioneer Blvd $ $
Public Safety Center 11940 Carson St $ $
Teen Center
22325 Norwalk Blvd $ $
Lee Ware Recreation
Center
22300 Wardham Ave $ $
Helen Rosas Center 22150 Wardham Ave $ $
Total for all Facilities $ $
Attachment B “Cost Proposal”
Yes No
Section 2: On-Call Repair Services Pricing
UNIT MINIMUM HOURS COST
Labor Charge Hours $ _ Per Hour
After Hours Labor
(To be used for work
performed after 4:30 PM
Monday – Friday, and all of
Sat., Sun., and holidays.
Hours $ Per Hour
Replacement Equipment,
Parts, Materials, and
Equipment Rentals Markup %
(Maximum 15%)
%
Sample Project: See sample project attachment.
Other Costs: In the space below, please indicate if other costs/services may be associated with providing the requested services in this RFP that are not included in the tables above. The costs provided in this section may be used to assist in the determination of the contract award. If the “Yes” box is checked, separate page(s) must be attached as part of the Cost File.
Attachment B “Cost Proposal”
The undersigned certifies that submission of this Proposal is made without prior understanding, arrangement, agreement, or connection with any corporation, firm or person submitting a Proposal for the same services and is in all respects fair and without collusion of fraud. The undersigned certifies that they have not entered into any arrangement or agreement with any City of Hawaiian Gardens public officer. The undersigned understands collusive practices are a violation of State and Federal law and can result in fines, prison sentences, and civil damage awards.
Proposer Signature Date
Printed Name and Title
CITY OF HAWAIIAN GARDENS
CITY COUNCIL
STAFF REPORT
Agenda Item #B9
DATE: June 25, 2025
TO: Honorable Mayor and Members of the City Council
FROM: Ernesto Marquez, City Manager
BY: Neema Ghanbari, Public Works Manager
RECOMMENDATION:
RECOMMENDATION TO RECEIVE AND FILE THE PUBLIC WORKS DEPARTMENT PERMITS REPORT FOR THE MONTH OF MAY 2025
SUMMARY
The Engineering Division, as part of the Public Works Department, is responsible for the implementation of the policies and objectives of the community as set forth in the City of Hawaiian Gardens’ General Plan, Municipal Code, and oversees the project management for the construction of the City’s capital improvements, infrastructure, and public facilities.
The Engineering Division reviews applications and issues construction, and encroachment permits for any work that is done in the public right-of-way, such as the streets and alleys, and if the public rights-of-way are used for equipment parking/staging and to conduct any construction, repair, or maintenance of any property or utilities within or adjacent. Work on or use of the public right-of-ways may include: underground and above-ground utilities repair/replacement by utility companies and their contractors, driveway construction, temporary use for staging of equipment and vehicles, and contractors working on behalf of the City for public improvements. The permits and final inspections will ensure that any work is conducted in accordance with City Engineering specifications and appropriate standards and that any traffic control and safety measures are properly in place and followed.
The attached chart is a summary of all permits issued during the month of May 2025.
Agenda Item #B9
June 25, 2025
FISCAL IMPACT
None.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENT
A. Monthly Public Works Permits Report List for May 2025.
ATTACHMENT A
No. Permit Date Contractor For Location Type Amount
1 1529 05/28/25 Golden State Water 12236 Centralia St. Emergency Water Main Leak Repair $ 801.00 2 1530 05/28/25 Golden State Water 12104 215th St. Installation of a New 2" Service Line $ 801.00 2 Total for Month: $ 1,602.00
52 Total for Fiscal Year: $ 56,433.00
`
Total Permits for Fiscal Year:
City of Hawaiian Gardens - Public Works Department
Monthly Report - Public Works Permits Issued
May 2025
Total Permits for Month:
CITY OF HAWAIIAN GARDENS
CITY COUNCIL
STAFF REPORT
Agenda Item #B10
DATE: June 25, 2025
TO: Honorable Mayor and Members of the City Council
FROM: Ernesto Marquez, City Manager
BY: Neema Ghanbari, Public Works Manager
RECOMMENDATION:
RECOMMENDATION TO RECEIVE AND FILE THE PUBLIC WORKS DEPARTMENTENGINEERING DIVISION CIP STATUS REPORT FOR THE MONTH OF MAY 2025
SUMMARY
The City of Hawaiian Gardens Public Works Department- Engineering Division has prepared its May 2025 monthly status report on Capital Improvements currently being carried out within the City of Hawaiian Gardens. This report deals with different types of projects that have been currently budgeted and monitored by the Public Works Department.
FISCAL IMPACT
None.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENT
A. Engineering Division CIP Status Report for May 2025
STREETS, PARKWAYS, & TRAFFIC PROJECTS
Project Name Project Location Current Status Schedule
FY 2021-22
Residential Streets Rehabilitation FY 2021-2022,
Project 101
Total Budget: $1,265,516
Various • On December 8, 2022, IE submitted the
final PS&E to the City for review and
acceptance.
• On December 12, 2022, the City
submitted the final PS&E to LACDA for
review, approval, and advertising the
project for bid.
• Mandatory Pre-bid meeting was
conducted on February 21, 2023.
• On February 28, 2023, the City Clerk
received five (5) sealed bids for the
project.
• On March 28, 2023, the construction
contract was awarded to the lowest
responsible bidder, Excel Paving
Company in the amount of $998,872.
• The City Hall parking lot improvements
and punch list were completed in July.
• On September 26, 2023, the City
Council accepted the Residential
Streets Rehabilitation as complete and
authorized the City Clerk to file the
Notice of Completion with LA County.
Completed
Carson Street Signals Hardware Improvements
(HSIP 5387-012), Project 106
Total Budget: $914,414
8 Intersections on
Carson St
• On November 8, 2022, the service
request for Carson Street Signal
Synchronization Project was
submitted to LA County Public Works
for signal timing design.
• On August 15, 2023, IE submitted the
final PS&E to the City for review and
acceptance.
• On August 22, 2023, the City Council
approved the construction plans and
authorized the Public Works Manager
to advertise the project and seek public
bids.
• Mandatory Pre-bid meeting was
conducted on September 19, 2023.
Completed
ATTACHMENT A
• On September 28, 2023, the City Clerk
received four (4) sealed bids for the
project.
• On October 24, 2023, the City Council
awarded the construction contract to
the lowest responsible bidder,
Crosstown Electric & Data, Inc., in the
amount of $795,778.
• On November 13, 2023, staff
conducted a pre-construction meeting
with the contractor and discussed the
requirements, schedule, and
procurement for the equipment.
• On April 23, 2024, staff conducted the
second pre-construction was held and
followed by issuing a Notice to Proceed
with Construction.
• Construction commenced in May and
was completed in November 2024.
• In November 2024, the City was
notified by Caltrans' Local Assistance
Engineer that the funding request had
been approved. As a result, the City will
receive an additional $302,500,
bringing the total HSIP project funds to
$700,000.
• On December 11, 2024, the City Council
accepted the Carson Street HSIP
Project as complete and authorized the
City Clerk to file the Notice of
Completion with LA County.
Norwalk Boulevard Signals Hardware
Improvements (HSIP 5387-013), Project 107
Total Budget: $549,400
4 Intersections on
Norwalk Blvd
• After a field review staff realized that
there may be a conflict between the
proposed design and the existing utility
lines. The plans were sent back to IE for
verification or revisions in June.
• On August 15, 2023, IE submitted the
final PS&E to the City for review and
acceptance.
• On August 22, 2023, the City Council
approved the construction plans and
authorized the Public Works Manager
Completed
to advertise the project and seek public
bids.
• Mandatory Pre-bid meeting was
conducted on September 19, 2023.
• On September 28, 2023, the City Clerk
received three (3) sealed bids for the
project.
• On October 24, 2023, the City Council
awarded the construction contract to
the lowest responsible bidder,
Crosstown Electric & Data, Inc., in the
amount of $463,765.
• On November 13, 2023, staff
conducted a pre-construction meeting
with the Contractor and discussed the
requirements, schedule, and
procurement for the equipment.
• On April 23, 2024, the staff held the
second pre-construction meeting,
which was followed by the issuance of
a Notice to Proceed with construction.
• Construction commenced in May and
was completed in November 2024.
• On December 11, 2024, the City Council
accepted the Carson Street HSIP
Project as complete and authorized the
City Clerk to file the Notice of
Completion with LA County.
FY 2022-23
Residential Street Slurry Seal, Project 110
Total Budget: $904,543
Various Residential
Streets
• In May 2024, the engineering
department staff prepared the bid
documents for the project.
• On July 24, 2024, the City Council
approved the project plans and
specifications to slurry seal thirty-two
(32) residential streets as part of the FY
2022-23 Residential Street
Rehabilitation Project.
• On August 14, 2024, the City Clerk
received four (4) sealed bids for the
Project. The lowest responsive bidder
was All American Asphalt, of Corona,
Completed
California, with a bid amount of
$514,600.
• On August 28, 2024, the City Council
awarded the construction contract to
All American Asphalt, with a bid
amount of $514,600.
• Construction began in October 2024
and was completed in January 2025.
• On January 22, 2025, the City Council
accepted the FY 2022-23 Residential
Street Slurry Seal, Project 110 as
complete and authorized the City Clerk
to file the Notice of Completion with LA
County.
FY 2023-24
Carson Street Beautification- Phase ll, Project 108
Total Budget: $5,970,000
Carson St between
Pioneer Blvd &
Bloomfield Ave
• Kick-off meeting for Design was held on
October 4, 2022.
• 1
st Project status meeting was held on
November 1, 2022.
• On November 8, 2022, IE submitted the
35% PS&E to the City.
• On April 20, 2023, IE submitted 65%
PS&E to the City.
• On May 2023 staff reviewed the 65%
PS&E and sent the comments to IE for
review and proceeding with the design
to 95% completion.
• On September 22, 2023, IE submitted
the 95% PS&E to the City.
• On December 20, 2023, staff reviewed
the 95% PS&E and sent the comments
to IE for review.
• On January 8, 2024, staff met with IE to
discuss the project design status,
engineer’s estimate, and preparation
of final PS&E and presentation to the
City Council.
• On February 13, 2024, IE submitted
100% PS&E to the City for review and
comments.
• City reviewed the 100% PS&E and
submitted the comments to IE for
Completed
preparation of the Final PS&E by March
2024.
• On March 13, 2024, the City Council
approved the plans and specifications
and authorized staff to seek public bids
for the project.
• On April 24, 2024, the City Clerk
received four (4) sealed bids for the
project.
• On May 8, 2024, the construction
contract was awarded to the lowest
responsive bidder, Hardy & Harper Inc.
• The pre-construction meeting was held
on July 10, 2024.
• On November 20, 2024, the City
Council awarded the palm trees
removal and Installation contract to
Moon Valley Nurseries and allocated an
additional $270,000 from Reserve
Funds previously designated for Capital
Improvement Program (CIP) projects to
the Carson Street Beautification-Phase
ll.
• On June 11, 2025, the City Council
accepted the Carson Street
Beautification Phase ll, Project 108 as
complete and authorized the City Clerk
to file the Notice of Completion with LA
County.
Arterial & Residential Street Rehabilitation,
Project 112
Total Budget: $1,530,468
Norwalk Blvd
between Tilbury St &
Centralia St
223rd Street between
Belshire Ave &
Wardham Ave
• On June 13, 2023, the City Council
approved the street list and allocated
the budget for the FY 2023-24
Residential and Arterial Rehabilitation
Project.
• In July 2024, a design RFS for additional
work was requested from Willdan
Engineering.
• On August 22, 2024, the Design RFS was
submitted to the City and subsequently
signed by the CM.
• On October 11, 2024, the 65% PS&E
was submitted to the City.
Construction began in May and will
be completed in July 2025.
• On November 7, 2024, the comments
for 65% PS&E were submitted to
Willdan.
• On December 19, 2024, the 100% PS&E
was submitted to the City.
• On January 21, 2025, the final PS&E
was submitted to the City.
• On February 19, 2025, the City Clerk
received eight (8) sealed bids for the
project.
• On March 12, 2025, the construction
contract was awarded to Sequel
Contractors of Santa Fe Springs,
California, the lowest responsive
bidder, for the amount of $1,248,182.
Citywide Concrete Rehabilitation, Project 114
Total Budget: $150,000
Citywide • On March 26, 2024, the bid package
was prepared by engineering staff
and approved by the City Engineer.
• On April 16, 2024, the City Clerk
received six (6) sealed bids for the
project.
• On April 24, 2024, the City Council
awarded the construction contract to
the lowest responsive bidder, S&H
Civilworks in the amount of $102,020.
• The pre-construction meeting was held
on May 15, 2024.
• Construction began in June and was
completed in July 2024.
• On August 14, 2024, the City Council
accepted the Citywide Concrete
Rehabilitation as complete and
authorized the City Clerk to file the
Notice of Completion with LA County.
Completed
FY 2024-25
Norwalk Boulevard Pedestrian Safety
Improvements (Hawk Signal), Project 117
Total Budget: $365,000
Norwalk Blvd
between 215th St and
Tilbury St
• On August 1, 2024, the design RFS
was signed by CM.
• The 35% PS&E was submitted to the
City in September 2024.
• The 90% PS&E was submitted to the
City in November 2024.
Bid opening will be held on June 25,
2025.
• The 100% PS&E was submitted to the
City in January 2025.
• In February 2025, the City was
notified by Caltrans that the project
had been selected for the HSIP Cycle
12 grant. The City has been awarded
$350,000 in State Funds to support
the construction of the project.
FACILITY PROJECTS
Project Name Project Location Current Status Schedule
FY 2022-23
C. Robert Lee Roof Replacement, Project 102
Total Budget: $784,419
C. Robert Lee
Building (21815
Pioneer Blvd)
• City requested IE to separate reroofing project from HVAC Replacement.
• On February 27, 2023, IE submitted
the final PS&E for the roof
replacement to the city.
• Staff reviewed and accepted the final
design and advertised the project for
bids.
• The pre-bid meeting was conducted
on March 14, 2023.
• On March 28, 2023, the City Clerk
received three (3) sealed bids for the
project.
• On April 25, 2023, the construction
contract was awarded to the lowest
responsible bidder, Best Contracting
Services in the amount of $519,589.
• Construction began in May and was
completed in July 2023.
• The City issued a change order to the
Best Contracting Services for the City
Hall Administration Building roofing
replacement/improvements in the
amount of $193,764.
• The improvements were completed in
November and notice of completion
was filed with the County in December
2023.
Completed
C. Robert Lee HVAC Replacement, Project 103
Total Budget: $567,000
C. Robert Lee
Building (21815
Pioneer Blvd)
• On August 23, 2023, IE submitted the
100% PS&E to the City for review.
• On October 4, 2023, the final PS&E
was submitted to the City for
acceptance.
• Staff reviewed and accepted the final
design and advertised the project for
bids.
• The pre-bid meeting was held on
November 14, 2023.
• On November 21, 2023, the City
Clerk received two (2) sealed bids
for the project.
• On January 9, 2024, the construction
contract was awarded to the lowest
responsible bidder, RAN Enterprises
Inc. in the amount of $494,000.
• The pre-construction meeting was
held on January 26, 2024.
• Due to the lead time required for
HVAC unit procurement,
construction commenced in midOctober and was completed in November 2024.
• On December 11, 2024, the City
Council accepted the C. Robert Lee
HVAC Replacement Project as
complete and authorized the City
Clerk to file the Notice of
Completion with LA County.
Completed
City Hall Parking Lot Improvements
Total Budget: $20,000
City Hall • Engineering Division staff to review
the budget and recommend a
strategy for the parking lot pavement
improvements.
• The City Hall parking lot
improvements were completed by a
change order to the contractor of
Street Rehabilitation, Project 101 in
June 2023.
Completed
Lee Ware Clinic Restroom Renovation, Project 104
Total Budget: $155,664
Lee Ware Clinic
(22310 Wardham
Ave)
• On February 21, 2023, IE submitted
the Final PS&E to the City for
acceptance.
Completed
• The Per-bid meeting was conducted
on March 15, 2023.
• On March 22, 2023, the City Clerk
received four (4) sealed bids for the
project.
• On April 25, 2023, the construction
contract was awarded to the lowest
responsible bidder, Empire Design &
Build in the amount of $85,000.
• On August 8, 2023, the City Council
accepted the project construction as
complete and authorized the City
Clerk to file the Notice of
Completion with LA County.
FY 2023-24
Citywide Water Efficiency, Project 113
Total Budget: $230,800
Furgeson Elementary
School, Fedde Middle
School and C. Robert
Lee Restrooms, and
Pioneer Park
Irrigation System
• On September 5, 2023, a grant
application was submitted to the
Central Basin Municipal Water
District (CBMWD) for the Water
Efficiency Project.
• On March 21, 2023, the City was
granted a reimbursement fund from
CBMWD in the amount up to
$230,800 for the proposed Water
Efficiency, Project 113.
• On April 10, 2024, the City Council
accepted the project funding of
$230,800 from CBMWD for the
water efficiency project at various
locations, allocated reimbursable
funding for the project, authorized
the City Manager to execute the
expense reimbursement Agreement
with CBMWD, and signed the
construction contract with Empire
Design and Build and Anguiano Lawn
Care, Inc. for the total contracts
amount not to exceed $230,800.
• Construction began in May and was
completed in June 2024.
Completed
Citywide Catch Basin Connector Pipe Screen (CPS)
Inserts Installation, Project 111
Total Budget: $290,093
Citywide • The latest Statewide Trash Order
requires that 50% of "priority" catch
basins be retrofitted by 2026.
• The final bid package was reviewed
and approved by the City Engineer in
February 2024.
• On March 13, 2024, the City Council
approved the plans and
specifications and authorized staff
to seek public bids for the project.
• On March 29, 2024, the project was
advertised in Los Cerritos
Community Newspaper and on the
CIP List website.
• On April 15, 2024, the City Clerk
received two (2) sealed bids for the
project.
• On April 24, 2024, the City Council
awarded the construction contract
to the lowest responsive bidder,
United Storm Water, Inc., in the
amount of $189,997.
• In May 2024, the contractor
submitted the permit request
package to the LA County Flood
Control District.
• The contractor was authorized to
proceed with construction in midSeptember 2024, and the project was completed in January 2025.
• On March 12, 2025, the City Council
accepted the project construction as
complete and authorized the City
Clerk to file the Notice of
Completion with LA County.
Completed
FY 2024-25
City Hall Roof Replacement, Project 118
Total Budget: $570,000
City Hall • On October 10, 2024, the design RFS
was signed by the CM.
• On January 6, 2025, the 75% PS&E
was submitted to the City for review
and comments.
Construction will begin in July and will
be completed by the end of August
2025.
• On February 5, 2025, the Comments
were submitted to the Willdan
Design team to revise the plans.
• On March 12, 2025, the 100% PS&E
was submitted to the City for review.
• On April 9, 2025, the final PS&E was
submitted to the City.
• On April 15, 2025, the plans were
approved by the City’s building and
safety department.
• On May 21, 2025, the City Clerk
received three (3) sealed bids for the
project.
• On May 28, 2025, the City Council
awarded the construction contract
to the lowest responsive bidder,
Courtney, Inc., in the amount of
$507,240.
PARKS PROJECTS
Project Name Project Location Current Status Schedule
FY 2021-22
Pioneer Park Renovation, Project 105
Total Budget: $362,902
Pioneer Park
(22222 Pioneer
Blvd)
• Preliminary project estimate has a
shortfall of $80,000.
• IE to complete the design and include
Base Bid, Additive Bid #1, and Additive
Bid #2 items into the project
specifications.
• On March 24, 2023, the 100% PS&E was
submitted to the City for final review.
• On March 29, 2023, the comments for
100% PS&E were submitted to IE for
final revision.
• On May 18, 2023, the final PS&E was
submitted to the City.
• On June 13, 2023, the City Council
approved the Plans and Specifications
and authorized staff to advertise the
project for bids.
Completed
• On July 25, 2023, the City Council
awarded the construction contract to
R.E. Schultz Construction in the amount
of $249,340.
• The pre-construction meeting was held
on August 9, 2023.
• On January 8, 2024, the Construction
started and was completed on March 4,
2024.
• On April 10, 2024, the City Council
accepted the project construction as
complete and authorized the City Clerk
to file the Notice of Completion with LA
County.
MISCELLANEOUS
Project Name Project Location Current Status Schedule
FY 2024-25
SCE Utility Undergrounding on Norwalk Boulevard
(Rule 20A), Project 115
Total Budget: 1,050,000
Norwalk Blvd
between 215th St &
Tilbury St
• On October 19, 2022, staff met with
all utility project coordinators to
discuss the status of the project.
• On April 20, 2023, the City received
notification from SCE indicating that
Charter's plans for joint-trench
bidding were found to be
incomplete and failing to meet SCE
standards and the joint trench
construction requirements.
• On May 30, 2023, Edison received
Spectrum/Charter Communication's
final/complete plans.
• In June 2023, the SCE Project
Manager submitted all final plans to
their construction Division for
scheduling and advertising for bids
and the selection of the contractor.
• on July 25, 2023, an Edison
representative and project manager
were at the City Council meeting to
Completed
update the City Council about the
project status and delays.
• The Construction contract was
awarded to Doty Bros in December
2023.
• In January 2024, Charter notified
SCE that they would not participate
in the joint trench contract.
However, they intend to proceed
independently.
• The Rule 20A Underground project
started on April 8, 2024.
• SCE, Charter Communications, and
Verizon started undergrounding
their overhead cable lines in May
2024.
ENGINEERING STUDY & REPORTS
Project Name Project Location Current Status Schedule
Engineering & Traffic Speed Survey
Total Budget: $85,000
Citywide • On January 11, 2024, the Request for
Proposal (RFP) for the preparation of
the Citywide Engineering and Traffic
Survey report was prepared by
engineering staff and advertised in
Los Cerritos Community Newspaper
and on the City’s website.
• On February 1, 2024, the Public
Works Department received five (5)
Proposals.
• On February 14, 2024, the City
Council awarded the professional
services agreement to Minagar &
Associates for the preparation of the
Engineering & Traffic Speed survey.
• The kick-off meeting was held on
February 27, 2024.
• The project was completed in midJune 2024.
• On July 10, the 2024 Citywide
Engineering and Traffic Speed Survey
Completed
report was approved by the City
Council.
Bike Master Plan
Total Budget: $370,000
Citywide
• In 2023, the engineering division staff
applied for Caltrans ATP Cycle 6 grant
funding and received $370,000 to
prepare and develop the City of
Hawaiian Gardens Bicycle Master
Plan.
• On January 23, 2024, the Request for
Proposal (RFP) for the preparation of
the Citywide Bicycle Master Plan was
prepared by engineering staff and
advertised in Los Cerritos Community
Newspaper and on the City’s website.
• On February 12, 2024, the Public
Works Department received four (4)
Proposals.
• On March 13, 2024, the City Council
awarded the professional services
agreement to Tool Design Group for
preparation of the Citywide Bicycle
Master Plan.
• The kick-off meeting was held on
March 26, 2024.
• The first pop-up event and network
workshop were held on June 6, 2024.
• The first Community Advisory
Committee (CAC) meeting was held
on June 25, 2024.
• In July 2024, the Consultant
developed outreach materials and
website content, reviewed public
comments, and created a draft
network.
• Toole Design Group hosted the
second Community Engagement
meeting at the Public Safety Center
parking lot on August 6, 2024.
- In Progress
• Two roundtable discussions were
held on December 17, 2024, at the
Senior Center and Teen Center.
• Two CAC meetings were held in June
and October 2024.
• A school engagement meeting was
held on February 28, 2025, at
Hawaiian Elementary School.
• On March 12, 2025, the proposed
Citywide Bicycle Master Plan
Network was presented by the
consultant and approved by the City
Council.
Pavement Management Program
Total Budget: $82,000
Citywide • On January 11, 2024, the Request for
Proposal (RFP) for updating the City’s
Pavement Management Program
was prepared by engineering staff
and advertised on the City’s website.
• On February 1, 2024, the Public
Works Department received three (3)
Proposals.
• On February 28, 2024, the City
Council awarded the professional
services agreement to NCE for the
preparation of the Citywide
Pavement Management Program
update.
• The kick-off meeting was held on
March 12, 2024.
• On February 12, 2025, the City
Council approved and adopted the
2025 Updated 5-Year Pavement
Management Program.
Completed
CITY OF HAWAIIAN GARDENS
CITY COUNCIL
STAFF REPORT
Agenda Item #B11
DATE: June 25, 2025
TO: Honorable Mayor and Members of the City Council
FROM: Ernesto Marquez, City Manager
BY: Pablo Rubio, City Clerk
RECOMMENDATION:
Recommendation to approve the minutes for the City Council meeting of Wednesday, June 11, 2025.
SUMMARY
The City Clerk’s office is to prepare and present the meeting minutes to the City Council for review and approval.
FISCAL IMPACT
None.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENTS
A. June 11, 2025 - Minutes
CITY OF HAWAIIAN GARDENS
CITY COUNCIL MINUTES
Maria Teresa Del Rio, Mayor Pro Tem
Victor Farfan, Councilmember
Luis Roa, Councilmember
Ernie Vargas, Councilmember
Dandy De Paula, Mayor
Wednesday, June 11, 2025
Regular Meeting, 6:00 PM
Ernesto Marquez,City Manager
Norma Tabares, City Attorney
Pablo Rubio, City Clerk
MINUTES
CALL TO ORDER
The City Council meeting was called to order on Wednesday, June 11, 2025 at 6:04 PM.
INVOCATION
The invocation was led by Pablo Rubio, City Clerk.
FLAG SALUTE
The flag salute was led by Mayor De Paula.
ROLL CALL
PRESENT
Councilmember Roa
Councilmember Vargas
Mayor Pro Tem Del Rio
Mayor De Paula
ABSENT
1 Councilmember Farfan
Pablo Rubio, City Clerk, announced a quorum.
PUBLIC COMMENTS GENERAL OR ITEMS ON OR OFF THE AGENDA Kathleen Wiechelman spoke.
Kyo Kim spoke.
Susy Vigil spoke.
Irene Zapata spoke.
Reynaldo Rodriguez spoke.
Jesus Mendoza spoke.
PROCLAMATIONS AND CERTIFICATES
There were no Proclamation or Certificates.
PRESENTATIONS
1. SWEARING IN CEREMONY – JAIME RIVAS, A HAWAIIAN GARDENS RESIDENT WHO
GRADUATEDFROMPEPPERDINEUNIVERSITYANDPASSEDTHEBAR
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 1
Irene Zapata spoke.
Reynaldo Rodriguez spoke.
Jesus Mendoza spoke.
PROCLAMATIONS AND CERTIFICATES
There were no Proclamation or Certificates.
PRESENTATIONS
1. SWEARING IN CEREMONY – JAIME RIVAS, A HAWAIIAN GARDENS RESIDENT WHO GRADUATED FROM PEPPERDINE UNIVERSITY AND PASSED THE BAR Mayor De Paula administered the Oath for Jaime Rivas.
The City Council recessed to Closed Session at 6:31 PM.
The City Council reconvened from Closed Session at 6:42 PM.
2. INTRODUCTION TO STAFF OF THE RECREATION AND COMMUNITY SERVICE
DEPARTMENT
Joe Jimenez, Recreation and Community Services Director, introduced new Recreation Staff Members.
Councilmember Roa spoke.
AGENDA ORGANIZATION
There were no changes to the Agenda Organization.
A. PUBLIC HEARING(S) / HEARING(s)
There were no Public Hearings.
B. CONSENT CALENDAR
1. WAIVE READING IN FULL OF ALL ORDINANCES AND RESOLUTIONS ON THE AGENDA That the City Council waive reading in full of all ordinances and resolutions on the agenda and declare that said titles which appear on the public agenda shall be determined to have been read by title and further reading waived.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
2. Recommendation to adopt Resolution No. 0122025, approving the Amended and Restated Joint Exercise of Powers Agreement for the Los Angeles Gateway Region Integrated Regional Water Management Authority; and authorize the Mayor to execute the agreement.
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 2
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
2. Recommendation to adopt Resolution No. 0122025, approving the Amended and Restated Joint Exercise of Powers Agreement for the Los Angeles Gateway Region Integrated Regional Water Management Authority; and authorize the Mayor to execute the agreement.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
3. Recommendation to receive and file warrants processed during the period of May 17 to May 30, 2025.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
4. Recommendation to authorize the City Manager to execute a professional services agreement with Matrix Consulting Group to provide consulting services to update the City Fee Schedules and prepare a Development Impact Fee Study.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
5. Recommendation to adopt Resolution No. 0102025, authorizing an amendment to the agreement
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 3
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
5. Recommendation to adopt Resolution No. 0102025, authorizing an amendment to the agreement for reimbursement for helicopter patrol services by and between the City of Hawaiian Gardens and the City of Lakewood – Sky Knight Program.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
6. Recommendation to approve the minutes for the City Council meeting of Wednesday, May 28, 2025; and the Special Meeting of Thursday, May 22, 2025.
SUGGESTED ACTION: Approve Recommendation.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to adopt the Consent Calendar as presented, in its entirety.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
C. DISCUSSION ITEM(S)
1. Recommendation to accept the construction improvements by Hardy & Harper, Inc., for the Carson Street Beautification Phase II, Project 108, and authorize the City Clerk to file the Notice of Completion.
SUGGESTED ACTION: Approve Recommendation.
Neema Ghanbari, Public Works Manager, presented the staff report.
Mayor De Paula spoke.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to approve recommendation.
Themotioncarriedbythefollowingvote:
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 4
1. Recommendation to accept the construction improvements by Hardy & Harper, Inc., for the Carson Street Beautification Phase II, Project 108, and authorize the City Clerk to file the Notice of Completion.
SUGGESTED ACTION: Approve Recommendation.
Neema Ghanbari, Public Works Manager, presented the staff report.
Mayor De Paula spoke.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to approve recommendation.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
2. Recommendation to discuss and consider approving a donation to Hawaiian Gardens VFW Post 7243.
SUGGESTED ACTION: Approve Recommendation.
Ernesto Marquez, City Manager, spoke.
Shadic Anderson, Senior Vice Commander, spoke.
Mayor Pro Tem Del Rio spoke.
Councilmember Vargas spoke.
Councilmember Roa spoke.
Mayor De Paula spoke.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to approve recommendation and approve a $5,000 donation to VFW Post 7243.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
3. Recommendation to adopt Resolution No. 0112025, adopting a twoyear budget for the fiscal years of 20252026 and 20262027.
SUGGESTED ACTION: Approve Recommendation.
Linda Hollinsworth, Finance Director, presented the staff report.
Ernesto Marquez, City Manager, spoke.
Councilmember Vargas spoke.
Mayor De Paula spoke.
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 5
3. Recommendation to adopt Resolution No. 0112025, adopting a twoyear budget for the fiscal years of 20252026 and 20262027.
SUGGESTED ACTION: Approve Recommendation.
Linda Hollinsworth, Finance Director, presented the staff report.
Ernesto Marquez, City Manager, spoke.
Councilmember Vargas spoke.
Mayor De Paula spoke.
Councilmember Roa spoke.
Mayor Pro Tem Del Rio spoke.
Mayor De Paula spoke.
A motion was made by Councilmember Roa, seconded by Mayor Pro Tem Del Rio, to approve recommendation and adopt Resolution No. 0112025.
The motion carried by the following vote:
AYES: 4; Roa, Vargas, Del Rio, De Paula
NOES: 0;
ABSENT: 1; Farfan
RECUSE: 0;
Motion carried: 4–0–1–0
D. NEW BUSINESS
There were no New Business items.
E. ORAL STAFF REPORT(S)
Joe Jimenez, Recreation and Community Services Director, announced that the first concert of the Summer Concert Series will take place on June 13, 2025; and that the Youth Soccer Program will hold its Closing Ceremony on June 14, 2025.
Neema Ghanbari, Public Works Manager, announced that a Community Block Cleanup will be held on June 14, 2025; and a tire recycle event will be held on June 14, 2025.
Ernesto Marquez, City Manager, announced that he requested a more proactive effort from LASD to curtail the illegal fireworks activity in the city.
Steve Gomez, Public Safety Director, announced that Public Safety collaborated with Public Works for new digital street signs educating the community of the new illegal fireworks fines.
F. CITY ATTORNEY REPORT(S)
There were no Oral City Attorney Reports.
G. ORAL COUNCIL REPORT(S)
Councilmember Roa thanked staff for their work in approving the twoyear city budget; and announced he stands in solidarity with the immigrant community.
Mayor Pro Tem Del Rio announced she stands in solidarity with the immigrant community.
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 6
new digital street signs educating the community of the new illegal fireworks fines.
F. CITY ATTORNEY REPORT(S)
There were no Oral City Attorney Reports.
G. ORAL COUNCIL REPORT(S)
Councilmember Roa thanked staff for their work in approving the twoyear city budget; and announced he stands in solidarity with the immigrant community.
Mayor Pro Tem Del Rio announced she stands in solidarity with the immigrant community.
Mayor De Paula delivered a message that the City of Hawaiian Gardens does not collaborate or participate in any Federal Immigration Enforcement activity.
H. CLOSED SESSION
1. PUBLIC EMPLOYEE PERFORMANCE EVALUATION
Pursuant to Government Code Section 54957
Title: City Manager
2. CONFERENCE WITH LABOR NEGOTIATORS
Pursuant to Government Code section 54957.6
Agencydesignated representative: Ernesto Marquez, City Manager Employee Organizations: AFSCME Local 3624 Rank & File Unit Union AFSCME Local 3624 Management Unit Union
Norma Tabares, City Attorney, read the Closed Session items into the record.
The City Council recessed to Closed Session at 7:42 PM.
The City Council reconvened from Closed Session at 8:35 PM.
Pablo Rubio, City Clerk, conducted a roll call and announced a quorum.
Norma Tabares, City Attorney, stated no reportable action from Closed Session.
I. ADJOURNMENT
The City Council adjourned the meeting at 8:36 PM to the next Regular City Council meeting to be held on Wednesday, June 25, 2025 at 6:00 PM.
CITY COUNCIL MINUTES
REGULAR MEETING
JUNE 11, 2025 Page 7
CITY OF HAWAIIAN GARDENS
CITY COUNCIL
STAFF REPORT
Agenda Item #C1
DATE: June 25, 2025
TO: Honorable Mayor and Members of the City Council
FROM: Ernesto Marquez, City Manager
BY: Ernesto Marquez, City Manager
RECOMMENDATION:
Recommendation to discuss the ABC Unified School District Proposed School Closures.
SUMMARY
In recent years, the ABC Unified School District (“District”) has engaged in a process to consider targeted school closures due to declining enrollment, which presents a challenge for public school districts throughout the State of California.
Most recently, on June 3, 2025, the District Board of Education (“Board”) conducted a public hearing related to consolidation and reconfiguration of certain school sites, including Furgeson Elementary School, which falls within the boundaries of the City of Hawaiian Gardens (“City”). On June 17, 2025, the Board considered an action to approve the plan to consolidate and reconfigure schools to address declining enrollment districtwide (Agenda Item 1.3-A). The vote to adopt the plan was not approved at that same meeting. The decision to permanently close a school lies entirely within the Board’s decision-making authority.
Residents have expressed concern regarding the closure of Furgeson and the harmful effects this decision could have on local families. The City desires to continue to be a steadfast partner with the District. Nonetheless, in light of the potential impacts on Hawaiian Garden residents, this item has been added at the request of Councilmember Vargas to share information with the community and for City Council discussion.
FISCAL IMPACT
There is no fiscal impact.
SUGGESTED ACTION
Approve Recommendation.
ATTACHMENTS
None.