City of Hawaiian Gardens 10/14/2025
8:58:41AM
For the Period 9/1/2025 thru 9/30/2025
Inspection Totals Completed by Inspector
TRANS TECH
CEILING INSULATION 1
ELECTRIC RELEASE 2
ELECTRICAL FINAL 2
FINAL 5
FOOTING 2
INTERIOR LATH 1
PLUMBING FINAL 1
ROOF FRAMING 1
ROOF SHEATHING 3
ROUGH ELECTRICAL 1
ROUGH FRAMING 1
ROUGH GAS TEST 1
ROUGH MECHANICAL 1
ROUGH PLUMBING 1
SHEARWALL EXTERIOR 1
SHEARWALL INTERIOR 1
SOLAR FINAL 1
WALL INSULATION 1
TOTAL INSPECTIONS for TRANS TECH: 27
TOTAL INSPECTIONS COMPLETED: 27