City of Hawaiian Gardens 6/30/2026
4:43:23PM
For the Period 6/1/2026 thru 6/30/2026
Inspection Totals Completed by Inspector
TRANS TECH
BUILDING FINAL 1
DRYWAIL NAILING 2
ELECTRIC RELEASE 2
ELECTRICAL FINAL 5
FINAL 3
FOUNDATION/SLAB 1
HOT MOP 1
INTERIOR LATH 2
RE-ROOF FINAL 2
ROOF SHEATHING 2
ROUGH CONDUIT 1
ROUGH ELECTRICAL 1
ROUGH FRAMING 2
ROUGH MECHANICAL 1
ROUGH PLUMBING 2
SOLAR FINAL 1
TOP OUT 1
UNDERGROUND PLUMBPRE 1
WATER HEATER FINAL 1
TOTAL INSPECTIONS for TRANS TECH: 32
TOTAL INSPECTIONS COMPLETED: 32
INSP60