EV Charging – Requirements & Estimated Costs for New Multi-Family Development Hayward’s Current Reach Code
(% of dwelling units)
2022 CalGreen
(% of parking spaces)
2022
Model Reach Code
2022
Model Reach Code
Affordable Housing
Option A
Option B
(Recommended by Staff)
Multi-Family
25% Level 2 EV Capable
75% Level 2 EV Ready
10% Level 2 EV Capable
25% low power Level 2 EV Ready
5% high power Level 2 EVSE
60% Level 1 EV Ready
40% high power Level 2 EVSE
60% Level 1 EV Ready
25% low power Level 2 EV Ready
15% high power Level 2 EVSE
60% high power Level 2 EV Ready
40% high power Level 2 EVSE
80% low power Level 2 EV Ready
20% high power Level 2 EVSE
Costs for a 100-unit Multi-Family Project*
L1 Ready
60 60
L2 Capable
25 15
L2 Low Power Ready
38 25
80 L2 High Power Ready
75 60
L2 High Power EVSE
8 40
15 40
20 Total Ports
100
61 100
100
100
100
Total Cost
$146,421
$194,185
$175,635
$397,801
$273,079
Cost/Port
$2,400
$1,942
$1,756
$3,978
$2,731
% of dwellings w/access
100%
40-60%
100%
100%
100%
100%
% of total const. cost**

0.3%

0.4%

0.4%

0.8%

0.6%
* Costs are estimated for 2022 and do not include the cost of transformers or increase panel capacity. Assuming 1.5 parking spaces per dwelling unit. ** The “% of total construction cost” may be as high as double as what is when accounting for transformers, etc. This is especially true of ‘Option A’ which includes the highest power requirements.

EV Charging – Requirements for Other Land Use Types
2019 CalGreen
Hayward’s Current Reach Code
2022 CalGreen
Model Reach Code
(potential requirements)
Recommended
Single Family & Townhome
One Level 2 EV Capable for one parking space per dwelling unit Two Level 2 EV Ready spaces per dwelling unit
No changes from 2019 CalGreen
One Level 2 EV Ready space
One Level 1 EV Ready space
Two Level 2 EV Ready spaces per dwelling unit
No change from current Reach Code.

Non-Res Office
6% Level 2 EV Capable
20% Level 2 EVSE;
30% Level 2 EV Capable
5% Level 2 EVCS;
10% Level 2 EV Capable
20% Level 2 EVSE;
30% Level 2 EV Capable
20% Level 2 EVSE;
30% Level 2 EV Capable
No change from current Reach Code.

Non-Res Non-Office
15% Level 2 EVSE
10% Level 2 EVSE;
10% Level 2 EV Capable
10% Level 2 EVSE;
10% Level 2 EV Capable
Hotel/
Motel
NA
NA
NA
5% Level 2 EVSE;
25% low power Level 2 EV Ready
5% Level 2 EVSE;
25% low power Level 2 EV Ready
EV Charging Cost Estimates
The following cost estimates are from a 2019 study prepared for Peninsula Clean Energy (PCE) and Silicon Valley Clean Energy (SVCE) analyzing the costs for: 1) a 60-unit multi-family project; 2) a 150-unit multi-family project; and 3) an office building with 60 parking spaces. The costs below are for EV Ready and do include costs for transformers. This study does not include costs for EVSE, and does not include and has a overall 20% contingency to account for ADA compliance. ADA can be a significant source of cost and in this study is only intended to capture a limited scope of ADA compliance.

Figure1. Cost Break-down for 60-unit Multi-family Residential Project Table 1. Estimated Incremental Cost of installing EV Infrastructure: 60-unit Multi-family Residential Project NC = New Construction
Figure2. Cost Break-down for 150-unit Multi-family Residential Project Table 2. Estimated Incremental Cost of installing EV Infrastructure: 150-unit Multi-family Residential Project NC = New Construction
Figure 3. Cost Break-down for Office Building with 60 Parking Spaces Table 3. Estimated Incremental Cost of installing EV Infrastructure: Office Building with 60 Parking Spaces NC = New Construction

Page 1 of 8 ends

https://bayareareachcodes.org/wp-content/uploads/2020/03/PCE_SCVE-EV-Infrastructure-Report-2019.11.05.pdf