Special Council Infrastructure
Committee Meeting
Main Street Complete Streets Update
June 16, 2022
Public Works & Utilities Department
1 Main Street Complete Streets
-
CIC Meeting
- Review Concept 4, which incorporates feedback and concerns from the community - Review estimated construction costs for Concept 4
- Recommendations & Next Steps
- Questions & Discussion
2 Main Street Complete Street
–
Public Meetings & Outreach
• July 24, 2017 CIC meeting: staff presented 3 design concepts for feedback and comments. • January 22, 2020 CIC meeting: staff re-introduced the 3 design concepts. • February 26, 2020: staff met with Fire and Police department to review design concepts and received feedback. • June 22, 2020 Virtual Community meeting: staff reviewed 2 design concepts (1 & 2) with public. • June 22, 2020: received design concept feedback and bus stop design recommendations from AC Transit. • July 15, 2020 DHIA meeting: staff reviewed 2 design concepts (1 & 2). • July 22, 2020 CIC meeting: staff presented design alternatives suggested by the community members and staff analysis and reviewed design concepts 1 & 2. Committee narrowed it down to Concept 1 with exception. • October 28, 2020 CIC meeting: staff presented an updated project cost estimate and alternative scope of work to the CIC. • March 16, 2021: Council approved a resolution to enter into an agreement with CSW/ST2. 3 Main Street Complete Street
–
Public Meetings & Outreach (continued)
• April 28, 2021 CIC meeting: staff presented a project cost estimate for Concept 1 along with an alternative. • January 26, 2022: virtual meeting with the DHIA and Chamber to present Concept 4 for feedback. • April 27, 2022: coordinated with Fire department and AC Transit to review Concept 4 and receive feedback. • May 5, 2022: staff met with local businesses at the project site for an in-person meeting to present Concept 4 for feedback. 4 Main Street Complete Streets
–
Existing Conditions
5 Tree root damage to sidewalk Street pavement cracking Mid-block crossing Un-necessary red curbs
Main Street Complete Streets
–
CIC Meeting
Concept 4
6 Proposed Improvements and Amenities from A Street to C Street • Center left turn lane & delivery truck loading
• New decorative sidewalks
• New bulb-outs at curb returns
• Decrease pedestrian crossing distance and increase safety • Increase pedestrian signal timing to allow seniors to cross safely • Pedestrian refuge area at A Street and Main Street
• New rapid flashing beacon system at two mid-block pedestrian crossings • New streetlights
• New street trees
• Repair and re-pave the street
• Re-stripe and re-sign existing loading zones
• Remove un-necessary red painted curbs to add parking
• Enhance AC Transit bus stop at B Street
• New Big Belly trash and recycling receptables
• New bike lanes with buffer and high visibility striping Main Street Complete Streets
–
CIC Meeting
Concept 4
7 Main Street Complete Streets
–
CIC Meeting
Concept 4
8 A Street to B StreetA Street B Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
9 Intersection of Main Street & A Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
10 Intersection of Main Street & B Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
11 B Street to C StreetB Street C Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
12 Intersection of Main Street & C Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
13 Proposed Improvements and Amenities from C Street to D Street • Center left turn lane & delivery truck loading
• New bulb-out at C Street curb return
• Decrease pedestrian crossing distance and increase safety • Increase pedestrian signal timing to allow seniors to cross safely • New street trees
• Repair and re-pave the street
• Repair damaged sidewalk
• Re-stripe and re-sign existing loading zones and curb paint • New Big Belly trash and recycling receptables
• New bike lanes with buffer and high visibility striping Main Street Complete Streets
–
CIC Meeting
Concept 4
14 C Street to D StreetC Street D Street
Main Street Complete Streets
–
CIC Meeting
Concept 4
15 Proposed Improvements and Amenities from A Street to McKeever Avenue • Center left turn lane & delivery truck loading
• New bulb-outs at curb returns at A Street
• Decrease pedestrian crossing distance and increase safety • Increase pedestrian signal timing to allow seniors to cross safely • New street trees
• Repair and re-pave the street
• Repair damaged sidewalk
• Re-stripe and re-sign existing loading zones and curb paint • New Big Belly trash and recycling receptables
• New bike lanes with buffer and high visibility striping Main Street Complete Streets
–
CIC Meeting
Concept 4
16 A Street to McKeever AvenueMcKeever
Avenue
A Street
Levine Court
Main Street Complete Streets
–
CIC Meeting
Estimated Project Costs
17 Funding Summary
OBAG Grant $1.7 Million
City of Hayward Contribution $550,000
Safe Routes for Seniors $1.0 Million
Total Funds Available $3.25 Million
Main Street Complete Streets
–
CIC Meeting
Recommendations
-Staff recommends the Committee receive public comments and provide feedback on Concept 4 -Authorize staff to prepare construction documents utilizing Concept 4.
Next Steps
-Take direction from the committee and move forward accordingly 18 Questions & Discussion
?
!