August 15, 2023
WPCF Administration Building
60% Design Review Workshop

ATTACHMENT II
2 Agenda

1. Introduction and Objectives

2. 60% Site Design

3. Exterior Design Walkthrough

4. 60% Building Design

5. Cost Estimate

6. Next Steps
3 Objectives

1. Review 60% Design

2. Answer general questions to support 60% review

3. Approval to commence 90% design
4 60% Site Design
Paving and
Grading
Site Civil Plan
5 Site Civil Plan
6 Paving and
Grading
Yard Utilities
Site Civil Plan
7 Yard Utilities
Site Civil Plan
8 Landscape
Landscape Plan
Landscape
Landscape Design

RELOCATED LEMON TREE
BENCH
PLAZA

BIKE RACK

FLAGPOLE

ELECTRICAL TOWERS

DROP-OFF PLAZA

SIGNAGE TYP BY OTHERS

DEMONSTRATION GARDEN

AMPHITHEATER SEATING
Landscape
Furnishings
11 Landscape
Plant Palette
12 Landscape
Plant Palette
13 Brown and Caldwell 14
Landscape
Demonstration Garden - Precedents
15 Public Entry View from the Northeast side
Exterior Design Walkthrough
16 Exterior Design Walkthrough
Public Entry View from the drop-off plaza
17 Exterior Design Walkthrough
Demonstration Garden view
18 Public Entry View
Exterior Design Walkthrough
19 Service Entry View from the Southeast side
Exterior Design Walkthrough
20 Exterior Design Walkthrough
Laboratory Entry View
21 Exterior Design Walkthrough
Staff Entry View
LEED
Scorecard
22 23
60% Building Design
First Floor Plan
N
13,038 sf
21,563 sf total
24 Architecture
24 Laboratory Area
25 Architecture
N
25 Second Floor Plan
N
8,525 sf
21,563 sf total
Architecture
Break room and Training Room
Architecture
27 RCP First Floor
Architecture
28 N
RCP Second Floor
Architecture
29 N
Elevations
Architecture
30 Elevations
Architecture
31 Sections
Architecture
32 Sections
Architecture
33 Sections
Architecture
34 Wall Sections
Architecture
35 Structural
36 Foundation Plan
Structural
37 Second Floor Framing
38 Roof Framing
Structural
–Plumbing
–HVAC
–Fire protection
–Dedicated fire service from potable water main
– Pre-action system for Electrical and SCADA/Operations –Power (from 12kV Substation)
Building Mechanical and Electrical
39 HVAC
40 First Floor Schematic
Air to Water
Heat Pump
(efficient)
Exhaust Air
Hydronic
System
HVAC
41 Second Floor Schematic
Variable Refrigerant
Flow Heat Pump
(efficient)
Fresh Air Supply
Exhaust Air
Electrical
42 Single Line Diagram
Redundant Feeds from
MCC81111 and 81112
New Switchboard in
Electrical Room
Solar PV
Parking Cover
Panelboards
I&C
43 SCADA Block Diagram
Server Racks in
SCADA Room
Remote
Workstations
I&C
44 Plan Workstation Server Racks
Control Room SCADA Room
PLC Panel
45 Cost Estimate
Difference
($ millions)
60% Design
Estimate
($ millions)
PDR Estimate
($ millions)
Item Description
$0.5$0.8$0.3Demolition01
($1.2)--$1.2Deep Pile Foundation
($1.2)$2.0$3.2Site/Civil02
$1.4$1.4(included above)Yard Piping and Landscaping03
$4.2$24.8$20.6Building04
($0.2)$2.9$3.1Furnishings, Fixtures & Equipment05
$3.5$31.9$28.4TOTALS
Cost Estimate
46 Class 2 (Expected accuracy: -15% to +20%)
Facilities Plan Estimate = $20.5 million
Next Steps
47 90% DESIGN (August – December 2023)
• 90% Design Submittal 11/10/23
• City Review Period 11/11 – 12/05
• City Permitting Department 11/13 – 12/19
• OPCC Submittal 12/12
• City Review Period 12/13 – 12/28
100% DESIGN (December – March 2024)